This solicitation seeks bids for a waterway signs project in Sault Ste. Marie, Michigan. The U.S. Army Corps of Engineers Detroit District requires a contractor to furnish and install new water safety signs and sign frames at the Soo Locks, including coast guard day boards, warning signs, and sign frames installed on steel cased concrete piers and a concrete block. The work includes mobilization, sign and frame installation, site restoration, and demobilization. The project cost is estimated between $500,000 and $1,000,000. The solicitation will use full and open competition under NAICS code 237990 with a $39.5 million average annual receipts size standard. The government intends to award a firm-fixed price construction contract determined by sealed bid in accordance with FAR Part 14. Interested contractors must register in the System for Award Management to conduct business with the Department of the Army Corps of Engineers Detroit District. Final questions and answers will amend the solicitation before the response date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY20 Soo Safety Signs FY20SOOSIGNS

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

08/18

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

1.1.2 Project Type

1.1.3 Submission of Submittals

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

1.4.2 For Information Only

1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL

1.5.1 O&M Data and Text of Posted Operating Instructions

1.6 PREPARATION

1.6.1 Transmittal Form

1.6.2 Submittal Format

1.6.2.1 Format of SD-01 Preconstruction Submittals

1.6.2.2 Format for SD-02 Shop Drawings

1.6.2.2.1 Drawing Identification

1.6.2.3 Format of SD-03 Product Data

1.6.2.3.1 Product Information

1.6.2.3.2 Standards

1.6.2.3.3 Data Submission

1.6.2.4 Format of SD-04 Samples

1.6.2.4.1 Sample Characteristics

1.6.2.4.2 Sample Incorporation

1.6.2.4.3 Comparison Sample

1.6.2.5 Format of SD-05 Design Data

1.6.2.6 Format of SD-06 Test Reports

1.6.2.7 Format of SD-07 Certificates

1.6.2.8 Format of SD-08 Manufacturer's Instructions

1.6.2.8.1 Standards

1.6.2.9 Format of SD-09 Manufacturer's Field Reports

1.6.2.10 Format of SD-10 Operation and Maintenance Data (O&M)

1.6.2.11 Format of SD-11 Closeout Submittals

1.6.3 Electronic File Format

1.7 QUANTITY OF SUBMITTALS

1.7.1 Number of SD-01 Preconstruction Submittal Copies

1.7.2 Number of SD-02 Shop Drawing Copies

1.7.3 Number of SD-03 Product Data Copies

1.7.4 Number of SD-04 Samples

1.7.5 Number of SD-05 Design Data Copies

1.7.6 Number of SD-06 Test Report Copies

Amendment 0001 SECTION 01 33 00 Page 1

1.7.7 Number of SD-07 Certificate Copies

1.7.8 Number of SD-08 Manufacturer's Instructions Copies

1.7.9 Number of SD-09 Manufacturer's Field Report Copies

1.7.10 Number of SD-10 Operation and Maintenance Data Copies

1.7.11 Number of SD-11 Closeout Submittals Copies

1.8 INFORMATION ONLY SUBMITTALS

1.9 PROJECT SUBMITTAL REGISTER AND DATABASE

1.9.1 Submittal Management

1.9.2 Preconstruction Use of Submittal Register

1.9.3 Action Codes

1.9.3.1 Government Review Action Codes

1.10 VARIATIONS

1.10.1 Considering Variations

1.10.2 Proposing Variations

1.10.3 Warranting that Variations are Compatible

1.10.4 Review Schedule Extension

1.11 SCHEDULING

1.11.1 QC Organization Responsibilities

1.12 GOVERNMENT APPROVING AUTHORITY

1.12.1 Review Notations

1.13 DISAPPROVED SUBMITTALS

1.14 APPROVED SUBMITTALS

1.15 WITHHOLDING OF PAYMENT

PART 2 PRODUCTS

PART 3 EXECUTION

ATTACHMENTS:

ENG Form 4025-R

-- End of Section Table of Contents --

Amendment 0001 SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

08/18

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

1.1.2 Project Type

The Contractor's Quality Control (CQC) System Manager is to check and approve all items before submittal and sign and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

1.1.3 Submission of Submittals

Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:

SD-01 Preconstruction Submittals

Submittals that are required prior to or commencing with the start of work on site.

