Amend 1 Division 01
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30 Amend 0004.pdf | ||
| Amend 0003 Specs and Drawings.pdf | ||
| SF30 Amend 0003.pdf | ||
| Amend 0002 SF30 MOD.pdf | ||
| Amend 0002 Wage Determination.pdf | ||
| Amend 0002 Div 01 Specifications.pdf | ||
| GJ FIO_Part3of3.pdf | ||
| GJ FIO_Part2of3.pdf | ||
| GJ FIO_Part1of3.pdf | ||
| SF30 Amend 1 09-R-0054.pdf | ||
| Pre-Proposal Conf Minutes 9 Sep 09.pdf | ||
| Sign In Sheet 9 Sept 09.pdf | ||
| SPECS_VOL 2.pdf | ||
| RFP 09-R-0054.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA - Grand Junction 3rd Floor Add. to Surgery Center 1678
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 SCRAP MATERIAL
1.2 WRITTEN GUARANTEES AND GUARANTOR'S LOCAL REPRESENTATIVE
1.3 PRICING OF CONTRACTOR FURNISHED PROPERTY
1.4 TEMPORARY ELECTRIC WIRING
1.4.1 Temporary Power and Lighting
1.4.2 Construction Equipment
1.4.3 Circuit Protection
1.5 UTILITIES NOT SHOWN
1.6 GENERAL SAFETY REQUIREMENTS
1.6.1 General
1.6.2 The Prime Contractor's Superintendent
1.6.3 Job Hazard Analysis
1.6.4 Violations
1.6.5 Elevated Work Areas
1.6.6 Fire Prevention
1.6.7 Record Keeping/Reporting Requirements
1.6.8 Accident Reporting
1.6.9 Monthly Safety Inspections
1.7 PLANNED UTILITY OUTAGES AND STREET CLOSURES
1.8 EXCAVATION PERMITS
1.9 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.10 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.11 EQUIPMENT DATA FORM
1.12 SPECIAL CONSTRUCTION REQUIREMENTS
1.12.1 Contractor Badges
1.12.2 Construction Security Requirements
1.12.3 Construction Restraints
1.12.4 Operations and Storage Areas
1.12.5 Alterations
1.12.6 Infection Prevention Measures
1.12.7 Disposal, Retention and Recycling
1.12.8 Protection of Existing Vegetation, Structures, Equipemnt, Utilities and Improvements
1.12.9 Restoration
1.12.10 Physical Data
1.12.11 Temporary Use of Mechanical and Electrical Equipment
1.12.12 Temporary Use of Existing Elevators
1.12.13 Occupied and Existing Buildings
1.12.14 Night Work
1.12.15 Safety Plan
1.13 LABOR RATES
1.14 WEEKLY COORDINATION MEETING
1.15 RED ZONE MEETING
1.16 MAJOR PHASE AND FINAL PROJECT COMPLETION
1.17 AFTER AWARD DOCUMENTS
1.18 MONTHLY SAFETY INSPECTION
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
01 00 00 - 1 AM-01
-- End of Section Table of Contents --
01 00 00 - 2 AM-01
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 SCRAP MATERIAL
Materials specified to be removed and become the property of the Contractor are designated as scrap, and the Contractor, by signing this contract, hereby acknowledges that he has made due allowance for value, if any, of such scrap in the contract price.
1.2 WRITTEN GUARANTEES AND GUARANTOR'S LOCAL REPRESENTATIVE
Prior to completion of the contract, the Contractor shall obtain and furnish to the Contracting Officer's representative written guarantees for all the equipment and/or appliances furnished under the contract. The Contractor shall furnish with each guarantee: The name, address, and telephone number of the guarantor's representative nearest to the location where the equipment and/or appliances are installed, who, upon request of the Using Service's representative, will honor the guarantee during the guaranty period and will provide the services prescribed by the terms of the guarantee.
1.3 PRICING OF CONTRACTOR FURNISHED PROPERTY
At the request of the Contracting Officer, the Contractor shall promptly furnish and shall cause any subcontractors to furnish, in like manner, unit prices and descriptive data required by the Government for property record purposes of fixtures and equipment furnished and installed by the Contractor.
