Questions and Answers 6 Jul 22.docx

DOCX document 14 KB Posted

Attached to
HRF EXEVAL Role Player Support
Solicitation number
W911YP22R0020
Issued by

View the file

Other files

File Type Posted
Q and A 29 June 2022.pdf PDF
Q and A 27 June 2022.pdf PDF
PWS Role Player EXEVAL FY 22 (updated 24 May 22).docx DOCX document
Annex A - Role Player - FY22 EXEVAL (updated 24 May 22).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

On the Q & A document dated 29JUN22 in reference to role player parking, one government response says the role player parking area is 12 miles from the actual training site, but further down, another government response says it is only ¾ mile. Can the government clearly define how far the contractor will be responsible for transporting role players from their designated parking area to the actual training location?

Answer: There are two parking areas. The first is the POV parking area on Camp Williams Main directly adjacent to state route 68. This is the meeting area where POVS will park and then the role players will be transported by the contractor down to the range area and rubble pile(12 miles). There is a second parking area by the rubble pile that is 3/4 of a mile to the main footprint where the DECON line is.

During support of previous CERFP CTEs, a forklift has been required for emplacing mannequins under pieces of rubble and lifting them onto structures. Although the contractor is responsible for emplacing mannequins in the rubble pile, there is no mention of a requirement to provide a forklift. Does this mean that the training scenario will not require the placement of mannequins under heavy pieces of rubble or on top of structures?

Answer: Exact placement of mannequins and scenarios on the rubble pile is determined by exercise planners. For this exercise the contractor will only be responsible for taking the mannequins to and from the medical/DECON area to the rubble pile. The government will lift the concrete slabs and emplace the mannequins under them. Additionally, the contractor will medical tag and modulate the mannequins prior to placement on the rubble pile.