Text version
BASE PERFORMANCE YEAR
| ALL LINE ITEMS SHALL BE BASED ON SPECIFICATIONS AND ALL ATTACHMENTS. | |||||||||||
| LINE ITEM# | WORK DESCRIPTION | UNIT | Unit Price | Actual Quantity | Proposal BY Unit Price | Proposal Base Year | TOTAL | Proposal OY Unit Price | Proposal Option Year | PROP. TOTAL COST | BASE YEAR TOTAL COST |
| $2,006,517.67 | $0.00 |
| 100 | Dismantle, Demo, Removal of One Story Wooden Structure | SF | $0.00 | 50,000 | 5.42 | 271,000 | 0 | 5.59 | 279,500 |
| 200 | Dismantle, Demo, Removal of Two Story Wooden Structure | SF | $0.00 | 6,667 | 6.49 | 43,267 | 0 | 6.69 | 44,600 |
| 300 | Dismantle, Demo, Removal of One Story Masonry Structure | SF | $0.00 | 3,333 | 5.77 | 19,233 | 0 | 5.95 | 19,833 |
| 400 | Dismantle, Demo, Removal of Metal Building with Exterior Walls | SF | $0.00 | 10,667 | 2.59 | 27,627 | 0 | 2.67 | 28,480 |
| 500 | Dismantle, Demo, Removal of Metal Structures with No Exterior Walls | SF | $0.00 | 2,333 | 2.20 | 5,133 | 0 | 2.27 | 5,297 |
| 600 | Dismantle, Removal, Service Disconnect of Relocatable Structures, include removal of huricane tiedowns and grounding | SF | $0.00 | 16,667 | 0.80 | 13,333 | 0 | 0.83 | 13,833 |
| 700 | For Building With No Interior Walls, Deduct | SF | $0.00 | 1,667 | 0.20 | 333 | 0 | 0.21 | 350 |
| 800 | Minimum Labor/Equipment Charge | EA | $0.00 | 20 | 250.00 | 5,000 | 0 | 257.50 | 5,150 |
| SELECTIVE DEMOLITION, UTILITIES AND COMMUNICATIONS, INCLUDE HAUL, SALVAGE | |||||||||
| 900 | Remove Existing Aerial Primary or Secondary Conductors | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| 1000 | Remove Existing Pole Through 60', Include Accessories | EA | $0.00 | 7 | 950.00 | 6,333 | 0 | 978.50 | 6,523 |
| 1100 | Demo Down Guy Wire to Include Apparatus | EA | $0.00 | 5 | 400.00 | 2,000 | 0 | 412.00 | 2,060 |
| 1200 | Remove Pole-Mounted Transformer, 1 Phase, Up to 100 kVA | EA | $0.00 | 3 | 1,750.00 | 5,833 | 0 | 1,802.50 | 6,008 |
| 1300 | Remove Pad-Mounted Transformer, 1 Phase, Up to 200 kVA | EA | $0.00 | 3 | 1,500.00 | 5,000 | 0 | 1,545.00 | 5,150 |
| 1400 | Remove Pad-Mounted Transformer, 3 Phase, Up to 300 kVA | EA | $0.00 | 2 | 1,800.00 | 3,600 | 0 | 1,854.00 | 3,708 |
| 1500 | Demo Man-hole/ Hand-hole | EA | $0.00 | 5 | 700.00 | 3,500 | 0 | 721.00 | 3,605 |
| 1600 | Remove Outside Communication Line | LF | $0.00 | 1,000 | 3.00 | 3,000 | 0 | 3.09 | 3,090 |
| 1700 | Disconnect and move SIPR safe | EA | $0.00 | 2 | 1,600.00 | 2,667 | 0 | 1,648.00 | 2,747 |
| 1800 | Place Flowable Fill in Abandoned Pipe, 2"-4" | LF | $0.00 | 1,000 | 3.00 | 3,000 | 0 | 3.09 | 3,090 |
| 1900 | Place Flowable Fill in Abandoned Pipe, +4"-8" | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| SELECTIVE DEMOLITION, SITE, INCLUDE HAUL, SALVAGE | |||||||||
| 2000 | Pavement Removal, Bituminous, to 4" thickness | SY | $0.00 | 16,667 | 2.80 | 46,667 | 0 | 2.89 | 48,167 |
| 2100 | Pavement Removal, Bituminous, Additional 1" | SY | $0.00 | 1,333 | 2.00 | 2,667 | 0 | 2.06 | 2,747 |
