W56MES43211446
FY15 Duluth Facility Energy Optimization, Duluth, MN
This project is being advertised as SMALL BUSINESS via Federal Business Opportunities (FBO.gov) as an Invitation for Bid (IFB).
The North American Industrial Classif ication System (NAICS) code applicable to this requirement is 236220 (Commercial and Institutional Building Construction).
The small business size standard for this requirement is less than $36.5M in average annual receipts.
The estimated price for this project is betw een $250,000 and $500,000.
NOTE: Block 11 contains full information for determining the performance period and the contractor is cautioned NOT to make any additions, deletions, or other modifications to this block.
X
LLOYD W SMITH 313-226-2797
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
14-May-2015
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10 ALT1
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________17 Jun 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING BRANCH
USACE DETROIT DISTRICT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
W911XK
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: (313) 226-2134 TEL: FAX:
W911XK-15-B-0007 50
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W911XK-15-B-0007
Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
IGF::OT::IGF
FFP
FY15 Duluth Facility Energy Optimization
**FOR ACCOUNTING PURPOSES ONLY**
FOB: Destination
MILSTRIP: W56MES43211446
PURCHASE REQUEST NUMBER: W56MES43211446
NET AMT
INSTRUCTIONS TO BIDDERS
1. A public Bid Opening will be conducted at the Contracting Office indicated in Box 7, at the date and time indicated for receipt of bids/offers in Box 13 of the Standard Form 1442 at the front of this solicitation. The Bid Opening will be broadcast via live audio telephone conference. Interested parties may access the conference by calling one of the following numbers and entering the access code when prompted. Callers may log into the conference up to 5 minutes before the stated time.
1. AUDIO CONFERENCE ACCESS INFORMATION:
2. USA Toll-Free: 888-675-2535
3. USA Caller Paid/International Toll : 215-446-0145
4. ACCESS CODE: 3071395
5. SECURITY CODE: 1234
2. All Bidders are reminded to complete and submit with your bid all FAR and DFARS Provisions related to
Representations and Certifications.
3. Bidders shall complete and submit any additional full text certifications that are included in the solicitation. An
Bidder may also complete the certifications at https://www.sam.gov in lieu of completing the representations and certifications in this solicitation provided that all the FAR and DFARS certifications contained in the solicitation have been completed on line.
4. All offerors shall be registered at https://www.sam.gov with the NAICS code that is shown on the front page of the solicitation.
5. Remember to sign the SF 1442 before submitting your bid.
NOTE: Failure to comply with the above instructions may result in a Bidder not being eligible for award.
FORMAL COMMUNICATIONS
1. INQUIRIES
Bidders shall not include identifying information in any submitted inquiry. ***Please Note: Offerors shall only submit one question per inquiry. Inquiries containing multiple questions may be rejected.
1.1 Prospective Offerors should submit questions concerning this Request for Proposal via Bidder Inquiry in ProjNet at www.projnet.org/projnet.
1.1.1 To submit and review bid inquiry items, bidders will need to be a current registered user or self register into the system. To self-register, go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.
1.1.2 From this page, you may view all bidder inquiries or add inquiry.
1.1.3 Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is: W911XK-15-B-0007 The Bidder Inquiry Key is: UB4CW2-7RPWUE
1.2 The Bidder Inquiry System will be unavailable for new inquires 5 business days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.
1.3 Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
1.4 The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
2. TELEGRAPHIC BIDS
2.1 TELEGRAPHIC BIDS ARE NOT ACCEPTABLE.
2.1.1 Any telegram to modify or withdraw a bid sent to this office must be physically delivered to the office designated for receipt of bid/offer by the date and time set for bid opening/receipt of proposals.
No one from this office will be dispatched to the local telegraph office to pick up any telegram for any reason.
3. FACSIMILE BIDS
3.1 Facsimile bids, modifications thereto, or cancellations of bid will not be accepted.
4. AMENDMENTS
4.1 Acknowledgement of each amendment by the offeror must be made in the space provided on the SF 1442, or by returning a signed copy of the amendment by the time set for receipt of proposals. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding. Questions (on a non-attribution basis) and answers shall be furnished to all prospective bidders via the web site. For security reasons all potential bidders, plan rooms and printing companies are required to register in SAM at www.sam.gov.
Section 00100 - Bidding Schedule/Instructions to Bidders
BID SCHEDULE
ITEM SUPPLIES/SERVICES
QTY
UNIT
UNIT
PRICE
TOTAL
0001 Remove and Replace Windows – Area Office, Second Floor
1 Job
0002 Base Bid – Replace exterior HID fixtures with LED – Area Office, Visitor Center, and Vessel Yard
1 Job
TOTAL AMOUNT OF BASE BID
0003 Option 1 - Replace storage tank water heater with tankless type Visitor Center
TOTAL AMOUNT OF OPTION 1
0004 Option 2 - Replace interior lighting with high efficiency fixtures – Area Office, first floor & basement
TOTAL AMOUNT OF OPTION 2
0005 Option 3 - Replace interior lighting with high efficiency fixtures – Area Office, Second Floor
TOTAL AMOUNT OF OPTION 3
0006 Option 4 – Replace interior lighting with high efficiency fixtures – Visitor Center
TOTAL AMOUNT OF OPTION 4
TOTAL AMOUNT OF ALL OPTIONS
TOTAL AMOUNT OF BID
SCOPE OF WORK
1.0 PROJECT DESCRIPTION:
The work includes a variety of electrical, mechanical, and window upgrades selected for their projected energy conservation potential. The primary objective of this project is to reduce energy consumption via natural gas and electricity through the execution of the improvements described below. The scope of work requires the contractor to provide all labor, materials, equipment, and all other items and services necessary to complete the work.
