Updated_Specifications_Basewide_HVAC_Amend_0001.pdf
PDF 4 MB Posted
- Attached to
- Basewide HVAC Construction Federal contract opportunity
- Solicitation number
- W9124318B0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9124319C0001_HVAC_AWARD.pdf | ||
| Amendment_0002.released.pdf | ||
| Amendment_W91243-18-B-0001-0001.pdf | ||
| Updated_Drawings_Basewide_HVAC_Amend_0001.pdf | ||
| Basewide_HVAC_Site_Visit_Pictures_FBO_Post.docx | DOCX document | |
| PreBidConferenceB0001.pdf | ||
| Basewide_HVAC_Pre-Bid_Site_Visit_Sign_in_Roster_12Sep18.pdf | ||
| z_Specifications_NEANG__Repair_HVAC_Basewide.pdf | ||
| W9124318B0001.released.pdf | ||
| z_Repair_HVAC_Basewide_Drawings_B3.pdf | ||
| SPEC_Section_010000_-_NGCB_15-2603.pdf | ||
| NGCB_15-2603_-_AF_Form_66.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
NEANG SEPTEMBER 11, 2018
REPAIR HVAC BASEWIDE 06565.006 ADDENDUM NO. 1
CONTRACT MODIFICATION PROCEDURES 012600 - 1
SECTION 012600
CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
1.2 MINOR CHANGES IN THE WORK
A. Contracting Officer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.
1.3 PROPOSAL REQUESTS
A. Government-Initiated Proposal Requests: Contracting Officer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Contracting Officer are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request or 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Contracting Officer.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
CONTRACT MODIFICATION PROCEDURES 012600 - 2
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
1.4 CHANGE ORDER PROCEDURES
A. On Government's approval of a Work Change Proposal Request, Contracting Officer will issue a Change Order for signatures of Government and Contractor.
1.5 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Contracting Officer may issue a Construction Change Directive.
Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION
GENERAL COMMISSION REQUIREMENTS 019113 - 1
SECTION 01 91 13
GENERAL COMMISSIONING REQUIREMENTS
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes general requirements that apply to implementation of commissioning without regard to specific systems, assemblies, or components.
B. Commissioning is systematic processes to provide documented confirmation that building systems perform according to the criteria set forth in the design intent and satisfy the owner’s operational needs.
C. The commissioning process does not take away from or reduce the responsibility of the system designers, installing contractors, or general contractor to provide a finished and fully functioning product.
D. Abbreviations. The following are common abbreviations used in the Specifications and in the Commissioning Plan. Definitions are found in Section 1.3.
A/E- Architect and Design Engineers GC- General Contractor CxA- Commissioning Authority MC- Mechanical Contractor
CC Controls Contractor OR- Owner's Representative CM- Construction Manager TAB- Test and Balance Contractor Cx- Commissioning Subs- Subcontractors to General EC- Electrical Contractor CO Contracting Officer
E. The commissioning activities have been developed to support the U.S. Green Building Council (USGBC) LEED ™ rating program and to support delivery of project performance in accordance with Commissioning activities and documentation for the LEED™ credit EAP1 (Energy and Atmosphere Prerequisite for Fundamental Building Systems Commissioning) and EAC3 (Energy and Atmosphere requirements for the Enhanced Building System Commissioning).
1.3 SYSTEMS TO BE COMMISSIONED
A. The following systems will be commissioned in this project.
1. HVAC Systems
2. Chilled Water Systems
1.4 DEFINITIONS
A. Acceptance Phase. Phase of construction after startup and initial checkout when functional performance tests, operations and maintenance documentation review and training occurs.
B. Approval. Acceptance that a piece of equipment or system has been properly installed and is functioning in the tested modes according to the Contract Documents.
GENERAL COMMISSION REQUIREMENTS 019113 - 2
C. Architect/Engineer (A/E): The prime consultant (architect) and sub-consultants who comprise the design team, generally the HVAC mechanical designer/engineer and the electrical designer/engineer.
D. BoD: Basis of Design. A document that records concepts, calculations, decisions, and product selections used to meet the OPR and to satisfy applicable regulatory requirements, standards, and guidelines. The document includes both narrative descriptions and lists of individual items that support the design process.
