W911S7-17-B-0002.pdf

PDF 198 KB Posted

Attached to
Brick Wall Repair Federal contract opportunity
Solicitation number
W911S7-17-B-0002
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Leonard Wood

About this file

W911S7-17-B-0002 Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Brick Wall Repair, newest first.
File Type Posted
Abstract_of_Offers_2_of_2.pdf PDF
Abstract_of_Offers_1_of_2.pdf PDF
Bid_Opening_Sign-In_Sheet.pdf PDF
W911S7-17-B-0002_Questions_And_Answers.pdf PDF
Amendment_0003.pdf PDF
Sign-In_Sheet.pdf PDF
Amendment_0002.pdf PDF
Admentment_0001.pdf PDF
SOW_6_June.pdf PDF
8079_a1v8-2017.pdf PDF
Presolicitation_Notice_Brick_Repair_Abrams_Theater_Requirement.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0010979000

1. Repair brick w all in Bldg. 804, Abrams Theater, Fort Leonard Wood, Missouri. See SOW for specif ications.

2. This acquisition is restricted to Total Small Business. The NAICIS is 238140 w ith a size stanard of $15M.

3. The magnitude of this effort is betw een $250,000 and $500,000.

4. Draw ing 8079 is electronically svailable for this project and w ill be provided at Solicitation.

5. A Site Visit w ill be conducted at 10:00AM (local time) on 14 June 2017. See FAR 52.236-27 fro details.

6. Written questions shall be submitted to shamarian.n.plummer.civa@mail.mil no later than 3:00PM(local time) June 14 2017.

080305)

X

SHAMARIAN N. PLUMMBER 573-596-1803

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

07-Jun-2017

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________120 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________26 Jun 2017 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

MICC - FT LEONARD WOOD

U.S. ARMY MISSION AND INSTALLATION CONTRACTIN

8112 NEBRASKA AVENUE, BUILDING 11400

FORT LEONARD WOOD MO 65473

W911S7

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

573-596-0267FAX:TEL: 573-596-0610 TEL: FAX:

W911S7-17-B-0002 39

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W911S7-17-B-0002

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job 0001 Repair wall Bldg 804

FFP

Remove damaged brick and provide new. Provide new metal flashing and coping as shown in drawing C8079.1 and in the specifications for bldg. 804, Abrams Theater, Fort Leonard Wood, MO., 65473.

FOB: Destination

PURCHASE REQUEST NUMBER: 0010979000

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

STATEMENT OF WORK

The Statement of Work is herein incorporated as ATTCHMENT A.

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

CLAUSES INCORPORATED BY REFERENCE

52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC

0001 120 dys. ADC 1 DIRECTORATE OF PUBLIC WORKS

W90NM5

OPERATION BRANCH

16037 MINNESOTA AVE, BUILDING 2222

FT LEONARD WOOD MO 65473-8944

FOB: Destination

W90NM5

52.211-13 Time Extensions SEP 2000

Section G - Contract Administration Data

CONTRACT ADMINISTRATION

RESPONSIBILITY FOR ADMINISTRATION OF CONTRACT

The MICC – Fort Leaonard Wood, Contracting Office is responsible for the administration of this contract. The Contracting Officer alone is authorized to take action on behalf of the Government which results in changes in the terms of the contract, including deviations from specifications, details and delivery schedules.

252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

JUN 2012

252.246-7000 Material Inspection And Receiving Report MAR 2008

CLAUSES INCORPORATED BY FULL TEXT

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)

(a) Definitions. As used in this clause--

Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.

Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.

(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall--

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:

(1) Document type. The Contractor shall use the following document type(s).

Document type: The contractor shall use the following document types.

(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.

Construction Invoice

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC HQ0490 Issue By DoDAAC W911S7 Admin DoDAAC W911S7 Inspect By DoDAAC W90NM2 Ship To Code W90NM2 Ship From Code W90NM2

(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.

