Amend_11_-_W9126G-13-R-0017.pdf
PDF 1 MB Posted
- Attached to
- Phase 2 Awardees
- Solicitation number
- W9126G-13-R-0017
About this file
Amendment 11 Fort Hood MATOC
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Ft_Hood_SB_MATOC_Pool_of_Contractors_POC_email_info.docx | DOCX document | |
| Phase_2_Participants_Revised_1April2014.docx | DOCX document | |
| Amend_13_-_W9126G-13-R-0017.pdf | ||
| Amend_12_-_W9126G-13-R-0017.pdf | ||
| Site_Visit_SLIDES_Hood_Bldg_52019.pdf | ||
| Site_Visit_Sign_in_Sheet_Hood_Bldg_52019.pdf | ||
| Amend_10_-_W9126G-13-R-0017.pdf | ||
| Amend_9_W9126G-13-R-0017.pdf | ||
| Phase_2_Participants_Revised_13Nov13.docx | DOCX document | |
| Seed_Task_Order_Appendices.zip | ZIP file | |
| MATOC_Appendices.zip | ZIP file | |
| am_8.pdf | ||
| Phase_2_Participants.docx | DOCX document | |
| Amend_7_Ft_Hood_MATOC.doc | DOC document | |
| Amend6_Ft_Hood_MATOC.pdf | ||
| Amend_5_W9126G-13-R-0017.pdf | ||
| Amend_4__03Apr13.pdf | ||
| Amend_3_W9126G-13-R-0017.pdf | ||
| Amendment_0001_W9126G-13-R-0017.pdf | ||
| Amendment_0002_W9126G-13-R-0017.pdf | ||
| Solicitation_W9126G13R0017.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The Solicitation W9126G-13-R-0017 for the Fort Hood Small Business IDIQ New MATOC FY13 is amended as follows:
See SF30 Continuation Sheet(s)
NOTE: The proposal receipt date is extended to 03 Jan 2014, 2:00 p.m., Central Time.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
W9126G-13-R0017
X 9B. DATED (SEE ITEM 11)
26-Feb-2013
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Dec-2013
CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A19
P.O. BOX 17300
FORT WORTH TX 76102-0300
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
W9126G-13-R-0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. Proposal Receipt Date: The proposal receipt date has been changed to 03 Jan 2014, 2:00 p.m. Central Time.
2. Bidder Inquiries: The ProjNet Bidder Inquiry Website will remain open for questions until 18 Dec 2013, 8:00 a.m. Central Time.
3. Replacement Sections: Replace the following sections in their entirety with the attached new sections, bearing the notation “W9126G-13-R-0017, Amendment No. 0011”.
MATOC CONTRACT SECTIONS
DIVISION 01 – GENERAL REQUIREMENTS
• 01 33 16 – DESIGN AFTER AWARD
4. Drawings: The following seed task order drawings in Appendix A have been replaced in their entirety with the attached new drawings, bearing the notation “W9126G-13-R-0017, Amendment No. 0011”.
• CD-100 – SITE DEMOLITION PLAN
• C-101 – SITE LAYOUT PLAN
End of Summary of Changes
Ft. Hood MATOC FHMATOC
SECTION 01 33 16
DESIGN AFTER AWARD
02/11
PART 1 GENERAL
1.1 INTRODUCTION
1.1.1. The information contained in this section applies to the design required after award. After award, the Contractor will develop the accepted proposal into the completed design, as described herein.
1.1.2. The Contractor may elect to fast track the design and construction that is, proceed with construction of parts of the sitework and facilities prior to completion of the overall design. To facilitate fast tracking, the Contractor may elect to divide the statement of work into no more than six
(6) design packages, at least one design package per item of work, single building, or group of buildings. A design package may be any portion of the project but a package shall include all drawings, specifications, design analysis, etc. for all design disciplines required for that portion. See Sections 01 33 00 SUBMITTAL PROCEDURES and 01 32 01.00 10 PROJECT SCHEDULE for requirements for identifying and scheduling the design packaging plan in the submittal register and project schedule. See also Sections 01 10 00 STATEMENT OF WORK and 01 57 20.00 10 ENVIRONMENTAL PROTECTION for any specified permit requirements. If early procurement of long-lead item construction materials or installed equipment, prior to completion of the associated design package, is necessary to facilitate the project schedule, the Contractor shall also identify those long-lead items and how it will assure design integrity of the associated design package to meet the contract requirements (The Contract consists of the Solicitation requirements and the accepted proposal). Once the Government is satisfied that the long-lead items meet the contract requirements, the Contracting Officer will allow the Contractor to procure the items at its own risk.
1.1.3. The Contractor may proceed with the construction work included in a separate design package after the Government has reviewed the final (100%) design submission for that package, review comments have been addressed and resolved to the Government's satisfaction and the Contracting Officer (or the Administrative Contracting Officer) has agreed that the design package may be released for construction.
