Amendment 0004. BID OPENING REMAINS 6 SEP 2016 2 00 P.M. LOCAL TIME.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W45VAK61259696
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This solicitation W9126G-16-B-0024 is hereby amended as show n on the pages following:
See pages following
BID OPENING REMAINS ON 6 SEP 2016 @2:00 P.M. LOCAL TIME.
1. CONTRACT ID CODE PAGE OF PAGES
J 1
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9126G-16-B-0024
X 9B. DATED (SEE ITEM 11)
25-Jul-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Aug-2016
CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
2000 FORT POINT ROAD
GALVESTON TX 77550-1229
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9126G-16-B-0024 Page 2 of XX
A0004-2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. The specifications for Solicitation No. W9126G-16-B-0024, Houston Ship Channel, Texas, in Chambers County, Texas, Deferred Environmental Restoration M-7/8/9 and M-10, are hereby amended as follows:
a) Specifications.
(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45, entitled BID SCHEDULE, supersedes that issued with this Solicitation.
(2) SECTION 01 22 00.10, MEASUREMENT AND PAYMENT – The enclosed SECTION 01 22 00.10, entitled MEASUREMENT AND PAYMENT, supersedes that issued with this Solicitation.
(3) SECTION 31 09 13.05 45, SETTLEMENT PLATES – The enclosed SECTION 31 09 13.05
45, entitled SETTLEMENT PLATES, is in addition to those issued with this Solicitation.
2. This amendment shall be attached to and become a part of the solicitation.
3 Encl:
1. SECTION 00 11 00.00 45, BIDSCHEDULE
2. SECTION 01 22 00.10, MEASUREMENT AND PAYMENT
3. SECTION 31 09 13.05 45, SETTLEMENT PLATES
SWG FILE NO.:HSC 401-553 SOLICITATION NO.: W9126G-16-B-0024
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 11 00.00 45
BID SCHEDULE
PART 1 GENERAL
1.1 BID SCHEDULE
1.1.1 Schedule No. 1
1.1.2 Option No. 1
1.1.3 Option No. 2
1.1.4 Option No. 3
1.2 MODIFICATIONS (CESWG)
1.3 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)
-- End of Section Table of Contents --
DOCUMENT 00 11 00.00 45 Page 1
(TO ACCOMPANY AMENDMENT NO. 0004 TO SOLICITATION NO. W9126G-16-B-0024)
SECTION 00 11 00.00 45
BID SCHEDULE
AMENDMENT NO. 0004
PART 1 GENERAL
1.1 BID SCHEDULE
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.1 Schedule No. 1
Item No.
Description Estimated Quantity
Unit Unit Price
Estimated Amount
SCHEDULE NO. 1
0001 Mobilization and Demobilization 1 JOB SUM $___________
0002 Maintenance Dredging Bayport Ship Channel Station 150+00 to 239+22 to PA 15
1,779,300 C.Y. $_________$___________
0003 DER Borrow Bayport Ship Channel Station 211+15 to 239+22 to Atkinson Marsh Cells M7/8/9 and M10
1,206,708 C.Y. $_________$___________
0004 DER Shaping and Grading Atkinson Marsh Cell M7/8/9 11,300 L.F. $_________$___________
0005 DER Shaping and Grading Atkinson Marsh Cell M10 10,700 L.F. $_________$___________
0006 DER Atkinson Marsh Cell Spillbox Removal 2 EA $_________$___________
0007 DER Gorini Marsh Circulation Channel 1 JOB SUM $___________
0008 DER Seeding and Fertilizing
1 JOB SUM $___________
TOTAL SCHEDULE NO. 1 $___________
NOTE: The Government may delay issuing the Notice to Proceed not to exceed 140 days after award. Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD, is for Schedule No. 1 work.
DOCUMENT 00 11 00.00 45 Page 2
BID SCHEDULE (CONT'D)
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.2 Option No. 1
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 1
0009 DER Houston Ship Channel, PA 14 Retention Dike
7,200 LF $_________ $___________
0010 DER Borrow Houston Ship Channel Station 26+484 to 30+089 to PA 14
210,310 C.Y. $_________ $___________
0011 DER Borrow Houston Ship Channel Station 26+484 to 30+089 to M7/8/9 and M10
210,310 C.Y. $_________ $___________
TOTAL OPTION NO. 1 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________
NOTE FOR OPTION NO. 1: The Government may exercise this Option by written notice to the Contractor prior to completion of all authorized work at anytime but no later than 30 days prior to completion date of SCHEDULE NO.