The base work includes, but is not limited to, removal and replacement of single pane windows with energy efficient double-pane windows and replacement of exterior HID fixtures with LED fixtures.
Optional bid items include but are not limited to, the replacement of water heaters and the replacement of interior lighting fixtures with more energy efficient selections. The interior lighting options are split up between the Visitor Center, Area Office second floor, and the basement and first floor of the Area Office.
The buildings will be occupied during performance of work under this contract. The portions of the contract most likely to affect occupants are the window replacement on the second floor and the interior lighting upgrades. In order to minimize impacts to the occupants, rooms shall be vacated of occupant(s) as follows: For the second floor window replacement, relocate half the floor at a time, separating rooms 206, 208, and 209 as one half and the remainder of the rooms as the second half. For interior lighting upgrades the contractor can move occupants on a one or two room basis as coordinated with the COR. All occupants will relocate to the third floor conference area in accordance the contractors proposed schedule. The Government will relocate computers and personal materials; however, relocation of office furniture will be the responsibility of the contractor. It shall be the Contractors responsibility to protect all property from damage, including dust and debris. All required work in a room, including final cleaning of the entire room, must be completed with no deficiencies prior to commencing work of any kind in another room. Before work is started, and as part of the Contractor's Work Plan submittal, the Contractor shall outline a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
All work in areas open to the public inside the Lake Superior Maritime Visistor Center, must be performed and cleaned up for the day prior to 10:00 a.m. Work in areas not open to the visiting public may be performed during normal visitation hours provided construction noise generating activities are kept to an absolute minimum. If noise levels due to the Contractors operations become a distraction to the visiting public, the Contracting Officer reserves the right to have the Contractor modify their operations, at no additional expense to the Government.
Location- All work is located at the Duluth Area Office, Lake Superior Maritime Visitor Center, and Vessel Yard Warehouses, all of which are U.S. Army Corps of Engineers facilities.
Duluth Area Office & Lake Superior Maritime Visitor Center, 600 S. Lake Ave., Duluth, MN 55802-2310 Duluth Area Office Vessel Yard, 901 Minnesota Ave, Duluth, MN 55802-2310.
Background-
Duluth Area Office- The Duluth Area Office is part of the US Army Corps of Engineers Detroit District. The Area Office and Visitor Center are separate from each other and were constructed in different time frames, however are connected with a vestibule and atrium area, which houses some museum items. The office area was constructed in two parts; the original office building, which was constructed in the early 1900's and an addition to the office that was constructed in the 1940's. The office building is three stories plus the lower level or basement, each of which is approximately 3000 square feet. Therefore, the total square footage of the office area is 12,000 square feet. The office building houses not only the Corps of Engineers on the lower level and first floor, but also other government personnel on the second and third floors. The building is primarily constructed of concrete and brick with concrete floors and a flat roof system.
Lake Superior Maritime Visitor Center- The Visitor Center was also constructed in two parts, with the original construction in 1972 and an expansion in 1978. The expansion consisted of adding wings onto each side and connecting the visitor center and office area with an atrium. The Visitor Center (10,640 sq. ft.) is a two-story building with displays, a gift shop, meeting rooms, and visitor’s restrooms. It is constructed of metal panels, double-pane glass windows and door lites, and steel doors.
Vessel Yard- The Vessel Yard serves the Duluth Area Office floating plant and survey crew. Facilities at the vessel yard include a garage (3600 sq ft), an office/storage building (3,600 sq ft), a warehouse (5,000 sq ft), a machine shop (2000 sq ft), and a welding shop 2,400 sq ft).
Historical Preservation- The Duluth Area Office has been determined eligible for listing on the National Register of Historic Places (NRHP) and the Vessel Yard is listed on the NRHP and therefore requires coordination with the Minnesota State Historic Preservation Office (SHPO). This coordination will be performed by the government upon receiving submittals from the contractor. No work shall start until the SHPO has concurred with government’s determination under Section 106 of the National Historic Preservation Act. This design is focused on maintaining the historical integrity of the facility while meeting the energy efficiency goals. It is expected that product selections will be with this goal in mind. The Secretary of Interior’s Standards for Rehabilitation shall be followed for guidance on preservation of historic buildings.
1.1 Remove and Replace Windows (Base Item):
The existing windows in the 2nd floor Area Office are single pain windows that have reached the end of their useful life. They are wood-trimmed with steel frames. The aged window frames do not provide a tight seal between the occupant and the exterior and allow significant infiltration year-round.