| 2200 | Pavement Removal. Sidewalk, 4" Typ. | SY | $0.00 | 3,333 | 4.00 | 13,333 | 0 | 4.12 | 13,733 |
| 2300 | Pavement Removal, Concrete, to 6" Thickness | SY | $0.00 | 2,667 | 5.75 | 15,333 | 0 | 5.93 | 15,813 |
| 2400 | Pavement Removal, Concrete, +6" to 12" Thickness | SY | $0.00 | 1,000 | 10.00 | 10,000 | 0 | 10.30 | 10,300 |
| 2500 | Curbs, Concrete, Reinforced | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| 2600 | Remove Fencing Post & Fabric, Barbwire, Gates, Up to 7' Tall | LF | $0.00 | 1,333 | 5.50 | 7,333 | 0 | 5.67 | 7,560 |
| 2700 | Remove Fencing Post & Fabric, Barbwire, Gates, Greater Than 7' Tall | LF | $0.00 | 333 | 8.00 | 2,667 | 0 | 8.24 | 2,747 |
| SITE REESTABLISHMENT | |||||||||
| 2800 | Fill, Compact, Grading | CY | $0.00 | 5,000 | 8.75 | 43,750 | 0 | 9.02 | 45,100 |
| 2900 | Excavation (off-site) | CY | $0.00 | 1,667 | 5.00 | 8,333 | 0 | 5.15 | 8,583 |
| 3000 | Place Top Soil and Prepare for Seeding | SY | $0.00 | 8,333 | 5.00 | 41,667 | 0 | 5.15 | 42,917 |
| 3100 | Hydromulch | SY | $0.00 | 8,333 | 2.20 | 18,333 | 0 | 2.27 | 18,917 |
| 3200 | Install Bermuda Sod | SY | $0.00 | 20,000 | 3.50 | 70,000 | 0 | 3.61 | 72,200 |
| 3300 | Flexterra FGM | SY | $0.00 | 1,667 | 1.50 | 2,500 | 0 | 1.55 | 2,583 |
| 3400 | Scour Stop | SF | $0.00 | 67 | 12.00 | 800 | 0 | 12.36 | 824 |
| ASBESTOS REMOVAL, INCLUDING HAUL, DISPOSAL | |||||||||
| 3500 | Remove Asbestos Insulation from Piping to include Attached Fittings, Valves & accessories, Complete, 1/2" through 6" pipe | LF | $0.00 | 667 | 7.50 | 5,000 | 0 | 7.73 | 5,153 |
| 3600 | Remove Asbestos Insulation from Piping to include Attached Fittings, Valves & accessories, Complete, above 6", pipe | LF | $0.00 | 667 | 8.50 | 5,667 | 0 | 8.76 | 5,840 |
| 3700 | Remove Asbestos Insulation From Duct-work,Complete | SF | $0.00 | 667 | 5.50 | 3,667 | 0 | 5.67 | 3,780 |
| 3800 | Remove Asbestos From Furnaces, Water Tanks, Stacks, Water Heaters and Other Equipment to Include Attached Fittings, Valves & Accessories, Complete | SF | $0.00 | 667 | 9.00 | 6,000 | 0 | 9.27 | 6,180 |
| 3900 | Remove Blown-in Asbestos Insulation from Building Walls and Ceilings | SF | $0.00 | 11,000 | 2.50 | 27,500 | 0 | 2.58 | 28,380 |
| 4000 | Remove Asbestos Type Blown-in Acoustical Insulation | SF | $0.00 | 1,100 | 3.00 | 3,300 | 0 | 3.09 | 3,399 |
| 4100 | Remove Wall Acoustical Plaster w/ ACH, Complete | SF | $0.00 | 1,100 | 4.00 | 4,400 | 0 | 4.12 | 4,532 |
| 4200 | Remove Wall , Hard Veneer Plaster w/ ACH, Complete | SF | $0.00 | 433 | 5.00 | 2,167 | 0 | 5.15 | 2,232 |
| 4300 | Remove Asbestos Cement Board, Complete | SF | $0.00 | 1,100 | 4.00 | 4,400 | 0 | 4.12 | 4,532 |
| 4400 | Remove Asbestos Floor Tile & Carpet Over Floor Tile Complete, w/ Underlayments and Any Floor Overlays to Subfloor, Complete | SF | $0.00 | 10,000 | 3.65 | 36,500 | 0 | 3.76 | 37,600 |
| 4500 | Remove Existing Asbestos Contaminated Soil | CF | $0.00 | 1,333 | 14.00 | 18,667 | 0 | 14.42 | 19,227 |