E. CxA: Commissioning Authority. An independent agent, not otherwise associated with the A/E team members or the Contractor. The CxA directs and coordinates the commissioning activities in accordance with the commissioning specifications and Commissioning Plan.
F. Cx Plan: Commissioning Plan: A document that outlines the organization, schedule, allocation of resources, responsibilities of the commissioning team, and documentation requirements of the commissioning process.
G. Datalogging: Monitoring flows, temperatures, humidity, occupancy, sound levels, status, pressures, etc. of equipment and/or systems using stand-alone dataloggers separate from the control system.
H. Deferred Functional Tests : Functional tests that are performed after substantial completion due to partial occupancy, equipment, seasonal requirements, design or other site conditions that disallow the test from being performed.
I. Deficiency: A condition in the installation or function of a component, piece of equipment or system that is not in compliance with code, industry standard, owner’s requirements or the contract documents.
J. Design Intent: A dynamic document that provides the explanation of the ideas, concepts and criteria that are considered to be very important to the owner. It is initially the outcome of the programming and conceptual design phases.
K. Factory Testing: Testing of equipment at the factory or on-site by factory personnel with an Owner’s representative present.
L. Final Commissioning Report: The compiled record of the executed commissioning process and documentation.
M. Functional Performance Test (FPT): Test of the dynamic function and operation of equipment and systems using manual (direct observation) or monitoring methods. Functional performance testing is the dynamic testing of systems (rather than just components) under full operation.
Systems are tested under various modes and are demonstrated to operate through all the control system’s sequences of operation and components are verified to be responding as the sequences state. The commissioning authority develops the functional test procedures in a sequential written form, coordinates, oversees and documents the actual testing, which is performed by the installing contractor or vendor. FPTs are performed after prefunctional checklists are completed by the contractor, test and balance is finalized without issues, controls checkout is complete and documented, and equipment and system startup are complete.
N. General Contractor (GC): The general contractor for this project; Generally refers to all the general contractor’s subcontractors as well. Also referred to as the Contractor, in some contexts.
GENERAL COMMISSION REQUIREMENTS 019113 - 3
O. Issues Log: The CxA shall maintain the Commissioning Issues Log, a written record of each issue identified during the commissioning process. The issues log shall include detail of non-compliance, date identified, responsible party, and record of resolution.
P. Monitoring: The recording of parameters (flow, temperature, current, status, pressure, etc.) of equipment operation using dataloggers or the trending capabilities of control systems.
Q. Non-Compliance: See Deficiency.
R. Non-Conformance: See Deficiency.
S. Owner's Project Requirements (OPR): A document that details the functional requirements of a project and the expectations of how it will be used and operated. These include Project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.
T. Owner’s Representative: Contracting Officer.
U. Prefunctional Checklist: A record of equipment installation provided by the CxA to the installing contractors for completion. Equipment checklists are primarily static inspections to verify that installation is in compliance with project documents and document procedures to prepare the equipment or system for initial operation. Prefunctional checklist items may include simple testing of the function of a component, a piece of equipment or system. Prefunctional checklists augment and are combined with the manufacturer’s start-up checklist. The Prefunctional Checklists shall be completed by the installing contractor and reviewed and signed by the general contractor and/or construction manager to verify that the equipment and systems are complete and ready for functional performance testing. The checklists shall be submitted to the CxA prior to functional performance testing.
V. Sampling: Functionally testing only a fraction of the total number of identical or near identical pieces of equipment.
W. Seasonal Performance Tests: Functional performance tests that are deferred until the system(s) will experience conditions closer to their design conditions.
X. Systems Manual: The Systems Manual is intended to provide future operations staff the information needed to understand and optimally operate the commissioned systems. The Systems Manual will be developed by the commissioning team with guidance and reviewed by the commissioning authority. The manual will include the final version of the owner’s project requirements, basis of design, single line diagrams, as-built sequence of operations and control drawings, operating instructions for building systems, recommended schedule for retesting of commissioned systems with blank test forms, and maintenance requirements not included in the O&M Manuals.
Y. Systems, Subsystems, Equipment, and Components: Where these terms are used together or separately, they shall mean "as-built" systems, subsystems, equipment, and components.