Examples of Preconstruction Submittals include:

Construction Progress Schedule

Amendment 0001 SECTION 01 33 00 Page 3

List Of Proposed Products

Baseline Network Analysis Schedule (NAS)

Submittal Register

Schedule Of Prices Or Earned Value Report

Accident Prevention Plan

Work Plan

Quality Control (QC) plan

Environmental Protection Plan

Data Management Plan

Pre-Construction File Geodatabase Construction Site Plan Hazard Material Zones (if known) Utility Findings Data

SD-02 Shop Drawings

Drawings, diagrams and schedules submitted to the Government by the Contractor, subcontractor, or any lower tier subcontractor pursuant to a construction contract that is specifically prepared to illustrate some portion of the work. This includes:

-Detail provided by the contractor/subcontractor, manufacturer or fabricator showing the proposed fabrication and assembly of structural elements.

-Detail showing the installation (i.e., fit, and attachment details) of materials or equipment. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the contractor to explain in detail specific portions of the work required by the contract.

-Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

-The Government may duplicate, use and disclose, in any manner and for any purpose, shop drawings delivered under this contract.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Amendment 0001 SECTION 01 33 00 Page 4

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards ensuring work can be judged. Includes assemblies or portions of assemblies that are to be incorporated into the project and those that will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports

Daily logs and checklists

Final acceptance test and operational test procedure

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (SDS)concerning impedances, Amendment 0001 SECTION 01 33 00 Page 5 hazards and safety precautions.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.

Factory test reports.

SD-10 Operation and Maintenance Data

Data provided by the manufacturer, or the system provider, including manufacturer's help and product line documentation, necessary to maintain and install equipment, for operating and maintenance use by facility personnel.

Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

Data incorporated in an operations and maintenance manual or control system. Operating and maintenance manuals are referenced to feature level metadata in the file geodatabse.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings and file geodatabase. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

SD-74 Geospatial Data

Geospatial data is defined as information that identifies the geographic location and characteristics of natural or constructed features and boundaries on the earth. Geospatial data affected by these requirements are those generated in the following systems:

- Ground Penetrating Radar

- Geographic Information System (GIS);

- Land Information System (LIS);

- Remote Sensing or Image Processing system;

- Automated Mapping/Facilities Management (AM/FM) system;

- Other computer system that employs or references data using either absolute, relative, or assumed coordinates.

The geospatial data's Horizontal coordinate system is to be delivered in North American Datum (NAD) 1983, State Plane Michigan North FIPS 2111 Feet, Units – US Feet. The vertical datum will be defined in

Amendment 0001 SECTION 01 33 00 Page 6 the International Great Lakes Datum (IGLD) 1985, Units – US Feet.

SD-75 File Geodatabase (GDB)

An, Environmental Systems Research Institute (ESRI) ArcGIS, Version 10.X or ArcGIS Pro 2.X native digital format file geodatabase (GDB), with a Windows 7 or above operating system. The contractor shall ensure that all digital files and data (e.g., base files, reference files, symbol libraries, etc.) are compatible with the Government's target GIS (i.e., GIS software, operating system, RDBMS software, schema) and adhere to the standards and requirements specified herein.

The term “compatible” means that data can be accessed directly by the target system without translation, preprocessing, or post- processing of the digital data files. It is the responsibility of the contractor to ensure this level of compatibility.

1.2.2 Approving Authority

Office or designated person authorized to approve the submittal.

1.2.3 Work

As used in this section, on-site and off-site construction required by contract documents, including construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor QC approval.

Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.

1.4.2 For Information Only

Submittals not requiring Government approval will be for contractor QC approval. Within the terms of the Contract Clause 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."

1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL

As soon as practicable after award of contract, and before procurement or fabrication, forward to the Government submittals required in the technical sections of this specification, including shop drawings, product data and samples. In addition, forward a copy of the submittals to the Contracting Officer's representative.

