W91238-15-R-0077
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
A. Extend the proposal due date from 2 Nov 2015 to 6 Nov 2015 2pm B. Revise section 00 22 00, 4.3.3.3 Project Schedule NTP date from 01 Jun 14 to 21 Mar 2016.
C. Revise attachment #2 Specifications - Section 01 10 10: paragraph 11.1.1.1 (see attach. #3 for revision) D. Revise attachment #2 Specifications - Section 01 10 10: paragraph 15.1.1 (see attach. #3 for revision) E. Revise attachment #2 Specifications - RFP Concept Draw ing, CLIN 2 C Bus One Line Concept Diagram (see attach. #3 for revision) F. Revise attachment #2 Specifications - Attachment 10, Div 25 Integrated Automation: paragraph under "Integrated Automation Enterprise Contract". (see attach. #3 for revision) G. Revise attachment #2 Specifications - Electrical BAS Points sheets provided as reference. (see attach. #3 for revision)
1. CONTRACT ID CODE PAGE OF PAGES
J 1 30
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Oct-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91238-15-R-0077
X 9B. DATED (SEE ITEM 11)
13-Oct-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Oct-2015
CODE
US ARMY CORPS OF ENGINEERS, SACRAMENTO
CONTRACTING DIVISION
1325 J STREET
SACRAMENTO CA 95814-2922
W91238 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION - CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
SUMMARY OF CHANGES
SECTION 00 01 10 - TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Attachment I - Statement of Work
5 14-SEP-2015
Attachment 2 Attachment II - Specifications
781 18-SEP-2015
to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Attachment I - Statement of Work
5 14-SEP-2015
Attachment 2 Attachment II - Specifications
781 18-SEP-2015
Attachment 3 Attachment III - Specifications Amd. 03
108 29-OCT-2015
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 02-Nov-2015 02:00 PM to 06-Nov-2015 02:00 PM.
SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS
The following have been modified:
SECTION 00 22 10
SOLICITATION SECTIONS PERTAINING TO OFFEROR’S SUBMISSION AND EVALUATION
PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS,
BASIS OF AWARD, AND EVALUATION CRITERIA
1. OVERVIEW.
a. This action is a "Best Value" solicitation for a design build general construction contract to upgrade electrical for DECC building 891 on Hill AFB, Utah. The Contracting Officer will award to those responsible offerors whom the Source Selection Authority determines offers the best overall value to the Government, considering all non-price factors described herein, and price of the project. The project requirements will be provided in the amendment to initiate phase two.
b. This solicitation utilizes a two-phase source selection process requiring two separate proposal submittals, a phase-one (non-price technical volume) proposal and a phase-two (price and technical volumes) proposal. Phase- one will consist of an evaluation of only non-price factors which include Experience and Capability, Technical Approach, and Past Performance of the offeror. Approximately four (4) of the most highly qualified offerors in phase-one will be given the opportunity to submit a proposal under phase-two. Phase-two will consist of an evaluation of price and a non-price factors which may include a Technical Solution and Management Approach. The phase-two technical volume requirements will be provided in the amendment to initiate phase-two. The most highly qualified offeror in phase-two will be awarded as a result of this solicitation.
c. The Government neither intends to conduct discussions during phase-one, nor request revised phase-one proposals. However, the Government reserves the right to conduct phase-one discussions, if it deems such to be in its best interest in accordance with FAR 15.306.
2. BASIS OF AWARD.
2.1. ELIGIBILITY FOR CONTRACT AWARD
In accordance with the requirements of Part 9 of the Federal Acquisition Regulation (FAR), no contract shall be entered into unless the Contracting Officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met. This includes the FAR requirement that no award shall be made unless the contracting officer makes an affirmative determination of responsibility. To be determined responsible, a prospective contractor must meet the general standards in FAR Part 9 and any special standards set forth in the solicitation.
2.2. SOURCE SELECTION USING THE TRADE-OFF PROCESS
The Government will select the offer that represents the best value to the Government by using the tradeoff process described in FAR Part 15. This process permits tradeoffs between price and technical (“non-price”) factors and allows the Government to accept other than the lowest priced offer. The award decision will be based on a comparative analysis and an integrated assessment of proposals against all source selection criteria in the solicitation.