1.1.4. INTEGRATED DESIGN. To the maximum extent permitted for this project, use a collaborative integrated design process for all stages of project delivery with comprehensive performance goals for siting energy, water, materials, and indoor enironmental quality and ensures incorporation of these goals. Consider all stages of the buiding lifecycle, including deconstruction.
1.2 DESIGNER OF RECORD
The Design-Build Contractor (“Design-Builder”, “D-B” or simply “Contractor”) shall identify, for approval, the Designer of Record (“DOR”) that will be responsible for each area of design. One DOR may be
SECTION 01 33 16 Page 1
W9126G-13-R-0017, Amendment No. 0011 responsible for more than one area. All areas of design disciplines shall be accounted for by a listed, Professional Registered, DOR. The DOR’s shall stamp, sign, and date each design drawing and other design deliverables under their responsible discipline at each design submittal stage (see contract clause Registration of Designers). If the deliverables are not ready for release for onstruction, they should be identified as "preliminary" or "not for release for construction" or by using some other appropriate designation. The DOR(s) shall also be responsible for maintaining the integrity of the design and for compliance with the contract requirements through construction and documentation of the as-built condition by coordination, review and approval of extensions of design, material, equipment and other construction submittals, review and approval or disapproval of requested deviations to the accepted design or to the contract, coordination with the Government of the above activities, and by performing other typical professional designer responsibilities.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 POST-AWARD ACTIVITIES & CONFERENCES
3.1.1 Design Quality Control Plan
The DB Contractor shall submit for Government acceptance, a Design Quality Control Plan in accordance with Section 01 45 04.00 10 CONTRACTOR QUALITY CONTROL before design may proceed.
3.1.2 Post Award Conference
3.1.2.1. The government will conduct a post award contract administration conference at the project site, as soon as possible after contract award.
This will be coordinated with issuance of the contract notice to proceed (NTP). The Contractor and major sub-contractor representatives shall participate. All designers need not attend this first meeting. Government representatives will include COE project delivery team members, facility users, facility command representatives, and installation representatives.
The Government will provide an agenda, meeting goals, meeting place, and meeting time to participants prior to the meeting.
3.1.2.2. The post award conference shall include determination and introduction of contact persons, their authorities, contract administration requirements, discussion of expected project progress processes, and coordination of subsequent meetings for quality control (see Section 01 45 01 USACE QUALITY CONTROL), Partnering (see below and SCR: Partnering), and the initial design conference (see below).
3.1.2.3. The government will introduce COE project delivery team members, facility users, facility command representatives, and installation representatives. The DB Contractor shall introduce major subcontractors, and other needed staff. Expectations and duties of each person shall be defined for all participants. A meeting roster shall be developed and distributed by the government with complete contact information including name, office, project role, phone, mailing and physical address, and email address.
3.1.3 Partnering & Project Progress Processes
3.1.3.1. The initial Partnering conference may be scheduled and conducted
SECTION 01 33 16 Page 2 at any time with or following the post award conference. The Government proposes to form a partnership with the DB Contractor to develop a cohesive building team. This partnership will involve the COE project delivery team members, facility users, facility command representatives, installation representatives, Designers of Record, major subcontractors, contractor quality control staff, and contractor construction management staff. This partnership will strive to develop a cooperative management team drawing on the strengths of each team member in an effort to achieve a quality project within budget and on schedule. This partnership will be bilateral in membership and participation will be totally voluntary. All costs, excluding labor and travel expenses, shall be shared equally between the Government and the Contractor. The Contractor and Government shall be responsible for their own labor and travel costs. Normally, partnering meetings will be held at or in the vicinity of the project installation.
3.1.3.2. As part of the partnering process, the Government and Contractor shall develop, establish, and agree to comprehensive design development processes including conduct of conferences, expectations of design development at conferences, fast-tracking, design acceptance, Structural Interior Design (SID)/ Furniture, Fixtures & Equipment (FF&E) design approval, project closeout, etc. The government will explain contract requirements and the DB Contractor shall review their proposed project schedule and suggest ways to streamline processes.
3.1.4 Initial Design Conference
The initial design conference may be scheduled and conducted at the project installation any time after the post award conference, although it is recommended that the partnering process be initiated with or before the initial design conference. Any design work conducted after award and prior to this conference should be limited to site and is discouraged for other items. All Designers of Record shall participate in the conference. The purpose of the meeting is to introduce everyone and to make sure any needs the contractor has are assigned and due dates established as well as who will get the information. <AM#11> See also Attachment F, BUILDING INFORMATION MODELING REQUIREMENTS for discussion concerning the BIM Implementation Plan demonstration at this meeting. </AM#11> The DB Contractor shall conduct the initial design conference.