1. Award of this Option is contingent upon availability of funds. An additional time of 50 calendar days will be added to this Contract for completion of this Option.
DOCUMENT 00 11 00.00 45 Page 3
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.3 Option No. 2
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 2
0012 Maintenance Dredging Bayport Channel Station 180+00 to 239+22 to M10
500,000 C.Y. $_________ $___________
TOTAL OPTION NO. 2 $___________
TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1 AND 2 $___________
NOTE FOR OPTION NO. 2: The Government may exercise this Option by written notice to the Contractor not later than 30 calendar days prior to the required completion date of all authorized work. Award of this Option is contingent upon availability of funds. An additional time of 60 calendar days will be added to this Contract for completion of this Option.
DOCUMENT 00 11 00.00 45 Page 4
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.4 Option No. 3
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 3
0013 Settlement Plates 1 JOB SUM $___________
TOTAL OPTION NO. 3 $___________
TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, AND 3 $___________
NOTE FOR OPTION NO. 3: The Government may exercise this Option by written notice to the Contractor no later than 30 days after issuance of Notice to Proceed. Award of this Option is contingent upon availability of funds.
No additional time will be added to this Contract for completion of this Option due to the work being done concurrent with Schedule No. 1.
DOCUMENT 00 11 00.00 45 Page 5
(TO BE ATTACHED TO STANDARD FORM 1442)
1.2 MODIFICATIONS (CESWG)
If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment of each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.
1.3 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
-- End of Document --
DOCUMENT 00 11 00.00 45 Page 6
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 LUMP SUM PAYMENT ITEMS
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.2.2 DER Gorini Marsh Circulation Channel
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.3 DER Seeding and Fertilizing
1.2.3.1 Payment
1.2.3.2 Unit of Measure
1.2.4 (AM#4)Settlement Plates
1.2.4.1 Payment
1.2.4.2 Unit of Measure
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 Dredging Maintenance Material
1.3.1.1 Payment
1.3.1.2 Dredging Partial Payment
1.3.1.3 Measurement
1.3.1.4 Government Surveys
1.3.1.5 Surveys During Progress of Work
1.3.1.6 Unit of Measure
1.3.2 Dredging New Work
1.3.2.1 Payment
1.3.2.2 Dredging Partial Payment
1.3.2.3 Measurement
1.3.2.4 Government Surveys
1.3.2.5 Surveys During Progress of Work
1.3.2.6 Unit of Measure
1.3.3 DER Shaping and Grading Atkinson Marsh Cells
1.3.3.1 Payment
1.3.3.2 Measurement
1.3.3.3 Unit of Measure
1.3.4 DER Houston Ship Channel, PA 14 Retention Dike
1.3.4.1 Payment
1.3.4.2 Measurement
1.3.4.3 Unit of Measure
1.3.5 DER Atkinson Marsh Cell Spillbox Removal
1.3.5.1 Payment
1.3.5.2 Unit of Measure
1.3.5.3 Unit of Measure
PART 2 PRODUCTS (Not Used)
SECTION 01 22 00.10 Page 1
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 22 00.10 Page 2
SECTION 01 22 00.10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Surveys; G
Submit drawings of surveys during progress of work by soundings or sweepings.
1.2 LUMP SUM PAYMENT ITEMS
Payment items for the work of this Contract for which Contract lump sum payments will be made are listed in the BID SCHEDULE and specified below.
All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for which separate payment is not otherwise provided.
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
Payment will be made for costs associated with "Mobilization and Demobilization", as defined in the SECTION 00 72 00 CONTRACT CLAUSES.
Payment for costs in connection with the plant necessary to perform the work, to include transportation and other costs incidental to delivery of the plant and other equipment to the general work area in condition ready for operation, and after completion of the work for removal of the plant and equipment from the work site.
1.2.1.2 Unit of Measure
Unit of measure: Job.