2.3. RELATIVE IMPORTANCE OF PRICE TO THE TECHNICAL EVALUATION
FACTORS
All non-price evaluation factors, when combined, will be greater than price. The Government is concerned with striking the most advantageous balance between technical merit (“quality”) and cost to the Government (i.e., the price). If competing technical proposals are determined to be essentially equal, price could become the controlling factor.
2.4. EVALUATION OF THE PRICE PROPOSAL
a. Price to the Government will be evaluated and considered but will not be scored or combined with other aspects of the proposal evaluation. The proposed price will be analyzed for reasonableness. It may also be analyzed to determine whether it reflects a clear understanding of the requirements; and is consistent with the offeror’s Technical Proposal. Additionally, all offers will be analyzed for unbalanced pricing.
b. The price evaluation adjustment for Small Disadvantaged Businesses will not apply to this procurement as it is currently suspended for Department of Defense.
c. Information required to be submitted in the Price Proposal volume in addition to the executed SF 1442 with acknowledgement of amendments and the completed pricing schedule will be used to determine the offeror’s eligibility for contract award in accordance with paragraph 2.1 above (for example, the offeror’s representations and certifications; the bid guarantee; and the offeror’s pre-award survey information).
2.5. THE TECHNICAL EVALUATION FACTORS
a. The Government will evaluate each offeror’s technical proposal based on how well the proposal addresses each of the evaluation factors, listed below, and on how well the offeror has performed on related projects through the evaluation of the past performance information provided from references or obtained from other sources. Each of the evaluation factors will be evaluated by the Government and an adjectival rating and risk rating will be determined by consensus of the Government evaluation board for all technical factors other than past performance. The Past Performance factor will be evaluated by the Government and a relevancy and confidence level will be determined by consensus of the Government evaluation board.
b. The evaluation factors correlate directly to the main organizational tabs identified in the proposal submission instructions.
a. Phase-One Proposal (Section 00 22 10), Non-Price Factors:
i. FACTOR 1: Experience and Capability
1. Prime Contractor/Key Subcontractor Example Projects
Demonstrating Experience and Capability
2. Prime Contractor/Key Subcontractor Corporate Resumes
ii. FACTOR 2: Technical Approach
1. Approach to the work
2. Bonding Capability
iii. FACTOR 3: Past Performance
1. Prime Contractor/Key Subcontractor Example Projects Past
Performance
2. Key Subcontractor Authorization Letters
b. Phase-Two Proposal (Section 00 22 20), to be included with the amendment initiating phase two.
c. The Source Selection Authority will consider both phase one and phase two proposal evaluation with their relative strengths and weaknesses in determining the best value to the Government.
2.6 RELATIVE IMPORTANCE OF THE TECHNICAL EVALUATION FACTORS
The Technical Evaluation Factors are listed below in descending order of importance, as follows:
Factor 1 – Experience and Capability is the most important factor.
Factor 2 – Technical Approach is less important than Factor 1.
Factor 3 – Past Performance is less important than Factor 2.
Phase-two factors and their level of importance will be incorporated into the amendment to initiate phase-two.
2.7 GENERAL TECHNICAL EVALUATION CRITERIA
a. The offeror’s conformance with the specified format and submission requirements will be considered during the technical evaluation. Failure to comply with the formatting and/or submission requirements may be seen as indicative of the type of problems that could be expected during contract performance. Lack of conformance may therefore result in a higher risk assessment, in addition to any other impacts on the evaluation. Material omission(s) may cause the technical proposal to be rejected as unacceptable. However, in accordance with FAR 52.215-1, the Government may waive informalities and minor irregularities in proposals. For example, a failure by a proposed key subcontractor to submit a properly executed letter of commitment may be considered as increasing risk, but will not be considered a proposal deficiency.
b. Technical proposals which do not provide the specified information in the specified location in accordance with the submission instructions may be downgraded. The Government is under no obligation to search for information that is not in the specified location.
c. Proposals which are generic, vague, or lacking in detail may be downgraded. Responses that are essentially blanket offers of compliance are not adequate substitutes for the detailed and complete technical information necessary to establish that an offeror can meet US Government needs. The proposal submission instructions are written to give prospective contractors, where feasible, an indication of the level of detail desired by the Government. The offeror’s failure to include information that the Government has indicated should be included may result in the proposal being downgraded and/or being found deficient if inadequate detail is provided.
d. Any prescribed page and formatting limitations will be strictly adhered to and enforced by the Government. The Government will not evaluate any excess information resulting from the offeror’s failure to comply with the submission instructions. Examples: If an offeror were to submit three pages in response to an item with a two page limitation, the information on the first two pages would be evaluated but the information on the third page would not be evaluated. If an offeror were to submit a fold-out sheet (e.g. 11”x17”) in response to a one-page limitation where fold-out sheets were not authorized, only the information that could reasonably have been submitted on one 8-1/2 x 11 inch sheet would be evaluated. If an offeror were to submit three 8-1/2 x 11 inch pages in response to a one not-to-exceed 11 x 17 inch page limitation, only the information that could reasonably have been submitted on one 11 x 17 inch sheet would be evaluated. If an offeror submitted alternates that were not requested (e.g. key subcontractor), the information will not be evaluated.
e. The degree of risk to the Government inherent in the offeror’s technical proposal will be a consideration under every evaluation factor. There are two main risks that should be mitigated in the contractor’s proposal:
1. Operational Availability. The offeror should demonstrate 1) a clear understanding of the importance of operational availability of the customer’s mission systems, 2) address the understanding in their technical approach, and 3) demonstrate how they shall maintain operational availability of the customer’s equipment in a Tier III environment.
2. Ability to Execute. The offeror should demonstrate, in their proposal, the ability to meet the requirements of the solicitation within the price and schedule offered in their response.
f. A “deficiency” is a material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. “Weakness” means a flaw in a proposal that increases the risk of unsuccessful contract performance. A “significant weakness” is a proposal flaw that appreciably increases the risk of unsuccessful contract performance. The Government cannot accept an offer with a deficiency in its technical proposal. The term “acceptable” is therefore used in this context to describe a technical proposal that does not contain a deficiency and thus could be accepted by the Government, notwithstanding any weaknesses or significant weaknesses in the proposal.
g. The Government cannot make award based on a deficient offer. Therefore, a rating of “Unacceptable” under any factor will render the offer ineligible for award, unless the Government elects to enter into discussions with that offeror and all deficiencies are remedied in a revised proposal.
h. Failure of a proposed key subcontractor to furnish authorization for the Government to discuss its past performance with the offeror will not be considered a proposal deficiency.
However, the Government will not be able to disclose to the offeror any details pertaining to their performance problems that may impact their overall rating.
i. Technical/Risk Rating for other than past performance.
RATING DESCRIPTION
Outstanding
Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses.
Risk of unsuccessful performance is very low.
Good
Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses.
Risk of unsuccessful performance is low.
Acceptable
Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance.
Risk of unsuccessful performance is no worse than moderate.
Marginal
Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths.
Risk of unsuccessful performance is high.
Unacceptable Proposal does not meet requirements and contains one or more deficiencies.
Proposal is unawardable.
j. Past Performance Evaluation. The past performance evaluation results in an assessment of the offeror’s probability of meeting the solicitation requirements. The past performance evaluation considers each offeror's demonstrated recent and relevant record of performance in supplying products and services that meet the contract’s requirements. One performance confidence assessment rating is assigned for each offeror after evaluating the offeror's recent past performance, focusing on performance that is relevant to the contract requirements.
There are two aspects to the past performance evaluation. The first is to evaluate the offeror’s past performance to determine how relevant a recent effort accomplished by the offeror is to the effort to be acquired through the source selection. The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The Government will review this past performance information and determine the quality and usefulness as it applies to performance confidence assessment.
1. Past Performance Relevancy Ratings
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant
Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
2. Past Performance Confidence Assessments - In conducting a performance confidence assessment, each offeror shall be assigned one of the ratings in the table below:
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral)
No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
3. GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS FOR A TWO-
PHASE DESIGN- BUILD PROPOSAL.
3.1 GENERAL INSTRUCTIONS.
3.1.1 Media, Page Size, Margins, Fonts, and Page Limitations.
Submit only the hard-copy paper documents and electronic files specifically authorized elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. Do not include links to information on websites in lieu of incorporating the information physically into the proposal. Except where another size is specifically authorized for a specific submission, use only 8 1/2” x 11” paper. Use at least 1 inch margins, which may include headers and footers. Do not justify the right margin. Ensure that all text and graphics areclearly legible. Do not use a font size smaller than 10, unusual font styles such as script, or condensed fonts. For submissions with page limitations, the pages will be counted as follows: One side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, a foldout sheet will count as one page.
Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are excluded from page limitations.
3.1.2 Proposal Binding.
The preferred method for assembling proposals is a method that enables the rapid insertion or deletion of pages such as three ring binders. Ensure recommended capacity is not exceeded and that pages turn freely. Do not use spring clamps, spiral binding systems, or heat binding systems.
3.1.3 Conditioning of Offer.
Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal volumes. Inclusion of any standard company terms and conditions that conflict with the terms and conditions of the solicitation may result in a determination that the offer is unacceptable and thus ineligible for award. Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of the offer; see “Inquiries”, located in Section 00 21 16, for points of contact. Notwithstanding the above, the offeror must clearly describe in the proposal cover sheet submitted with the price volume any exceptions, within the offer, to the contractual and/or technical terms and conditions of the solicitation.
3.1.4 Restrictions on Offeror-Provided Information.
“Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can nonetheless be provided to the Government as part of the offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must clearly mark the information in accordance with FAR 52.215-1, “Instructions to Offeror – Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”. Files shall not contain classified data.
3.2 GENERAL PROPOSAL PREPARATION.
The proposal shall be submitted as summarized below and as required by the specifications.
a. Phase-One Proposal.
(1) Technical Volume
(a) Submittal Information:
--The completed Standard Form 1442 with continuation pages, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s DUNS or DUNS+4 Number is entered in the block with its name and address.
--Your acknowledgement of any and all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment.
--Joint Venture Agreement --Your completed Representations, Certifications, and Other Statements of Bidders/Offerors (Section 00 45 00).
(b) Preface
(c) Technical Factors
(1) Factor 1: Experience and Capability
(2) Factor 2: Technical Approach
(3) Factor 3: Past Performance
b. Phase-Two Proposal.
(1) Volume I – Price Volume
(a) Proposal Cover Sheet
(b) Standard Form 1442, Acknowledgement of Amendments, Joint Venture Agreement
(c) Pricing Schedule
(d) Work Breakdown Structure
(e) Bid Guarantee
(f) Pre-Award Survey Information
(2) Volume II – Technical Volume
(a) Factor 4: Technical Solution
(b) Factor 5: Management Approach
Each offeror must submit a phase-one proposal consisting of only a “technical” volume and each selected phase-two offeror must submit a phase-two proposal consisting of both a “price” volume and a “technical” volume. The price volume includes the signed offer and the offeror’s proposed prices. The technical volume includes all required information relating to the “non-price” evaluation factors. The two volumes must be submitted as separate, physically distinct volumes. Both volumes must be received at the location shown in Block 8 of Standard Form 1442, not later than the date and time specified in Block 13 of Standard Form 1442. The information in the two volumes is evaluated separately and independently. Therefore, all information intended by the offeror to be evaluated as part of the price volume must be submitted as part of the price volume. All information intended by the offeror to be evaluated as part of the technical volume must be submitted as part of the technical volume. Do not merely cross-reference similar material between the technical and price volumes.
3.2.1 Marking of Proposal Volumes.
Mark each volume as either the “Price Volume” or the “Technical Volume”. In addition, mark the outside front cover of each volume with the project title and location, solicitation number, name and address of the offeror, and volume copy number. (Markings which identify the offeror are not required on either the back cover or on the spine/binding.)
3.2.2 Tabbing of Proposal Volumes.
Offers are to be formatted and tabbed in accordance with the instructions that follow for each proposal volume.
3.2.3 Table of Contents.
Include a table of contents for each proposal volume.
4 PHASE-ONE PROPOSAL.
4.1 NUMBER OF SETS OF THE TECHNICAL VOLUME.
The Technical Proposal is to be submitted in one hard “original” and four (4) copies. In addition, submit one complete copy of the technical proposal on Compact Disk (CD).
4.2 FORMAT, CONTENTS, AND LIST OF TABS FOR THE TECHNICAL VOLUME.
Use 8-1/2” x 11” pages for the narrative portions of the proposal. There is not a page limit for the overall technical proposal; however, there may be limits imposed at the tab level. Organize your technical proposal as indicated below. The tabs directly correlate to the technical evaluation factors. Although the Government may use information contained anywhere within the technical proposal in its evaluation of any technical evaluation criteria, the Government is not obligated to search for or to consider information that is not located in the specified location.
Number the pages. Do not include information pertaining to your proposed pricing for this project in the technical proposal. Limit your submittals to the information specified; excess information will not be evaluated.