1.4 TEMPORARY ELECTRIC WIRING
1.4.1 Temporary Power and Lighting
The Contractor shall provide construction power facilities in accordance with the safety requirements of the National Electrical Code NFPA 70 and the SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1. The Contractor, or his delegated subcontractor, shall enforce all the safety requirements of electrical extensions for the work of all subcontractors. All work shall be accomplished by skilled electrical tradesmen in a workmanlike manner, as approved by the Contracting Officer.
1.4.2 Construction Equipment
In addition to the requirements of EM 385-1-1, SAFETY AND HEALTH REQUIREMENTS MANUAL, all temporary wiring conductors installed for operation of construction tools and equipment shall be either Type TW or THW contained in metal raceways, or may be multi-conductor cord. Temporary wiring shall be secured above the ground or floor in a workmanlike manner and shall not present an obstacle to persons or equipment. Open wiring may only be used outside of buildings, and then only in strict accordance with the provisions of the National Electrical Code.
1.4.3 Circuit Protection
In addition to the present requirements in EM 385-1-1 and the National Electrical Code, all 15 and 20 ampere receptacle outlets used for obtaining power during construction shall have ground fault circuit interrupters
01 00 00 - 3 AM-01
(GFCI) for personnel protection. Block and brick saws shall also be equipped with GFCI. The Contracting Officer may allow an exception to this requirement for circuits for concrete vibrators or circuits operating at other than 60 Hertz normal (in both cases an assured grounding program as described in the National Electrical Code, except utilizing the daily inspection frequency of the grounding means of such equipment, may be permitted). The assured grounding program will not be permitted as a substitute for usage of GFCIs except as described above. All generator powered 15 and 20 ampere, 60 Hertz receptacle outlets shall have GFCIs, and shall be properly grounded. A testing means shall be provided which will impose a measured fault of 5 milliamperes, plus or minus 1 milliampere, and result in tripping the GFCI unit.
1.5 UTILITIES NOT SHOWN
If the Contractor encounters, within the construction limits of the entire project, utilities not shown on the plans and not visible as to the date of this contract and such utilities will interfere with construction operations, he shall immediately notify the Contracting Officer in writing to enable a determination by the Contracting Officer as to the necessity for removal or relocation. If such utilities are removed or relocated as directed by the Contracting Officer, the Contractor shall be entitled to equitable adjustment for any additional pertinent work or delay.
1.6 GENERAL SAFETY REQUIREMENTS
1.6.1 General
The Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, (see Contract Clauses, Section 00700, ACCIDENT PREVENTION) and the Occupational Safety and Health Act (OSHA) Standards for Construction (Title 29, Code of Federal Regulations Part 1926 as revised from time to time);
General Industry Standards (Title 29, Code of Federal Regulations Part 1910 as revised from time to time); and the National Fire Protection Association Codes (NFPA 241) are applicable to this contract. In case of conflict the most stringent requirement of the standards is applicable.
1.6.2 The Prime Contractor's Superintendent
The Prime Contractor's superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis (see below), tool box meetings, walk through inspections, correction of violations, etc., and including that of the subcontractor's work. The site Superintendent shall have a 30 hour OSHA safety course certification and assure all other contractor employees have attended the 10 hour OSHA training.
1.6.3 Job Hazard Analysis
Based on the construction schedule, the Contractor shall submit a job hazard analysis of each major phase of work prior to entering that phase of activity. The analysis shall include major or high risk hazards, as well as commonly recurring deficiencies that might possibly be encountered for that operation, and shall identify proposed methods and techniques of accomplishing each phase in a safe manner. The Prime Contractor's superintendent shall take active participation in the Job Hazard Analysis, including the subcontractors' work. Prior to start of actual work a meeting shall be held with Prime Contractor, Government, and affected subcontractor to review the Job Hazard Analysis. In addition, job site meetings shall be held to indoctrinate foreman and workers on details of this analysis.
