This is Amendment 3. Please adhere to the new guidelines. All questions should now go to Brian Edwards at 817-886-1053 brian.edwards@usace.army.mil Kristi Likes is no longer the Contract Specialist
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The Solicitation for FY18 TEMF Vehicle Maintenance Shop, Fort Hood, Texas is amended as follows.
NOTICE: The submission date and time for the contractor proposal(s) has been extended to 24 Oct 2018, at 2pm CDT.
See SF30 Continuation Sheet(s)
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
W912618R1986
X 9B. DATED (SEE ITEM 11)
27-Aug-2018
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Oct-2018
CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A19
P.O. BOX 17300
FORT WORTH TX 76102-0300
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
W9126G18R1986
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. The submission date and time for the contractor proposal(s) has been extended to 24 Oct 2018, at 2pm CDT.
2. The Specification Sections noted under “CHANGES TO THE SPECIFICATIONS” have been replaced, deleted or augmented with new sections as part of refinements to the project design.
3. The Drawings noted under “CHANGES TO THE DRAWINGS” below have been replaced, deleted or augmented with new sheets as part of refinements to the project design.
CHANGES TO SOLICITATION W9126G18R1986
CHANGES TO THE SPECIFICATIONS
1. Replacement Sections - The following specification sections noted W9126G18R1986, AMENDMENT 0003, are replaced in their entirety.
00 10 00 SOLICITATION, OFFER, AND AWARD, SF-1442
00 11 00 CONTRACT LINE ITEM SCHEDULE
00 22 11 DESIGN-BID-BUILD SELECTION PROCEDURES
01 33 00 A SUBMITTAL REGISTER
03 30 00.00 10 CAST-IN-PLACE CONCRETE
05 50 13 MISCELLANEOUS METAL FABRICATIONS
10 21 13 TOILET COMPARTMENTS
22 00 00 PLUMBING, GENERAL PURPOSE
23 35 00.00 10 OVERHEAD VEHICLE TAILPIPE & WELDING FUME EXHAUST SYSTEM
31 00 00 EARTHWORK
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS & SITE FACILITIES
35 56 10 FACTORY FABRICATED FUEL STORAGE TANKS
2. Deleted Sections - The following specification sections are deleted in their entirety.
10 22 13 WIRE MESH PARTITIONS
3. Additional Sections - The following new specification sections noted W9126G18R1986, AMENDMENT 0003 below, are added to the specifications set.
01 45 35 SPECIAL INSPECTIONS
07 84 00 FIRESTOPPING
12 93 00 SITE FURNISHINGS
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
CHANGES TO THE DRAWINGS
4. Volume 1 Replacement Drawings - The following revised drawings noted W9126G18R1986, AMENDMENT 0003 below, are replaced in their entirety.
G-002 VOL I - INDEX OF DRAWINGS
C-001 GENERAL NOTES
` CS100 OVERALL SITE PLAN
CS101 SITE PLAN I
CS102 SITE PLAN II
CS103 SITE PLAN III
CS104 SITE PLAN IV
CS105 SITE PLAN V
CG100 OVERALL GRADING PLAN
CG101 GRADING PLAN I
CG102 GRADING PLAN II
CG103 GRADING PLAN III
CG104 GRADING PLAN IV
CG105 GRADING PLAN V
CG109 OVERALL STORM DRAINAGE PLAN
CG110 STORM DRAINAGE PLAN I
CG111 STORM DRAINAGE PLAN II (NOT ON LIST)
CG112 STORM DRAINAGE PLAN III
CG113 STORM DRAINAGE PLAN IV
CP100 OVERALL PAVING PLAN
CP101 PAVING PLAN I
CP103 PAVING PLAN III
CP110 OVERALL JOINT PATTERN PLAN
CP111 JOINT PATTERN PLAN I
CP112 JOINT PATTERN PLAN II
CP113 OVERALL JOINT PATTERN ELEVATION PLAN
CP114 JOINT PATTERN ELEVATION PLAN I
CP115 JOINT PATTERN ELEVATION PLAN II
CP116 OVERALL PAVEMENT MARKINGS AND SIGNAGE PLAN
CP117 PAVEMENT MARKINGS AND SIGNAGE PLAN I
CU100 OVERALL UTILITY PLAN
CU101 UTILITY PLAN I
CU103 UTILITY PLAN III
C-502 PAVING DETAIL II
C-507 HANDICAP ACCESS DETAIL 1 AND PAVING JOINT DETAILS
C-531 MISCELLANEOUS DETAILS
C-532 CHAIN LINK GATE DETAILS
LP100 OVERALL LANDSCAPE PLAN
LP101 LANDSCAPE PLAN I
LP102 LANDSCAPE PLAN II
LP103 LANDSCAPE PLAN III
LP104 LANDSCAPE PLAN IV
E-001 ELECTRICAL EXTERIOR LEGEND
ES101 ELECTRICAL SITE PLAN I
ES103 ELECTRICAL SITE PLAN III
ES504 EXTERIOR DETAILS 4
ET101 EXTERIOR COMMUNICATIONS PLAN I
ET103 EXTERIOR COMMUNICATIONS PLAN III
ET105 EXTERIOR COMMUNICATIONS PLAN V
ET502 COMMUNICATIONS HANDHOLE DETAILS
5. Volume 1 Additional Drawings - The following new drawings noted W9126G18R1986, AMENDMENT 0003 below, are added to the drawing set.