Amendment 0001 SECTION 01 33 00 Page 7

1.5.1 O&M Data and Text of Posted Operating Instructions

Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.

In the event the Contractor fails to deliver O&M data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the items to which such O&M data apply.

1.6 PREPARATION

1.6.1 Transmittal Form

Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms are included in the RMS CM software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.6.2 Submittal Format

All electronic documents shall be dated within the body of the document.

The date in the document will govern over the file date. All requirements for .pdf format shall be submitted in searchable .pdf format whether or not the word "searchable" is used in each instance.

1.6.2.1 Format of SD-01 Preconstruction Submittals

When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.6.2.2 Format for SD-02 Shop Drawings

Provide shop drawings not less than 11x17 inches nor more than 30x42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required. Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.

a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.

b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.

Submit two (2) electronic copies of drawings in PDF format on two (2) separate discs.

Amendment 0001 SECTION 01 33 00 Page 8

1.6.2.2.1 Drawing Identification

Include on each drawing the drawing title, number, date, and revision numbers and dates.

Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.

1.6.2.3 Format of SD-03 Product Data

Present product data submittals for each section as a complete .pdf electronic file. Include a table of contents, listing the page and catalog item numbers for product data.

Indicate, by prominent notation, each product that is being submitted;

indicate the specification section number and paragraph number to which it pertains.

1.6.2.3.1 Product Information

Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.

Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.

1.6.2.3.2 Standards

Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance.

1.6.2.3.3 Data Submission

Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of the construction effort.

Submit the manufacturer's instructions before installation.

1.6.2.4 Format of SD-04 Samples

1.6.2.4.1 Sample Characteristics

Furnish full sized samples unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:

Amendment 0001 SECTION 01 33 00 Page 9

1.6.2.4.2 Sample Incorporation

Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at the time of use.

1.6.2.4.3 Comparison Sample

Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.

1.6.2.5 Format of SD-05 Design Data

Provide design data and certificates on 8 1/2 by 11 inch .pdf's.

Submittals containing numerous pages shall be grouped in one .pdf document.

1.6.2.6 Format of SD-06 Test Reports

Provide electronic reports in 8 1/2 by 11 inch .pdf's as a complete document.

By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.

1.6.2.7 Format of SD-07 Certificates

Provide design data and certificates on 8 1/2 by 11 inch .pdf's.

Submittals containing numerous pages shall be grouped in one searchable .pdf document.

1.6.2.8 Format of SD-08 Manufacturer's Instructions

Provide manufacturer's instructions submittals for each section as a complete pdf document. Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry, and technical-society publication references. If supplemental information is needed to clarify the manufacturer's data, submit it as specified for SD-07 Certificates.

Submit the manufacturer's instructions before installation.

1.6.2.8.1 Standards

Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance.

1.6.2.9 Format of SD-09 Manufacturer's Field Reports

Provide electronic reports in 8 1/2 by 11 inch complete document.

Amendment 0001 SECTION 01 33 00 Page 10

By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.

1.6.2.10 Format of SD-10 Operation and Maintenance Data (O&M)

Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.

1.6.2.11 Format of SD-11 Closeout Submittals

When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.6.3 Electronic File Format

Provide submittals in electronic .pdf format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate searchable PDF files from original documents with bookmarks so that the text included in the PDF file is searchable and can be copied. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature or a scan of a signature.

E-mail electronic submittal documents smaller than 10MB to an e-mail address as directed by the Contracting Officer. Provide electronic documents over 10 MB on an optical disc.

1.7 QUANTITY OF SUBMITTALS

1.7.1 Number of SD-01 Preconstruction Submittal Copies

Unless otherwise specified, submit one searchable electronic submittal.

1.7.2 Number of SD-02 Shop Drawing Copies

Submit searchable electronic copies of submittals of shop drawings requiring review and approval by a QC organization or requiring review and approval by the Contracting Officer.

1.7.3 Number of SD-03 Product Data Copies

Submit in compliance with quantity requirements specified for shop drawings.