01 00 00 - 4 AM-01
1.6.4 Violations
If recurring violations and/or gross violation indicate that the safety performance is unsatisfactory, corrective action shall be taken as directed, and at the discretion of the Contracting Officer the retention or some part thereof will be withheld from the progress payment until corrective action has been completed.
1.6.5 Elevated Work Areas
Workers in elevated work areas in excess of 6 feet above an adjoining surface require special safety attention. In addition to the provisions of EM-385-1-1, the following safety measures are required to be submitted to the Contracting Officers Representative. Prior to commencement of work in elevated work areas, the Contractor shall submit drawings depicting all provisions of his positive protection system including, but not limited to, all details of guard rails.
a. Positive protection for workmen engaged in the installation of structural steel and steel joists shall be provided by safety nets, tie-offs, hydraulic manlifts, scaffolds, or other required means. Decking crews must be tied-off or work over nets or platforms not over 6 feet below the work area. Walking on beams and/or girders and climbing of columns is prohibited without positive protection.
b. Perimeter guard rails shall be installed at floor, roof, or wall openings more than 6 feet above an adjoining surface and on roof perimeters. Rails shall be designed to protect all phases of elevated work including, but not limited to, roofing operations and installation of gutters and flashing. Rails around roofs may not be removed until all work on the roof is complete and all traffic on or across the roof ceases. Rails shall be designed by a licensed engineer to provide adequate stability under any anticipated impact loading. As a minimum, the rails shall consist of a top rail at a height of 42 inches, a mid-rail, and a toe board. Use of tie-offs, hydraulic manlifts, scaffolds, or other means of roof edge protection methods may be utilized on small structures such as family housing, prefabricated metal buildings, etc.
1.6.6 Fire Prevention
Twenty-four hours' notice shall be given to the Contracting Officer for coordination with VA personnel prior to conducting any fire hazardous operation. Cutting or welding will be permitted only in areas that are or have been made fire safe. Where possible, all combustibles shall be located at least 35 feet horizontally from the work site. Where such location is impracticable, combustibles shall be protected with fire blankets and/or protective welding screens to prevent slag from running out of the work area. Edges of covers at the floor shall be tight to prevent sparks from going under them. This precaution is also important at overlaps where several covers are used to protect a large pile. The Contractor shall not allow any welding/cutting or open flame operations in facilities that are protected by a wet pipe fire sprinkler or an automatic detection system, if the system is out of service. First priority of work will be to return the suppression/detection system to operational condition. Return the fire detection and/or suppression system back to an operational status (if possible) during periods that the facility is unoccupied, and at the end of the work day. The Contractor shall post a fire guard for a 24-hour period (or certify to the Contracting Officer that the facility is safe) after welding, cutting, and open flame operations in a facility when: (a) fire detection and suppression system
01 00 00 - 5 AM-01
cannot be returned to service; (b) fire detection or suppression systems do not exist. The Contractor is responsible for providing their own appropriate flammable storage containers and for securing their own gas cylinders. Other fire prevention precautions shall be in accordance with the latest National Fire Codes.
1.6.7 Record Keeping/Reporting Requirements
On all contract operations, the Prime Contractor shall be responsible for recording and reporting all accident exposure and experience incident work. (This includes exposure and experience of the prime contractor and his/her sub contractor(s)). As a minimum these records shall include exposure work hours and a log of occupational injuries and illnesses.
(OSHA Form 200 or state equivalent as prescribed by 29 CFR 1904.5) Reference EM 385-1-1, 01.D.04.
1.6.8 Accident Reporting
In addition to the requirements for reporting accidents in accordance with EM 385-1-1, Section 1, the Prime Contractor will submit at the 50 percent point and 100 percent of project completion, a written summary of worker's compensation claims filed by workers on the project. The report will include all subcontractors. The main report covering the Prime Contractor claims will be certified as "correct and true" by the Contractor's compensation insurance carrier. The same certification will be required for subcontractor reports.