3.1.5 Pre-Construction Conference
Before starting construction activities, the Contractor and Government will jointly conduct a pre-construction administrative conference to discuss any outstanding requirements and to review local installation requirements for start of construction. It is possible there will be multiple Pre-Construction Conferences based on the content of the design packages selected by the Contractor. The Government will provide minutes of this meeting to all participants. The preconstruction conference can be held concurrently with the post-award conference if construction is anticipated to start soon. See Section 01 31 00.00 44 PROJECT MEETINGS for additional requirements.
3.2 STAGES OF DESIGN SUBMITTALS AND OVER THE SHOULDER PROGRESS REVIEWS
The stages of design submittals described below define Government expectations with respect to process and content. The Contractor shall determine how to best plan and execute the design and review process for this project, within the parameters listed below. As a minimum, the Government expects to see at least one interim design submittal, at least
SECTION 01 33 16 Page 3 one final design submittal before construction of a design package may proceed and at least one Design Complete submittal that documents the accepted design. The Contractor may sub-divide the design into separate packages for each stage of design and may proceed with construction of a package after the Government accepts the final design for that package. See also discussion on waivers to submission of one or more intermediate design packages where the parties partner during the design process. <AM#11>See also Attachment F, BUILDING INFORMATION MODELING REQUIREMENTS for discussion concerning BIM and the various stages of design submittals and over-the-shoulder progress reviews</AM#11>
3.2.1 Site/Utilities
To facilitate fast-track design-construction activities the contractor may submit a final (100%) site and utility design as the first design submittal or it may elect to submit interim and final site and utility design submittals as explained below. Following review, resolution, and incorporation of all Government comments, and submittal of a satisfactory set of site/utility design documents, after completing all other pre-construction requirements in this contract and after the pre-construction meeting, the Government will allow the Contractor to proceed with site development activities, including demolition where applicable, within the parameters set forth in the accepted design submittal. For the first site and utility design submission, whether an interim or final, the submittal review, comment, and resolution times from this specification apply, except that the Contractor shall allow the Government a 14 calendar day review period, exclusive of mailing time. No on-site construction activities shall begin prior to written Government clearance to proceed.
3.2.2 Interim Design Submittals
The Contractor may submit either a single interim design for review, representing a complete package with all design disciplines, or split the interim design into smaller, individual design packages as it deems necessary for fast-track construction purposes. As required in Section 01 32 01.00 10 PROJECT SCHEDULE, the Contractor shall schedule its design and construction packaging plan to meet the contract completion period. This submission is the Government's primary opportunity to review the design for conformance to the solicitation and to the accepted contract proposal and to the Building Codes at a point where required revisions may be still made, while minimizing lost design effort to keep the design on track with the contract requirements. The requirements for the interim design review submittals and review conferences are described hereinafter. This is not necessarily a hold point for the design process; the Contractor may designate the interim design submittal(s) as a snapshot and proceed with design development at its own risk. See below for a waiver, where the parties establish an effective over-the-shoulder progress review procedure through the partnering process that would eliminate the need for or expedite a formal intermediate design review on one or more individual design packages.
3.2.3 Over-the-Shoulder Progress Reviews
To facilitate a streamlined design-build process, the Government and the Contractor may agree to one-on-one reviewer or small group reviews, electronically, on-line (if available within the Contractor's standard design practices) or at the Contractor's design offices or other agreed location, when practicable to the parties. The Government and Contractor
SECTION 01 33 16 Page 4 will coordinate such reviews to minimize or eliminate disruptions to the design process. Any data required for these reviews shall normally be provided in electronic format, rather than in hard copy. If the Government and Contractor establish and implement an effective, mutually agreeable partnering procedure for regular (e.g., weekly) over-the shoulder review procedures that allow the Government reviewers the opportunity to keep fully informed of the progress, contents, design intent, design documentation, etc. of the design package, the Government will agree to waive or to expedite the formal intermediate design review period for that package. The Contractor shall still be required to submit the required intermediate design documentation, however the parties may agree to how that material will be provided, in lieu of a formal consolidated submission of the package. It should be noted that Government funding is extremely limited for non-local travel by design reviewers, so the maximum use of virtual teaming methods must be used. Some possible examples include electronic file sharing, interactive software with on-line or telephonic conferencing, televideo conferencing, etc. The Government must still perform its Code and Contract conformance reviews, so the Contractor is encouraged to partner with the reviewers to find ways to facilitate this process and to facilitate meeting or bettering the design-build schedule.
The Contractor shall maintain a fully functional configuration management system as described herein to track design revisions, regardless of whether or not there is a need for a formal intermediate design review. The formal intermediate review procedures shall form the contractual basis for the official schedule, in the event that the partnering process determines that the formal intermediate review process to be best suited for efficient project execution. However, the Government pledges to support and promote the partnering process to work with the Contractor to find ways to better the design schedule.