1.7.4 Number of SD-04 Samples

a. Submit one sample, or set of samples showing the range of variation, of each required item. One approved sample or set of samples will be

Amendment 0001 SECTION 01 33 00 Page 11 retained by the approving authority.

b. Submit one sample panel or provide one sample installation where directed. Include components listed in the technical section or as directed.

c. Submit one sample installation, where directed.

d. Submit one sample of nonsolid materials.

1.7.5 Number of SD-05 Design Data Copies

Submit in compliance with quantity requirements specified for shop drawings.

1.7.6 Number of SD-06 Test Report Copies

Submit in compliance with quantity and quality requirements specified for shop drawings, other than field test results that will be submitted with QC reports.

1.7.7 Number of SD-07 Certificate Copies

Submit in compliance with quantity requirements specified for shop drawings.

1.7.8 Number of SD-08 Manufacturer's Instructions Copies

Submit in compliance with quantity requirements specified for shop drawings.

1.7.9 Number of SD-09 Manufacturer's Field Report Copies

Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.

1.7.10 Number of SD-10 Operation and Maintenance Data Copies

Submit a searchable electronic copy of O&M data to the Contracting Officer for review and approval.

1.7.11 Number of SD-11 Closeout Submittals Copies

Unless otherwise specified, submit two searchable electronic sets of administrative submittals each on their own disc.

1.8 INFORMATION ONLY SUBMITTALS

Submittals without a "G" designation must be certified by the QC manager and submitted to the Contracting Officer for information-only. Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans

Amendment 0001 SECTION 01 33 00 Page 12 and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.9 PROJECT SUBMITTAL REGISTER AND DATABASE

1.9.1 Submittal Management

Maintain a submittal register for the project in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM). The Government will provide the initial submittal register in electronic format.

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.

1.9.2 Preconstruction Use of Submittal Register

Submit the submittal register as an electronic database, using the submittal management program furnished to Contractor . Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following fields on the register database submitted following approval of project schedule:

Column (a) Activity Number: Activity number from the project schedule.

Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.

Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.

Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.

1.9.3 Action Codes

Entries for columns (j) and (o) are to be used as follows (others may be prescribed by the Transmittal Form):

1.9.3.1 Government Review Action Codes

"A" - "Approved as submitted"; "Completed"

"B" - "Approved, except as noted on drawings"; "Completed"

"C" - "Approved, except as noted on drawings; resubmission required"; "Resubmit"

"D" - "Returned by separate correspondence"; "Completed"

"E" - "Disapproved (See attached)"; "Resubmit"

"F" - "Receipt acknowledged"; "Completed"

Amendment 0001 SECTION 01 33 00 Page 13

"G" - "Other (Specify)"; "Resubmit"

"X" - "Receipt acknowledged, does not comply with contract requirements"; "Resubmit"

1.10 VARIATIONS

Variations from contract requirements require Contracting Officer approval pursuant to contract Clause FAR 52.236-21 Specifications and Drawings for Construction, and will be considered where advantageous to the Government.

1.10.1 Considering Variations

Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation that results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.

1.10.2 Proposing Variations

When proposing variation, provide a written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals that include variations proposed by the Contractor. Set forth in writing the reason for any variations and note such variations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.

1.10.3 Warranting that Variations are Compatible

When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.10.4 Review Schedule Extension

In addition to the normal submittal review period, a period of 14 calendar working days will be allowed for the Government to consider submittals with variations.

1.11 SCHEDULING

Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.

Amendment 0001 SECTION 01 33 00 Page 14

a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.

b. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but that have been omitted from the register or marked "N/A."

c. If the Contracting Officer's Representative agrees that the submittal is N/A the submittal will be returned to contractor with a "D" code (no further action required).

Contracting Officer review will be completed within 14 calendar working days after the date of submission unless specified differently elsewhere.

1.11.1 QC Organization Responsibilities

a. Review submittals for conformance with project design concepts and compliance with contract documents.

b. Ensure that material is clearly legible.

c. Sign the certifying statement or approval statement. The QC organization member designated in the approved QC plan is the person signing certifying statements.

e. Retain a copy of approved submittals and approved samples at the project site.

1.12 GOVERNMENT APPROVING AUTHORITY

When the approving authority is the Contracting Officer, the Government will:

a. Note the date on which the submittal was received from the QC manager .

b. Review submittals for approval within the scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with comments and markings appropriate for the action indicated.