| 4600 | Clean-up Gross Contaminated Areas | CF | $0.00 | 3,333 | 5.00 | 16,667 | 0 | 5.15 | 17,167 |
| 4700 | Remove Asbestos Contaminated Suspended Ceiling Tile and Grid to Include Disposal | SF | $0.00 | 11,000 | 1.90 | 20,900 | 0 | 1.96 | 21,560 |
| 4800 | Remove Carpet Glued to Concrete or Wood with Asbestos Contaminated Mastic to Include Disposal | SF | $0.00 | 6,667 | 2.75 | 18,333 | 0 | 2.84 | 18,933 |
| 4900 | Remove and Dispose of Asbestos Containing Roof Felt and Mastic (up to 3 Layers) | SF | $0.00 | 667 | 3.00 | 2,000 | 0 | 3.09 | 2,060 |
| 5000 | Remove and Dispose of Asbestos Containing Roof Flashing | LF | $0.00 | 2,000 | 2.50 | 5,000 | 0 | 2.58 | 5,160 |
| 5100 | Remove and Dispose of Asbestos Containing Glazing and Puty | SF | $0.00 | 667 | 8.00 | 5,333 | 0 | 8.24 | 5,493 |
| LEAD-BASED PAINT REMOVAL | |||||||||
| 5200 | Lead-Based Paint Removal | SF | $0.00 | 1,333 | 11.00 | 14,667 | 0 | 11.33 | 15,107 |
| 5300 | Mold Remediation | SF | $0.00 | 1,333 | 2.00 | 2,667 | 0 | 2.06 | 2,747 |
| 5400 | Initial Asbestos, Lead-Based Pain, Mold Building Survey: | $0.00 | |||||||
| 5400-1 Building Up to 5000 SF | EA | $0.00 | 5 | 2,200.00 | 11,000 | 0 | 2,266.00 | 11,330 | |
| 5400-2 Building Greater Than 5000SF, Up to 10,000 SF | EA | $0.00 | 8 | 2,400.00 | 20,000 | 0 | 2,472.00 | 20,600 | |
| 5400-3 Building Greater Than 10,000 SF, Up to 20,000 SF | EA | $0.00 | 3 | 3,000.00 | 8,000 | 0 | 3,090.00 | 8,240 | |
| 5400-4 Building Greater Than 20,000 SF | EA | $0.00 | 1 | 3,800.00 | 2,533 | 0 | 3,914.00 | 2,609 | |
| 5500 | Construction/Post-Construction Asbestos Sample Testing | EA | $0.00 | 2 | 500.00 | 833 | 0 | 515.00 | 858 |
| 5600 | Unpriced Unit Items (10%) | ||||||||
| DO NOT BID ON THIS LINE ITEM. THIS LINE ITEM WILL ONLY BE USED FOR PROJECTS WHERE NO PRE-PRICED LINE ITEMS EXIST ELSEWHERE IN THE BID SCHEDULE. IT WILL BE NEGOTIATED AT TIME OF OCCURRENCE. | |||||||||
| 5700 | Bond (2.5% of Total) | LS | $0.00 | 1 | |||||
| 5800 | Asbestos Fees | EA | $0.00 | 20 | 75.00 | 1,500 | 0 | 75.00 | 1,500 |
| 5900 | As-Built Drawings | EA | $0.00 | 10 | 2,300.00 | 23,000 | 0 | 2,369.00 | 23,690 |
| TOTAL | 987,943 | 0 | 1,018,574 |
OPTION YR 1
| ALL LINE ITEMS SHALL BE BASED ON SPECIFICATIONS AND ALL ATTACHMENTS. | |||||||||||
| LINE ITEM# | WORK DESCRIPTION | UNIT | Unit Price | Actual Quantity | Proposal BY Unit Price | Proposal Base Year | TOTAL | Proposal OY Unit Price | Proposal Option Year | PROP. TOTAL COST | Option Yr 1 TOTAL COST |
| $2,006,517.67 | $0.00 |
| 100 | Dismantle, Demo, Removal of One Story Wooden Structure | SF | $0.00 | 50,000 | 5.42 | 271,000 | 0 | 5.59 | 279,500 |
| 200 | Dismantle, Demo, Removal of Two Story Wooden Structure | SF | $0.00 | 6,667 | 6.49 | 43,267 | 0 | 6.69 | 44,600 |
| 300 | Dismantle, Demo, Removal of One Story Masonry Structure | SF | $0.00 | 3,333 | 5.77 | 19,233 | 0 | 5.95 | 19,833 |