SECTION 01 22 00.10 Page 3
1.2.2 DER Gorini Marsh Circulation Channel
1.2.2.1 Payment
Payment will be made for costs associated with "DER Gorini Marsh Circulation Channel" in Schedule No. 1, which will include the costs necessary to excavate and restore circulation to the Gorini Marsh as specified in SECTION 35 20 23.16 45 PIPELINE DREDGING.
1.2.2.2 Unit of Measure
Unit of measure: Job.
1.2.3 DER Seeding and Fertilizing
1.2.3.1 Payment
Payment will be made for costs associated with "DER Seeding and Fertilizing" in Schedule No. 1, which will include the costs associated with site preparation, spreading, laying, fertilizing and watering the hydraulic fill dikes as specified in SECTION 32 92 19 SEEDING.
1.2.3.2 Unit of Measure
Unit of measure: Job.
1.2.4 (AM#4)Settlement Plates
1.2.4.1 Payment
Payment for "Settlement Plates" in Option No. 3, will be made for costs associated with plant, labor, material, and equipment necessary to complete the work as specified.
1.2.4.2 Unit of Measure
Unit of measure: Job.
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work in this Contract on which the Contract unit price payments will be made are listed in the BID SCHEDULE and specified below. The unit price and payment made for each item listed will constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, site erosion protection, clearing, removal of debris, stripping, drainage, foundation preparation, surveys and for performing the work required for each of the unit price items.
1.3.1 Dredging Maintenance Material
1.3.1.1 Payment
Payment for "Maintenance Dredging Bayport Ship Channel Station 150+00 to 239+22 to PA 15" in Schedule No. 1, and "Maintenance Dredging Bayport Channel Station 180+00 to 239+22 to M10" in Option No. 2, will be made for costs associated with the removal of dredged material, transportation, and placement at the Placement Area.
SECTION 01 22 00.10 Page 4
1.3.1.2 Dredging Partial Payment
Partial payment will be based on approximate quantities determined by fathometer soundings or sweepings taken behind the dredge. The Contractor may use its own hydrographic surveys to determine quantities for pay requests, but final quantities will be based on Government Before-Dredging and After-Dredging surveys.
1.3.1.3 Measurement
The material removed will be measured by cubic yard in place, by means of soundings taken before and after dredging. The total quantity of dredged material will be the theoretical quantity between the bottom surface shown by fathometer soundings of the last survey made "before-dredging" and the bottom surface shown by the fathometer soundings of a survey made "after-dredging", within the limits of the overdepth and side and end slopes, less deductions that may be required for misplaced material.
1.3.1.4 Government Surveys
The Government will use the tide staffs shown on the drawings for vertical control. Real Time Kinematic (RTK) or Virtual Reference Station (VRS) will not be used. Differential Global Positioning System (DGPS) will be used for horizontal control.
Processing survey data will be performed with HYPACK 2016 software using the Kingfisher Method (updated 5/6/2016). Volumes will be computed by average end area using cross sectional survey lines. Before and After Dredge cross sections will be run on 100-foot stations and at changes in the template. If the Contractor elects to use HYPACK 2016 software, the Government will provide the survey line files for the Contractor's use.
1.3.1.5 Surveys During Progress of Work
Contract depth will be determined by surveys taken behind the dredge as work progresses. The Contractor shall take progress soundings or sweepings.
1.3.1.6 Unit of Measure
Unit of measure: cubic yard.
1.3.2 Dredging New Work
1.3.2.1 Payment
Payment for "DER Borrow Bayport Ship Channel Station 211+15 to 239+22 to Atkinson Marsh Cells M7/8/9 and M10" in Schedule No. 1, and "DER Borrow Houston Ship Channel Station 26+484 to 30+089 to PA 14" in Option No. 1, and "DER Borrow Houston Ship Channel Station 26+484 to 30+089 to M7/8/9 and M10" in Option No. 1, will be made for costs associated with the borrow of dredged material, transportation, and placement at the Placement Area.