1.6.9 Monthly Safety Inspections
A monthly on-site inspection will be made by the insurance carriers of the prime and subcontractors. The Contractor's safety program will be reviewed and a meeting will be held with the Contracting Officer's Representative to discuss the job-site safety. A written report will be made by the Contractor stating the results of the inspection and the actions taken.
1.7 PLANNED UTILITY OUTAGES AND STREET CLOSURES
Utility outages shall be restricted to off-duty hours and weekends (4:30 p.m. to 7:00 a.m.), with the outage duration not to exceed 4 hours.
Streets may be closed during normal working hours with the closure duration as short as possible. All utility outages and street closures shall be scheduled as far in advance as possible with the Contracting Officer and in no case less than 15 days before the outage or closure. The Contractor shall obtain in writing from the Contracting Officer a statement or schedule giving the permissible times of utility outages or road closures for particular installations and the maximum time allowed for such outage.
The Contractor shall strictly observe such schedules and will be held responsible for any violations. The Contractor will be required to sumita a VA Utility Shut Down Form, which will be provided after contract award.
1.8 EXCAVATION PERMITS
All excavation permits will be issued to the Contractor from the VA, through the Contracting Officer. The appropriate form, for this request, may be obtained from the Contracting Officer. Processing time required is 14 calendar days, a monthly renewal may be required. Contractor shall maintain all utility markings. Questions concerning the excavation permit should be directed to the Contracting Officer.
1.9 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with
01 00 00 - 6 AM-01
the CONTRACT CLAUSE, Section 00700, entitled "DEFAULT (FIXED PRICE CONSTRUCTION)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations.
The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON 5-DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(22) (17) (13) (08) (05) (03) (01) (02) (03) (05) (12) (22)
c. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. (ER 415-1-15, 31 OCT 89)
1.10 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
a. Allowable cost for construction and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data when the Government can determine both ownership and operating costs for each piece of equipment or equipment groups of similar serial and series from the Contractor's accounting records. When both ownership and operating costs cannot be determined from the Contractor's accounting records, equipment costs shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule", Region VII.
Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.
b. Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205 36 substantiated by certified copies of paid invoices. Rates for equipment rented from an organization under common control, lease purchase or sale leaseback arrangements will be determined using the schedule except that rental costs leased from an organization under common
01 00 00 - 7 AM-01
control that has an established practice of leasing the same or similar equipment to unaffiliated lessees are allowable. Costs for major repairs or overhaul are unallowable.
c. When actual equipment costs are proposed and the total amount of the pricing action is over $25,000, cost or pricing data shall be submitted on Standard Form 1411, "Contract Pricing Proposal Cover Sheet". By submitting cost or pricing data, the Contractor grants to the Contracting Officer or an authorizing representative the right to examine those books, records, documents and other supporting data that will permit evaluation of the proposed equipment costs. After price agreement, the Contractor shall certify that the equipment costs or pricing data submitted are accurate, complete and current.
1.11 EQUIPMENT DATA FORM
In conjunction with paragraph, EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE, above the Contractor shall furnish SPK Form 450 for all necessary equipment to perform work requiring adjustment of contract price and shall submit these forms with the modification proposals. A sample form is at the end of this section.
1.12 SPECIAL CONSTRUCTION REQUIREMENTS
1.12.1 Contractor Badges
a. Provide a list of all employees and subcontractor on site, with a copy of their drivers license or other acceptable picture ID, and keep current on a daily basis.
b. Provide all employees a laminated copy of a picture ID with a lanyard or acceptable clip device: ID must be worn in the visible location at all times when on the Medical Center Property.
1.12.2 Construction Security Requirements
a. Security Plan:
1) The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2) The Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
b. Security Procedures:
1) Contractor's employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2) For working outside the "regular hours" as defined in the contract, The Contractor shall schedule all time in no less than 10 days to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section. Failure to have identification displayed in a proper manner will be cause for removal from the Medical Center grounds.
3) No photography of VA premises is allowed without written permission of the Contracting Officer.
01 00 00 - 8 AM-01
4) Firearms and use of alcohol are prohibited on the Medical Center grounds.
