AV Project GFE Equipment.docx
DOCX document 17 KB Posted
- Attached to
- Audio Visual Equipment Purchase and Installation Federal contract opportunity
- Solicitation number
- W9124X-11-R-0005
About this file
Government Furnished Equipment
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Intel AV Questions and Answers.docx | DOCX document | |
| INTEL FACILITY Cross Section.pdf | ||
| AV Building 600 Second Floor.vsd | VSD drawing | |
| Bld 600 Ops Floor AV PWS 20110729.doc | DOC document | |
| Synopsis - Solicitation.docx | DOCX document | |
| Site Visit.docx | DOCX document | |
| Bld 600 Ops Floor AV PWS 20110729 | — | |
| Synopsis - Solicitation.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
This Document Is To Aid In Planning Only and Information Is Approximate GFE Equipment:
Room 213: Operations Floor ** 12 Computers (DVI-D), (16 outputs)
* 2ea Television: Sharp Aquos 65” Plasma, LC-65SE94U ** 8ea Projectors: Panasonic PT-D5700U
| * 20ea Speakers: JBL, Model- Control 26 CT (Integrate 5 into each quadrant) |
| Total Out/In needed: 16/22 |
Room 217: Server Room ** 2ea Computers (DVI-D) ** 1ea Ethernet Switch: LinkSys, SRW2048
* 2ea HD Tuner: Contemporary Research 232-ATSC
| * 4ea Audio Amplifiers: BiAmp CPA130 (1 for each quadrant of Rm 213) |
| ** 4ea Amino Mpeg2 Decoder: Aminet110H |
| ** 1ea DVR: Philips, HDRW720/17 |
| ** 1 ea DVD/VCR Combo: JVC SR-MV55 |
| ** 1ea Crestron Control Processor Pro2 (Master) |
| ** 1ea RGB Spectrum QuadView XL Image Processor |
| ** 1ea Touchpanel: TPS-12G-QM |
| Total Out/In needed: 10/1 |
Hallways:
** 2 ea Samsung LCD Television, LN26B460B2DXZA Total Out/In needed: 0/2 Room 227: Training
| * Screen: Da-Lite Electrol, DIR311-08 |
| ** 3ea Computers (DVI-D) |
| * 1ea Projector: InFocus LP640 |
This Document Is To Aid In Planning Only and Information Is Approximate This Document Is To Aid In Planning Only and Information Is Approximate
* 2ea Speakers: JBL, Model- Control 26 CT (integrated from Sound Room) Total Out/In needed: 3/1 Room 231: Sound Room
| ** 3ea Computers (DVI-D) |
| ** 3ea Monitors, 22” Widescreen (DVI-D) |
| ** 1ea DVD/VCR Combo: JVC SR-MV55 |
| ** 1ea Crestron Control Processor Pro2 (Slave) |
| ** 1ea Touchpanel: TPS-12G-QM |
| ** 1ea Ethernet Switch: Cisco SR224 |
| ** 2ea Audio Amplifiers: Crown XLS602 (to Rm 233) |
| * 1ea Audio Amplifiers: Crown XLS802 (integrate to support audio in Rm 227) |
| Total Out/In needed: 5/3 |
Room 233: Auditorium
* 1ea Screen: Da-Lite Electrol, DIR9121-08 ** 1ea Projectors: Panasonic PT-D5700U
| ** 2ea Television: Sharp Aquos 52”, LC-52D64U |
| ** 1ea Touchpanel: TPS-12G-QM (integrate, relocated from Ops Floor) |
| ** 1ea Laptop (DVI-D) |
| Total Out/In needed: 1/3 |
| * | Fiber Infrastructure needs to be installed |
| ** | Fiber Infrastructure exists |
Note: “Total Out/In needed” is an estimate of what the end user will need to support legacy and deliverable equipment based on limited knowledge of the systems involved. Contractor is responsible for all design details necessary to complete the project.
Note2: End user has decided to include moving of the 2 legacy Sharp Aquos 65” Plasma, LC-65SE94U televisions from their current locations to the north and south walls above the center doors.
This Document Is To Aid In Planning Only and Information Is Approximate
File details come from the government source that posted it. Updated .