(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.

Contract Administrator: ShaMarian Plummer, (573) 596-0131 ext. 61803, shamarian.n.plummer.civ@mail.mil Contracting Officer: David Westall, (573) 596-0252, david.r.westall.civ@mail.mil

(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.

(End of clause)

Section H - Special Contract Requirements

INSTRUCTION TO CONTRACTORS

H-1 USE OF TOBACCO PRODUCTS ON FORT LEONARD WOOD

The Contractor and its employees shall be familiar with and shall comply with the provisions of Executive Order 13058, Protecting Federal Employees and the Public From Exposure to Tobacco Smoke in the Federal Workplace, and Title 41 CFR Part 102-74.315 [73 Federal Register 77518, Dec. 19, 2008].

H-2 FIRE PREVENTION

a. The current Fire Regulation, AR 420-1, Chapter 25: Fire Emergency Services, and Fort Leonard Wood Supplement FLW 420-2 are by this reference made a part of this solicitation and resultant contract. The Contractor’s operations shall conform to all applicable portions of those documents. All personnel entering on duty as Contractor’s employees shall be instructed in the fire prevention program of the Post and shall be advised of the requirement of the Post Fire Regulations as they pertain to this particular contract.

b. The Contractor shall obtain a written “Hot Work Permit” (DA Form 5383-R) prior to commencing all hot work outside an approved shop area. Permits will be issued by the Fort Leonard Wood Fire Department, (573) 596-0883, after all necessary precautions have been taken, such as wetting down the area, protection of combustible material, and positioning of first aid fire extinguishers of proper type and class. Permits must be obtained in advance for use of open flame devices, such as blow torches, portable furnaces, tar kettles, or gas and electric welding and cutting equipment. Preparation and protection for such areas are the responsibility of the Contractor accomplishing the work. An inspection conducted by the Fire Department prior to commencing work may be required; however, the Contractor shall conduct an inspection of the area at least 30 minutes after completion of all work. The Contractor shall be liable for any fire loss to Government property attributable to negligence on the part of the Contractor, including failure to comply with fire prevention measures prescribed by terms of this contract.

c. The Fire Prevention-Protection Division is responsible for monitoring the Contractor in the area of fire prevention and advising the Contracting Officer of all deficiencies. The Contracting Officer will alert the Contractor if a violation is a fire hazard or fire protection deficiency.

d. The provision in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in the terms of the contract.

H-3 NORMAL WORKING HOURS

a. The Contractor shall schedule his working hours to coincide with the working hours of the military reservation.

Normal working hours of the reservation are 7:30 a.m. to 4:00 p.m., Monday thru Friday, Legal Public Holidays excepted. The Contractor shall not perform work on the reservation beyond the aforementioned working hours without the written approval of the Contracting Officer.

For informational purposes, the Government observes the following holidays:

New Year’s Day, 1 January Martin Luther King, Jr.’s Birthday, the third Monday in January Presidents’ Day, the third Monday in February Memorial Day, the last Monday in May Independence Day, 4 July Labor Day, the first Monday in September Columbus Day, the second Monday in October Veterans Day, 11 November Thanksgiving Day, the fourth Thursday in November Christmas Day, 25 December When such holidays fall on a Saturday, the preceding Friday will be considered a holiday. When such holidays fall on a Sunday, the succeeding Monday will be considered a holiday. (Applicable to Government personnel only.)

b. If the Contractor for his convenience desires to perform work during other than normal working hours or on other than normal workdays, he shall notify the Contracting Officer in writing at least 72 hours in advance. The Contractor shall not perform work beyond the normal working hours or normal workdays without the Contracting Officer’s written approval.

H-4 UTILIZATION OF HEAVY TRACKED OR WHEELED EQUIPMENT

All projects that require the use of any heavy tracked or wheeled equipment on the streets will require prior approval by the Directorate of Public Works.