Z. Startup: The initial starting or activating of dynamic equipment, including executing prefunctional checklists.
AA. Subs: The subcontractors to the GC who provide and install building components and systems.
BB. Trending: Monitoring using the building control system.
GENERAL COMMISSION REQUIREMENTS 019113 - 4
1.5 COORDINATION
A. Commissioning Team. The members of the commissioning team consist of the Commissioning authority (CxA), the Contracting Officer (CO), Owner's Representative (OR), the General Contractor (GC or Contractor), the architect and design engineers (A/E), the Mechanical Contractor (MC), the Electrical Contractor (EC), the testing, adjusting, and balance (TAB) representative, the Controls Contractor (CC), any other installing subcontractors or suppliers of equipment.
B. Management. The CxA directs and coordinates the commissioning activities and the reports to the owner’s representative. All members work together to fulfill their contracted responsibilities and meet the objectives of the Contract Documents.
C. Commissioning Kickoff Meeting. The CxA will provide an overview of the commissioning events at the commissioning kickoff meeting. The Commissioning Plan shall be provided and discussed. The roles and responsibilities of all commissioning team members will be discussed and a preliminary schedule provided.
D. Scheduling. The CxA will work with the GC according to established protocols to schedule the commissioning activities. The CxA will provide sufficient notice to the GC for scheduling commissioning activities. The GC will integrate all commissioning activities into the master schedule. All parties will address scheduling problems and make necessary notifications in a timely manner in order to expedite the commissioning process.
1.6 COMMISSIONING PROCESS
A. Commissioning Plan. The commissioning plan provides guidance in the execution of the commissioning process and includes the roles and responsibilities for each member of the commissioning team. The specifications will take precedence over the Commissioning Plan.
B. Commissioning Process. The following narrative provides a brief overview of the typical commissioning tasks during construction and the general order in which they occur.
1. The Commissioning Plan will be presented and discussed during the Commissioning Kickoff Meeting. The meeting will be conducted by the CxA and will review the commissioning process, commissioning schedule, and team member responsibilities.
2. Additional commissioning meetings may be required throughout construction, scheduled by the CxA with necessary parties attending, to plan, scope, coordinate, schedule future activities and resolve issues.
3. The CxA shall conduct a design review of the design documents, OPR and BOD prior to the mid-construction documents phase and provide backcheck in the subsequent design submission.
4. Submittals and associated equipment documentation is submitted to the CxA. The CxA shall review contractor submittals applicable to systems being commissioned for compliance with the OPR and BOD. The review shall be concurrent to the A/E submittal review.
5. The CxA shall record all design review comments, submittal review comments, equipment installation deficiencies, and functional testing non-compliance issues in the Issues Log. The issues log shall include detail of non-compliance, date identified, responsible party, and record of resolution. The issues log will be distributed to the commissioning team for response and/or resolution.
6. The CxA works with the Subs in developing startup plans and startup documentation formats, including providing the Subs with prefunctional checklists to be completed, during the startup process.
GENERAL COMMISSION REQUIREMENTS 019113 - 5
7. Prefunctional Checklists are provided by the CxA for each piece of equipment and/or system to be commissioned. The Subs, under their own direction, execute and document the prefunctional checklists and perform startup and initial checkout. The GC and/or CM shall review the completed checklists, sign, and provide to the CxA. The CxA documents that the checklists and startup were completed according to the approved plans. This may include the CxA witnessing start-up of selected equipment.
8. The CxA develops specific equipment and system functional performance test procedures. The installing contractors shall review the procedures and provide any comments within two (2) weeks of issuance.
9. The functional performance test procedures are executed by the Subs, under the direction of, and documented by the CxA. Required participants for functional performance testing will be provided in advance by the CxA for each functional test procedure test form.
10. Items of non-compliance in material, installation, setup, and/or operation will be documented by the CxA and are corrected at the Sub’s expense and the system retested.
11. The CxA reviews the training provided by the Subs as per existing specification requirements. The CxA will verify that the requirements for training operating personnel and building occupants have been completed.
12. The CxA will conduct a warranty phase site visit to review the operation of the building with operations and maintenance staff and occupants within 10 months after substantial completion. The CxA shall provide a plan for resolving outstanding commissioning-related issues.