The Contractor shall remove and replace all thirteen (13) exterior windows located on the 2nd floor of the Area Office, as indicated on the project drawings. New windows shall be double-pane heavy duty windows with insulated, thermally broken aluminum frames. The glass shall be low-e coated in order to reduce solar heat gain, see section 2.1.11 Insulating Glass Unit for required U-factor and SHGC. Install fragment retention film on No. 4 surface (innermost, room side) to meet DoD minimum antiterrorism standard for buildings, see section 2.1.13 – 18 for details on required film.
Fig. 1 Construction Details of Typical Double-Glazing Unit
Contractor shall provide windows that match the historical aspects of the facility (i.e. the window frame is sectioned in a similar style, the functional aspects of the window remain, restoring all surfaces to match original appearance color duplication, retention of the same glass to frame ratio, matching of the historic reveal, and duplication of the frame width, depth, and such existing decorative details as arched tops, etc.) 3 There is a bird deterrent system (bird-wire) on the window sills and the contractor shall work around the wire, as to not cause damage to the system. Any bird-wire damaged during construction must be replaced back to original condition.
1.2 Replace Exterior HID Fixtures with LED (Base Item):
All wall mounted high-intensity discharge (HID) fixtures shall be removed and replaced with light-emitting diode (LED) wall mounted fixtures. Replacement should be implemented across the site to include the Visitors Center, Area Office, and Vessel Yard. As shown on the plans, new LED twist-in bulbs shall be installed in place of existing incandescent bulbs. See the drawings for an itemized list of existing fixture location and type along with replacement fixture details. All LED fixtures shall be daylight type for light color.
1.3 Replace Visitor Center Tank water Heater with Tankless Type (Option 1):
The Visitors Center has one 83 gal electric tank type water heater serving both the men’s and woman’s restrooms, located on the first floor. The contractor shall remove this water heater located in the mechanical room and install two (2) tankless electric water heaters in its place, one serving the men’s room and the other serving the woman’s room. New water heaters shall be installed in conjunction with undresink circulation pumps as indicated on the drawings. Circulator pumps shall be compatible with tankless water heater systems. Pumps shall be installed, one per bathroom, on the last sink on the hot water line. The two (2) water heaters will serve a total of eight (8) lavatories, four (4) lavatories per restroom, specific heater type, location, and electrical requirements are detailed in the drawings.
1.4 Replace Interior Lighting with High Efficiency Fixtures (Option 2, 3, &4):
The Area Office and Visitor Center are lit with T12 surface mounted lensed troffer style light fixtures with magnetic ballasts. New LED fixtures with unit drivers shall be installed in place of the existing fixtures. The replacement shall include a complete fixture replacement rather than a retrofit of the existing fixtures. Replace the T12 two lamp fixtures with surface mounted LED fixtures with equivalent lumen values. Fixtures used should be consistent throughout each building. See drawings for an itemized list of existing fixture location and type along with replacement fixture details. A total of 10 T8 fixtures, located on the Area Office first floor, shall be reused and relocated to the basement as shown on the plans.
For the Area Office first and second floor lighting, include fixture mounted dual technology occupancy sensors with photocell and dimming features. One sensor shall be installed on the first fixture of each switch circuit to control that fixture and the remaining fixtures in that series. See drawings for sensor details.
2.0 PRODUCT:
Provide manufacturer’s printed data sufficient to show that all proposed equipment comply with the specified requirements and with the manufacturer’s requirements and recommendations for the equipment specified; include data for all products used.
2.1 Windows (Base Item):
Aluminum Framing:
2.1.1 Provide windows that comply with AAMA/WDMA/CSA 101/I.S.2/A440 and the requirements specified herein. Provide windows of types, performance classes, performance grades, combinations, and sizes indicated or specified. Window materials may contain post-consumer or post-industrial recycled content. Design of windows shall accommodate hardware, glass, weather-stripping, screens, and accessories to be furnished. Each window must be a complete factory assembled unit with or without glass installed. Contractor shall field verify all window dimensions on all windows to be replaced, prior to fabrication.
Dimensions shown on drawings are for reference only. Provide windows with insulating glass and thermal break necessary to achieve a minimum Condensation Resistance Factor (CRF) of 80 when tested in accordance with AAMA 1503.
2.1.2 Casement Windows: Type C-CW30 (Casement window, CW performance classification, 30 performance grade) see North American Fenestration Standard (NAFS-08)
Ventilators must be rotary crank operated. Provide ventilators with two separate locking devices or a two-point locking device operated by rods from a single lever handle.
Conceal rods where possible. Provide casement windows in combination with fixed windows similar to existing windows.
2.1.3 Fixed Windows: Type FW-CW30 (Fixed window, CW performance classification, 30 performance grade) see North American Fenestration Standard (NAFS-08)
2.1.4 Window Anchors: Anchoring devices for installing windows must be made of aluminum, cadmium-plated steel, stainless steel, or zinc-plated steel conforming to AAMA/WDMA/CSA 101/I.S.2/A440.