CS101A SITE PLAN I BID OPTION 1
CS102A SITE PLAN II BID OPTION 1
CS103A SITE PLAN III BID OPTION 1
CS104A SITE PLAN IV BID OPTION 1
CG101A GRADING PLAN I BID OPTION 1
CG102A GRADING PLAN II BID OPTION 1
CG103A GRADING PLAN III BID OPTION 1
CG104A GRADING PLAN IV BID OPTION 1
CG110A STORM DRAINAGE PLAN I BID OPTION 1
CG111A STORM DRAINAGE PLAN II BID OPTION 1
CG112A STORM DRAINAGE PLAN III BID OPTION 1
CG113A STORM DRAINAGE PLAN IV BID OPTION 1
CP101A PAVING PLAN I BID OPTION 1
CP103A PAVING PLAN III BID OPTION 1
CP111A JOINT PATTERN PLAN I BID OPTION 1
CP114A JOINT PATTERN ELEVATION PLAN I BID OPTION 1
CP117A PAVEMENT MARKING AND SIGNAGE PLAN I BID OPTION 1
CU101A UTILITY PLAN I BID OPTION 1
CU103A UTILITY PLAN III BID OPTION 1
LP101A LANDSCAPE PLAN I
LP102A LANDSCAPE PLAN II
LP103A LANDSCAPE PLAN III
LP104A LANDSCAPE PLAN IV
ES101A ELECTRICAL SITE PLAN I BID OPTION 1
ES103A ELECTRICAL SITE PLAN III BID OPTION 1
ET101A EXTERIOR COMMUNICATIONS PLAN I BID OPTION 1
ET103A EXTERIOR COMMUNICATIONS PLAN III BID OPTION 1
ET105A EXTERIOR COMMUNICATIONS PLAN V BID OPTION 1
6. Volume 2 Replacement Drawings - The following revised drawings noted W9126G18R1986, AMENDMENT 0003 below, are replaced in their entirety.
1S-202 ADMIN AREA ELEVATION
1A-001 GENERAL NOTES & ABBREVIATIONS
1A-102 1ST FLOOR PARTIAL PLAN AREA B
1A-401 RESTROOM ELEVATIONS
1A-403 MILLWORK DETAILS
1A-502 PLAN DETAILS II
1A-571 MISCELLANEOUS DETAILS
1A-602 DOOR DETAILS
1A-701 AIR BARRIER PLANS AND SECTIONS
1A-702 AIR BARRIER SECTIONS
1M-508 MECHANICAL DETAILS
1M-602 MECHANICAL SCHEDULES
1EP113 1ST FLOOR – AREA C EQUIPMENT ROOM
1EP601 POWER RISER ROOM
1ET401 ENLARGED COMMUNICATION ROOMS
1ET601 TELECOMMUNICATIONS RISER DIAGRAM I
7. Volume 3 Replacement Drawing - The following revised drawing noted W9126G18R1986, AMENDMENT 0003 below, is replaced in its entirety.
G-002 VOL III – INDEX OF DRAWINGS
2A-001 GENERAL NOTES AND ABBREVIATIONS
2EP601 POWER RISER DIAGRAM & PANEL SCHEDULES
2ET101 TELECOMMUNICATION PLAN
2ET601 TELECOMMUNICATION RISER DIAGRAM
6A-001 GENERAL NOTES AND ABBREVIATIONS
6EP101 POWER PLAN, RISER DIAGRAM, AND PANEL SCHEDULE
6ET101 TELECOMMUNICATION PLAN
6ET601 TELECOMMUNICATION RISER DIAGRAM
8. Volume 3 Deleted Drawings - The following drawings are deleted in their entirety.
3S-101 FOUNDATION PLAN
3S-301 FOUNDATION SECTIONS
3S-700 LOADING DOCK I
3S-701 LOADING DOCK II
3A-001 GENERAL NOTES AND ABBREVIATIONS
3A-101 PLANS, ELEVATIONS, SECTIONS
3A-310 WALL SECTIONS
3A-405 STAIR DETAILS
3A-406 RAMP DETAILS
3A-602 DOOR & LOUVER SCHEDULE
3FA001 FIRE ALARM LEGEND
3FA101 FIRE ALARM PLAN
3FA501 FIRE ALARM DETAILS 1
3FA502 FIRE ALARM DETAILS 2
3FX-101 FIRE PROTECTION FLOOR PLAN
3FX-501 FIRE PROTECTION DETAILS
3M001 MECHANICAL GENERAL NOTES AND LEGENDS
3M101 MECH FLOOR PLAN
3E-001 ELECTRICAL LEGEND
3EG101 LIGHTNING PROTECTION PLAN
3EG501 GROUNDING DETAILS 1
3EG502 GROUNDING DETAILS II
3EG503 GROUNDING DETAILS III
3EG504 GROUNDING DETAILS IV
3EG601 GROUNDING RISER DIAGRAM
3EL001 LIGHTING FIXTURE SCHEDULE & CONTROL SCHEDULE
3EL101 LIGHTING PLAN
3EL501 LIGHTING DETAILS
3EP101 POWER PLAN
3EP601 POWER RISER DIAGRAM & PANEL SCHEDULE
3ET101 TELECOMMUNICATION PLAN
3ET501 TELECOMMUNICATIONS DETAILS
3ET601 TELECOMMUNICATIONS RISER DIAGRAM
9. Volume 3 Additional Drawings - The following new drawings noted W9126G18R1986, AMENDMENT 0003 below, are added to the drawing set.