3.2.4 Final Design Submissions
This submittal is required for each design package prior to Government acceptance of that design package for construction. The requirements for the final design submittal review conferences and the Government's acceptance for start of construction are described herein after.
3.2.5 Design Complete Submittals
After the final design submission and review conference for a design package, the Contractor shall revise the design package to incorporate the comments generated and resolved in the final review conferences, perform and document a back-check review and submit the final, design complete documents, which shall represent released for construction documents. The requirements for the design complete submittals are described hereinafter.
3.2.6 Holiday Periods for Government Review or Actions
The Contractor shall not schedule meetings, Government reviews or responses during the last two weeks of December or other designated Government Holidays (including Friday after Thanksgiving) and shall exclude such dates and periods from any durations specified herein for Government actions.
3.2.7 Late Submittals and Reviews
If the Contractor cannot meet its scheduled submittal date for a design package, it must revise the proposed submittal date and notify the
SECTION 01 33 16 Page 5 government in writing, at least one (1) week prior to the submittal, in order to accommodate the Government reviewers’ other scheduled activities.
If a design submittal is over one (1) day late in accordance with the latest revised design schedule, or if notification of a proposed design schedule change is less than seven (7) days from the anticipated design submission receipt date, the Government review period may be extended up to seven (7) days due to reviewers’ schedule conflicts. If the Government is late in meeting its review commitment and the delay increases the Contractor’s cost or delays completion of the project, the Suspension of Work and Defaults clauses provide the respective remedy or relief for the delay.
3.3 DESIGN CONFIGURATION MANAGEMENT
3.3.1 Procedures
The Contractor shall develop and maintain effective, acceptable design configuration management (DCM) procedures to control and track all revisions to the design documents after the Interim Design Submission through submission of the As-Built documents. During the design process, this will facilitate and help streamline the design and review schedule.
After the final design is accepted, this process provides control of and documents revisions to the accepted design (See Special Contract Requirement: Deviating From the Accepted Design). The system shall include appropriate authorities and concurrences to authorize revisions, including documentation as to why the revision must be made. The DCM data shall be available to the Government reviewers at all times. The Contractor may use its own internal system with interactive Government concurrences, where necessary or may use the Government's “DrChecks Design Review and Checking System” (see below and Attachment C).
3.3.2 Tracking Design Review Comments
Although the Contractor may use its own internal system for overall design configuration management, the Government and the Contractor shall use the DrChecks Design Review and Checking System to initiate, respond to, resolve and track Government design compliance review comments. This system may be useful for other data which needs to be interactive or otherwise available for shared use and retrieval. See Attachment C for details on how to establish an account and set-up the DrChecks system for use on the project.
3.3.3 Design and Code Checklists
The Contractor shall develop and complete various discipline-specific checklists to be used during the design and quality control of each submittal. These completed checklists shall be submitted with each design submittal, as applicable, as part of the project documentation. See Section 01 45 00.00 10 QUALITY CONTROL. For sample checklists, see Section 01 33
16, ATTACHMENT D - SAMPLE FIRE PROTECTION AND LIFE SAFETY CODE REVIEW
checklist, and within the U.S. Green Building Council website at http://www.usgbc.org/ for the LEED checklist.
3.4 INTERIM DESIGN REVIEWS AND CONFERENCES
3.4.1 General
At least one interim design submittal, review and review conference is required for each design package (except that, per paragraph 3.2.1, the Contractor may skip the interim design submission and proceed directly to
SECTION 01 33 16 Page 6 final design on the sitework and utilities package). The DB Contractor may include additional interim design conferences or over-the-shoulder reviews, as needed, to assure continued government concurrence with the design work.
The interim submittal review periods and conferences shall be included in the project schedule and shall indicate what part of the design work is at what percentage of completion. The required interim design conferences shall be held when interim design requirements are reached as described below. See also Paragraph: Over-the-Shoulder Progress Reviews for a waiver to the formal interim design review.
3.4.2 Procedures
After receipt of an Interim Design submission, the Contractor shall allow the Government fourteen (14) calendar days after receipt of the submission to review and comment on the interim design submittal. For smaller design packages, especially those that involve only one or a few separate design disciplines, the parties may agree on a shorter review period or alternative review methods (e.g., over-the –shoulder or electronic file sharing), through the partnering process. For each interim design review submittal, the COR will furnish, to the Contractor, a single consolidated, validated listing of all comments from the various design sections and from other concerned agencies involved in the review process using the DrChecks Design Review and Checking System. The review will be for conformance with the technical requirements of the solicitation and the Contractor's RFP proposal. If the Contractor disagrees technically with any comment or comments and does not intend to comply with the comment, he/she must clearly outline, with ample justification, the reasons for noncompliance within five (5) days after receipt of these comments in order that the comment can be resolved. The Contractor shall furnish disposition of all comments, in writing, through DrChecks. The Contractor is cautioned that if it believes the action required by any comment exceeds the requirements of this contract, that it should take no action and notify the COR in writing immediately. The Interim Review conference will be held for each design submittal at the installation. The Contractor shall bring the personnel that developed the design submittal to the review conference. The conference will take place the week after the receipt of the comments by the Contractor. For smaller fast-track packages that involve only a few reviewers, the parties may agree to alternative conferencing methods, such as teleconferencing, or televideo, where available, as determined through Partnering.
3.4.3 Conference Documentation
3.4.3.1. In order to facilitate and accelerate the Government code and contract conformance reviews, the Contractor shall identify, track resolution of and maintain all comments and action items generated during the design process and make this available to the designers and reviewers prior to the Interim and subsequent design reviews.
3.4.3.2. The DB Contractor shall prepare meeting minutes and shall enter final resolution of all comments into DrChecks. Copies of comments, annotated with comment action agreed on, will be made available to all parties before the conference adjourns. Unresolved problems will be resolved by immediate follow-on action at the end of conferences. Valid comments shall be incorporated. The Government reserves the right to reject design document submittals if comments are significant. Participants shall determine if any comments are critical enough to require further design development prior to government concurrence. Participants shall also determine how to proceed in order to obtain government concurrence with the
SECTION 01 33 16 Page 7 design work presented.
3.5 INTERIM DESIGN REQUIREMENTS
Interim design deliverables shall include drawings, specifications, and design analysis for the part of design that the DB Contractor considers ready for review.
3.5.1 Drawings
Drawings shall include comments from any previous design conferences incorporated into the documents to provide an interim design for the “part” submitted.
3.5.2 Design Analyses
3.5.2.1 The designers of record shall prepare and present design analyses with calculations necessary to substantiate and support all design documents submitted. Address design substantiation required by the applicable codes and references and pay particular attention to the following listed items:
3.5.2.2 For parts including sitework, include site specific civil calculations.
3.5.2.3 For parts including structural work, include structural calculations.
(a) Identify all loads to be used for design.
(b) Describe the method of providing lateral stability for the structural system to meet seismic and wind load requirements. Include sufficient calculations to verify the adequacy of the method.
(c) Provide calculations for all principal roof, floor, and foundation members and bracing and secondary members.
(d) Provide complete seismic analyses for all building structural, mechanical, electrical, architectural, and building features as dictated by the seismic zone for which the facility is being constructed.
(e) (e) Computer generated calculations must identify the program name, source, and version. Provide input data, including loads, loading diagrams, node diagrams, and adequate documentation to illustrate the design. The schematic models used for input must show, as a minimum, nodes/joints, element/members, materials/properties, and all loadings, induced ettlements/deflections, etc., and a list of load combinations.
Include an output listing for maximum/minimum stresses/forces and deflections for each element and the reactions for each loading case and combination.
3.5.2.4 For Security (Anti-Terrorism): Provide a design narrative and calculations where applicable, demonstrating compliance with each of the 22 standards in UFC 4-010-01 which includes Design of Buildings to Resist Progressive Collapse (use the most recent version of UFC 4-023-03, regardless of references to any specific version in UFC 4-010-01). Where sufficient standoff distance is not being provided, show calculations for blast resistance of the structural system and building envelope. Show
SECTION 01 33 16 Page 8 complete calculations for members subjected to ATFP loads, e.g., support members of glazed items (jambs, headers, sills), connections of windows to support members and connections of support members to the rest of the structure. For 3 story and higher buildings, provide calculations to demonstrate compliance with progressive collapse requirements.
3.5.2.5 For parts including architectural work, include building floor area analysis.
3.5.2.6 For parts including mechanical work, include HVAC analysis and calculations. Include complete design calculations for mechanical systems.
Include computations for sizing equipment, compressed air systems, air duct design, and U-factors for ceilings, roofs and exterior walls and floors. Contractor shall employ commercially available energy analysis techniques to determine the energy performance of all passive systems and features. Use of hourly energy load computer simulation is required (see paragraph 3.5.5.2 for list of acceptable software). Based on the results of calculations, provide a complete list of the materials and equipment proposed with the manufacturer's published cataloged product installation specifications and roughing-in data.
3.5.2.7 For parts including life safety, include building code analysis and sprinkler and other suppression systems. Notwithstanding the requirements of the Codes, address the following:
(a) A registered fire protection engineer (FPE) must perform all fire protection analyses. Provide the fire protection engineer’s qualifications. NICET certification is not sufficient to address this requirement. A registered fire protection engineer is a professional engineer who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveys (NCEES).
(b) Provide all references used in the design including Government design documents and industry standards used to generate the fire protection analysis.
(c) Provide classification of each building in accordance with fire zone, building floor areas and height and number of stories.
(d) Provide discussion and description of required fire protection requirements including extinguishing equipment, detection equipment, alarm equipment and water supply. Alarm and detection equipment shall interface to requirements of Electronic Systems.
(e) Provide hydraulic calculations based on water flow test for each sprinkler system to insure that flow and pressure requirements can be met with current water supply. Include copies of Contractor's water flow testing done to certify the available water source.
3.5.2.8 For parts including plumbing systems:
(a) List all references used in the design.
(b) Provide justification and brief description of the types of plumbing fixtures, piping materials and equipment proposed for use.
(c) Detail calculations for systems such as sizing of domestic hot
SECTION 01 33 16 Page 9 water heater and piping; natural gas piping; LP gas piping and tanks, fuel oil piping and tanks, etc., as applicable.
(d) When the geotechnical report indicates expansive soils are present, indicate in the first piping design submittal how piping systems will be protected against damage or backfall/backflow due to soil heave (from penetration of slab to the 5 foot building line). 3.5.2.9 For elevator systems:
(a) List all criteria codes, documents and design conditions used.
(b) List any required permits and registrations for construction of items of special mechanical systems and equipment.
3.5.2.10 For parts including electrical work, include lighting calculations to determine maintained footcandle levels, electrical load analysis and calculations, electrical short circuit and protective device coordination analysis and calculations and arc fault calculations.
3.5.2.11 For parts including telecommunications voice/data (including SIPRNET, where applicable), include analysis for determining the number and placement of outlets.
3.5.2.12 For Cathodic Protection Systems, provide the following stamped report by the licensed corrosion engineer or NACE specialist with the first design submission. The designer must be qualified to engage in the praactice of corrosion control of buried or submerged metallic surfaces.
He/she must be accredited or certified by the National Association of Corrosion Engineers (NACE) as a NACE Accreditied Corrosion Specialist or a NACE certified Cathodic Protection Specialist, or must be a registered professional engineer with a minimum of five years experience in corrosion control and cathodic protection. Clearly describe structures, systems or components in soil or water to be protected. Describe methods proposed for protection of each.
3.5.2.13 Air Barrier System: Provide a narrative of the design and installation requirements for the Air Barrier system. As part of the design quality control process an air barrier consultant shall review drawing details to assure that details of critical Air Barrier components are properly detailed and incorporated during the design drawings and process (i.e. window flashing details, penetration in air barrier details, door flashing details, roofing/ceiling barrier interface details and etc.).
Furnish the Government written review details and results.
3.5.3 Geotechnical Investigations and Reports:
3.5.3.1 The contractor’s licensed geotechnical engineer shall prepare a final geotechnical evaluation report, to be submitted along with the first foundation design submittal. This information should be made available as early as possible during the over-the-shoulder progress review process. The geotechnical report shall summarize the subsurface conditions and provide recommendations for the design of appropriate utilities, foundations, floor slabs, retaining walls, embankments, and pavements. The Contractor’s geotechnical report shall recommend foundation systems to be used, allowable bearing pressures for footings, lateral load resistance capacities for foundation systems, elevations for footings, grade beams, slabs, etc. Provide an assessment of post-construction settlement potential including total and differential. Provide recommendations regarding lateral
SECTION 01 33 16 Page 10 earth pressures (active, at-rest, passive) to be used in the design of retaining walls. Include the recommended spectral accelerations and Site Class for seismic design along with an evaluation of any seismic hazards and recommendations for mitigation, if required. Include calculations to support the recommendations for bearing capacity, settlement, and pavement sections. Include supporting documentation for all recommended design parameters such as Site Class, shear strength, earth pressure coefficients, friction factors, subgrade modulus, California Bearing Ratio (CBR), etc.
Provide earthwork recommendations, expected frost penetration, expected groundwater levels, recommendations for dewatering and groundwater control and the possible presence of any surface or subsurface features that may affect the construction of the project such as sinkholes, boulders, shallow rock, old fill, old structures, soft areas, or unusual soil conditions.
Include pH tests, salinity tests, resistivity measurements, etc., required to design corrosion control and grounding systems. Include the raw field data. Arrange a meeting with the Government subsequent to completion and evaluation of the site specific geotechnical exploration to outline any differences encountered that are inconsistent with the Government provided preliminary soils information. Clearly outline differences which require changes in the foundation type, or pavement and earthwork requirements from that possible and contemplated using the Government furnished preliminary soils investigation, which result in a change to the design or onstruction.
Any equitable adjustment is subject to the provisions of the contract’s Differing Site Conditions Clause.
3.5.3.2 Vehicle Pavements: The Contractor’s geotechnical report shall contain flexible and rigid pavement designs, as applicable for the project, including design CBR and modulus of subgrade reaction and the required compaction effort for subgrades and pavement layers. Provide Information on the types of base course materials available in the area and design strengths.
3.5.3.3 The DB Contractor and the professional geotechnical engineer consultant shall certify in writing that the design of the project has been developed consistent with the Contractor’s final geotechnical report. The certification shall be stamped by the consulting professional geotechnical engineer and shall be submitted with the first design submission. If revisions are made to the initial design submission, a new certification shall be provided with the final design submission.
3.5.4 LEED Documentation:
The Contractor shall register the project in LEED. Assign a LEED Accredited Professional, responsible to track LEED planning, performance and documentation for each LEED credit through construction closeout.
Incorporate LEED credits in the plans, specifications and design analyses. Develop LEED supporting documentation as a separable portion of the Design Analysis and provide with each required design submittal.
Include the LEED Project checklist for each non-exempt facility (one checklist may be provided for multiple facilities in accordance with the LEED-NC Application Guide for Multiple Buildings and On-Campus Building Projects and the LEED 3.0 Documentation Requirements and Submittals Checklist (Attachment E, herein) with each submittal. Final design submittal for each portion of the work must include all required design documentation relating to that portion of work (example - all site credit design documents with final site design). Submittal requirements are as indicated in Attachment E, LEED 3.0 Documentation Requirements and Submittals Checklist. Submit all documentation indicated on Attachment E as due at final design at final design submittal (for fast-track projects with
SECTION 01 33 16 Page 11 multiple final design submittals, this shall be at the last scheduled final design submittal). All project documentation related to LEED shall conform to USGBC requirements for both content and format, including audit requirements and be separate from other design analyses. Maintain and update the LEED documentation throughout project progress to construction closeout and shall compile product data, receipts, calculations and other data necessary to substantiate and support all credits claimed. The Government may audit any or all individual credits.
Audit documentation is not required to be submitted unless requested. These requirements apply to all projects. If the project requires the Contractor to obtain USGBC certification, the Contractor shall also be responsible for obtaining USGBC certification and shall provide written evidence of certification with the construction closeout LEED documentation submittal. Install the USGBC building plaque at the location indicated by the Government upon receipt. If Contractor obtains USGBC interim design review, submit the USGBC review to the Government within 30 days of receipt for information only.
3.5.4.1 LEED Documentation for Technology Solution Set. “If the Solicitation provides a Prescriptive Technology Solution Set, use of the Technology Solution set has no effect on LEED documentation requirements.
Provide all required LEED documentation, including energy analysis, in accordance with LEED requirements when using the Technology Solution Set.”
3.5.5 Energy Conservation:
3.5.5.1 Interim and Final Design submittals shall demonstrate that each building including the building envelope, HVAC systems, service water heating, power, and lighting systems meet the Mandatory Provisions and the Prescriptive Path requirements of ASHRAE 90.1-2004. Use Compliance Documentation forms available from ASHRAE and included in the ASHRAE 90.1-2007 User’s Manual for this purpose. The Architectural Section of the Design Analysis shall include completed forms titled “Building Envelope Compliance Documentation Parts I and II”. The Heating Ventilating and Air Conditioning (HVAC) Section of the Design Analysis shall include a completed form titled “HVAC Simplified Approach Option - Part I” if this approach is allowed by the Standard. Otherwise, the HVAC Section of the Design Analysis shall include completed forms titled “HVAC Mandatory Provisions - Part II” and “HVAC Prescriptive Requirements - Part III”. The Plumbing Section of the Design Analysis shall include a completed form titled “Service Water Heating Compliance Documentation”. The Electrical Section of the Design Analysis shall include an explanatory statement on how the requirements of ASHRAE 90.1-2007 Chapter 8 Power were met. The Electrical Section of the Design Analysis shall also include a completed form titled “Lighting Compliance Documentation”.
3.5.5.2 Interim and Final Design submittals which address energy consuming systems, (heating, cooling, service hot water, lighting, power, etc.) must also include calculations in a separate Energy Conservation Section of the Design Analysis which demonstrate and document (a) the baseline energy consumption for the facility or facilities under contract, that would meet the requirements of ANSI/ASHRAE/IESNA Standard 90.1-2004 and (b) the energy consumption of the facility or facilities under contract utilizing the materials and methods required by this construction contract. Use the USGBC Energy and Atmosphere (EA) Credit 1 compliance template / form or an equivalently detailed form for documenting compliance with the energy reduction requirements. This template / form is titled PERFORMANCE RATING METHOD and is available when the project is registered for LEED. The calculation methodology used for this documentation and analysis shall
SECTION 01 33 16 Page 12 follow the guidelines set forth in Appendix G of ASHRAE 90.1-2004, with two exceptions: a) receptacle and process loads may be omitted from the calculation; and b) the definition of the terms in the formula for Percentage Improvement found in paragraph G1.2 are modified as follows:
Baseline Building Performance shall mean the annual energy consumption calculated for a building design intended for use as a baseline for rating above standard design meeting the minimum requirements of the energy standard, and Proposed Building Performance shall mean annual energy consumption calculated for the proposed building design intended for construction. This calculation shall address all energy consuming systems in a single integrated methodology. Include laboratory fume hoods and kitchen ventilation loads in the energy calculation. They are not considered process loads. Individual calculations for heating, cooling, power, lighting, power, etc. systems will not be acceptable. The following building simulation software is acceptable for use in calculating building energy consumption: Hourly Analysis Program (HAP) by Carrier Corp., TRACE 700 by Trane Corp., DOE-2 by US Department of Energy, EnergyPlus by DOD/DOE.
3.5.6 Specifications
Specifications may be any one of the major, well known master guide specification sources (use only one source) such as MASTERSPEC from the American Institute of Architects, SPECTEXT from Construction Specification Institute or Unified Facility Guide Specifications (UFGS using MASTERFORMAT 2004 numbering system), etc. (including specifications from these sources).
Manufacturers’ product specifications, utilizing CSI’s Manu-Spec, three part format may be used in conjunction with the selected specifications.
The designers of record shall edit and expand the appropriate Specifications to insure that all project design requirements, current code requirements, and regulatory requirements are met. Specifications shall clearly identify, where appropriate, specific products chosen to meet the contract requirements (i.e., manufacturers’ brand names and model numbers or similar product information).
3.5.7 Building Rendering
DB Contractor shall present and provide a draft color computer, artist, or hand drawn rendering with the conceptual design submittal of the building exterior. Perspective renderings shall include a slightly overhead view of the entire building to encompass elevations and the roof configuration of the building. After Government review and acceptance, provide a final rendering, including the following:
Three (3) 18” x 24” color prints, framed and matted behind glass with project title underneath the print. One (1) Image file (high resolution) in JPG format on CD for those in the submittal distribution list.
3.5.8 Interim Building Design Contents
The following list represents what the Government considers should be included in the overall completed design for a facility or project. It is not intended to limit the contractor from providing different or additional information as needed to support the design presented, including the require design analyses discussed above. As the Contractor develops individual design packages and submits them for Interim review, include as much of the applicable information for an individual design package as is developed at the Interim design level for review purposes. These pieces shall be developed as the design progresses toward the design complete
SECTION 01 33 16 Page 13 stage.
3.5.8.1 Lawn and Landscaping Irrigation System
3.5.8.2 Landscape, Planting and Turfing
3.5.8.3 Architectural
(a) Design Narrative
(b) Architectural Floor Plans, Typical Wall and Roof Sections, Elevations
(c) Finish schedule
(d) All required equipment
(e) Special graphics requirements
(f) Door and Window Schedules
(g) Hardware sets using BHMA designations
(h) Composite floor plan showing all pre-wired workstations
(i) Structural Interior Design (SID) package: See ATTACHMENT A for specific requirements
(j) Furniture, Fixtures & Equipment (FF&E) design package: See ATTACHMENT B for specific requirements
(k) Air Barrier Design: Details of all Air Barrier components, (i.e.
window flashing details, penetrations in air barrier details, door flashing details, roofing/ceiling barrier interface details and etc.)
3.5.8.4 Structural Systems. Include:
(a) Drawings showing principal members for roof and floor framing plans as applicable
(b) Foundation plan showing main foundation elements where applicable
(c) Typical sections for roof, floor, and foundation conditions
3.5.8.5 Plumbing Systems
(a) Show locations and general arrangement of plumbing fixtures and major equipment
(b) Plan and isometric riser diagrams of all areas including hot water, cold water, waste and vent piping. Include natural gas (and meter as required), (natural gas and meter as required), (LP gas), (fuel oil) and other specialty systems as applicable.
(c) Include equipment and fixture connection schedules with descriptions, capacities, locations, connection sizes and other information as required
3.5.8.6 HVAC Systems
(a) Mechanical Floor Plans: The floor plans shall show all principle architectural features of the building which will affect the mechanical design. The floor plans shall also show the following:
(1) Room designations.
(2) Mechanical legend and applicable notes.
(3) Location and size of all ductwork and piping.
(4) Location and capacity of all terminal units (i.e., registers, diffusers, grilles, hydronic baseboards).
(5) Pre-Fabricated Paint Spray Booth (where applicable to project scope)
(6) Paint Preparation Area (where applicable to project scope)
SECTION 01 33 16 Page 14
(7) Exhaust fans and specialized exhaust systems.
(8) Thermostat location.
(9) Location of heating/cooling plant (i.e., boiler, chiller, cooling tower, ect).
(10) Location of all air handling equipment.
(11) Air balancing information.
(12) Flue size and location.
(13) Piping diagram for forced hot water system (if used).
(b) Equipment Schedule: Provide…