PHASE-ONE TECHNICAL VOLUME
TAB CONTENTS
1. FACTOR 1 – EXPERIENCE AND CAPABILITY
Prime Contractor/Key Subcontractor Example Projects Demonstrating Experience and Capability Prime Contractor/Key Subcontractor Corporate Resumes
2. FACTOR 2 – TECHNICAL APPROACH
Approach to the work Bonding Capability - Letter of Assurance from Bonding Agency
3. FACTOR 3 – PAST PERFORMANCE
Prime Contractor/Key Subcontractor Example Projects Past Performance Key Subcontractor Authorization Letters
4.3 DETAILED SUBMISSION REQUIREMENTS AND EVALUATION CRITERIA FOR
THE TECHNICAL PROPOSAL.
4.3.1 Preface – Prime Contractor/Key Subcontractor Introduction
a. The Offeror is required to propose a specific project team including key subcontractors for evaluation in response to this Request for Proposals. For purposes of this procurement, the terms “key subcontractors” are used to refer only to the prospective subcontractors whose qualifications, experience, and past performance will be evaluated by the Government as part of the source selection process. For reasons of efficiency, not all of the subcontractors critical to successful post-award contract performance have been included in this group. In order to streamline the proposal submission and evaluation process, please limit your submission to the information specifically requested. Information pertaining to other subcontractors not designated as “key” by the Government will be considered excess and may not be evaluated.
b. For the purposes of this procurement, a key subcontractor is defined as any subcontractor performing “key” major work elements for which capability information is required to be submitted for evaluation as part of the Offeror’s technical proposal. The Government has designated the following major work elements as “key”:
-- Architect-Engineer Design Firm
c. Any changes to key subcontractors in your Phase 2 proposal from your Phase 1 proposal will not be allowed.
d. The Offeror’s attention is directed to the clause in Section 00 73 00 titled “Personnel, Subcontractors and Outside Associates”. In accordance with this clause, any post-award changes to the key personnel and/or key subcontractors in the accepted proposal will require contracting officer approval.
e. Provide a brief introduction narrative. Identify and provide the name, DUNS number, address, point of contact e-mail address, and a brief description of the role and authority of each firm that will be involved in performance of this contract at the prime contractor and key subcontractor level. If the proposed prime contractor is a Joint Venture, describe the relationship, role, and authority (to include management authority) of each firm. (Note: If a proposed firm has branch offices, provide information for each individual branch office that will perform work under the contract with its own workforce.) List the major work elements to be self-performed by the offeror’s in-house work force, the major work elements to be performed by each key subcontractor, and any other major work to be subcontracted to other contractors. The submission is limited to two (2) 8-1/2”x11” pages for narrative.
f. The Government will not evaluate the Preface - Prime Contractor/Key Subcontractor Introduction. The purpose of this narrative is to provide a brief introduction for information purposes; however, if applicable, the government reserves the right to consider it throughout the evaluation of the other factors.
4.3.2 Tab 1 of the Technical Volume: Factor 1 – Experience and Capability.
4.3.2.1 General
a. The information provided under this tab will be used to evaluate the experience and capability of the offeror and proposed key subcontractors. The resumes and example projects will provide the primary basis for the Government’s evaluation of the offeror’s qualifications and experiences.
b. The Government is interested in selecting a contractor with the ability to demonstrate their experience and capability to reduce performance risk associated with successful completion of the project.
c. The more similarities an example project has with the prospective contract, the greater the degree of relevancy. Relevant is defined as projects similar in project type/scope, physical size, complexity;
dollar value, contract type, and degree of subcontract/teaming.
4.3.2.2. Prime Contractor/Key Subcontractor Example Projects Demonstrating Experience and Capability.
a. The offeror should if possible submit “example projects” per (1) and (2) below, that demonstrate the prime’s and/or key subcontractor’s experience and capability meeting the Evaluation Criteria to successfully perform. The offeror should explain how the work performed by the proposed firm in the example project is relevant to the subject project. Example projects can demonstrate multiple experiences and capabilities. However, if an example project is being used for multiple experiences and capabilities, ensure sufficient information is provided to demonstrate those applicable experiences and capabilities. Each example project submitted does not need to demonstrate multiple experiences and capabilities; however, all the example projects should collectively demonstrate experience and capability to perform the subject project. Submit:
(1) Two (2) but no more than three (3) example projects demonstrating the offeror’s recent/relevant design-build experience and/or capability on design-build and/or construction projects; and
(2) Two (2) but no more than three (3) example projects demonstrating the experience and capability of the Architect-Engineer design firm’s recent/relevant design and/or design-build experience and capability; and
b. Do not submit construction projects that are not substantially complete. (For this purpose, “substantially complete” means that only punch list items remain for project acceptance or that the majority of the elements of the project have been turned over to the customer for beneficial occupancy.) If a design-build project is being used by an A-E to demonstrate their design capability, the design portion of the contract must be complete in order for it to be considered.
c. Provide a Summary Matrix that indicates which submitted example project(s) demonstrates which experience and/or capability. The example provided is not mandatory, develop and provide your own matrix that best explains your proposal.