3S-101A FOUNDATION PLAN
3S-301A FOUNDATION SECTIONS
3S-700A LOADING DOCK I
3S-701A LOADING DOCK II
3A-001A GENERAL NOTES AND ABBREVIATIONS
3A-101A PLANS, ELEVATIONS, SECTIONS
3A-310A WALL SECTIONS
3A-405A STAIR DETAILS
3A-406A RAMP DETAILS
3A-602A DOOR & LOUVER SCHEDULE
3FA001A FIRE ALARM LEGEND
3FA101A FIRE ALARM PLAN
3FA501A FIRE ALARM DETAILS 1
3FA502A FIRE ALARM DETAILS 2
3FX-101A FIRE PROTECTION FLOOR PLAN
3FX-501A FIRE PROTECTION DETAILS
3M001A MECHANICAL GENERAL NOTES AND LEGENDS
3M101A MECH FLOOR PLAN
3E-001A ELECTRICAL LEGEND
3EG101A LIGHTNING PROTECTION PLAN
3EG501A GROUNDING DETAILS 1
3EG502A GROUNDING DETAILS II
3EG503A GROUNDING DETAILS III
3EG504A GROUNDING DETAILS IV
3EG601A GROUNDING RISER DIAGRAM
3EL001A LIGHTING FIXTURE SCHEDULE & CONTROL SCHEDULE
3EL101A LIGHTING PLAN
3EL501A LIGHTING DETAILS
3EP101A POWER PLAN
3EP601A POWER RISER DIAGRAM & PANEL SCHEDULE
3ET101A TELECOMMUNICATION PLAN
3ET501A TELECOMMUNICATIONS DETAILS
3ET601A TELECOMMUNICATIONS RISER DIAGRAM
End of Summary of Changes
Firm-Fixed Priced construction project to Construct a Tactical Equipment Maintenance Facility at Fort Hood, Texas.
This is an Unrestricted Acquisition. The construction magnitude of this project is betw een $25,000,000 to $100,000,000.
NAICS Code: 236220 FSC: Y1EA Size Standard: $36.5 million
**If the contractor fails to provide adequate and acceptable bond documents and insurance certif icate w ithin ten days af ter contract aw ard, such f ailure shall constitute ground for termination f or default w ithout the requirement for the Contracting Off icer to f irst issue a "show cause" letter. The Government w ill not allow the contractor to w ork on the project unless the bond documents and insurance certif icate have been accepted by the Contracting Off icer and a signed Notice to Proceed has been issued to the contractor.
KRISTI LIKES 817.886.1088
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED (RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________720 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A17
FORT WORTH TX 76102-0300
W9126G
PAGE OF PAGES
1 OF
CODE W9126G
(Title, identifying no., date):
12B. CALENDAR DAYS
(hour)
Sealed envelopes containing offers
CESWF-EC
819 TAYLOR STREET, ROOM 4A17
FORT WORTH, TX 76102
FORT WORTH TX 76102
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
817-886-6403FAX:TEL: 817-886-1043 TEL: 817-886-1680 FAX:
W9126G18R1986 2
27 AUGUST 2018
11 October 2018
2PM
(AM#0003) 24 (AM#0003)
Section 00 10 00 - Solicitation, Offer and Award, SF-1442
W9126G18R1986, AMENDMENT 0003
M2ECAJMC
Line
M2ECAJMC
Rectangle
M2ECAJMC
Typewritten Text
M2ECAJMC
Line
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9126G18R1986, AMENDMENT 0003
Section: 00 11 00 W9126G18R1986
Item Unit Line Item No. Description Quantity Unit Price Amount
0001 All work required for construction of the Tactical Equiment Motorpool Facity (TEMF) as described in the RFP, exclusive of all other work listed seperately 1 JOB $ *** $
0002 All work required by the RFP documents to construct outside the 5ft line of the facility except work completed by privatized utilities for the TEMF. 1 JOB $ *** $
0003 All work required by the RFP documents to complete work perform by American Water for the TEMF. 1 JOB $ *** $
0004 All work required by the RFP documents to complete work perform by Dominion Electric for the TEMF. 1 JOB $ *** $
0005 Caisson Lengths/Reinforcing Steel (Piers)(36” Diameter). 262 VLF $ $
0006 Caisson Lengths/Reinforcing Steel (Piers)(30” Diameter).
1253 VLF $ $
0007 Caisson Lengths/Reinforcing Steel (Piers)(24” Diameter). 570 VLF $ $
Fort Hood, TX
CONTRACT LINE ITEM SCHEDULE
TEMF
FY 18,
TOTAL BASE OFFER
BASE OFFER: All work required by the plans and specifications exclusive of work required by the Option Items.