H-5 PREVENTION OF TRAINEE ABUSE

The Contractor and its employees shall be familiar with and shall comply with the provisions of Fort Leonard Wood (FLW) Regulation 350-12, Training Leadership, as presently written and as subsequently amended. The Contractor, upon its request, shall be furnished with a copy of FLW Regulation 350-12. However, failure to request a copy of the regulation will not relieve the Contractor from complying with the requirements of this paragraph.

H-6 EMPLOYEES OF CONTRACTOR

a. The Contractor shall furnish to the Contracting Officer upon commencement of work under this contract a written statement containing the complete name, address, and job title of each employee including subcontractor employees engaged in performance of the work under this contract. In the event of a change in employees necessitated by illness, change in personnel, or other reasons, the Contractor shall advise the Contracting Officer of the change and shall furnish him the same information on the new employee prior to his arrival on the premises.

b. The Contractor shall be responsible for the performance and conduct of his employees, to include subcontractor employees, at all times while performing under the contract. Employees of the Contractor or subcontractor may be denied entry to the installation by the military police or other authorized Government authority if it is determined that such entry may be contrary to good order, discipline or the security of the installation. Pursuant to 18 U.S.C.

1382, the Installation Commander may bar individuals from entry on the installation.

H-7 LIABILITY OF CONTRACTOR

The Contractor shall be liable for injuries or damages to persons or property resulting from the negligent acts or omissions of the Contractor, his agents, employees and/or subcontractors.

H-8 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES FOR UNCLEARED

NON-CAC ELIGIBLE CONTRACTORS

1. The Contractor shall comply with, and in the instance of contractor/sub-contractor employees, shall ensure compliance with the following instructions when access to the Fort Leonard Wood installation/facilities are required for contract performance. These local instructions are incorporated in this contract, in order to implement local installation antiterrorism/operations security policies and procedures, and to supplement Federal Acquisition Regulation (FAR) clause 52.204-9, which, if applicable to this contract, is located in Section I. In the event of conflict between any portion of this supplement and/or FAR 52.204-9; and any other provision within the SOW, PWS, or specifications; clause 52.204-9 (if listed in Section I) shall take precedence. In the event of conflict between this supplement and any other provision within the SOW, PWS, or specifications, this supplement shall take precedence.

a. An uncleared contractor is an individual who falls into one of two categories: (1) CAC-eligible; and (2) Non-CAC eligible. The Common Access Card (CAC) is the DoD federal personal identity verification credential.

CAC Eligibility is defined in Army Directive 2014-05, dated March 7, 2014.

b. Army Directive 2014-05 provides that all contractor and/or subcontractor personnel who do not possess a CAC, another Federal personal identity verification card, or other authorized DoD identification card and who require unescorted access to Army installations must have a validated need for such access and undergo a vetting process to determine their fitness for access. Accordingly, non-CAC eligible, uncleared contractor and/or sub-contractor personnel requiring access to the Fort Leonard Wood installation and facilities, to perform under this contract, will submit personal identity information through the Fort Leonard Wood Installation Pass implementation system detailed in subparagraph (1) below. There is no charge to the Contractor or employees for this pass.

Request for pass must be submitted a minimum of ten working days prior to date access is planned.

(1) The requesting Contractor personnel and sub-contractor’s personnel shall submit their requests for installation pass to their sponsor via the web based Fort Leonard Wood Installation Pass Application IM3500 Secure Webportal, located at the following web link: https://vcc1.icmvcc.com/im3500/. The minimum information required to complete the pass application at the Fort Leonard Wood Installation Pass