5) VA reserves the right to close down or shut down the project site and order Contractor's employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
c. Guards:
1) Guards and/or required security shall be provided by the VA staff or police
d. Key Control:
1) The Contractor shall provide duplicate keys and lock combinations to the Contracting Officer for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2) The Contractor shall turn over all permanent lock cylinders to the Contracting Officer, who will turn over to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.
e. Document Control:
1) Before starting any work, the Contractor shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of "sensitive information".
2) The Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3) Certain documents, sketches, videos or photographs and drawings may be marked "Law Enforcement Sensitive" or "Sensitive Unclassified". Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4) These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5) All paper waste or electronic media such as CD's and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6) Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of "sensitive information".
7) All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
(a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
(b) "Sensitive information" including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
f. Motor Vehicle Restrictions
01 00 00 - 9 AM-01
1) Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2) Limited permits shall be issued by the Medical Center Police for the Contractor and its employees for parking in designated areas only.
Contractor employees shall park off-site.
1.12.3 Construction Restraints
a. Smoking and use of smokeless tobacco (and spitting) is not allowed in and adjacent to construction areas inside the existing building and additions under construction. Smoking is permitted only in designated areas as approved by the Contracting Officer.
b. The Contractor shall furnish and erect exterior construction fences and barricades where necessary to divert unauthorized traffic from the area and to separate and protect the construction site from unauthorized entrance or activity.
c. To minimize interference of construction activity with the flow of traffic, the method and scheduling of required cutting, altering, and removal of existing roads, walks, and entrances must be approved by the Contracting Officer.
d. Keep roads, walks, and entrances to parking and adjacent occupied buildings clear of construction materials, debris, and standing equipment and vehicles. Wherever excavation for new utility lines cross existing roads at least one lane must be open to traffic at all times. Provide a flagman where roads are limited to one lane passing due to contruction activities or when directed by Contracting Officer.
e. The Contractor shall protect existing utilities and maintain adequate storm drainage of the construction site. Temporary interruptions or shutdown of any utility or electrical/mechanical system shall be requested, in writing, from the Contracting Officer at least 15 calendar days in advance prior to the desired time. Use the VA provided "Utility Shutdown Approval" Form.
(1) No utility service such as water, gas, medical gas, steam, fuel, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the Contracting Officer.
(2) The Contractor shall submit a written request to interrupt any such services to the Contracting Officer in writing, 15 calendar days in advance of proposed interruption. The request shall state reason, date, exact time of, and approximate duration of such an interruption. Interruptions in utility services shall be of the shortest possible durations for the work at hand. All outages shall be coordinated with the VA Representativer.
(3) Any utility outages must be conducted after normal working hours or on weekends.
f. No equipment or vehicles shall be left on the streets, outside the Contractor's fenced areas, blocking access routes and/or sidewalks during off-work hours.
01 00 00 - 10 AM-01
Prior to the start of each phase, the Contractor and the Government shall conduct a joint pre-construction survey to verify existing conditions.
g. Any Contractor employee with potential to be in patient areas must be TB tested.
1.12.4 Operations and Storage Areas
a. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
b. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
c. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
d. Working space and space available for storing materials shall be as determined by the Contracting Officer.
e. Workmen are subject to rules of Medical Center applicable to their conduct.
Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times. //
f. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1) Do not store materials and equipment in other than assigned areas.
2) Provide unobstructed access to Medical Center areas required to remain in operation.
3) Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Contracting Officer. All such actions shall be coordinated with the Utility Company involved:
01 00 00 - 11 AM-01
g. 1) Phasing:
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered.
Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
h. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2100 mm (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 15 inches. Bottom of fences shall extend to one inch above grade. Remove the fence when directed by Contracting Officer.
i. When a building is turned over to Contractor, Contractor shall accept entire responsibility therefore.
1) Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2) Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman. Coordinate also with Contracting Officer.
j. Utilities Services: Maintain existing utility services for the Medical Center at all times. Provide temporary facilities, labor, materials, equipment, including temporary engine generators as required, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the Contracting Officer.
1) No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the Contracting Officer. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Medical Center Director's prior knowledge and written approval as submitted on the Energized Circuit Work Permit. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and for additional requirements.