(1) The Summary Matrix is limited to one page (NTE 11” x 17”). For example:
Capability #1 #2 #3 #4 #5 Prime Contractor X X X
Architect-Engineer Design Firm
X X
d. Formatting and Other Restrictions.
(1) Start the information for each example project on a new page.
(2) Use the “Project Information Form” below to submit the example projects. Use of an alternate format could result in a lower rating if all of the specified information is not provided. (Note: Do not submit a group of related jobs as one project unless all of the work was done under the same contract, or for indefinite delivery contracts, under one task order.)
(3) The Summary Matrix is limited to one (1) 8-1/2”x11” page.
PROJECT INFORMATION FORM
1. Example Project Number: Start with “1” for the first of all submitted projects and number consecutively.
2. Name of Contractor(s)/Key Subcontractor (s) that Project is Demonstrating Experience:
Provide the name of the proposed firm(s) that this example project is demonstrating experience and capability.
3. Contract Number and Awarded Prime Contractor Name: Provide contract number assigned by the procuring Contracting Office and the name of the contractor that was awarded the contract.
4. Title and Location: Title and location of project or contract.
5. Month and Year Project Work Commenced and Month and Year Project was Completed. Include original completion date and actual completion date and a succinct description for changes in these two dates.
6. Project Owner: Project owner or user, such as a government agency or installation, an institution, or corporation or private individual.
7. Point of Contact Name: Provide name of a person associated with the project owner or the organization that contracted for the construction, who is very familiar with the project and the firm’s (or firms’) performance.
8. Point of Contact Telephone Number: Include area code.
9. Description of the Project: Provide contract type, dollar amount, physical size, and brief description of prime contracted effort. If the firm (prime/key subcontractor) performed as a subcontractor, describe the work effort pertaining to the subcontracted effort, not the prime contract requirement. For each firm (prime/key subcontractor) that was involved on the example project, provide sufficient detail to establish the relevance to the current project to include (1) the performance period in month and year, (2) original contract amount and final dollar value (include an explanation for the difference), (3) physical size and (4) principal elements and special features of the work self-performed by that contractor’s employees.
10. Provide name of firm(s) (prime/key subcontractor) and branch offices, if appropriate, that were involved in the example project, their roles, and their respective contract numbers.
11. Please list the other projects you were completing concurrently (please include dollar value for each concurrent project).
f. Evaluation Criteria.
(1) Demonstrations of experience and capability in the following areas will be evaluated for relevancy (similar project type/scope, physical size, complexity, dollar value, contract type, and degree of subcontract/teaming with the requirements of this acquisition) and recency (example projects completed before 2010 will be considered by the Government to be less recent, than projects completed on or after 2010; the more recent the project is, the greater the consideration):
(a) Prime Contractor’s general contractor/construction/project management experience and capability.
(b) Architect-Engineer Design firm’s experience and capability.
(c) Experience and capability with the typical effort and/or listed Government potential projects described in 4.3.2.1. Experience and capability specific to potential project types identified in 4.3.2.1(b) will be viewed more favorably.
(e) Experience of proper management of scope, schedule, and budget.
The more relevant and/or recent the example projects are to the above criteria the more favorable the rating.
(2) Demonstrations of experience and capability in the following areas will be considered advantageous. (A lack of any of the below items will not be considered unfavorable).
(a) Prime contractor and Architect-Engineer designer teaming experience on similar design-build projects.
(b) Prior experience on Corps of Engineers construction projects.
(c) Generally, projects performed by an office of a team member that will not be performing work on this project with its own workforce will be given less consideration than projects performed by the office that will be performing work on this project with its own workforce.