Application IM3500 Secure Webportal listed in paragraph b, above, is as follows: 1. Point of Contact Email (Valid sponsor’s email address). A valid sponsor is the COR, COTR, or other Government employee designated in writing by the Contracting Officer (KO) at time of contract award, post award conference, or pre-construction conference; or the KO if no other designation is made. 2. Visitor’s email address; 3. ID Number (Visitor’s Driver’s License Number); 4. ID Jurisdiction (State that issued the visitor driver’s license); 5. Visit Start Date (The first date of visitor’s visit); 6. Visit End Date (The last date of visitor’s visit, not to exceed the length of the contract or one year, whichever is shorter); 7. Visitor’s Name (Last name, First name, Middle name & suffix); 8. Phone Number and Address; 9. Date of Birth; 10. Eye Color; 11. Hair Color; 12. Sponsoring Organization and Applicant’s Company Name. Additionally, vehicle information may be required (Vehicle VIN Number, Plate Number, Plate Jurisdiction, Vehicle Year of Manufacture, Vehicle Make, Vehicle Model, Vehicle Color, and Vehicle Type)

(2) The information collected at this website will be used by the government to query, at a minimum, the National Crime Information Center Interstate Identification Index (NCIC-III) and the Terrorist Screening Database (TSDB) to determine if the person requesting unescorted access presents a potential threat to the good order, discipline, or health and safety on the installation. Army Directive 2014- 05, enclosure 2, establishes Army policy for adjudication and screening standards to control the access of unescorted uncleared contractors (contractor and subcontractor personnel) to Army installations and facilities.

(3) Uncleared contractor personnel will, in the absence of an approved waiver, be denied unescorted access to Fort Leonard Wood should the above mentioned checks contain credible derogatory information indicating that the individual may present a threat to the good order, discipline, or health and safety on the installation. Such derogatory information includes, but is not limited to that provided within Enclosure 2, Army Directive 2014-05 (Policy and Implementation Procedures for Common Access Card Credentialing and Installation Access for Uncleared Contractors), which is available to the public at the following website: http://www.apd.army.mil/ .

(4) Access Denial Waiver Process. An explanation of the waiver process for individual denials of access is provided in Army Directive 2014-05. The denial of unescorted entry onto the military installation of one or several of the contractor’s or subcontractor’s personnel shall not be considered an excuse for nonperformance of contract requirements. Nor is the Government responsible for providing escorts for individuals denied unescorted access to the Installation.

c. All contractor and subcontractor personnel performing tasks on this contract shall at all times comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures provided herein and otherwise provided to the Contractor by an authorized Government representative.

Contractors are warned that Installation area access control plans may require increased vigilance and restrictions on access to military installations in the case of heightened Force Protection Condition (FPCON) levels. If task completion is hampered by temporary Government limitations on access to the Installation, the Contractor and Contracting Officer shall negotiate any extensions on delivery necessitated by emergency situations. In addition, if heightened security requires the submission of additional security information and/or the implementation of additional security measures the Contractor shall fully cooperate with Government security procedures and requests for information.

d. Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (CFR clause 52.204-9, Personal Identity Verification of Contract Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

e. Contractor and all associated subcontractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (Army Directive 2014-05/AR 190-13).

H-9 ACCIDENT PREVENTION AND SAFETY REQUIREMENTS

a. In order to provide safety controls for protection to the life and health of employees and other persons, for prevention of damage to property, materials, supplies and equipment, and for avoidance of work interruption in the performance of this contract, the Contractor shall comply with all pertinent provisions of the Occupational Safety and Health Act of 1970, Public Law 91-596. The Contractor shall also take or cause to be taken such additional measures as the Contracting Officer may determine to be reasonable and necessary for the purpose.

b. The Contractor shall maintain an accurate record of, and shall report to the Contracting Officer in the manner and on the forms prescribed by the Contracting Officer, exposure data and all accidents resulting in death, traumatic injury, occupational disease and damage to property, materials, supplies, and equipment incident to work performed under this contract.

c. The Contracting Officer will notify the Contractor of any non-compliance with the foregoing provisions and the action to be taken. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor or his representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

d. Compliance with the provisions of this clause by subcontractors shall be the responsibility of the Contractor.