2) Contractor shall submit a request to interrupt any such services to the Contracting Officer, in writing, 15 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3) Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved
01 00 00 - 12 AM-01
by Medical Center may occur at other than Contractor's normal working hours.
4) Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the Contracting Officer. Major interruptions are considered to be any utility interruption which impacts direct patient care space or direct patient care support space (Dietetics, Lab, etc.)
5) In case of a contract construction emergency, service will be interrupted on approval of Contracting Officer. Such approval will be confirmed in writing as soon as practical.
6) Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Contractor.
k. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned are required to be entirely removed. Open penetrations are to be covered, filled and sealed with appropriate fire stopping materials.
l. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1). Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times.
2) Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the Contracting Officer.
m. Coordinate the work for this contract with other construction operations as directed by VA Construction Inspector. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE
OF ROADWAYS.
1.12.5 Alterations
a Survey: Before any work is started, the Contractor shall make a thorough survey with the Contracting Officer and VA Representative of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1) Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered.
2) Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3) Shall note any discrepancies between drawings and existing conditions at site.
4) Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and Contracting Officer.
01 00 00 - 13 AM-01
b. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of Contracting Officer to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236 2) and "CHANGES" (FAR 52.243 4 and VAAR 852.236 88) of Section 00 72 00, GENERAL CONDITIONS.
c. Re Survey: Thirty days before expected partial or final inspection date, the Contractor and Contracting Officer together shall make a thorough re survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1) Re survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
d. Protection: Provide the following protective measures:
1) Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2) Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3) Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.12.6 Infection Prevention Measures
a. Successful contractor shall furnish a project manager on site at all times that has completed the Healthcare Construction Certification training offered by ASHE and the AHA or an equivalent Hospital Construction certification before working inside the medical center. Documentation of the training and certification will be furnished to the VA and Contracting Officer and the certificates will be kept up to date. Implement the requirements of VAMC's Infection Control Risk Assessment (ICRA) team and obtain an INFECTION CONTROL CONSTRUCTION PERMIT from the VA. ICRA Group may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded.Implement the requirements of VAMC's Infection Control Risk Assessment (ICRA) team. ICRA Group may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded.
b. Establish and maintain a dust control program as part of the contractor's infection preventive measures in accordance with the guidelines provided by ICRA Group. Prior to start of work, prepare a plan detailing project-specific dust protection measures, including periodic status reports, and submit to Contracting Officer and Facility ICRA team
01 00 00 - 14 AM-01
for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES.
c. Medical center Infection Control personnel shall monitor for airborne disease (e.g. aspergillosis) as appropriate during construction. A baseline of conditions may be established by the medical center prior to the start of work and periodically during the construction stage to determine impact of construction activities on indoor air quality. In addition:
1) The Contracting Officer and VAMC Infection Control personnel shall review pressure differential monitoring documentation to verify that pressure differentials in the construction zone and in the patient-care rooms are appropriate for their settings. The requirement for negative air pressure in the construction zone shall depend on the location and type of activity. Upon notification, the contractor shall implement corrective measures to restore proper pressure differentials as needed.
2) In case of any problem, the medical center, along with assistance from the contractor, shall conduct an environmental assessment to find and eliminate the source.
d. In general, following preventive measures shall be adopted during construction to keep down dust and prevent mold.
1) Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by VA Construction Inspector. Blank off ducts and diffusers to prevent circulation of dust into occupied areas during construction.
2) Do not perform dust producing tasks within occupied areas without the approval of the Contracting Officer. For construction in any areas that will remain jointly occupied by the medical Center and Contractor's workers, the Contractor shall:
(a) Provide dust proof temporary drywall construction barriers to completely separate construction from the operational areas of the hospital in order to contain dirt debris and dust. Barriers shall be sealed and made presentable on hospital occupied side. Install a self-closing door in a frame, commensurate with the partition, to allow worker access. Maintain negative air at all times. A fire retardant polystyrene, 6-mil thick or greater plastic barrier meeting local fire codes may be used where dust control is the only hazard, and an agreement is reached with the Contracting Officer and Medical Center.