2.1.5 Finishes - Anodic: Exposed aluminum surfaces must be factory finished with an anodic coating. Clean exposed aluminum surfaces and provide an anodized finish conforming to AA DAF45 and AAMA 611. Finish must be: Architectural Class II (0.01 to 0.0175 mm 0.4 mil to
0.7 mil).
2.1.6 Screens: AAMA/WDMA/CSA 101/I.S.2/A440. Provide one insect screen for each operable exterior sash or ventilator. Design screens to be easily removable from inside the building, and to permit easy access to operating hardware.
2.1.7 Weather-stripping: Provide for ventilating sections of all windows to ensure a weather-tight seal meeting the infiltration requirements specified in AAMA/WDMA/CSA 101/I.S.2/A440.
Provide easily replaceable factory-applied weather-stripping. Use molded vinyl, molded or molded-expanded neoprene or molded or expanded Ethylene Propylene Diene Terpolymer (EPDM) compression-type weather-stripping for compression contact surfaces. Use treated woven pile or wool, or polypropylene or nylon pile bonded to nylon fabric and metal or plastic backing strip weather-stripping for sliding surfaces. Do not use neoprene or polyvinylchloride weather-stripping where they will be exposed to direct sunlight.
2.1.8 Fasteners: Use fasteners as standard with the window manufacturer for windows, trim, and accessories. Self-tapping sheet-metal screws are not acceptable for material more than 2 mm 1/16 inch thick.
2.1.9 Thermal-Barrier Windows: Provide thermal-barrier windows, complete with accessories and fittings, where indicated. Specify material and construction except as follows:
1. Aluminum alloy must be 6063-T6.
2. Frame construction, including operable sash, must be factory-assembled and factory-sealed inner and outer aluminum completely separated from metal-to-metal contact. Join assembly by a continuous, concealed, low conductance divider housed in an interlocking extrusion of the inner frame. Metal fasteners, straps, or anchors will not bridge the connection between the inner and outer frame.
3. Operating hardware for each sash must consist of spring-loaded nylon cushion blocks and pin locks designed to lock in predetermined locations.
4. Sash must be completely separated from metal-to-metal contact by means of woven-pile weather-stripping, plastic, or elastomeric separation members.
Glazing:
2.1.10 Clear Glass: Type I annealed flat glass, Class 1 (clear), Quality q3, conforming to ASTM
C1036. Provide for glazing openings not indicated or specified otherwise. Use double-strength sheet glass or 3 mm (1/8 inch) float glass for all panes.
2.1.11 Insulating Glass Units: Two panes of glass separated by a dehydrated 13 mm (1/2 inch) airspace. Non-residential glazed systems (including frames, glass, and all films or coatings) shall be certified by the National Fenestration Rating Council with a whole-window Solar Heat Gain Coefficient (SHGC) maximum of 0.45 determined according to NFRC 200 procedures, a U-factor maximum of 0.40 Btu/hr-ft2-F in accordance with NFRC 100, and have a ratio of Visible Transmittance (VT) divided by SHGC not less than 1.10. The SHGC and U-factor shall be met through any combination of Low-E coatings, argon gas void filling, and tinting film. Glazing shall meet or exceed a luminous efficacy of 1.0. Dimensional tolerances shall be as specified in IGMA TR-1200. Spacer shall be black, roll-formed, thermally broken aluminum, with bent or tightly welded or keyed and sealed joints to completely seal the spacer periphery and eliminate moisture and hydrocarbon vapor transmission into airspace through the corners. Primary seal shall be compressed polyisobutylene and the secondary seal shall be a specially formulated silicone.
2.1.12 Low-E Coatings: Low-E coatings shall be low-emissivity coating placed on No. 2 and No. 3 surfaces (inside surface on both panes). Coatings can be a combination tinting and Low-E coating to help meet the requirements in paragraph 2.1.11. The coatings shall be spectrally sensitive to increase the visible transmittance of light. Furnish a 5 year warranty for coatings, providing for replacement of film if cracking, crazing, peeling or inadequate adhesion occurs.
2.1.13 Warranty for Insulating Glass Units: Warranty insulating glass units against development of material obstruction to vision (such as dust, fogging, or film formation on the inner glass surfaces) caused by failure of the hermetic seal, other than through glass breakage, for a 10-year period following acceptance of the work. Provide new units for any units failing to comply with terms of this warranty within 45 working days after receipt of notice from the Government.
Fragment Retention Film for Glass:
Fragment retention film shall be installed on the No. 4 surface (innermost, indoor side) for entire glazing surface on all 13 windows.
2.1.14 Standard Products: Provide fragment retention film which is the standard product of a manufacturer regularly engaged in the manufacture of such products and that essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening.