H-10 CONTRACTOR CORRESPONDENCE AND CONTRACTUAL DOCUMENT SUBMISSION

REQUIREMENTS

All Contractor and subcontractor originated correspondence under this contract shall be on the originating firm’s letterhead, except in the case where pre-printed Government forms are used, shall be typed or handwritten in a legible manner, and shall be submitted in the signed original, with supporting copies as required by the Contracting Officer. All contractual documents shall be submitted to the Government in an electronic format and accessible through Microsoft Word/Excel or Adobe Reader (.pdf), unless otherwise stated.

H-11 QUALIFICATIONS OF CONTRACTOR PERSONNEL

Contractor Personnel: The Contractor shall be responsible for selecting and staffing personnel who are well qualified to perform the work required. No personnel will be utilized to perform the work of any wage classification required to perform the tasks called for by the contract, which does not possess the necessary training and experience to qualify as a Journeyman in the particular occupational classifications the work is associated with in the local area (Missouri).

Apprentices and Trainees: A limited number of apprentices and trainees may be utilized to perform contract requirements to the extent permitted by FAR 52.222-9 and the regulations cited therein.

Qualifications: Unless another standard is required by law or specified elsewhere in the specifications for a particular occupational classification, the standard to be applied in determining an individual’s qualifications to perform at the Journeyman level shall be as follows: A Journeyman is an individual who has been performing work in a particular building trade for at least four years under the supervision of a Master. A Master id defined as an individual who has at least four years of satisfactory experience as a Journeyman in a particular building trade.

H-12 Not Applicable

H-13 BID GUARANTEE AND BOND REQUIREMENTS

a. BID GUARANTEE. The offeror (bidder) shall furnish a hardcopy bid guarantee in the form of a firm commitment, such as a bid bond, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States in accordance with FAR Clause 52.228-1, Bid Guarantee, stated elsewhere in the solicitation. The bid guarantee shall be twenty percent (20%) of the bid price or $3,000,000 whichever is lesser. The penal sum may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid guarantee is not required for bids of $150,000 or less. For contracts with option years the bid guarantee shall be twenty percent (20%) of the bid price for the base period of performance or $3,000,000 whichever is less.

b. PERFORMANCE AND PAYMENT BONDS. The Contractor shall furnish a hardcopy Performance Bond (Standard Form 25) and a hardcopy Payment Bond (Standard Form 25-A), each with good and sufficient surety or sureties acceptable to the Government within ten (10) days after contract award date.

c. On requirements-type contracts, performance and payment bonds will be required on the first delivery order issued under the contract. Thereafter as additional delivery orders (DD Form 1155) are issued the contractor shall cause the penal amount of each bond to be increased to equal the total contract price as of the date of the most current delivery order. The contractor shall utilize a Standard Form 1415, (Consent of Surety and Increase of Penalty) to increase the penal sum. The initial performance bond (SF 25) and payment bond (SF 25-A) shall be submitted within seven (7) days after the date of the initial order (Block 3 of DD Form 1155). Thereafter a SF 1415 shall be submitted within seven (7) after the execution of each additional delivery order. The contractor may not proceed with the work on any delivery order until the penal sum of the performance and payment bonds has been adjusted to reflect the total contract price.

d. The penal amount of the performance bond shall equal—

(1) Performance Bond: The penal amount of the performance bond shall equal one hundred percent (100%) of the contract/delivery order price.

(2) Payment Bond: The penal amount of payment bonds shall equal one hundred percent (100%) of the contract/delivery order price.

e. Should a contractor performing a Requirements Contract determine during contract performance that it wishes to utilize a different Surety for future delivery orders; the contractor shall obtain a Consent of Surety (SF 1414) from the existing Surety prior to submitting any bonds from an alternative Surety to the Contracting Officer.

