SOW_draft_16-Q-5098_Construction_Bldg_1467_22_Mar_16_Redacted.pdf
PDF 66 KB Posted
- Attached to
- Building 1467 Renovations Federal contract opportunity
- Solicitation number
- W9124D-16-B-0001
View the file
Other files for this federal contract opportunity
Show all 50
Building 1467 Renovations has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 1467 has 130,000 SF of usable space and is currently CAT Code 61050, ADMIN GEN PURP facility.
This building will not be changing CAT Codes when the building is renovated. There will be minor modifications made to the exterior of the facility. The interior of the facility will be reconfigured through renovation and demolition to meet the purposed layout in the sketches attached.
WORK:
• All electrical, plumbing, fire suppression, fire detection, communications, ADA access will be brought into code compliance through the planned renovations and full replacement of the expired utilities.
• Force Protection will be modified as necessary and a secure space will be added in the basement of the facility.
• Types for work to be performed will be demolition, wall construction, plumbing, electrical, communications, window/doors, painting, finish work, asbestos‐lead‐mold remediation or removal and other items related to general construction.
• The parking lots associated with this facility will have minor renovations related to striping, signage, curbing and asphalt included in this construction contract.
• Water and sewer lines will be replaced to 15' outside of the building and cleaned out to the mainline from there.
• Expected contract completion date NLT 1 June 2017 to allow 1st TSC to move in and set up for July 2017 arrival of the 1st TSC Command.
Note Communication will be provided through the NEC contract but the contractor will have to coordinate installation concurrently throughout this contract. As well Furniture installation contract will be let and will also be concurrent to reach the finish date of 1 June 2017.