2.1.15 Fragment Retention Film: Fragment retention film shall be polyester, polyethylene terephthalate, or a composite, optically clear and free of waves, distortions, impurities, and adhesive lines. The film may be a single layer or laminated. Lamination of the film shall only occur at the factory of the fragment retention film manufacturer. The film shall include an abrasion resistant coating on the surface that does not receive the film adhesive. Fragment retention film shall be a minimum thickness of 0.10 mm (0.004 inch). Fragment retention film can be a combination tinting or Low-E coating to help meet the requirements in paragraph
2.1.11. The film shall be supplied with an optically clear weatherable pressure sensitive adhesive. The adhesive shall contain ultraviolet inhibitors to protect the film for its required life and shall limit ultraviolet transmission to not more than 8 percent of the radiation between 300 and 380 nanometers. The adhesive shall not be water activated. A water soluble detackifier and/or release liner may be incorporated over the adhesive to facilitate film application. The adhesive shall be 90 percent cured within 30 days of installation. Adhesives on film thicknesses of 0.25 mm 0.010 inch and greater shall be a minimum of 0.02 mm
0.0008 inch thick. The following tests to indicate compliance with specified requirements shall be performed by an independent testing laboratory, and the laboratory reports shall be signed by a responsible official of the laboratory.
2.1.16 Impact Performance: Fragment retention film shall be tested for impact in accordance with ANSI Z97.1 or 16 CFR 1201. Tests shall be conducted on fragment retention film applied to
3.1 to 6.4 mm 1/8 to 1/4 inch-thick annealed flat glass which conforms to the requirements of ASTM C1036, Type I, Class 1, Quality q3. The film tested shall be applied to the glass with a splice located at the midpoint of the specimen. Sketches showing location and configuration of splice shall be included in submitted certified test reports. After the impact portion of the test is conducted, satisfactory performance of the test specimens shall be determined using ANSI Z97.1, paragraph 5.1.3 or 16 CFR 1201, paragraph 1201.4 (e)--INTERPRETATION OF RESULTS. To be qualified for use under this specification, the manufacturer shall provide a report that the fragment retention film satisfactorily performed in accordance with ANSI Z97.1, paragraph 5.1.3 (1), (3), or (4) or with 16 CFR 1201, paragraph 1204.4 (e) (1) (i), (iv), or (v). ANSI Z97.1, paragraph 5.1.3 (2) or 16 CFR 1201, paragraph 1204.4 (e) (1)
(ii) shall not constitute passing criteria.
2.1.17 Tensile Strength: The fragment retention film samples tested shall exhibit a minimum tensile strength at break of 172.4 MPa 25,000 psi when tested in accordance with ASTM D882.
Method A, Static Weighing, Constant Rate of Grip Separation Test, shall be used to conduct this test. The rate of grip separation shall not exceed 0.2 mm/s 1/2 inch per minute.
2.1.18 Peel Strength: Testing shall be conducted following 1,200 hours accelerated weathering exposure. The fragment retention film shall exhibit a minimum peel strength of 930 N/m 5.3 pounds/inch for 0.10 mm 0.004 inch thick film and 790 N/m 4.5 pounds/inch for 0.18 mm
0.007 inch thick and thicker film when tested in accordance with ASTM D3330/D3330M.
Method A shall be used to conduct the tests. A glass substrate shall be used and a maximum dwell time of 45 days is permitted.
2.1.19 Surface Abrasion: The fragment retention film shall exhibit a change in haze not to exceed
3.2 percent following 100 turns, using 500-gram weights on a CS 10F abrasive wheel when tested in accordance with ASTM D1044.
2.1.20 Warranty: Furnish a 5 year warranty for fragment retention film material, providing for replacement of film if cracking, crazing, peeling, or inadequate adhesion occurs.
2.2 Exterior Lighting (Base Item):
LED Luminaires:
2.2.1 UL 1598, NEMA C82.77 and UL 8750. Provide luminaires as detailed on project plans.
Provide luminaires complete with light sources of quantity, type, and wattage indicated. All luminaires of the same type shall be provided by the same manufacturer.
General Requirements:
2.2.2 LED luminaire housings shall be die cast or extruded aluminum.
2.2.3 LED luminaires shall be rated for operation within an ambient temperature range of minus 30 degrees C (minus 22 degrees F) to 40 degrees C (104 degrees F).
2.2.4 Luminaires shall be UL listed for wet locations per UL 1598. Optical compartment for LED luminaires shall be sealed and rated a minimum of IP65 per NEMA IEC 60529.
2.2.5 LED luminaires shall produce a minimum efficacy as shown in the following table, tested per
IES LM-79. Theoretical models of initial raw LED lumens per watt are not acceptable.
Application Luminair Efficacy in
Lumens per Watt Exterior Pole/Arm-Mounted Area and Roadway Luminaires 65
Exterior Pole/Arm-Mounted Decorative Luminaires 65 Exterior Wall-Mounted Area Luminaires 60 Bollards 35 Parking Garage Luminaires 70
2.2.6 Housing finish shall be baked-on enamel, anodized, or baked-on powder coat paint. Finish shall be capable of surviving ASTM B117 salt fog environment testing for 2500 hours minimum without blistering or peeling. The finish color shall be similar to the existing fixtures to be replaced.