H-14 REQUIRED INSURANCE

a. The Contractor shall, at its own expense, procure and maintain during the entire period of his performance under this contract the following minimum insurance:

TYPE AMOUNT

(1) Workmen’s Compensation Workmen’s Compensation Insurance Shall comply with applicable Federal and State Workers’ compensation and occupational disease statutes and shall extend to cover employee’s liability for accidental bodily injury or death and for occupational disease with a minimum liability of the greater of: $100,000.00 or the State minimum Requirements

(2) Comprehensive General Liability with minimum limits of:

Per accident or occurrence for bodily injury $500,000.00

(3) Comprehensive Automobile Liability with minimum limits of:

Per Person $200,000.00 Per Accident for Bodily Injury $500,000.00 Per Accident for Property Damage $ 20,000.00

b. Prior to commencement of work hereunder, the Contractor shall furnish to the Contracting Officer, a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance shall not be effective for such periods as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the Contracting Officer.

c. The Contractor shall insert the substance of this clause, including this paragraph c, in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule, or elsewhere in the contract. At least five (5) days before entry of each such subcontractor’s personnel on the government installation, the contractor shall furnish (or ensure that there has been furnished) to the Contracting Officer a current certificate of insurance, meeting the requirements of paragraph b above, for each such subcontractor.

H-15 TAXES

The Missouri Department of Revenue agrees that contractors, subcontractors and material suppliers may claim an exemption from Missouri sales and use tax with respect to tangible personal property and materials purchased or used for the purpose of constructing, repairing or remodeling facilities for the United States of America, its agencies and instrumentalities (“the United States”). Therefore, the Contracting Officer shall provide a project exemption certificate to the successful contractor awarded this project. The Contractor shall further provide the project exemption to all subcontractors purchasing construction materials for this project.

NOTE: THE PROJECT EXEMPTION CERTIFICATE DOES NOT ALLOW CONTRACTORS TO PURCHASE

MACHINERY, EQUIPMENT, OR TOOLS USED IN FULFILLING THIS CONTRACT, TAX EXEMPT.

H-16 MATERIAL PAYMENT AUTHORIZATION

Consideration is hereby authorized for progress payments to the Contractor for materials to be utilized on the work covered by this contract, delivered to the Contractor at locations other than the site. The Contractor must furnish satisfactory evidence that he has acquired title to such material and the material will be inventoried by the Government. The reimbursement by the Government shall not be construed as relieving the Contractor from the sole responsibility for the protection and the security of the material or as waiving the right of the Government to require the fulfillment of all of the terms of the contract.

H-17 INSPECTION OF WORK

Technical surveillance of workmanship and inspection of materials for work being performed under this contract shall be the responsibility of the Director of Public Works or his authorized representative. This provision in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in the terms of the contract. In the event it is determined necessary to designate a COR for this contract, such designation shall be by a separate letter to the individual selected with a copy furnished to the Contractor.

H-18 PREPARATION OF PROGRESS SCHEDULES AND REPORTS

The reports contemplated by the clause herein entitled “Schedules for Construction Contracts” shall be accomplished on and in accordance with instructions pertaining to the forms, Contract Progress Schedule and Contract Progress Report. All contractual documents shall be submitted to the Government in an electronic format and accessible through Microsoft Word/Excel or Adobe Reader (.pdf), unless otherwise stated.

H-19 POSTAWARD ORIENTATION

A Postaward Orientation will be scheduled by the Contracting Officer after contract award and prior to commencement of work. The Contracting Officer will notify the Contractor of the time and date set for the meeting that will be held at Fort Leonard Wood, MO. At this meeting, the Contractor will be oriented with respect to Government procedures and line of authority, as well as contractual, administrative, and construction matters. The Contractor is required to furnish a current Certificate of Insurance and a letter appointing a construction superintendent at the meeting. The Contractor is responsible for costs associated with any scheduled conference.

H-20 UTILITIES

At work sites where Government utilities are currently available, the Government will provide necessary utilities for the completion of the work at no charge to the Contractor. The Contractor must satisfy himself as to the extent of Government utility services available at each site and include any costs associated with the providing of necessary utilities, not available from the Government, in the prices bid for the applicable bid item.