1.7 COMMISSIONING TEAM
A. Members Appointed by Contractor(s): Individuals, each having the authority to act on behalf of the entity he or she represents, to implement the commissioning process through coordinated action. The commissioning team shall consist of, but not be limited to, the General Contractor (GC), and representatives of the Contractor, including project superintendent and subcontractors, installers, suppliers, and specialists deemed appropriate by the CxA.
B. Members Appointed by Owner:
1. Commissioning Authority
2. Representatives of the facility user and operation and maintenance personnel.
3. Architect and engineering design professionals.
1.8 OWNER'S AND OWNER’S REPRESENTATIVE (OR) RESPONSIBILITIES
A. Provide the owner’s project requirement (OPR) documentation to the CxA and Contractor for information and use.
B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities as desired.
C. Provide the BoD documentation, prepared by Architect and approved by Owner, to the CxA and Contractor for use in developing the commissioning plan and systems manual.
D. Follow the Commissioning Plan.
E. Attend the commissioning kickoff meeting and additional meetings as necessary.
F. Participate in the warranty phase site visit to review the operation of the building with operations and maintenance staff and occupants within 10 months after substantial completion.
GENERAL COMMISSION REQUIREMENTS 019113 - 6
1.9 ARCHITECT/ENGINEERS (AE) RESPONSIBILITIES
A. The AE shall participate in and perform commissioning process activities including, but not limited to, the following:
1. Attend the commissioning kickoff meeting and selected commissioning team meetings.
2. Perform normal submittal review, construction observation, as-built drawing preparation, O&M manual preparation, etc., as contracted.
3. Prepare and provide the Basis of Design (BoD) document for use in developing the commissioning plan and systems manual.
4. Provide any design narrative and sequence documentation requested by the CxA. The designers shall assist (along with the contractors) in clarifying the operation and control of commissioned equipment in areas where the specifications, control drawings or equipment documentation is not sufficient for writing detailed testing procedures.
5. Provide written response to each commissioning design review comment, submittal review comment, and design-related construction phase deficiency within two (2) weeks of issuance by the CxA.
6. Prepare and submit information required for the Systems Manual as requested by the CxA, including (but not limited to): operating instructions for the integrated building systems, as-built documentation, and the final version of the BOD.
7. Participate in the resolution of non-compliance, non-conformance and design deficiencies identified during commissioning during design, construction and warranty-period commissioning.
1.10 CONTRACTOR'S (GC) RESPONSIBILITIES
A. Contractor shall assign representatives with expertise and authority to act on its behalf and shall schedule them to participate in and perform commissioning process activities including, but not
1. Facilitate the coordination of the commissioning work by the CxA and ensure that commissioning activities are being scheduled into the master schedule.
2. Follow the Commissioning Plan.
3. Attend commissioning kickoff meetings and additional meetings as necessary. Assist in coordination and scheduling of meetings as requested by the CxA.
4. Review and comment on the final Commissioning Plan.
5. Furnish a copy of all construction documents, addenda, requests for information, change orders and approved submittals and shop drawings related to commissioned equipment to the CxA.
6. Review the functional performance test procedures submitted by the CxA and provide comments within two (2) weeks of issuance by the CxA.
7. With the assistance of the subcontractors, coordinate and ensure that the commissioning process functional test procedures are executed for each system. Coordinate retesting as required.
8. Review commissioning progress and deficiency reports. Evaluate performance deficiencies identified in test reports and, in collaboration with entity responsible for system and equipment installation, recommend corrective action.
9. Coordinate the resolution of non-compliance and design deficiencies identified in all phases of commissioning. Review commissioning progress and deficiency reports and provide a written response to each issue within two (2) weeks of issuance by the CxA and weekly until the issue is resolved.
10. Upon completion of equipment installation and within one (1) week of scheduled commissioning functional performance testing, review, approve, and sign the completed Prefunctional Checklists and provide copies to the CxA for each piece of equipment and/or system to be commissioned. The Subs, under their own direction, execute and document the prefunctional checklists and perform startup and initial checkout.
GENERAL COMMISSION REQUIREMENTS 019113 - 7
11. Collect and review Training Agendas and provide copies to the CxA for review. Provide the Training Plan and coordinate the training of Owner personnel.