0008 Temporary Casing (Piers)(36” Diameter). 262 VLF $ $
0009 Temporary Casing (Piers)(30” Diameter). 1253 VLF $ $
0010 Temporary Casing (Piers)(24” Diameter). 570 VLF $ $
(AM#0003)
(AM#0003)
Section: 00 11 00 W9126G-18-R-1986
OPTIONS
0008 OPTION NO 01: All work required by the RFP to construct Distribution Storage Building 1 JOB $ *** $
TOTAL ALL OPTIONS
TOTAL OFFER (BASE + OPTIONS)
(AM#0003)
(AM#0003)
Contract Duration in Calendar Days After the Notice to Proceed is Received.* DAYS
*NOTE: Contract duration for all work shall not exceed the duration specified in Section 01 00 00.00 44
CONSTRUCTION SCHEDULE.
(AM#0003)
(AM#0003)
W9126G18R1986, AMENDMENT 0003
M2ECAJMC
Line
TEMF Vehicle Maintenance Shop
FY 2018
Fort Hood, TX
CONTRACT LINE ITEM SCHEDULE
NOTES:
NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.
NOTE NO. 2. Offerors must insert a price on all numbered items of the CLIN Schedule. Failure to do so may result in the offer being unacceptable
NOTE NO. 3. CONDITIONS GOVERNING EVALUATION OF OFFERS AND AWARD OF CONTRACTS:
The Government may require the delivery of the numbered line items, identified in the schedule as option items, in the quantity and at the price stated in the schedule. Subject to the availability of funds, the Contracting Officer may exercise the option by written notice to the Contractor within the time indicated below from the Notice to Proceed
NOTE NO. 4. All the extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
NOTE NO. 5. Include all costs for coordination and accommodation of Government-Furnished, Government- Installed Equipment, in the Contract Line Items for construction of the associated facilities.
NOTE NO. 6. The Offeror shall propose a total integrated contract duration in number of calendar days after the Notice to Proceed (NTP) is received by the Contractor, whether via electronic means or hard copy, whichever is the earliest method of delivery. The total number of proposed calendar days for construction through completion, ready for turnover shall not exceed the number of calendar days specified in Section 00 73 00 Supplemental Conditions and 01 00 00.00 44 Construction Schedule. The proposed duration shall become the required contract duration. The Government may issue the NTP via e-mail or Facsimile (FAX) or by other means. Day number 1 is the day after the date of receipt of the NTP
NOTE NO. 7. At the option of the Government, the Government may require the Contractor to perform the work identified as Optional line item(s) at the price(s) stated in the CLIN Schedule. The Contracting Officer may exercise one or more of the Option(s) by written notice to the Contractor within 120 calendar days after the date of the acknowledgment of the Notice to Proceed by the Contractor. There is no separate completion period for these option(s) and the work included therein shall be completed within the contract duration as proposed above.
Exercise of the Option(s) shall be evidenced on Standard Form 30, citing this CLIN Schedule note as the authority for exercising the Option. The Option shall be deemed exercised at the time the Government deposits the SF30 in the mail or, if earlier, at the time it is delivered to the Contractor.
NOTE NO. 8. 52.217-5 EVALUATION OF OPTIONS (JUL 1990)
(a) Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
TEMF Vehicle Maintenance Shop
FY 2018
Fort Hood, TX
CONTRACT LINE ITEM SCHEDULE
(b) The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
NOTE NO. 9. Responders are advised that this requirement may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process based on decisions related to DOD changes in force structure and disposition of the Armed Forces.
NOTE NO. 10. Any proposal that is materially unbalanced as to prices for the Base Schedule may be rejected.
An unbalanced proposal is one that is based on prices significantly less than the cost for some work and prices that are significantly overstated for other work and can also exist where only overpricing or underpricing exists.