2.2.7 Luminaires shall not exceed the following IES TM-15 Backlight, Uplight and Glare (B.U.G.)
ratings:
1. Maximum Backlight (B) rating shall be determined by lighting zone in which luminaire is placed.
2. Maximum Uplight (U) rating shall be U0.
3. Maximum Glare (G) rating shall be determined by lighting zone in which luminaires are placed.
2.2.8 Luminaires shall be fully assembled and electrically tested prior to shipment from factory.
2.2.9 Luminaire lenses shall be constructed of frosted tempered glass or UV-resistant acrylic.
2.2.10 Incorporate modular electrical connections, and construct luminaires to allow replacement of all or any part of the optics, heat sinks, power supply units, ballasts, surge suppressors and other electrical components using only a simple tool, such as a manual or cordless electric screwdriver.
2.2.11 Luminaires shall have a nameplate bearing the manufacturer's name, address, model number, date of manufacture, and serial number securely affixed in a conspicuous place.
2.2.12 Luminaire must pass 3G vibration testing in accordance with NEMA C136.31.
2.2.13 All factory electrical connections shall be made using crimp, locking, or latching style connectors. Twist-style wire nuts are not acceptable.
2.2.14 Factory Applied Finish: Electrical equipment shall have factory-applied painting systems which shall, as a minimum, meet the requirements of NEMA 250 corrosion-resistance test.
LED Light Sources:
2.2.15 Correlated Color Temperature (CCT) shall be in accordance with NEMA ANSLG C78.377:
Nominal CCT: 5000 degrees K, plus or minus 275 degrees K
2.2.16 Color Consistency: Manufacturer shall utilize a maximum 4-step MacAdam ellipse binning tolerance for color consistency of LEDs used in luminaires.
LED Power Supply Units (Drivers):
2.2.17 UL 1310. LED Power Supply Units (Drivers) shall meet the following requirements:
2.2.18 Minimum efficiency shall be 85 percent.
2.2.19 Shall be designed to operate on the voltage system to which they are connected, typically ranging from 120 V to 480 V nominal.
2.2.20 Operating frequency shall be: 50 or 60 Hz.
2.2.21 Power Factor (PF) shall be greater than or equal to 0.90.
2.2.22 Total Harmonic Distortion (THD) current shall be less than or equal to 20 percent.
2.2.23 Shall meet requirements of 47 CFR 15, Class B.
2.2.24 Shall be RoHS-compliant.
2.2.25 Shall be mounted integral to luminaire. Remote mounting of power supply is not allowed.
2.2.26 Power supplies in luminaires mounted under a covered structure, such as a canopy, or where otherwise appropriate shall be UL listed with a sound rating of A.
2.2.27 Shall be equipped with over-temperature protection circuit that turns light source off until normal operating temperature is achieved.
LED Luminair Surge Protection:
2.2.28 Provide surge protection integral to luminaire to meet C Low waveforms as defined by IEEE
C62.41.2, Scenario 1, Location Category C.
2.3 Electric Tankless Water Heater (Option 1):
Tankless Units:
2.3.1 Provide commercially sourced electric on demand water heater in accordance with equipment schedule on drawings.
2.3.2 Electrical Install: Provide electrical runs for required power back to circuit breaker panel in mechanical room.
2.3.3 Plumbing: Provide required plumbing for connections to required lavatory. PEX tubing shall be used for new installed lines, connected to existing copper lines with quick connect fittings.
2.3.4 Warranty: Furnish a 10 year warranty for the heat exchanger and 1 year warranty for associated parts.
Circulation Pump:
2.3.5 The contractor shall furnish and install hot water recirculation pumps as illustrated on the plans and in accordance with the following specifications:
2.3.6 The pumps shall be of the high efficiency type specifically designed for quiet operation.
2.3.7 Pump to be suitable for 203ºF (110ºC) operation at 150 psig (10 Bar) working pressure and
115V, 60Hz, 1Phase power.
2.3.8 The pumps shall have a shaft-less, wet rotor design with a ceramic ball bearing lubricated by the system fluid.
2.3.9 Pump to have built-in temperature sensor and 24-hour, adjustable timer.
2.3.10 Motor shall be spherical with an electronically commutated, permanent magnet motor
(ECM/PM).
2.3.11 Motor shall be non-overloading at any point on the pump curve and shall have built in overload protection.
2.4 Interior Lighting (Option 2, 3, & 4):
LED Luminaires:
2.4.1 UL 1598, NEMA C82.77, UL 8750, and NFPA 70. Provide luminaires as detailed on project plans. Provide luminaires complete with light sources of quantity, type, and wattage indicated.
All luminaires of the same type shall be provided by the same manufacturer.
LED Light Housing:
2.4.2 Factory Applied Finish: Electrical equipment shall have factory-applied painting systems meeting color requirements indicated in drawings.