1.12.1 Review Notations

Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "approved" or "accepted" authorize proceeding with the work covered.

Amendment 0001 SECTION 01 33 00 Page 15

b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize proceeding with the work covered provided that the Contractor takes no exception to the corrections.

c. Submittals marked "not approved," "disapproved," or "revise and resubmit" indicate incomplete submittal or noncompliance with the contract requirements or design concept. Resubmit with appropriate changes. Do not proceed with work for this item until the resubmittal is approved.

d. Submittals marked "not reviewed" indicate that the submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.

e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.

1.13 DISAPPROVED SUBMITTALS

Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause titled CHANGES. The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.14 APPROVED SUBMITTALS

The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.

Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained with in each submittal accurately conforms with the requirements of the contract documents.

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

Amendment 0001 SECTION 01 33 00 Page 16

1.15 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

Amendment 0001 SECTION 01 33 00 Page 17

01 33 00 - SUBMITTAL PROCEDURES
01 33 00 - SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
1.1.2 Project Type
1.1.3 Submission of Submittals
1.2 DEFINITIONS
1.2.1 Submittal Descriptions SD
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved G
1.4.2 For Information Only
1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.5.1 O&M Data and Text of Posted Operating Instructions
1.6 PREPARATION
1.6.1 Transmittal Form
1.6.2 Submittal Format
1.6.2.1 Format of SD-01 Preconstruction Submittals
1.6.2.2 Format for SD-02 Shop Drawings
1.6.2.2.1 Drawing Identification
1.6.2.3 Format of SD-03 Product Data
1.6.2.3.1 Product Information
1.6.2.3.2 Standards
1.6.2.3.3 Data Submission
1.6.2.4 Format of SD-04 Samples
1.6.2.4.1 Sample Characteristics
1.6.2.4.2 Sample Incorporation
1.6.2.4.3 Comparison Sample
1.6.2.5 Format of SD-05 Design Data
1.6.2.6 Format of SD-06 Test Reports
1.6.2.7 Format of SD-07 Certificates
1.6.2.8 Format of SD-08 Manufacturer's Instructions
1.6.2.8.1 Standards
1.6.2.9 Format of SD-09 Manufacturer's Field Reports
1.6.2.10 Format of SD-10 Operation and Maintenance Data O&M
1.6.2.11 Format of SD-11 Closeout Submittals

1.6.3 Electronic File Format

1.7 QUANTITY OF SUBMITTALS
1.7.1 Number of SD-01 Preconstruction Submittal Copies
1.7.2 Number of SD-02 Shop Drawing Copies
1.7.3 Number of SD-03 Product Data Copies
1.7.4 Number of SD-04 Samples
1.7.5 Number of SD-05 Design Data Copies
1.7.6 Number of SD-06 Test Report Copies
1.7.7 Number of SD-07 Certificate Copies
1.7.8 Number of SD-08 Manufacturer's Instructions Copies
1.7.9 Number of SD-09 Manufacturer's Field Report Copies
1.7.10 Number of SD-10 Operation and Maintenance Data Copies
1.7.11 Number of SD-11 Closeout Submittals Copies
1.8 INFORMATION ONLY SUBMITTALS
1.9 PROJECT SUBMITTAL REGISTER AND DATABASE
1.9.1 Submittal Management
1.9.2 Preconstruction Use of Submittal Register
1.9.3 Action Codes
1.9.3.1 Government Review Action Codes
1.10 VARIATIONS
1.10.1 Considering Variations
1.10.2 Proposing Variations
1.10.3 Warranting that Variations are Compatible
1.10.4 Review Schedule Extension
1.11 SCHEDULING
1.11.1 QC Organization Responsibilities
1.12 GOVERNMENT APPROVING AUTHORITY
1.12.1 Review Notations
1.13 DISAPPROVED SUBMITTALS
1.14 APPROVED SUBMITTALS
1.15 WITHHOLDING OF PAYMENT
PART 2 PRODUCTS
PART 3 EXECUTION

File details come from the government source that posted it. Updated .