NOTE NO. 11. ABBREVIATIONS
For the purpose of this solicitation, the units of measure are represented as follows:
a. JOB (job)
b. VLF (vertical linear feet)
END OF CLIN SCHEDULE
SECTION 00 22 11
DESIGN-BID-BUILD SELECTION PROCEDURES
1. OVERVIEW
2. BASIS OF AWARD
3. GENERAL INSTRUCTION
3.1. GENERAL PROPOSAL FORMAT
4. EVALUATION FACTORS AND WEIGHTING, VOLUME 1, TECHNICAL
4.1. GENERAL
4.2. PROPOSAL CONTENTS AND RELATED EVALUATION FACTORS
5. TAB A– FACTOR 1–PAST PERFORMANCE
5.1. SUBMISSION REQUIREMENTS
5.2. RELEVANCY DETERMINATION
5.3. CONFIDENCE EVALUATION CRITERIA
6. TAB B – FACTOR 2 – SUMMARY SCHEDULE
6.1. SUBMISSION REQUIREMENTS
7. TAB C –FACTOR 3 – SMALL BUSINESS PARTICIPATION
7.1. SUBMISSION REQUIREMENTS
8. PRICE AND OTHER REQUIRED INFORMATION, VOLUME 2, PRICE
8.1. TABLE 2 - Volume 2 – PRICE AND OTHER REQUIRED INFORMATION
8.2. GENERAL
9. TAB A – FACTOR 4 – PRICE (STANDARD FORM 1442 AND BID SCHEDULE)
9.1. SUBMISSION REQUIREMENTS
9.2. EVALUATION CRITERIA
10. TAB B – BID GUARANTEE
10.1. SUBMISSION REQUIREMENTS
10.2. EVALUATION CRITERIA
11. TAB C – REQUIRED PRE-AWARD INFORMATION
11.1. SUBMISSION REQUIREMENTS
11.2. EVALUATION CRITERIA
12. TAB D – SUBCONTRACTING PLAN
12.1. SUBMISSION REQUIREMENTS
12.2. EVALUATION CRITERIA
13. TAB E –REPRESENTATIONS AND CERTIFICATIONS
13.1 SUBMISSION REQUIREMENTS
13.2 EVALUATION CRITERIA
14. EVALUATION CRITERIA
14.1. GENERAL
14.2. DISCUSSIONS (IF NECESSARY)
15. EVALUATION AND RATING SYSTEM
15.1. GENERAL
15.2 REVIEW WRITE-UP
15.3 RATING SYSTEM
16. DEFINITIONS
17. PAST PERFORMANCE RATINGS
18. ATTACHMENTS
ATTACHMENT 1- PROPOSAL DATA SHEETS
ATTACHMENT 2- PAST PERFORMANCE ASSESSMENT WORKSHEET
ATTACHMENT 3- COMPANY PAST PERFORMANCE QUESTIONAIRRE
ATTACHMENT 4- SMALL BUSINESS PARTICIPATION PLAN
ATTACHMENT 5- CERTIFICATION REGARDING RESPONSIBILITY MATTERS (APR 2010)
1.0 OVERVIEW
This Request for Proposal (RFP) solicits for the construction of a Tactical Equipment Maintenance Facility (TEMF), Fort Hood, Texas. The Design-Bid-Build project shall consist of the construction of Standard design Vehicle Maintenance Shop with a large TEMF, Organizational Storage with accompanying parking and Supporting facilities.
This solicitation is for a Design-Bid-Build, Firm-Fixed Price (FFP) contract at Fort Hood, Texas. The work shall be in accordance with the Request for Proposal documents. The proposed project will be a competitive Unrestricted, Full-and-Open competition resulting in the award of a firm-fixed price contract procured in accordance with FAR 15.101, Negotiated Procurement using the “Tradeoff Process”.
The Tradeoff Process permits the tradeoffs among cost, price and/or non-cost factors and allows the Government to accept other than the lowest priced proposal. Offerors submit their performance and capability information for review and consideration by the Government. Relative weights among technical factors are provided in Section 4: Evaluation Factors & Weighting. The Source Selection Evaluation Board (SSEB) reviews, evaluates, and rates the proposals against the source selection criteria in the RFP. A competitive range consisting of the most highly qualified technical Offerors will be established prior to discussions (if held). Concurrently, the Government analyzes price proposals of Offerors utilizing the project cost proposal. Price will not be rated, but will be a factor in making the final best value determination for award. The Source Selection Authority (SSA) compares proposals and determines the best value for the government. The perceived benefits of the higher priced proposal must merit the additional cost, and the rationale for tradeoffs must be documented.
2.0 BASIS OF AWARD
The Contracting Officer (KO) will award a firm fixed-price contract to that responsible Offeror whose proposal the Source Selection Authority (SSA) determines offers the best overall value to the Government. Best Value means the expected outcome of an acquisition that, in the Government’s estimation, provides the greatest overall benefit in response to the requirement. In using the best value approach, the Government seeks to award a contract to the Offeror who gives the Government the greatest confidence that it will best meet our requirements.
This process may result in an award being made to a firm with a higher-priced offer where the decision is consistent with the evaluation criteria/factors and the SSA determines that the technical or service superiority and/or overall business approach and/or superior past performance of the higher-priced offer outweighs the cost difference.
The SSA, using sound business judgment, bases the award decision on an integrated assessment of the evaluation criteria in the factors described below. While the entire evaluation team strives for maximum objectivity, the selection process is subjective by nature and professional judgment is implicit throughout the best value process. Ultimately, the contract shall be awarded to the Offeror whose proposal, based upon the evaluation criteria, represents the best value to the Government.
Proposals must meet the criteria stated in the RFP in order to be eligible for award, to include responsiveness, technical acceptability and responsibility.
In order to determine which proposal(s) represent the best value, the Government will be determined by a comparative assessment of proposals against all source selection criteria in this RFP.
As technical ratings and relative advantages and disadvantages become less distinct, differences in price between proposals are of increased importance in determining the most advantageous proposal.
Conversely, as differences in price become less distinct, differences in technical ratings and relative advantages and disadvantages between proposals are of increased importance to the determination. All evaluation factors when combined are significantly more important than price.