LED Light Sources:
2.4.3 Correlated Color Temperature (CCT) shall be in accordance with NEMA ANSLG C78.377:
Nominal CCT: 4000 degrees K: 3985 plus or minus 275 degrees K
2.4.4 Color Rendering Index (CRI) shall be: Greater than or equal to 70 for 4000 degrees K light sources.
LED Power Supply Units (Drivers):
2.4.5 UL 1310. LED Power Supply Units (Drivers) shall meet the following requirements:
2.4.5.1 Minimum efficiency shall be 85 percent.
2.4.5.2 Drive current to each individual LED shall not exceed 600 mA, plus or minus 10 percent.
2.4.5.3 Shall be designed to operate on the voltage system to which they are connected, typically ranging from 120 V to 480 V nominal.
2.4.5.4 Operating frequency shall be: 50 or 60 Hz.
3.0 EXECUTION:
3.1 Windows Installation (Base Item):
Aluminum Framing:
3.1.1 Method of Installation: Install in accordance with the window manufacturer's printed instructions and details. Build in windows as the work progresses or install without forcing into prepared window openings. Set windows at proper elevation, location, and reveal; plumb, square, level, and in alignment; and brace, strut, and stay properly to prevent distortion and misalignment. Protect ventilators and operating parts against accumulation of dirt and building materials by keeping ventilators tightly closed and locked to frame. Bed screws or bolts in sill members, joints at mullions, contacts of windows with sills, built-in fins, and subframes in mastic sealant of a type recommended by the window manufacturer. Install and caulk windows in a manner that will prevent entrance of water and wind. Fasten insect screens securely in place.
3.1.2 Dissimilar Materials: Where aluminum surfaces are in contact with, or fastened to masonry, concrete, wood, or dissimilar metals, except stainless steel or zinc, protect the aluminum surface from dissimilar materials as recommended to AAMA/WDMA/CSA 101/I.S.2/A440.
Do not coat surfaces in contact with sealants after installation with any type of protective material.
3.1.3 Anchors and Fastenings: Make provision for securing units to each other, to masonry, and to other adjoining construction.
3.1.4 Adjustments after Installation: After installation of windows and completion of glazing and field painting, adjust all ventilators and hardware to operate smoothly and to provide weathertight sealing when ventilators are closed and locked. Lubricate hardware and operating parts as necessary. Verify that products are properly installed, connected, and adjusted.
3.1.5 Cleaning: Clean interior and exterior surfaces of window units of mortar, plaster, paint spattering spots, and other foreign matter to present a neat appearance, to prevent fouling of weathering surfaces and weather-stripping, and to prevent interference with the operation of hardware.
Glazing:
3.1.6 Preparation: Preparation, unless otherwise specified or approved, shall conform to applicable recommendations in the GANA Glazing Manual, GANA Sealant Manual, IGMA TB-3001, IGMA TM-3000, and manufacturer's recommendations. Determine the sizes to provide the required edge clearances by measuring the actual opening to receive the glass. Grind smooth in the shop glass edges that will be exposed in finish work. Leave labels in place until the installation is approved, except remove applied labels on heat-absorbing glass and on insulating glass units as soon as glass is installed. Securely fix movable items or keep in a closed and locked position until glazing compound has thoroughly set.
3.1.7 Glass Setting: Shop glaze or field glaze items to be glazed using glass of the quality and thickness specified or indicated. Glazing, unless otherwise specified or approved, shall conform to applicable recommendations in the GANA Glazing Manual, GANA Sealant Manual, IGMA TB-3001, IGMA TM-3000, and manufacturer's recommendations. Aluminum windows, wood doors, and wood windows may be glazed in conformance with one of the glazing methods described in the standards under which they are produced, except that face puttying with no bedding will not be permitted. Handle and install glazing materials in accordance with manufacturer's instructions. Use beads or stops which are furnished with items to be glazed to secure the glass in place. Verify products are properly installed, connected, and adjusted.
3.1.8 Sheet Glass: Cut and set with the visible lines or waves horizontal.
3.1.9 Patterned Glass: Set glass with one patterned surface with smooth surface on the weather side. When used for interior partitions, place the patterned surface in same direction in all openings.
Fragment Retention Film for Glass:
3.1.10 Surface Preparation: Clean the glass surface, to which the fragment retention film is to be applied, of paint, foreign compounds, smears, and spatters. After the initial cleaning, further clean the surface to receive the film in accordance with the film manufacturer's instructions.
3.1.11 Application: Provide fragment retention film on window and door glass where indicated.
After surface preparation, apply the fragment retention film in accordance with the manufacturer's recommendations and instructions. Film shall be applied to the interior (room) side of the glass. Multiple applications of film to achieve specified thicknesses is not allowed.
The film shall not be applied if there are visible dust particles in the air, if there is frost on the glazing, or if any room condition such as temperature and humidity do not meet the manufacturer's instructions. After film application, maintain room conditions as required by the manufacturer's instructions to allow for proper curing of the adhesive.
3.1.12 Application to New Glass Before Glazing: Apply fragment retention film so that it extends edge to edge of the glass sheet. The film reinforced glass shall then be set into the frame with glazing compounds or gaskets as specified in Section 08 81 00 GLAZING. Ensure compatibility when contact between the glazing compounds and/or gaskets and the film occurs. Coordinate fragment retention film application and curing with the glass supplier and window or door manufacturer prior to glazing installation.