12. Within two (2) weeks of scheduled commissioning functional performance testing, in coordination with the controls contractor, provide a list of final settings, setpoints, ranges, schedules, and/or trend logs required by the CxA.
1.11 SUB CONTRACTOR'S RESPONSIBILITIES
A. The subcontractors shall assign representatives with expertise and authority to act on their behalf and shall schedule them to participate in and perform commissioning process activities including, but not limited to, the following:
1. Follow the Commissioning Plan.
2. Attend commissioning kickoff meeting and additional meetings as necessary.
3. Complete and sign each Commissioning Prefunctional Checklist for systems to be commissioned as provided by the CxA at least one (1) week prior to functional performance testing.
4. Perform commissioning functional test procedures under the direction of the CxA.
5. Review and respond to each Commissioning Issue as identified on commissioning progress and deficiency reports. Where responsible for system and equipment installation, recommend corrective action for all issues identified. Provide a written response to each issue within two (2) weeks of issuance by the CxA and weekly until the issue is resolved.
6. Execute the resolution of non-compliance and deficiencies identified. Perform retesting as required.
7. Include all special tools and instruments (those only available from vendor, specific to a piece of equipment) required for testing equipment according to these Contract Documents in the base bid price to the Contractor, except for stand-alone data logging equipment that may be used by the CxA.
8. The Contractors will provide all tools or the use of tools to start, check-out and functionally test equipment and systems, except for specified testing with portable data-loggers, which may be supplied and installed by the CxA.
9. Provide information requested by CxA regarding equipment sequence of operation and testing procedures.
10. Conduct operations & maintenance training per project specifications.
1.12 CxA'S RESPONSIBILITIES
A. The CxA is not responsible for design concept, design criteria, compliance with codes, design or general construction scheduling, cost estimating, or construction management. The CxA may assist with problem-solving non-conformance or deficiencies, but ultimately that responsibility resides with the general contractor and the A/E. The primary role of the CxA is to develop and coordinate the execution of a testing plan, observe and document performance—that systems are functioning in accordance with the documented design intent and in accordance with the Contract Documents.
1. Coordinate and direct the commissioning activities using consistent protocols and forms, centralized documentation, clear and regular communications and consultations with all necessary parties, frequently updated timelines and schedules and technical expertise.
2. Create, execute, and revise, as necessary, the Commissioning Plan.
3. Coordinate the commissioning work and, with the GC, ensure that commissioning activities are being scheduled into the master schedule.
4. Review the owner’s project requirements and basis of design documents for clarity and completeness.
5. Conduct a commissioning design review of the design documents prior to the mid-construction documents phase and back-check the review comments in the subsequent design submittal.
GENERAL COMMISSION REQUIREMENTS 019113 - 8
6. Plan and conduct a commissioning kickoff meeting and other commissioning meetings as required. Provide meeting minutes within one (1) week of meeting date.
7. Review and comment on normal Contractor submittals applicable to systems being commissioned for compliance with the OPR and BOD, concurrent with the A/E reviews.
8. Assist in the resolution of issues identified during the commissioning process. Maintain a master deficiency and resolution log (Issues Log). Provide the commissioning team with written progress reports and test results.
9. Write and distribute Prefunctional Checklists and Functional Performance Test Procedures. Incorporate comments from the commissioning team as required.
10. Perform site visits, as necessary, to observe component and system installations. Attend selected planning and job-site meetings to obtain information on construction progress.
Review construction meeting minutes for revisions/substitutions relating to the commissioning process. Assist in resolving any discrepancies.
11. Review and approve completed Prefunctional Checklists thru onsite observation and review of contractor reports and startup documentation.
12. Coordinate, witness and approve manual functional performance tests performed by installing contractors. Coordinate retesting as necessary until satisfactory performance is achieved.
13. Verify that the training requirements for operating personnel and building occupants have been completed.
14. Provide a Final Commissioning Report.
15. Utilizing information provided by the contractor and design team from existing project requirements, develop a System Manual.
16. At 8-10 months into the 12 month warranty period, review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal commissioning. Provide a plan for resolving outstanding commissioning related issues. Identify areas that may come under warranty or under the original construction contract.