1.3.2.2 Dredging Partial Payment
Partial payment will be based on approximate quantities determined by fathometer soundings or sweepings taken behind the dredge. The Contractor may use its own hydrographic surveys to determine quantities for pay requests, but final quantities will be based on Government Before-Dredging
SECTION 01 22 00.10 Page 5 and After-Dredging surveys.
1.3.2.3 Measurement
The material removed will be measured by cubic yard in place, by means of soundings taken before and after dredging. The total quantity of dredged material will be the theoretical quantity between the bottom surface shown by fathometer soundings of the last survey made "before-dredging" and the bottom surface shown by the fathometer soundings of a survey made "after-dredging", within the limits of the overdepth and side and end slopes, less deductions that may be required for misplaced material.
1.3.2.4 Government Surveys
The Government will use the tide staffs shown on the drawings for vertical control. Real Time Kinematic (RTK) or Virtual Reference Station (VRS) will not be used. Differential Global Positioning System (DGPS) will be used for horizontal control.
Processing survey data will be performed with HYPACK 2016 software using the Kingfisher Method (updated 5/6/2016). Volumes will be computed by average end area using cross sectional survey lines. Before and After Dredge cross sections will be run on 100-foot stations and at changes in the template. If the Contractor elects to use HYPACK 2016 software, the Government will provide the survey line files for the Contractor's use.
1.3.2.5 Surveys During Progress of Work
Contract depth will be determined by surveys taken behind the dredge as work progresses. The Contractor shall take progress soundings or sweepings.
1.3.2.6 Unit of Measure
Unit of measure: cubic yard.
1.3.3 DER Shaping and Grading Atkinson Marsh Cells
1.3.3.1 Payment
Payment for "DER Shaping and Grading Atkinson Marsh Cell M7/8/9" and "DER Shaping and Grading Atkinson Marsh Cell M10" in Schedule No. 1 will be made for costs associated with final shaping and grading. Payment of 90 percent will be made upon completion of each 2,000 foot section meeting the requirements specified in SECTION 35 41 00 DIKE CONSTRUCTION. The remaining 10 percent will be paid upon acceptance of the completed dike.
1.3.3.2 Measurement
Shaping and grading of the rehabilitated dike of Atkinson Island Marsh Cell M7/8/9 and M10 will be measured for payment by the linear foot of dike measured along the centerline of the new dike to include completed dike that meets specified acceptance requirements as verified by surveys.
Portions of the dike that do not meet specified requirements will be subtracted from the measurement for payment, until the deficiency has been corrected and meets the acceptance requirements specified herein.
1.3.3.3 Unit of Measure
Unit of measure: linear foot
SECTION 01 22 00.10 Page 6
1.3.4 DER Houston Ship Channel, PA 14 Retention Dike
1.3.4.1 Payment
Payment for costs associated with "DER Houston Ship Channel, PA 14 Retention Dike" in Option No. 1, will be made by percentage completion of the total linear footage that meets the specified requirements shown on the Plans and specified in SECTION 35 41 00 DIKE CONSTRUCTION. Payment of 90 percent will be made upon completion of each approximate 3,600 linear foot section (northern and southern sections). The remaining 10 percent will be paid upon acceptance of the completed retention dikes. No separate payment will be made for borrow excavation, material or surface preparation prior to placement and construction of retention dike. No separate payment will be made for shaping and grading of the retention dike.
1.3.4.2 Measurement
Required PA 14 retention dikes will be measured for payment by linear foot percentage completion of linear footage of accepted dike as measured along the centerline of completed dike that meets specified acceptance requirements. Portions of the dike that do not meet specified requirements will be subtracted from the measurement for payment until the deficiency has been corrected and meets the acceptance requirements specified herein.
1.3.4.3 Unit of Measure
Unit of Measure: Linear Foot.
1.3.5 DER Atkinson Marsh Cell Spillbox Removal
1.3.5.1 Payment
Payment for "DER Atkinson Marsh Cell Spillbox" in Schedule No. 1, will be made for costs associated with removal of each spillbox, the plant, labor, material, and equipment necessary to complete the work as specified.
1.3.5.2 Unit of Measure
Measurement will be based on each spillbox removed.