The Government reserves the right to accept other than the lowest priced offer(s). The right is also reserved to reject any and all offers.
Offerors are reminded to include their best technical and price terms in their initial offer and not to automatically assume that they will have an opportunity to participate in discussions or be asked to submit a revised offer.
3.0 GENERAL INSTRUCTIONS
Firms formally organized as a single entity firms that have associated specifically for this project, consortia of firms or any other interested parties may submit proposals. Associations may be as joint ventures or as key team subcontractors. Any legally organized Offeror may submit a proposal.
Contractor Team Arrangements. Contractor Team Arrangements are considered an arrangement in which: two or more companies form a partnership or joint venture to act as a potential prime contractor; or (2) a potential prime contractor agrees with one or more other companies to have them act as its subcontractors under a specified Government contract or acquisition program. In accordance with FAR Subpart 9.6, the Government will recognize the integrity and validity of contractor team arrangements; provided, the arrangements are identified and company relationships are fully disclosed in the offer. The Offeror shall identify the major or critical aspects of the requirement to be performed by those identified in the Contractor Team Arrangement. The submission must contain a narrative that clearly explains the relevance to a particular factor of information concerning a company that is part of a Contractor Team Arrangement. The Government will consider the adequacy of this explanation in deciding the relevance of the information to this procurement.
Any Offeror submitting an offer in the name of a joint venture, shall include a fully executed copy of the joint venture agreement with the offer. Joint venture agreements which require SBA approval may be submitted absent the requisite SBA Servicing Agency approving authorities’ signature; however, the Offeror shall submit evidence from the Offeror’s SBA Servicing Agency that the Offeror has notified and discussed the proposed joint venture for this project with the appropriate SBA personnel.
Offerors shall submit their proposal (AM#0003) per the instructions provided in Section 00 21 00 via AMRDEC to Brian.L.Edwards@usace.army.mil (AM#0003). Proposals are due no later than the time and date specified in Block 13 of Standard Form 1442.
3.1 PROPOSAL FORMAT:
(1) Submit only the electronic documents. Submit only the electronic files specifically requested. All files submitted shall be in PDF format. Do not submit excess information, to include audio-visual materials, electronic media, etc. All pages shall be numbered.
(2) PDF pages shall be formatted to print on 8 ½ by 11 inch paper, unless another paper size is specifically authorized for a particular submission. Do not use a font size smaller than 10, an unusual font style such as script, or condensed print for any submission. All page margins must be at least 1 inch wide, but may include headers and footers of the solicitation, project title and company. PDF drawings and summary schedule diagrams shall be sized to print on 11x17 inch paper.
(3) Hard copies shall not be submitted, with the exception of the bid guarantee. Refer to Section 00 21 00,
1.12 Bid Guarantee for bid guarantee submission requirements.
(4) “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offerors—Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”.
(5) In the case of an Offeror that is part of a large, multi-segmented business concern, provide information directly pertaining to the specific segment of the business concern (i.e., the division, group, unit, etc.) that will mailto:Brian.L.Edwards@usace.army.mil perform work under the prospective contract.
(6) For submissions with page limitations, the corresponding PDF pages will be counted.
(7) Proposal revisions shall be submitted as page replacements with revised text readily identifiable, e.g., bold face print or underlining. The source of the revision or amendment, e.g., Error, Omission or Clarification shall be included and be annotated for each revision. Proposal replacement pages shall be numbered and clearly marked “REVISED”, with the date of revision.
(8) Within three (3) days of contract award, the contractor receiving the award shall electronically submit their conformed proposal.
4.0 EVALUATION FACTORS AND WEIGHTING, VOLUME 1, TECHNICAL
4.1 GENERAL:
Offerors are invited to submit a proposal, as indicated below. Attachment 1 shall be included with Volume 1, Technical. The Government will evaluate the proposals in accordance with the evaluation criteria described herein, using the evaluation rating systems outlined in the Design-Bid-Build selection procedures. Price information will be evaluated for fairness, reasonableness, and for material unbalancing, as described herein. The evaluation will be conducted in accordance with FAR Part 15.
4.2. PROPOSAL CONTENTS AND RELATED EVALUATION FACTORS
VOLUME 1 – Technical
Table 1 - Volume 1 – PROPOSAL CONTENTS AND RELATED EVALUATION FACTORS
Location Factor Number Description Relative Importance
TAB A Factor 1 PAST PERFORMANCE Most Important
TAB B Factor 2 SUMMARY SCHEDULE Less Important than Factor 1. More Important than Factor 3.
TAB C Factor 3 SMALL BUSINESS
PARTICIPATION
Less Important than Factor 1 & Factor 2.
5.0 TAB A – FACTOR 1 - PAST PERFORMANCE
5.1 SUBMISSION REQUIREMENTS:
5.1.1. The Offerors shall demonstrate past performance through the submission of similar projects, using the Construction – Past Performance Assessment Worksheet (PPAW, Attachment 2). If the Offeror is a Joint Venture, Partnership, Teaming Arrangement, or Parent company/subsidiary/affiliate as identified in the offeror’s proposal, provide past performance information for construction projects relevant to each of the proposed roles on this project. If any firm has multiple functions or divisions, limit the project examples to those performed by the division or unit submitting the offer. If projects were design-bid-build, identify them as such.