4.3.2.3. Prime Contractor/Key Subcontractor Corporate Resumes.
a. The offeror is required to submit a corporate resume for itself and each of the proposed key subcontractors. If proposing as a Joint Venture, submit a corporate resume for each firm.
b. The purpose of the corporate resume is to provide information that will substantiate that the prime and firm to which work will be subcontracted have the resources necessary and available for successful performance in the area they are proposed to perform.
c. In the event of a contractor that is part of a large, multi-segmented business concern, the information provided should directly pertain to the specific segment of the business concern (i.e., the division, group, unit, etc.) that will perform work under the prospective contract with its own workforce. Information pertaining to the business concern in general or to other offices or locations of the firm which will not be self-performing work under the prospective contract with their in-house personnel or affiliates should not be submitted.
d. A standard format for the corporate resume is not specified. However, the Government is interested in information such as the following:
(1) Contractor name, office address for the office that will be performing work under the prospective contract.
(2) Type of business organization; date organized; date and state of incorporation, if applicable.
(3) Number of personnel on the present payroll in the following categories: partners, officers, other key, remainder.
(4) Number of permanent personnel on the present payroll.
(5) Equipment owned (relevant to the work to be performed).
(6) Total value of work in past six years; Average annual gross income for the past six years.
(7) Largest job in past six years (contract amount, date completed, description, owner).
(8) Largest job ever completed (contract amount, date completed, description, owner).
(9) Type of work in which firm specializes
(10) How long the firm has been performing work similar to what they would be performing on the current acquisition.
(11) Relevant specialized experience.
(12) Relevant certifications, etc.
e. Formatting and Other Restrictions.
The submission for each contractor is limited to three (3) 8-1/2” x 11” pages.
f. Evaluation Criteria.
The information provided in the prime contractor’s corporate resumes will be evaluated to determine if the prime contractor has the resources necessary for successful performance. If there are proposed key subcontractors, the information provided in the subcontractors’ corporate resumes will be evaluated to determine if the proposed subcontractors have the resources necessary for successful performance of the identified subcontracted work. The greater the resume demonstrates the resources for successful performance of the requirement, the higher the rating.
4.3.3 Tab 2 of the Technical Proposal: Factor 2 – Technical Approach.
4.3.3.1. General
a. The information provided under this tab will be used to evaluate the offeror’s and proposed key subcontractor(s)’ approach and method to construct this project to determine the offeror’s ability to properly schedule and execute this project to ensure timely completion and a quality product. The approach and method must be in sufficient detail to clearly demonstrate (1) the offeror’s understanding of the principal components of work described in the project specifications and drawings and (2) the offeror’s understanding of the site and other conditions that could impact schedule. Two project risks that shall be addressed in offeror’s proposals are:
1) Operational Availability: The offeror should demonstrate 1) a clear understanding of the importance of operational availability of the customer’s mission systems, 2) address the understanding in their technical approach, and 3) demonstrate how they shall maintain operational availability of the customer’s equipment in a Tier III environment.
2) Ability to Execute: The offeror should demonstrate, in their proposal, the ability to meet the requirements of the solicitation within the price and schedule offered in their response.
b. The project schedule that is required is a preliminary schedule for pre-award evaluation purposes only. Therefore, the Government may at its discretion consider minor irregularities to be weaknesses in the proposal, rather than deficiencies. Nonetheless, the successful offeror will be required to submit a schedule after contract award that fully complies with all of the requirements in accordance with the submittal procedures, whether or not all pre-award discrepancies were noted or corrected during negotiations.
4.3.3.2 Narrative
a. The narrative shall demonstrate the planned approach to accomplish the project scope for both design and construction. The explanation should include the offeror’s plan to structure, organize, and manage the design-build project. Describe how the offeror plans to manage and direct the design with respect to quality and timely performance of design deliverables. The narrative shall reflect an understanding of the specifications, drawings, site, and other conditions.
b. The narrative shall also clearly demonstrate the offeror’s plan to effectively and pro-actively manage the designers, consultants and subcontractors on the team; and the ability to coordinate all work throughout the design and construction phase. The narrative shall reflect an understanding of the RFP requirements, including the required qualification of the designers.
c. Describe in general terms how the offeror will approach the safety and quality control. The narrative shall also address the offeror’s understanding of, familiarity with, and intended use of USACE-specific procedures and automated information management/tracking systems related to quality control.
d. Demonstrate the offeror’s understanding of the roles and planned interaction between the various contractor personnel involved, such as the on-site Project Superintendent, the CQC System Manager, the Site Safety and Health Officer, the CQC System Manager’s staff, and the subcontractors.