1.3.5.3 Unit of Measure
Unit of measure: Each
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 01 22 00.10 Page 7
DIVISION 31 - EARTHWORK
SECTION 31 09 13.05 45
SETTLEMENT PLATES
PART 1 GENERAL
1.1 SUMMARY
1.2 MEASUREMENT AND PAYMENT
1.3 SUBMITTALS
PART 2 PRODUCTS
2.1 SETTLEMENT PLATE
PART 3 EXECUTION
3.1 SETTLEMENT PLATE INSTALLATION
3.1.1 General
3.1.2 Placement
3.2 PROTECTION
3.3 CONTRACTOR QUALITY CONTROL
3.3.1 Compliance Inspection
3.3.2 Reports
ATTACHMENTS:
"Typical Settlement Plate"
-- End of Section Table of Contents --
SECTION 31 09 13.05 45 Page 1
SECTION 31 09 13.05 45
SETTLEMENT PLATES
AMENDMENT NO. 0004
PART 1 GENERAL
1.1 SUMMARY
The work covered in this Section consists of furnishing plant, labor, material, and equipment required for installation of settlement plates.
Settlement plates will be installed in the newly constructed dikes M-7/8/9 and M-10. Three settlement plates will be installed per cross section, with three locations within each marsh cell dike for a total of 18 settlement plates. The exact locations will be identified by the Contracting Officer's Representative, but generally, the south, east and west sides on each marsh cell will be identified for installation. This work will also include the land surveying of the settlement plates at each installation.
1.2 MEASUREMENT AND PAYMENT
Measurement and payment for settlement plates will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND
PAYMENT.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with the SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Settlement Plate Fabrication; G
SD-04 Samples
Settlement Plate; G
Submit one settlement plate prior to delivery to the worksite.
After the sample is approved, the Contractor may use this plate for installation.
PART 2 PRODUCTS
2.1 SETTLEMENT PLATE
The settlement plate shall be as specified in the attached Figure, "Typical Settlement Plate". Submit Settlement Plate Fabrication shop drawings prior to fabricating. Submit one Settlement Plate sample.
SECTION 31 09 13.05 45 Page 2
PART 3 EXECUTION
3.1 SETTLEMENT PLATE INSTALLATION
3.1.1 General
After the completion of each one third of marsh cell dikes, the Contractor shall install three settlement plates: one at five feet from the interior dike crest, one at the mid slope to the interior, and one at the interior toe. This installation shall occur within 30 days of each sections substantial completion. These cross sectional installations shall be performed at each one third section of marsh cell dike, which will produce a total of 18 individual installations. The location shall be approved and directed by the Contracting Officer's Representative.
3.1.2 Placement
The settlement plates shall be installed at the completion of the dike construction, grading, and compaction operations in each section, as approved by the Contracting Officer's Representative. Plates shall be installed by excavating 24 inches into the finished dike, tamping a firm receiving foundation, and then by hand backfilling and tamping. The top of pipe of the settlement plate shall extend at least 2 feet above the dike grade.
The Contractor shall provide the Contracting Officer with field measurements of the installation to include a shop drawing of the fabrication and installation at each location and a survey of the horizontal and vertical location of the top of the settlement rod, at a minimum using the equivalent or better accuracy of an RTK surveying system utilizing a base station. Survey methods shall be the same as used for acceptance surveys of the dike. Indicate XYZ coordinates of each settlement plate on the Record Drawings.
3.2 PROTECTION
The Contractor shall take reasonable precautions to avoid damaging any of the settlement monitoring equipment. If the Contractor does damage any settlement equipment, it shall be their responsibility to replace this equipment at no cost to the Government.
3.3 CONTRACTOR QUALITY CONTROL
3.3.1 Compliance Inspection
Prior to placement, the Contractor shall inspect each settlement plate for damage or other defects.
3.3.2 Reports
Reports of the inspection activity and corrective action taken shall be submitted with the daily reports.
SECTION 31 09 13.05 45 Page 3
| Amend-0004_W9126G-16-B-0024 |
| SF30 PAGE 2 |
| SPECS |
| 00 11 00.00 45 - BID SCHEDULE |
| 01 22 00.10 - MEASUREMENT AND PAYMENT |
| 31 09 13.05 45 - SETTLEMENT PLATES |
File details come from the government source that posted it. Updated .