Offerors can submit no more than five (5) projects (up to one PPAW per project) that are similar in size, scope, and complexity to the scope of the work for this solicitation to be considered relevant. Two (2) of the five (5) projects submitted for past performance may be a current construction project with at least 50% construction progress completed. If offeror is proposing as a Joint Venture (JV), Partnership and/or Teaming Arrangement and past performance cannot be provided as such, each partner shall submit past performance information, with no more than three
(3) projects each.
5.1.2. The Past Performance Questionnaire (PPQ) included in the solicitation (Attachment 3) is provided for the Offeror to submit to the client for each project the Offeror included for Factor 1, Past Performance that does not have an interim or final CPARS or CCASS evaluation or is a non- Federal Government project. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQ should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If any negative past performance information is received to which the Offeror has not an opportunity to respond, the contractor will be given an opportunity to provide rebuttal. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, (AM#0003) Kristi Likes Brian Edwards, via e-mail at: Kristi.L.Likes@usace.army.mil Brian.L.Edwards@usace.army.mil (AM#0003) prior to proposal closing date.
5.1.2.1. Offerors shall not incorporate by reference into their proposals PPQ’s previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
5.1.2.2. Do not request PPQ on projects that have interim or final CPARS or CCASS evaluations. If an interim or final CPARS or CCASS evaluation exists and a PPQ is provided for the same project, the CPARS or CCASS evaluation will be reviewed as the official past performance record for the project, and the PPQ will not be considered by the Source Selection Board or the Source Selection Authority.
5.1.2.3. For USACE or other DoD projects which are underway but do not yet have an interim or final CPARS or CCASS evaluation, one PPQ per contract may be submitted; to be considered, the PPQ shall be signed by the Administrative Contracting Officer (ACO) for the contract.
5.1.3. (AM#0001) Offerors shall submit the CPARS, CCASS or PPQ relevant to each project with their proposal for Factor 1, Past Performance. (AM#0001) Offerors are not required to submit any additional past performance information. The Government will utilize CPARS, CCASS and any other information deemed relevant to assess confidence in the Offeror’s ability to perform.
5.1.3.1. Offerors may submit information on past performance issues and corrective actions taken to prevent these issues from reoccurring. Discuss whether these corrective actions have been implemented on contracts awarded subsequent to the performance issues, the effectiveness of the corrective actions, and POC information for the subsequent contracts.
5.1.4. In addition to the above, the Government may review any other sources of information for evaluation of past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS number of team members (Partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquires of owner representative(s), Federal Awardees Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
5.1.5. The Offeror may provide a supplemental narrative (not project lists), not to exceed two pages, W9126G18R1986, AMENDMENT 0003 mailto:Kristi.L.Likes@usace.army.mil mailto:Brian.L.Edwards@usace.army.mil explaining how any corporate past performance that is not directly related to the specific projects above is applicable to this project and how the Government will benefit.
5.2 RELEVANCY DETERMINATION:
5.2.1. Offeror may submit no more than five (5) projects. Offeror must have a minimum of two (2) projects that are similar in size, scope, and complexity to the Tactical Equipment Maintenance Facility for this solicitation AND with the construction value of at least $25 million to be considered very relevant. Two (2) of the five (5) projects submitted for past performance may be a current construction project with at least 50% construction progress completed. Projects submitted at 100% complete must have been completed within the last six (6) years from the date of the solicitation.
5.2.2. The Government will evaluate the Offeror’s past performance to determine how relevant the past performance is to the project under consideration. Relevancy is a measure of the extent of similarity between the service/support effort, complexity, dollar value, contract type, and subcontract/teaming or other comparable attributes of past performance examples and the solicitation requirements; and a measure of the likelihood that the past performance is an indicator of future performance. Past performance on the projects identified in the project forms will receive more consideration than past performance provided in the supplemental narrative. The Government will place greater value on projects performed as a prime contractor than as a subcontractor, depending upon overall role and relevancy considerations. Federal Government project past performance will not be rated inherently more important than non-Federal Government project past performance.
5.2.3. More relevant past performance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance.
5.2.4. Contracts with lower degrees of relevance will not be as strong of predictors of likely future contract performance success and will typically have less influence on the final past performance confidence rating.
5.2.5. Contracts that have little or no relevance typically do not influence the performance confidence rating; however, any contracts with adverse past performance could reflect larger company-wide concerns and may have impact upon the past performance confidence rating.
5.2.6. Based on the relevancy of the projects submitted, an overall relevancy determination will be assessed as an interim step prior to establishing a confidence rating.
5.3 CONFIDENCE EVALUATION CRITERIA:
5.3.1. The SSEB will review the past performance information available, to include CPARS, CCASS and other past performance information deemed relevant, to determine the quality and usefulness as it applies to performance confidence assessment. If any firm has multiple functions or divisions, the Government will only evaluate past performance of the division or unit submitting the offer.
