F8F3CE6021A001 UCTL012047
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0004 to Solicitation W9124X-16-B-0001, Project UCTL 012047, Repair Operations Facility, Building 84, located in Reno, Nevada, is as follow s:
(Continued on Page 2)
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Aug-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9124X-16-B-0001
X 9B. DATED (SEE ITEM 11)
11-Jul-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Aug-2016
CODE
PURCHASING AND CONTRACTING
2452 FAIRVIEW DR.
CARSON CITY NV 89701
W9124X 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9124X-16-B-0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 4
The following items are applicable to this modification:
1. ATTACHMENT #1 INCLUDES QUESTIONS AND GOVERNMENT'S RESPONSES TO RFI 010.
2. ATTACHMENT #2 INCLUDES DRAWING REVISIONS AS APPLICABLE.
3. ALL OTHER TERMS OF THE SOLICITATION REMAIN UNCHANGED.
W9124X-16-B-0001
(End of Summary of Changes)
RFI 010
QUESTION:
Drawing E101-103
1. Wood Pole 7 and Pole 6-1 will become dead ends and should have a new anchor and down guy installed----please provide a detail if required.
ANSWER:
These poles shall be guyed per NV Energy standard CP0001M, section 11 (attached). Pole shall be guyed at 75ft or greater.
2. Please provide a MV trench detail.
See attached detail sheet E503.
3. Please provide a MV switch pad detail.
4. Please provide a transformer pad detail.
5. Please provide a detail for the two overhead to underground dips/risers for Pole
7 and Pole 6-1 (cross arms, cutouts, arrestors, etc.?) These two poles will need to be re-framed from tangents to dead ends.
6. Is there a one line of the existing 4kv system available?
See attached plans for NVANG 5KV Electrical Distribution System.
| Amendment 0004 - W9124X-16-B-0001 |
| ATTACHMENT 1 |
| ATTACHMENT 2 |
| Text1: ATTACHMENT 1 |
| DRAWING SCHEDULE: |
| i5: |
| ElECTAICAl LEGEND: |
| am: |
| I: |
| undefined: |
| undefined_2: |
| rr: |
| undefined_3: |
| undefined_4: |
| undefined_5: |
| undefined_6: |
| undefined_7: |
| CD: |
| a: |
| fill_23: |
| fill_24: |
| undefined_8: |
| undefined_9: |
| undefined_10: |
| MOW: |
| undefined_11: |
| lllClf11: |
| c: |
| undefined_12: |
| undefined_13: |
| c_2: |
| undefined_14: |
| undefined_15: |
| Text11111: ATTACHMENT 2 |
| undefined_16: |
| undefined_17: |
| i: |