W911S7-17-B-0002_Questions_And_Answers.pdf

PDF 6 KB Posted

Attached to
Brick Wall Repair
Solicitation number
W911S7-17-B-0002
Issued by

View the file

Other files

File Type Posted
Abstract_of_Offers_2_of_2.pdf PDF
Abstract_of_Offers_1_of_2.pdf PDF
Bid_Opening_Sign-In_Sheet.pdf PDF
Amendment_0003.pdf PDF
Sign-In_Sheet.pdf PDF
Amendment_0002.pdf PDF
Admentment_0001.pdf PDF
SOW_6_June.pdf PDF
W911S7-17-B-0002.pdf PDF
8079_a1v8-2017.pdf PDF
Presolicitation_Notice_Brick_Repair_Abrams_Theater_Requirement.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911S7-17-B-0002

Questions and Answers

1. On drawings Demolition Detail 1, it appears that the brick is double layer. Detail on drawings 3 & 2 appear to show that the contractor is to install block and brick. This is confusing. Will the government please clarify the demolition detail and also what is required for the contactor to install? (block and brick)

A. The Government has provided Drawing 8079_a1v8-2017, Demolition Detail 1 which directly represents the as-built drawings the Government has for this project. The

Contractor is required to provide a block and brick parapet as shown in the Typical

Wall Detail 2 and 3 provided.

2. Are the precast blocks that are installed vertical on the exterior walls to be re-caulked?

A. Yes, with backer rod as needed.