3.1.13 Cleaning: Clean the fragment retention film in accordance with the manufacturer's instructions.
3.2 Exterior Lighting (Base Item):
3.2.1 Electrical installations shall conform to IEEE C2, NFPA 70, and to the requirements specified herein.
Field Applied Painting:
3.2.2 Paint electrical equipment as required to match finish of adjacent surfaces or to meet the indicated or specified safety criteria.
3.3 Electric Tankless Water Heater (Option 1)
3.3.1 Removal and Preparation: Remove and dispose of existing 83 gallon electric tank type water heater, to include removing the water line connections and disconnecting the power.
3.3.2 Location: The mounting location for the water heater should allow for easy access and operation. The location is indicated in the drawings and shall be field adjusted by the contractor to meet manufacture’s requirements.
3.3.3 Installation: Install new electric on demand water heater units in accordance with the manufacturer's installation instructions. Electrical lines and plumbing shall be surface mounted in the mechanical room. Use galvanized rigid metal conduit for new electrical lines.
3.3.4 Pipe Insulation: Apply materials in conformance with the recommendations of the manufacturer. Install smooth and continuous contours on exposed work. Smoothly and securely paste down cemented laps, flaps, bands, and tapes. Apply adhesives on a full-coverage basis. Install insulation lengths tightly butted against each other at joints. Where lengths are cut, provide smooth and square and without breakage of end surfaces. Where insulation terminates, neatly taper and effectively seal ends, or finish as specified.
3.3.5 Electrical Requirements: Electrical installations shall conform to IEEE C2, NFPA 70, and requirements specified herein.
3.4 Interior Lighting (Option 2, 3, & 4):
3.4.1 Ensure all electrical installations conform to IEEE C2, NFPA 70, and to the requirements specified herein.
3.4.2 Suspended Fixtures: Set lighting fixtures plumb, square, and level with ceiling and walls, in alignment with adjacent lighting fixtures. Secure fixtures in accordance with manufacturers' directions and approved drawings, in conformance with the requirements of NFPA 70. Obtain approval of the exact mounting for lighting fixtures on the job before commencing installation. Independently support recessed and semi-recessed fixtures from the building structure by a minimum of four wires or straps per fixture and locate near each corner of each fixture. Ceiling grid clips are not allowed as an alternative to independently supported light fixtures. Independently support round fixtures smaller in size than the ceiling grid from the building structure by a minimum of four wires or straps per fixture spaced approximately equidistant around the fixture. Do not support fixtures by ceiling acoustical panels.
3.4.3 Field Quality Control: Upon completion of installation, verify that equipment is properly installed, connected, and adjusted. Conduct an operating test to show that equipment operates in accordance with requirements of this section.
4.0 PROJECT SCHEDULE:
The schedule shall be the basis for measuring Contractor progress. Lack of an approved schedule will result in an inability of the Contracting Officer’s Representative to evaluate the Contractor’s progress for the purposes of payment. For his Project Schedule the Contractor shall provide the following:
4.1 Feature of Work – All activities shall be identified in the project schedule according to the feature of work to which the activity belongs. Feature of work refers, but is not limited to, a work breakdown structure for the project.
4.2 Project Start Date – The schedule shall start no earlier than the date of which the Notice to Proceed was acknowledged. The Contractor shall include as the first activity in the project schedule and activity called “Start Project”. The “Start Project” activity shall have a constraint date equal to the date that the Notice to Proceed was acknowledged, and a zero-day duration. Evidence that the Contractor has started mobilization and preparation of submittal register, and other preparatory work will satisfy the requirement that work commence within ten (10) calendar days after receipt of Notice to Proceed. (See Clause titled COMMENCEMENT, PROSECUTION, AND COMPLETION
OF WORK, FAR 52.211-10.)
4.3 Interim Completion Date – No later than 30-Jan-2016, all thirteen (13) exterior windows shall be completely fabricated; all exterior lighting upgrades shall be completed; and all awarded options shall be completed.
4.4 No Work Allowed Period – 18-Jun-2016 (There is a local marathon this day)
4.5 Project Completion – All work shall be completed by 30-June-2016. Upon completion of the project remove construction debris, waste materials, packaging material and any other temporary products from the work site. The staging area shall be restored to original or better condition.
Additional Scheduling Concerns:
Other Contractors on Site: There is another contractor performing roofing work on the Duluth Area Office and it’s anticipated that this contractor will have scaffolding around the perimeter of the building through 31-Oct-2015. (See Clause titled Other Contracts, FAR 52.236-8.)
Weather: If the contractor schedules the window install during any portion of the heating season the room being worked in must be sealed off and heated to a minimum temperature of 60 degrees Fahrenheit in order to maintain thermal comfort of adjacent occupied spaces.
5.0 DELIVERY, STORAGE AND HANDLING:
Two separate contractor staging area locations are indicated on sheets 4 & 5 of the drawing set.
5.1 Deliver products in manufacturer's original containers, dry and undamaged,…