9 September 2018 Additional Bidder Inquires for Solicitation W91238-19-B-0012
1. In reference to a previous question, ID 8149484, the question was not asked in reference to cutoff wall spoils, rather it was referring to excess levee excavation or random fill that will be generated because of the amount of imported levee fill. Historically, the excess material would be placed along the landside levee toe rather than trucked offsite for disposal. Please advise if a landside toe road will be included in the Contract to accommodate the suitable excess random fill.
Answer: No landslide toe road will be included
2. As part of the 10,000 GPM bypass, is the Contractor required to provide an additional pump or a booster pump to assist the existing pumps? Or are the existing pumps capable of meeting the bypass requirement?
Answer: The existing pumps are anticipated to be capable of meeting bypass requirements