If the Government cannot establish the Offerors relevant past performance, it reserves the right to utilize the Past Performance Questionnaire to conduct telephone interviews on any source it deems relevant to the evaluation. Owners/references may be asked to comment on items such as quality of construction, timeliness, management of the work, subcontractor management, including timely payment to subs or suppliers, safety, level of support for such things as as-built documentation, O&M manuals, training, correcting construction errors, warranty work, etc. The Government will not release the information gathered to the Offeror at any time, in order for the Government to solicit candid, unbiased interview comments. The Government’s evaluation is not limited to past performance information on the cited example projects.
5.3.2. In determining the performance confidence rating for Past Performance, the degree of relevancy of all of the considered efforts; the overall performance record of the Offeror on each contract assessed; number and severity of problems, the demonstrated effectiveness of corrective actions taken (not just planned or promised); and trend data will be considered. Contracts with higher degrees of relevance will typically have a greater influence on the final performance confidence rating. Contracts with lower degrees of relevance will typically have less influence on the final performance confidence rating; however, any contracts with adverse past performance could reflect larger company-wide concerns and may impact upon the past performance confidence rating. Contracts which are comparatively more recent may be better predictors of likely future success than older contracts. The resulting relevant/recent assessment conclusions will then be combined, along with the assessed quality of performance on prior contracts, to arrive at a single performance confidence rating for the Past Performance Factor.
5.3.3. The confidence rating will be established based on the past performance of the firms or that of its predecessor, if applicable. An entity may not establish past performance based on the past performance of its key personnel apart from that of the entity. If the Government does not obtain past performance information and cannot establish a past performance record for the Offeror through other sources, a rating of Unknown (Neutral) confidence will be assigned.
5.3.4. If negative information is received, the Offeror will be given an opportunity to provide input as required by FAR 15. CPARS, CCASS that are part of the official record will be utilized as if the Offeror has already had an opportunity to respond.
6.0 TAB B – FACTOR 2 – Schedule Summary
6.1. SUBMISSION REQUIREMENTS:
6.1.1. Proposed Contract Duration: The Offeror shall propose the overall contract duration in the CLIN Schedule, not to exceed the maximum contract duration specified in Section 01 00 00.00 44. The proposed duration will become the contractually binding schedule. In assessing the reasonableness of the proposed contract duration, the Government will take into account how well the proposed summary schedule supports the proposed duration, as well as use other information, such as but not limited to, independent judgment concerning logic, constraints and typical construction durations. A proposed contract duration shorter than the maximum allowed duration will receive additional rating consideration, provided the schedule is realistic and deemed to be achievable. The Government will consider an unreasonably condensed contract duration, which places additional cost or schedule risk on the Government or which may create a risk of contract or performance failure, as a significant weakness or a deficiency, depending upon the evaluators' judgment.
6.1.2. Summary Schedule: Submit a summary level schedule for construction. This schedule will, after contract award, be replaced with a project schedule as required by Section 01 32 01.00 10 – Project Schedule. The schedule shall be task oriented, indicating the number of calendar days, after notice to proceed, by which milestones are to be achieved. Offeror may use a critical path or other method of their choice; however, schedules shall be graphically represented and shall include, at a minimum, Activity ID, Activity Description, Original Duration, early start and early finish dates, and total float for each activity.
The proposed schedule shall include an activity that shows the proposed overall contract duration in calendar days. Schedules must include the following items:
(a) Show activities for the Large TEMF, Organizational Storage Building, POL Storage Building, Unmanned Aerial Vehicle Storage Building, site work and utilities in sufficient detail to demonstrate an understanding of the scope of work to include design documents and to substantiate the reasonableness and realism of the proposed duration.
(b) Show submittal preparation and review/approval activities for long lead items to demonstrate an understanding of the submittal process and minimum review times for Government approved submittals. (See Section 01 33 00 Submittal Procedures.)
(c) Show activities for work in sufficient detail to demonstrate your understanding of the requirements for working in this area. (See Section 01 00 00.00 44 Construction Schedule).
(d) Show turnover per design documents. The time to complete the construction and turnover to the Government must consider the requirement for the Contractor’s CQC completion inspection and the subsequent joint Contractor-Government turnover inspection. Show closeout activities, to include the Red Zone meeting, record drawings, O&M manuals, to demonstrate your understanding of the closeout requirements for the contract
(e) Show activities for coordination with private utility providers and demonstrate your understanding of planning for completion of construction.
(f) Indicate the anticipated overall critical path on the schedule.
6.1.3. Evaluation Criteria: The Government will evaluate the schedule to assess the strength of understanding of the project scope, coordination and restrictions which must be considered in the schedule including long lead items, private utility provider coordination, and closeout process. The Government will evaluate the Offeror's capability to schedule the complete project within the proposed contract duration and the realism of the schedule. A schedule that offers advantage(s) to the Government over one that merely indicates an adequate understanding of the scope, restrictions, major milestones and general understanding of the contract requirements will receive additional consideration.
7 TAB C – FACTOR 3 – SMALL BUSINESS PARTICIPATION
7.1. SUBMISSION REQUIREMENTS:
7.1.1 All Offerors shall identify the extent to which…