H-21 EXCAVATION PERMIT REQUEST

If this project requires an excavation permit, the following procedures will apply:

a. The Contractor is required to process an Excavation Permit, FLW Form 364, prior to any digging of six inches (6”) or deeper, including installing posts or planting trees. Coordination with other Contractors and Army Agencies is required to properly locate all underground utilities. Utilities identified in the immediate area of the excavation site shall be located and marked prior to the Contractor proceeding with the excavation.

b. The Contractor shall make contact with the following contractors and Army Agencies at least two working days, but not more than ten working days, from the day excavations are expected to begin. An on-site meeting shall be held in advance to specifically point out the excavation location and to provide time for these persons to locate and mark underground utilities. A signature is required from each point of contact in order for DPW to approve the excavation permit. The completed excavation permit shall be furnished to the DPW Work Management office, Building 2200 for approval. A copy of the approved permit shall be furnished to the DPW Inspection Branch, Building 2202.

c. POINTS OF CONTACT:

1. To locate telephone lines owned by United Telephone System:

POC: Missouri One Call, Phone: 1-800-DIG-RITE

Information you will need: (a) Name, address and phone number of your company; (b) excavation location to include township, range, section and quarter section or street name and address/building number; (c) type of work and depth to be excavated.

You will be given a serial number for your project. KEEP FOR YOUR RECORDS. Note the time and date of your call. Once you have the serial number you need to contact Sam Spade, (573) 336-4242 or

(573) 336-4300, to arrange a meeting time.

2. To locate cable television lines (48 hour notice required):

POC: Cable America Dispatch, Phone: (573) 336-5284

3. To locate U.S. Army telephone lines:

POC: NEC, phone (573) 596-0680

4. To locate J-SIIDS lines, security alarm systems (located only at the Ammo supply Point):

POC: DOL, Phone: (573) 596-0874

5. To locate natural gas pipelines:

POC: Omega Pipeline Company (on FLW), Phone: (800) 282-4916 Missouri Gas Company (Railroad ROW) Phone :( 800) DIG-RITE

6. To locate underground primary (12.47/7.2 KV) electrical lines and area lighting circuits:

POC: Ext. Primary Electric, Phone: (573) 596-0068

7. To locate water, sanitary sewer, LLPG, fuel oil, steam, and EMCS (Energy Monitoring and Control System) lines, secondary Electrical line, chilled water, high temperature and cathodic Protection lines:

POC: Base Maintenance, Phone: (573) 596-0074

d. If any utilities are cut or damaged during excavations, the Contractor shall immediately notify the DPW Inspection Office, 573-596-0907

e. Only one approved permit is required per project. If a project entails a large scope of excavations, the utilities should be located in increments of work not exceeding one week’s worth of digging operations. This will ensure that markings and flags used to locate underground utilities are not disturbed before digging can begin. If the Contractor elects to have the utilities located in increments, the Contractor shall conduct an on-site meeting for each increment documenting the times, dates, and POCs in case of discrepancies.

f. A blank excavation permit can be obtained at the publications Office, Building 2314, or in the Work Management Office, DPW, Building 2200.

g. The Contractor is required to furnish the Contracting Officer with a drawing identifying any utility or other item permanently installed below the ground surface. If utilities, abandoned lines, or other items are uncovered during excavations which were not identified by excavation permit coordinators, these shall also be identified to the government. This is important in order to update basic information maps. The DPW Inspection Branch is at 573- 596-0907, Building 2202, or contact your Government inspector.

5152.233‐4000 AMC‐LEVEL PROTEST PROGRAM (Feb 2014) (LOCAL CLAUSE)

Prior to submitting an agency protest, it is preferable that you first attempt to resolve your concerns with the responsible contracting officer. However, you may also file a protest to the Headquarters (HQ), Army Materiel Command (AMC). The HQ AMC‐Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office (GAO) or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. The AMC protest decision goal is to resolve protests within 35 calendar days from filing. To be timely, protests must be filed within the periods specified in FAR

33.103. If you want to file a protest under the HQ AMC‐Level Protest Program, the protest must request resolution under that program and be sent to the address below.

Headquarters U.S. Army Materiel Command Office of Command Counsel‐Deputy Command Counsel 4400 Martin Road Rm: A6SE040.001 Redstone Arsenal, AL 35898‐5000 Fax: (256) 450‐8840 or email usarmy.redstone.usamc.mbx.protests@mail.mil

The AMC‐Level Protest procedures are found at:

http://www.amc.army.mil/amc/commandcounsel.html.

If internet access is not available, contact the contracting officer or HQ, AMC to obtain the HQ AMC‐Level Protest Procedures.

(End of Clause)

Section I - Contract Clauses

52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or

Improper Activity

MAY 2014

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal

Transactions

OCT 2010

52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights

APR 2014

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper

MAY 2011

52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

OCT 2016

52.204-13 System for Award Management Maintenance OCT 2016 52.209-6 Protecting the Government's Interest When Subcontracting

With Contractors Debarred, Suspended, or Proposed for Debarment

OCT 2015

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.211-10 Commencement, Prosecution, and Completion of Work APR 1984 52.214-29 Order Of Precedence--Sealed Bidding JAN 1986 52.219-3 Notice of HUBZone Set-Aside or Sole Source Award NOV 2011 52.219-8 Utilization of Small Business Concerns NOV 2016 52.219-14 Limitations On Subcontracting NOV 2011 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime

Compensation

MAY 2014

52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and

Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for

Construction

APR 2015

52.222-34 Project Labor Agreement MAY 2010 52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016

52.222-40 Notification of Employee Rights Under the National Labor Relations Act

DEC 2010

52.222-50 Combating Trafficking in Persons MAR 2015 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

MAY 2008

52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving

AUG 2011

52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-1 Authorization and Consent DEC 2007 52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-1 Bid Guarantee SEP 1996 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-16 Progress Payments APR 2012 52.232-17 Interest MAY 2014 52.232-23 Alt I Assignment of Claims (May 2014) - Alternate I APR 1984 52.232-27 Prompt Payment for Construction Contracts MAY 2014 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

JUL 2013

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984

52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Items JAN 2017 52.246-12 Inspection of Construction AUG 1996 52.249-2 Alt I Termination for Convenience of the Government (Fixed-

Price) (Apr 2012) - Alternate I

SEP 1996

52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies

DEC 2008

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.204-7006 Billing Instructions OCT 2005 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By

The Government of a Country that is a State Sponsor of Terrorism

OCT 2015

252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials

SEP 2014

252.225-7001 Buy American And Balance Of Payments Program-- Basic (Dec 2016)

DEC 2016

252.225-7002 Qualifying Country Sources As Subcontractors DEC 2016 252.225-7012 Preference For Certain Domestic Commodities DEC 2016 252.232-7004 DOD Progress Payment Rates OCT 2014 252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.247-7023 Transportation of Supplies by Sea APR 2014 252.247-7024 Notification Of Transportation Of Supplies By Sea MAR 2000

52.202-1 DEFINITIONS (NOV 2013)

When a solicitation provision or contract clause uses a word or term that is defined in the Federal Acquisition Regulation (FAR), the word or term has the same meaning as the definition in FAR 2.101 in effect at the time the solicitation was issued, unless--

(a) The solicitation, or amended solicitation, provides a different definition;

(b) The contracting parties agree to a different definition;

(c) The part, subpart, or section of the FAR where the provision or clause is prescribed provides a different meaning;

or

(d) The word or term is defined in FAR Part 31, for use in the cost principles and procedures.

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120-calendar days after issuance of the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to…