PART 2 - PRODUCTS
2.1 TEST EQUIPMENT
A. All standard testing equipment required to perform startup and initial checkout and required functional performance testing shall be provided by the installing contractor for the equipment being tested.
B. Special equipment, tools and instruments (only available from vendor, specific to a piece of equipment) required for testing equipment, according to these Contract Documents shall be included in the base bid price to the Contractor and provided to the owner at the completion of the project, except for stand-alone datalogging equipment that may be used by the CxA.
C. Datalogging equipment and software required to test equipment may be provided by the CxA, but shall not become the property of the Owner.
D. All testing equipment shall be of sufficient quality and accuracy to test and/or measure system performance with the tolerances specified in the specifications. If not otherwise noted, the following minimum requirements apply: Temperature sensors and digital thermometers shall have a certified calibration within the past year to an accuracy of 0.5F and a resolution of + or -
0.1F. Pressure sensors shall have an accuracy of + or - 2.0% of the value range being measured (not full range of meter) and have been calibrated within the last year. All equipment shall be calibrated according to the manufacturer’s recommended intervals and when dropped or damaged. Calibration tags shall be affixed or certificates readily available.
GENERAL COMMISSION REQUIREMENTS 019113 - 9
PART 3 - EXECUTION
3.1 MEETINGS
A. Commissioning Kickoff Meeting. The CxA will schedule, plan and conduct a commissioning kickoff meeting with the entire commissioning team in attendance. The Commissioning Plan will be provided and the roles and responsibilities of each commissioning team member will be discussed. Meeting minutes will be distributed to all parties by the CxA.
B. Additional Commissioning Meetings. The commissioning team shall attend additional commissioning meetings as planned and conducted by the CxA. These meetings will cover coordination, commissioning scheduling, planning issues, and deficiency resolution. The CxA will plan these meetings and will minimize unnecessary time being spent by Subs.
3.2 REPORTING
A. The CxA will provide regular reports to the Owner, with increasing frequency as construction and commissioning progresses, including keeping the commissioning team apprised of commissioning progress and scheduling changes through memos, progress reports, test reports, and meeting minutes.
B. The CxA shall provide the Commissioning Issues Log and updates to the commissioning team.
For each issue, the responsible party shall provide a written response to each issue within two
(2) weeks of issuance by the CxA and weekly until the issue is resolved.
C. A Final Commissioning Report by the CxA will be provided to the OR, focusing on documenting the executed commissioning process. All acquired commissioning documentation, logs, minutes, reports, deficiency lists, communications, findings, unresolved issues, etc., will be included with the Final Commissioning Report. Completed prefunctional checklists and executed functional tests will also be included.
D. The Systems Manual will be developed by the commissioning authority to provide future operations staff the information needed to understand and optimally operate the commissioned systems. The manual will include the final version of the owner’s project requirements, basis of design, single line diagrams, as-built sequence of operations and control drawings, operating instructions for building systems, recommended schedule for retesting of commissioned systems with blank test forms, and other information deemed helpful to the building operators.
3.3 SUBMITTALS
A. The commissioning process requires Submittal review simultaneously with engineering review for all equipment associated with systems to be commissioned.
B. The Commissioning authority will review and provide comment on submittals related to the commissioned equipment for conformance to the Contract Documents as it relates to the commissioning process, to the functional performance of the equipment and adequacy for developing test procedures. This review is intended primarily to aid in the development of functional performance testing procedures. The commissioning authority will provide response and record discrepancies or request additional details utilizing the commissioning issues log.
C. The final approval of submittals are the responsibility of the Design Team, though the CxA will review and offer comment and recommendation.
D. Contractor’s responsibility for deviations in submittals from requirements of the Contract Documents is not relieved by the Commissioning Authority’s review.
GENERAL COMMISSION REQUIREMENTS 019113 - 10
3.4 EQUIPMENT START-UP AND PREFUNCTIONAL CHECKLISTS
A. The following procedures apply to all equipment to be commissioned, according to Section 1.3, Systems to be Commissioned.