(b) HEPA filtration is required where the exhaust dust may reenter the breathing zone. Contractor shall verify that construction exhaust to exterior is not reintroduced to the medical center through intake vents, or building openings. Install HEPA (High Efficiency Particulate Accumulator) filter vacuum system rated at 95% capture of 0.3 microns including pollen, mold spores and dust particles. Insure continuous negative air pressures occurring within the work area. HEPA filters should have ASHRAE 85 or other prefilter to extend the useful life of the HEPA. Provide both primary and secondary filtrations units. Exhaust hoses shall be heavy duty, flexible steel reinforced and exhausted so that dust is not reintroduced to the medical center. Filters shall be checked and replaced at regular intervals to maintain the integrity of the HEPA vacuum system.
(c) Adhesive Walk-off/Carpet Walk-off Mats, minimum 600mm x 900mm (24" x 36"), shall be used at all interior transitions from the construction area to occupied medical center area. These mats shall be changed as often as required to maintain clean work areas directly outside construction area at all times.
01 00 00 - 15 AM-01
(d) Vacuum and wet mop all transition areas from construction to the occupied medical center at the end of each workday. Vacuum shall utilize HEPA filtration. Maintain surrounding area frequently. Remove debris as they are created. Transport these outside the construction area in containers with tightly fitting lids.
(e) The contractor shall not haul debris through patient-care areas.
(f) Using a HEPA vacuum, clean inside the barrier and vacuum ceiling tile prior to replacement. Any ceiling access panels opened for investigation beyond sealed areas shall be sealed immediately when unattended.
(g) There shall be no standing water during construction. This includes water in equipment drip pans and open containers within the construction areas. All accidental spills must be cleaned up and dried within 12 hours. Remove and dispose of porous materials that remain damp for more than 72 hours.
(h) At completion, remove construction barriers and ceiling protection carefully, outside of normal work hours. Vacuum and clean all surfaces free of dust after the removal.
e. Final Cleanup:
1) Upon completion of project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.
2) Perform HEPA vacuum cleaning of all surfaces in the construction area. This includes walls, ceilings, cabinets, furniture (built-in or free standing), partitions, flooring, etc.
3) All new air ducts shall be cleaned prior to final inspection.
1.12.7 Disposal, Retention and Recycling
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1) Reserved items (such as desks and file cabinets) which are to remain property of the Government shall be protected in such a manner as to prevent damage which would be detrimental to re installation and reuse.
2) Items not reserved shall become property of the Contractor and be removed by Contractor from the Medical Center.
3) Contractors will make a reasonable effort to salvage or recycle all applicable waste generated during the course of the project. Alternatives to land-fill will be considered, materials appropriate for recycling or salvage will be separated and taken to a recycling facility. A report detailing the type and quantity of material recycled will be furnished to the Contracting Officer. All hazardous wastes shall be separated, stored, and disposed of according to local, state and federal regulations. Legible manifests will be provided to the Contracting Officer after disposal of hazardous waste. Any discharge into the city sewer system will require prior Contracting Officer approval, any spills into the storm drains will be reported immediately to the Contracting Officer with appropriate mitigation activity as needed. The Contractor shall have the
01 00 00 - 16 AM-01
responsibility of instructing all sub-contractors of this requirement.
1.12.8 Protection of Existing Vegetation, Structures, Equipemnt, Utilities and Improvements
a. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree pruning compound as directed by the Contracting Officer.
b. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
c. Refer to Section 01 57 20.00 10, ENVIRONMENTAL PROTECTION, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.12.9 Restoration
a. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the Contracting Officer. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the Contracting Officer before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
b. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
c. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
d. Expense of repairs to such utilities and systems not shown on drawings
01 00 00 - 17 AM-01
or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243 4 and VAAR 852.236 88) and "DIFFERING SITE CONDITIONS" (FAR 52.236 2) of Section 00 72 00, GENERAL CONDITIONS.
1.12.10 Physical Data
a. Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by the design team.
b. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.
c. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly.