W911KB-10-B-0001-0004.pdf

PDF 57 KB Posted

Attached to
2010-2012 Maintenance Dredging, Nome Harbor, Nome Alaska
Solicitation number
W911KB-10-B-0001
Issued by

About this file

Amendment 0004 with Spec changes.

View the file

Other files

File Type Posted
10B0001Nomebidabstract.pdf PDF
W911KB10B00010005.pdf PDF
W911KB-10-B-0001-0003.pdf PDF
Amend 0003 drawing.pdf PDF
W911KB-10-B-0001-0002.pdf PDF
W911KB10B00010001.pdf PDF
01 22 00 00 10.pdf PDF
01 35 26.pdf PDF
00 73 00 00 29.pdf PDF
Dwgs-NOM008-BID.pdf PDF
W911KB10B0001.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Reference Project Title and Location: 2010-2012 Maintenance Dredging, Nome Harbor, Nome, Alaska

a. The above numbered Solicitation is hereby amended to add Contractor Questions and Responses, and make changes to the specifications. The specific changes are identified on Page 2, Summary of Changes.

b. The date/time for receipt of offers remains unchanged on 21 Jan 2010 at 2:00 pm.

c. Point of contact for this amendment is Yolanda M. Ikner at (907) 753-2553.

d. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Jan-2010

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB-10-B-0001

X 9B. DATED (SEE ITEM 11)

20-Nov-2009

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Jan-2010

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

PO BOX 6898

ELMENDORF AFB AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911KB-10-B-0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

QUESTIONS AND RESPONSES:

1. Question: Within the Bid Documents, Section 01 19 40.00 29, Part 3.2; the first paragraph calls for soundings to be taken at 25 foot intervals perpendicular to the project baseline. In the past, Stations 20+00 through 49+49.20, have been very problematic when running perpendicular to the baseline as the wind, and consequently seas, move up the channel. The requirement to run perpendicular to the project baseline may cause additional data acquisition time, additional weather days to be taken, and uncertain data quality to be acquired. In the past, we have been allowed to acquire data running parallel to the project baseline. Would you please consider rewording the bid documents to reflect the method used in previous years and to address the special requirements of this harbor?

Response: The request has been considered, however we do not propose to reword this section. The intent of the wording in Section 01 19 40.00 29 Para. 3.2 is to ensure that the break in slope and the side slopes at the dredge cut limits along the perimeter of the channel are adequately captured in both the pre and post surveys.

2. Question: Within the Bid Documents, Section 01 19 40.00 29, Part 3.2; the second and third paragraph call for the pre and post-dredge survey to be conducted within the entire survey limits (the area within the construction limits). The Dredged Material Placement Area, as shown on sheet W-3 of the provided drawings (Amendment # 3), falls outside of the survey limits. Does this mean pre and post-dredge surveys are not required within the Dredged Material Placement Area?

Response: Yes, pre and post-dredge surveys are not required within the Dredged Material Placement Area.

Please note that Profile P8 is required for the post-dredge survey and it falls partially within the Dredged Material Placement Area.

3. Question: Within the Bid Documents Section 01 19 40.00 29, Part 3.2.2; the first paragraph calls for quantity computations to be calculated using the average-end-area method. Each successive hydrographic survey quantity calculation is to be performed using the composite method. Is this correct? Would USACE consider both pre and post-dredge quantities to be calculated using the composite method as in previous years?

Response: Section 01 19 40.00 29 Para. 3.2.2 should read "composite" method for both pre and post-dredge quantities calculation. See amendment #4.

SPECIFICATIONS

The following Specification Sections are revised as indicated. The identifier "AM #4" appears before and after new and revised material. Revised Specification Sections are attached.

TECHNICAL SPECIFICATIONS:

SECTION 01 19 40.00 29 SPECIAL ITEMS (CIVIL WORKS)

Para 3.2.2

(End of Summary of Changes)

Amendment R0004 2010-2012 MAINTENANCE DREDGING

NOME, ALASKA

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 19 40.00 29

SPECIAL ITEMS (CIVIL WORKS)

PART 1 GENERAL

1.1 SCOPE

1.2 REFERENCES

1.3 ACCIDENT PREVENTION PLAN

1.3.1 Navigation Safety and Coordination Plan

1.4 FIRE SAFETY

1.5 INSPECTION

1.5.1 General Requirements

1.5.2 Contractor Furnished Equipment, Labor, Materials, and

Transportation

1.5.3 EXAMINATION AND ACCEPTANCE

1.5.3.1 Examination

1.5.3.2 Acceptance

1.6 CAMP FACILITIES

1.7 CAMP FACILITIES

1.8 UTILITIES

1.9 PARTNERING

1.10 SCHEDULING OF WORK

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 COORDINATION WITH OTHERS

3.1.1 Traffic

3.2 SURVEYS

3.2.1 Equipment

3.2.2 Quantity Computation Drawings

3.2.3 Plan-View Drawings

3.2.3.1 Government-Furnished

3.2.3.2 Contractor Submittals

3.2.3.3 Surveys

3.2.3.4 Field Notes

3.2.4 Existing Monuments

3.2.5 Accuracy

3.2.6 Certification

3.3 EQUIPMENT

3.4 MOBILIZATION AND PROGRESS SCHEDULE

3.5 EQUIPMENT SCHEDULE

3.5.1 Number

3.5.2 Type

3.5.3 Capacity

3.6 PLANT AND EQUIPMENT SCHEDULE

-- End of Section Table of Contents --

SECTION 01 19 40.00 29 Page 1

SECTION 01 19 40.00 29

SPECIAL ITEMS (CIVIL WORKS)

PART 1 GENERAL

1.1 SCOPE

Items included in this section cover special features and/or requirements which are not otherwise specified or indicated.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2008) Safety and Health Requirements Manual

1.3 ACCIDENT PREVENTION PLAN

The Contractor shall obtain the Contracting Officer's approval of the Accident Prevention Plan required by EM 385-1-1 prior to start of any work at the project site.

1.3.1 Navigation Safety and Coordination Plan

The Contractor shall submit a Navigation Safety and Coordination Plan as part of the Accident Prevention Plan. This plan shall include but not be limited to temporary lights at night and/or marker buoys during construction, "Notice to Mariners" and coordination with local officials, and reference to applicable U.S. Coast Guard regulations for construction vessels as well as SECTION 19, Floating Plant and Marine Activities, of

EM 385-1-1.

1.4 FIRE SAFETY

The Contractor shall obtain a permit from the organization having jurisdiction over the job site for any welding or open flame work.

1.5 INSPECTION

1.5.1 General Requirements

The Contractor shall install and maintain any required gauges, ranges, location marks and limit marks in proper order and position.

1.5.2 Contractor Furnished Equipment, Labor, Materials, and Transportation

The Contractor shall furnish, upon the request of the Contracting Officer, the use of such boats, boatmen, laborers, and material forming a part of

SECTION 01 19 40.00 29 Page 2 the ordinary and usual equipment and crew of the dredging plant as required by the Government for inspection of the work and suitable transportation from all points on shore designated by the Contracting Officer to and from the various points of plant. Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor.

1.5.3 EXAMINATION AND ACCEPTANCE

1.5.3.1 Examination

As soon as practicable after completion of each area of dredging, such work shall be thoroughly examined as specified in paragraph SURVEYS herein.

Should any shoals, lumps, or other lack of depth 1 foot or more above Project Depth be disclosed by this examination, the Contractor will be required to remove same.

1.5.3.2 Acceptance

Acceptance of whole or part of the work and the deductions or corrections of deductions made thereon will not be reopened after having once been made, except on evidence of collusion, fraud, or obvious error. The acceptance of a completed section shall not change the time of payment of the retained percentages of the whole or any part of the work.

1.6 CAMP FACILITIES

There are no Government owned camp facilities at the job site for the Contractor's use.

1.7 CAMP FACILITIES

There are no Government owned camp facilities at the job site for the Contractor's use.

1.8 UTILITIES

The furnishing of water, electricity, and other utilities for work under this contract will be the Contractor's responsibility.

1.9 PARTNERING

a. The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance, intended to achieve completion within budget, on schedule, and in accordance with plans and specifications.

b. This partnership will be bilateral in makeup, and its implementation will not require a formal partnering session.

Implementation of this initiative will be a topic of discussion at the Pre-construction Conference.

1.10 SCHEDULING OF WORK

Dredging in Nome shall be conducted in accordance with the State of Alaska

SECTION 01 19 40.00 29 Page 3

Permit included at the end of this section. There shall be no dredging within the inner harbor after midnight on June 14 and before midnight July 14 of any year. Outer harbor dredging can be conducted at any time. The boundary between the inner and outer harbor is indicated on the contract drawings.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 COORDINATION WITH OTHERS

3.1.1 Traffic

Dredging may be interrupted by vessels maneuvering or moored anywhere within the dredging limits. The Contractor shall keep advised of vessel arrivals and departures and conduct operations so that interference with vessels will not occur. The Contractor's operations shall allow access to and from the Port at all times. All dredging activities, with special emphasis placed upon those dredging activities near the face of the docks and in the entrance channel, shall be coordinated with the Port of Nome Harbormaster at 907-443-6619. The Contractor shall also coordinate with the Port of Nome Harbormaster in the unlikely event that it becomes necessary to have vessels moved out of the way of dredging operations.

3.2 SURVEYS

Surveys shall be performed through the use of an independent certified hydrographic surveyor for the Base requirement and option years 2011 and 2012 (if awarded). The independent certified hydrographic surveyor shall perform pre-dredge and post-dredge surveys. All surveys shall have soundings taken at 25 foot intervals perpendicular to the project baseline and shall be recorded and legibly plotted across the entire survey limits as shown on the contract drawings. Additional survey soundings shall be recorded and plotted where topographic anomalies or obstacles of 2 feet or greater are encountered.

A pre-dredge survey for each year awarded of the entire survey limits (the area within the construction boundary) shown on the contract drawings, shall be performed immediately prior to the start of dredging and submitted to the Government within 5 days. The Contractor shall notify the Contracting Officer in writing of its intent to perform a pre-dredge survey at least 10 days in advance.

The Post-dredge survey for each year awarded shall be performed within 1 day and submitted to the Government within 5 days following completion of final dredging to verify final dredging results for the dredging season.

The Contractor shall notify the Contracting Officer in writing of its intent to perform any post-dredge survey at least 3 days in advance. If the results of any post-dredge survey indicate that the specified project depth has not been achieved for any part of the project, dredging shall resume until the condition has been corrected and the post-dredge survey shall be repeated at no additional cost to the Government. This process shall continue until the specified project depth has been achieved. The Post-dredge survey shall include the entire survey limits (the area within the construction boundary) and profiles 1 thru 8 as shown on the drawings.

Profiles 1 thru 8 shall consist of soundings and/or elevations taken at a minimum of 25 foot intervals along the profile alignments shown on the drawings and shall be recorded and legibly plotted along the alignments

SECTION 01 19 40.00 29 Page 4 shown. Additional survey soundings and/or elevations shall be recorded and plotted where topographic anomalies or obstacles of 2 feet or greater are encountered.

3.2.1 Equipment

The Contractor shall provide information to the Contracting Officer on electronic, horizontal positioning and recording/depth finding equipment to be used in the work, demonstrating that it will provide surveys meeting all requirements of EM 1110-2-1003 for hydrographic surveying. The information provided shall include, as a minimum, the name, model and year of manufacture of the equipment, the electronic frequencies of the horizontal positioning and depth finding equipment, and the manufacturer's stated positioning accuracy and capability. In addition, the Contractor shall provide proof that the vessel to be used is safe and suitable for operation in the waters in which the work is to be performed, and that experienced staff will be used for operation of the vessel as well as the positioning and recording/depth finding equipment.

3.2.2 Quantity Computation Drawings

Quantity computations shall be performed for all surveys. Quantity computations for the pre-dredge survey shall show quantities available to project depth, required over-depth, and maximum pay-line for each area, as well as the total to each depth for all areas, calculated using the AM#4...

composite...AM#4 method and given in cubic yards. For all successive hydrographic surveys, quantity computations shall show the survey-to-survey overall quantity Cut and Fill between surveys, as well as the quantities available to project depth, required over-depth, and maximum pay-line for each area, and the total to each depth for all areas. Calculations shall be performed using the composite method and given in cubic yards.

In addition, the post-dredge survey shall show computations for material removed within the area dredged between successive surveys. Quantity removed to the maximum pay-line shall be shown and likewise any over-dredging within the dredge area for that survey interval shall be computed and recorded. Calculations shall be performed using the composite method and given in cubic yards.

Preliminary quantities shall be furnished to the Contracting Officer within 2 days after completion of any survey. Final quantities shall be furnished to the Contracting Officer within 10 days after completion of any survey.

3.2.3 Plan-View Drawings

3.2.3.1 Government-Furnished

The Contracting Officer will provide the Contractor with a CD-ROM disk(s) containing data in the AutoCAD .DWG format capable of producing a basic survey contract drawing, complete with area map, borders, title block, and miscellaneous information.

3.2.3.2 Contractor Submittals

3.2.3.3 Surveys

The Contractor shall provide CD(s) of all raw survey data to the Contracting Officer's Representative in the field immediately following any survey. Within 2 days of completing the field data collection for each

SECTION 01 19 40.00 29 Page 5 survey, the Contractor's independent hydrographic surveyor shall reduce the survey depth soundings to the nearest one-tenth (0.1) foot and email AutoCAD point files, AutoCAD DWG plots, and quantity computations to the Contracting Officer by email for review. All point file data shall be sorted, edited, tide corrected, and provided in a COGO format ready for use in AutoDESK software and shall not exceed 1.5 megabytes in size. The DWG plots shall include all pertinent title block information and dredged areas as required under SURVEYS above. Any information found in error on the Government-furnished drawings provided in paragraph Government-Furnished above, such as vicinity maps, notes, shorelines, floats, docks, navigational aids, control coordinates, etc., shall be replaced with accurate data as it becomes known. Each DWG drawing shall contain all pertinent data respective to its survey and be legibly and accurately plotted at the above specified spacing.

Within 10 days after completion of any survey, final survey drawings shall be stamped, signed, and dated by the independent hydrographic surveyor and submitted on CD(s) in an uneditable searchable Adobe PDF format for final Government review and signatures. The CD(s) shall also include final volume computations and all raw survey data.

3.2.3.4 Field Notes

Upon completing any survey, quantity calculations, or plan-view drawings, the Contractor shall furnish the originals of all field notes, notebooks, fathometer data, sorted and corrected electronic point files, and any other records relating to the survey or to the layout of the work to the Contracting Officer. The Contractor shall retain copies of all such materials furnished to the Contracting Officer.

3.2.4 Existing Monuments

As part of the pre-dredge survey, the position, elevation, and condition of existing control points mentioned or shown on the drawings shall be verified, and the USACE shall be notified of any deviances in location horizontal or vertical and supplied with the corrected surveyed data of any of the control monuments in writing professionally stamped by the State of Alaska Registered Land Surveyor.

If, during the performance of the work, the Contractor removes or destroys previously set brass or aluminum survey caps, the survey caps, shall be reinstated by the Contractor at his expense.

3.2.5 Accuracy

All surveys for layout, quantities and final As-Built conditions shall conform to standard third order traverse requirements as specified in Field Manual FM 3-34.331, , Ch. 1. The following accuracies shall be attained:

a. Azimuth closure shall not exceed 5 seconds per angle in traverse.

b. Distance closure error, after azimuth adjustment, shall not exceed 1 part in 5,000 parts.

c. Traverse adjustment shall be by the Compass Rule.

d. Levels shall be to third order standards.

e. Vertical control shall be in feet and refer to Mean Lower Low Water Datum (MLLW = 0.0 feet).

f. Horizontal control shall be as stated on the individual contract drawings.

SECTION 01 19 40.00 29 Page 6

3.2.6 Certification

The independent hydrographic surveyor shall be a State of Alaska Registered Land Surveyor (RLS) and have current hydrographic certification from the American Congress for Surveying and Mapping (ACSM), valid in the State of Alaska. The surveyor shall document at least 3 years of experience in hydrographic surveying of navigable channels.

3.3 EQUIPMENT

The Contractor agrees to keep equipment on the job sufficient to meet the requirements of the work. The equipment shall be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in the specifications and shall be subject to inspection by the Contracting Officer or his representative at all times. The equipment used shall be of a design and have characteristics similar to equipment which has been used successfully for a minimum of 3 years under similar conditions. It shall be the responsibility of the Contractor to prove the equipment has sufficient capacity to accomplish the work in a timely manner without damage to existing port facilities, or obstructing navigation.

3.4 MOBILIZATION AND PROGRESS SCHEDULE

The Contractor shall furnish a complete mobilization and projected work progress schedule within 10 days of Notice to Proceed. The equipment listed, manpower to be utilized, and proposed work schedule shall be furnished in sufficient detail to permit determination by the Contracting Officer that the contract requirements can readily be met.

3.5 EQUIPMENT SCHEDULE

The PLANT AND EQUIPMENT SCHEDULE attached to this section shall be completed by the Contractor as hereafter described, and submitted within 10 days of receipt of the Notice to Proceed.

3.5.1 Number

For equipment, give identifying number or name.

3.5.2 Type

Under this heading give general description. Sufficient detailed information shall be furnished to properly delineate the proposed equipment and operation.

3.5.3 Capacity

Under this heading, state the estimated capacity of the plant in cubic yards per day when working materials similar to those anticipated in the work, for each location, accounting for the variable distances to the dredged material placement area. No reduction in the stated capacity of the plant employed on the work shall be made except by written permission of the Contracting Officer. (The measure of the "capacity of the plant" shall be its actual performance on the work which these specifications apply).

3.6 PLANT AND EQUIPMENT SCHEDULE

Minimum Plant To Be Used* Crew Age and No. Type Capacity Requirements Condition Location.

SECTION 01 19 40.00 29 Page 7

*NOTE: In preparing the above tabulation, the Contractor shall insert the following information under the appropriate heading, using a separate line for each major item and additional pages if necessary.

a. Number. For dredges, towboats, and material scows give identifying number or name.

b. Type. Under this heading give description as follows: For clamshell dredges, show bucket capacity in cubic yards, horsepower of hoist engine, type of power, number of swings per hour, and maximum draft, beam, and length of dredge. Show pump size and pump and cutter-head horsepower (hp) for pipeline dredges. For hopper dredges, show number of drag arms including diameter(s) and length(s), hopper capacity, pump size(s) and horsepower, maximum draft, length, beam, and type and horsepower of propulsion. Show maximum draft, length, beam, and hopper capacity of material scows. Show maximum draft, length, beam, and horsepower of towboat. Indicate number of crew required for each item of plant.

SECTION 01 19 40.00 29 Page 8

S A M P L E L E T T E R

Contracting Officer Date__________________ Address (as stated in Notice of Award)

SUBJECT: Warranty Provisions, Contract

GENTLEMEN:

This is to acknowledge our responsibility in connection with the warranty provisions of this contract as set forth in the contract specifications.

The following items, equipment or systems furnished or installed under this contract are hereby warranted against defective design, material and workmanship for a period as indicated:

Warranted Item, Identification Warranty Expires at Equipment or System Serial Number, Etc. 11:59 PM Std. Time

Upon receipt of notice from the Government of failure of any part or parts of the warranted item, equipment, or system during the warranty period, the affected part or parts will be replaced promptly with new parts. Such replacement will include furnishing and installing the new part or parts, making all necessary repairs, restoring the item, equipment, or system to the operating condition specified in this contract and making all such tests as are necessary to ensure that there are no remaining defects. Such tests will be performed in the presence of the Representative of the Using Agency indicated below.

We are responsible to ______________________________________ for the warranty provisions of this contract. Correspondence regarding the failure of any of the preceding items, equipment or systems covered by the warranty provisions of this contract should be addressed to:

___________________________________ Telephone Number:

Very truly yours, Signed: ________________________________________ Title: _________________________________________ Organization: __________________________________

-- End of Section --

SECTION 01 19 40.00 29 Page 9

01 19 40 00 29.pdf
01 19 40.00 29 - SPECIAL ITEMS CIVIL WORKS
01 19 40.00 29 - SPECIAL ITEMS CIVIL WORKS
PART 1 GENERAL
1.1 SCOPE
1.2 REFERENCES
1.3 ACCIDENT PREVENTION PLAN
1.3.1 Navigation Safety and Coordination Plan
1.4 FIRE SAFETY
1.5 INSPECTION
1.5.1 General Requirements
1.5.2 Contractor Furnished Equipment, Labor, Materials, and Transportation
1.5.3 EXAMINATION AND ACCEPTANCE
1.5.3.1 Examination
1.5.3.2 Acceptance
1.6 CAMP FACILITIES
1.7 CAMP FACILITIES
1.8 UTILITIES
1.9 PARTNERING
1.10 SCHEDULING OF WORK
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.1 COORDINATION WITH OTHERS
3.1.1 Traffic
3.2 SURVEYS
3.2.1 Equipment
3.2.2 Quantity Computation Drawings
3.2.3 Plan-View Drawings
3.2.3.1 Government-Furnished
3.2.3.2 Contractor Submittals
3.2.3.3 Surveys
3.2.3.4 Field Notes
3.2.4 Existing Monuments
3.2.5 Accuracy
3.2.6 Certification
3.3 EQUIPMENT
3.4 MOBILIZATION AND PROGRESS SCHEDULE
3.5 EQUIPMENT SCHEDULE
3.5.1 Number
3.5.2 Type
3.5.3 Capacity

3.6 PLANT AND EQUIPMENT SCHEDULE