B. Prefunctional Checklists Equipment prefunctional checklists will be created by the CxA and distributed to the commissioning team for completion. No sampling strategies are used. The completion of the form with contractor signature ensures that functional performance testing may proceed without unnecessary delays. Equipment startup reports and associated required contractor test reports shall be attached to the associated prefunctional checklist. The completed prefunctional checklists shall be submitted to the CxA no later than one (1) week in advance of functional performance testing.
1. When completing prefunctional checklists, signatures are required for each installing contractor for verification of completion of their work.
2. The Subs and vendors shall execute startup and provide the CxA with a signed and dated copy of the completed start-up and prefunctional tests and checklists.
3. Only individuals that have direct knowledge and witnessed that a line item task on the prefunctional checklist was actually performed shall initial the item as complete. It is not acceptable for witnessing supervisors to fill out these forms.
4. The Subs shall clearly list any outstanding items of the initial start-up and prefunctional procedures that were not completed successfully, at the bottom of the Prefunctional Checklist form or on an attached sheet.
5. The installing Subs or vendors shall correct all areas that are deficient or incomplete in the checklists and tests in a timely manner, and shall notify the CxA as soon as outstanding items have been corrected and resubmit an updated start-up report and a Statement of Correction on the original non-compliance report or as a response to the commissioning issues log.
6. Items left incomplete, which later cause deficiencies or delays during functional performance testing may result in back charges to the responsible party. Refer to Part
3.7 herein for details.
3.5 FUNCTIONAL PERFORMANCE TESTING
A. This sub-section applies to all commissioning functional performance testing for all divisions.
B. The general list of equipment to be commissioned is found in Section 019113, Part 1.3.
C. Coordination and Scheduling. The Subs shall provide sufficient notice to the CxA regarding their completion schedule for the prefunctional checklists and startup of all equipment and systems. The CxA will schedule functional tests through the GC and affected Subs. The CxA shall direct, witness and document the functional performance testing of all equipment and systems. The Subs shall execute the tests.
1. Functional performance testing is conducted after equipment testing and startup has been satisfactorily completed.
2. The air balancing and water balancing is to be completed before functional performance testing of air-related or water-related equipment or systems.
3. Testing proceeds from components to subsystems to systems. When the proper performance of all interacting individual systems has been achieved, the interface or coordinated responses between systems can be checked.
4. Resolution Retesting will be scheduled after documented confirmation (controls trending, photograph, or completed work order form) that the issue has been resolved.
GENERAL COMMISSION REQUIREMENTS 019113 - 11
D. Execution of Functional Performance Testing. The CxA shall direct, witness, and document Functional performance testing. Each system should be operated through all modes of operation (seasonal, occupied, unoccupied, warm-up, cool-down, part- and full-load) where there is a specified system response. Verifying each sequence in the sequences of operation is required. Sample methods may be permitted as described in the Commissioning Plan.
E. Deficiency Resolution The CxA will document and recommend solutions to issues discovered during equipment installation and functional performance testing, however the burden of responsibility to solve, correct and demonstrate resolution of identified issues is with the GC, Subs and/or A/E.
3.6 DOCUMENTATION, NON-CONFORMANCE AND APPROVAL OF TESTS
A. Documentation. The CxA shall witness and document the results of all functional performance tests. The CxA will include the completed functional test procedures in the final commissioning report.
B. Non-Conformance.
1. All deficiencies or non-conformance issues shall be noted and reported on the issues log.
If there is a dispute about a deficiency, regarding whether it is a deficiency or who is responsible, the issue will be discussed at the commissioning meeting and the general contractor shall be responsible for delivering an operational system that is compliant with design documents. Final interpretive authority is with the A/E. Final acceptance authority is with the owner.
2. The CxA will record the results of the functional test on the test form, and final results will be documented on the test form upon successful retesting.
3. Corrections of minor deficiencies identified may be made during the tests at the discretion of the CxA. In such cases the deficiency and resolution will be documented on the issues log.
4. Every effort will be made to expedite the testing process and minimize unnecessary delays, while not compromising the integrity of the procedures. However, the CxA will not be pressured into overlooking deficient work or loosening acceptance criteria to satisfy scheduling or cost issues, unless there is an overriding reason to do so at the request of the owner.