Discussion should acknowledge lines of communication with the Government team.
e. The submission may include narrative and/or graphics and is limited to eight 8-1/2” x 11” pages.
Although a standard format is not specified, the information should be presented in essentially the same order as discussed above.
f. Evaluation Criteria
(1) The Government will evaluate to determine if the offeror’s approach makes sense logically and demonstrates feasibility in the approach to structure, organize, and manage the design-build project.
As part of its evaluation, the Government will evaluate whether the offeror’s approach describes the offeror’s plans to manage and direct the design with respect to quality and timely performance of design deliverables. The greater the narrative demonstrates knowledge and understanding of the specifications, drawings, and site, the higher the evaluation rating. The Government will specifically evaluate the offeror’s approach to mitigate the project risks identified in section 4.3.3.1.
(2) The Government will evaluate to determine if the offeror’s narrative clearly demonstrates the offeror’s plan to effectively and pro-actively manage the designers, consultants and subcontractors on the team; and the ability to coordinate work throughout the design and construction phase. The greater the narrative demonstrates knowledge and understanding of the RFP requirements, including the required qualification of the designers, the higher the evaluation rating.
(3) The Government will evaluate the proposed approach to safety and quality control including the offeror’s understanding of, familiarity with, and intended use of USACE-specific procedures and automated information management/tracking systems related to quality control. The greater the narrative demonstrates knowledge and understanding of the safety and quality control requirements of the contract, the higher the rating. Any experience specific to the USACE specific procedures, will be seen as more favorable; however, a lack of USACE specific experience will not result in a less than acceptable rating.
(4) The Government will evaluate the offeror’s understanding of the roles and planned interaction between the various contractor personnel involved, such as the on-site Project Superintendent, the CQC System Manager, the Site Safety and Health Officer, the CQC System Manager’s staff, and the subcontractors. As part of its evaluation, the Government will evaluate whether the offeror includes lines of communication with the Government team. The greater the narrative demonstrates knowledge and understanding of the requirement, the higher the evaluation rating.
4.3.3.3 Project Schedule
a. The offeror shall develop a proposed construction schedule (i.e., GANTT (NOT a Pert Chart)) relating to the technical approach for construction of the project, broken down to the “Feature of Work” level, that graphically illustrates the proposed integration, scheduling, and phasing of the major features on the critical and near-critical path for this project, including final close-out. The proposed schedule shall indicate the starting and completion times of all major elements of work beginning with the notice to proceed and indicating calendar days to completion of all options.
Assume for the purposes of this submission that the Government will exercise any options at award.
The schedule shall indicate sequences proposed to accomplish each work element and appropriate interdependencies between various work elements, identify long lead items, address proper sequencing of submittals to include review time by Government personnel and submittal corrections.
The schedule shall be as realistic as possible, demonstrating the offeror’s ability to propose a schedule that identifies all major elements of work for this project, meets the Government’s requirements, and is obtainable. For the purposes of the proposal submittal, assume a Notice to Proceed (NTP) date of 21 March 2016.
b. The project schedule must not exceed the contract performance period. The offeror may propose a completion period of lesser duration, SUBJECT TO THE FOLLOWING CONDITIONS:
(1) If an offer is accepted which proposed a shorter performance period than that required by the Government, the proposed shortened performance period will be incorporated into and will become a binding part of the resultant contract. Additionally, any assessment of liquidated damages will be based on the shortened performance period accepted by the Government.
(2) A compliance statement completed by the offeror and duly executed with an original signature by an official authorized to bind the company must be included in the technical proposal under this tab.
Failure to include this signed statement may render an offer which proposes a completion period of lesser duration ineligible for contract award.
c. Formatting and Other Restrictions:
(1) There is not a page limitation for this submission; however, pages must not exceed 11” x 17” in size. Ensure the font size is legible so each activity and its duration can be read.
(2) Number line items on the project schedule for easy reference.
(3) If the offeror is proposing a shortened performance period, the technical proposal must also include the offeror’s statement of compliance with 10 U.S.C. 2858 using the following format:
OFFEROR’S STATEMENT OF COMPLIANCE WITH 10 U.S.C. 2858
[Insert name of the offeror] hereby proposes that the period of performance for all construction is _____ calendar days from Notice to Proceed, inclusive of Government review periods and Government phasing requirements specified.
[Insert name of the offeror] hereby states that the offer of this…