5. Cost of Retesting.
a. The cost for the Sub to retest a prefunctional or functional test, if they are responsible for the deficiency, shall be theirs. If they are not responsible, any cost recovery for retesting costs shall be negotiated with the GC.
b. For a deficiency identified, not related to any prefunctional checklist or start-up fault, the following shall apply: The CxA and GC will direct the retesting of the equipment once at no “charge” for their time. However, the CxA’s and/or contractor’s time for a second retest will be charged to the GC, who may choose to recover costs from the responsible Sub.
c. The time for the CxA and GC to direct any retesting required because a specific prefunctional checklist or start-up test item, reported to have been successfully completed, but determined during functional performance testing to be faulty, will be backcharged to the GC, who may choose to recover costs from the party responsible for executing the faulty prefunctional test.
6. The Contractor shall respond in writing to the CxA every two (2) weeks concerning the status of each apparent outstanding discrepancy identified during commissioning.
Discussion shall cover explanations of any disagreements and proposals for their resolution.
7. The CxA retains the complete commissioning issues log throughout the project.
GENERAL COMMISSION REQUIREMENTS 019113 - 12
C. Failure Due to Manufacturer Defect. If 10%, or three, whichever is greater, of identical pieces (size alone does not constitute a difference) of equipment fail to perform to the Contract Documents (mechanically or substantively) due to manufacturing defect, not allowing it to meet its submitted performance spec, all identical units may be considered unacceptable by the CxA or OR. In such case, the Contractor and/or manufacturer shall replace or repair all identical items, at their expense and extend the warranty accordingly, if the original equipment warranty had begun. The replacement/repair work shall proceed with reasonable speed beginning within one week from when parts can be obtained
3.7 DEFERRED TESTING
A. Unforeseen Deferred Tests. If any check or test cannot be completed due to the building structure, required occupancy condition or other deficiency, execution of checklists and functional performance testing may be delayed upon approval of the OR. These tests will be conducted in the same manner as the seasonal tests as soon as possible. Services of necessary parties will be negotiated.
3.8 TRAINING OF OWNER PERSONNEL
A. The GC shall be responsible for training coordination and scheduling and ultimately for ensuring that training is completed.
B. The CxA shall be responsible for overseeing and approving the content and adequacy of the training of Owner personnel for commissioned equipment.
3.9 WRITTEN WORK PRODUCTS
A. The commissioning process generates a number of written work products described in various parts of the Specifications. The Commissioning Plan lists all the formal written work products, describes briefly their contents, who is responsible to create them, their due dates, who receives and approves them and the location of the specification to create them. In summary, the written products are:
Product Developed By
1. Commissioning Plan CxA
2. Cx Meeting Minutes CxA
3. Commissioning Schedules CxA with GC
4. Prefunctional Checklists CxA (completed by Subs and GC)
5. Issues Log (deficiencies) CxA (responses required by Subs and GC)
6. Functional Test Forms CxA (executed by Subs; documented by CxA)
7. O&M Training Verification CxA and GC
8. Final Commissioning Report CxA
9. Systems Manual CxA (with input from A-E, GC, and Subs)
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100
PROJECT MANAGEMENT AND COORDINATION
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility will be assigned to a specific contractor.
C. Related Sections include the following:
1. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
2. Section 018113 “Sustainable Design Requirements” for coordination of Work with project requirements to meet LEED Silver certification.
3. Section 019113 "General Commissioning Requirements" for coordinating the Work with
Government's Commissioning Authority.
1.3 DEFINITIONS
A. RFI: Request from Contractor seeking interpretation or clarification of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in project meeting room, in temporary field office, in web-based Project software directory, and in prominent location in each built facility. Keep list current at all times.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work.
Each contractor shall coordinate its own operations with operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Government and separate contractors if coordination of their Work is required.
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
9. Project closeout activities.
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
E. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
1. Requirements and procedures, and construction waste management.
1.6 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applicable Drawings as a basis for preparation of coordination drawings.
Prepare sections, elevations, and details as needed to describe relationship of various systems and components.
b. Coordinate the addition of trade-specific information to coordination drawings in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
f. Indicate required installation sequences.
g. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements.
Provide alternative sketches to Contracting Officer indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
B. Coordination Drawing Organization: Organize coordination drawings as…