| 400 | Dismantle, Demo, Removal of Metal Building with Exterior Walls | SF | $0.00 | 10,667 | 2.59 | 27,627 | 0 | 2.67 | 28,480 |
| 500 | Dismantle, Demo, Removal of Metal Structures with No Exterior Walls | SF | $0.00 | 2,333 | 2.20 | 5,133 | 0 | 2.27 | 5,297 |
| 600 | Dismantle, Removal, Service Disconnect of Relocatable Structures, include removal of huricane tiedowns and grounding | SF | $0.00 | 16,667 | 0.80 | 13,333 | 0 | 0.83 | 13,833 |
| 700 | For Building With No Interior Walls, Deduct | SF | $0.00 | 1,667 | 0.20 | 333 | 0 | 0.21 | 350 |
| 800 | Minimum Labor/Equipment Charge | EA | $0.00 | 20 | 250.00 | 5,000 | 0 | 257.50 | 5,150 |
| SELECTIVE DEMOLITION, UTILITIES AND COMMUNICATIONS, INCLUDE HAUL, SALVAGE | |||||||||
| 900 | Remove Existing Aerial Primary or Secondary Conductors | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| 1000 | Remove Existing Pole Through 60', Include Accessories | EA | $0.00 | 7 | 950.00 | 6,333 | 0 | 978.50 | 6,523 |
| 1100 | Demo Down Guy Wire to Include Apparatus | EA | $0.00 | 5 | 400.00 | 2,000 | 0 | 412.00 | 2,060 |
| 1200 | Remove Pole-Mounted Transformer, 1 Phase, Up to 100 kVA | EA | $0.00 | 3 | 1,750.00 | 5,833 | 0 | 1,802.50 | 6,008 |
| 1300 | Remove Pad-Mounted Transformer, 1 Phase, Up to 200 kVA | EA | $0.00 | 3 | 1,500.00 | 5,000 | 0 | 1,545.00 | 5,150 |
| 1400 | Remove Pad-Mounted Transformer, 3 Phase, Up to 300 kVA | EA | $0.00 | 2 | 1,800.00 | 3,600 | 0 | 1,854.00 | 3,708 |
| 1500 | Demo Man-hole/ Hand-hole | EA | $0.00 | 5 | 700.00 | 3,500 | 0 | 721.00 | 3,605 |
| 1600 | Remove Outside Communication Line | LF | $0.00 | 1,000 | 3.00 | 3,000 | 0 | 3.09 | 3,090 |
| 1700 | Disconnect and move SIPR safe | EA | $0.00 | 2 | 1,600.00 | 2,667 | 0 | 1,648.00 | 2,747 |
| 1800 | Place Flowable Fill in Abandoned Pipe, 2"-4" | LF | $0.00 | 1,000 | 3.00 | 3,000 | 0 | 3.09 | 3,090 |
| 1900 | Place Flowable Fill in Abandoned Pipe, +4"-8" | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| SELECTIVE DEMOLITION, SITE, INCLUDE HAUL, SALVAGE | |||||||||
| 2000 | Pavement Removal, Bituminous, to 4" thickness | SY | $0.00 | 16,667 | 2.80 | 46,667 | 0 | 2.89 | 48,167 |
| 2100 | Pavement Removal, Bituminous, Additional 1" | SY | $0.00 | 1,333 | 2.00 | 2,667 | 0 | 2.06 | 2,747 |
| 2200 | Pavement Removal. Sidewalk, 4" Typ. | SY | $0.00 | 3,333 | 4.00 | 13,333 | 0 | 4.12 | 13,733 |
| 2300 | Pavement Removal, Concrete, to 6" Thickness | SY | $0.00 | 2,667 | 5.75 | 15,333 | 0 | 5.93 | 15,813 |
| 2400 | Pavement Removal, Concrete, +6" to 12" Thickness | SY | $0.00 | 1,000 | 10.00 | 10,000 | 0 | 10.30 | 10,300 |
| 2500 | Curbs, Concrete, Reinforced | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| 2600 | Remove Fencing Post & Fabric, Barbwire, Gates, Up to 7' Tall | LF | $0.00 | 1,333 | 5.50 | 7,333 | 0 | 5.67 | 7,560 |
| 2700 | Remove Fencing Post & Fabric, Barbwire, Gates, Greater Than 7' Tall | LF | $0.00 | 333 | 8.00 | 2,667 | 0 | 8.24 | 2,747 |
| SITE REESTABLISHMENT | |||||||||
| 2800 | Fill, Compact, Grading | CY | $0.00 | 5,000 | 8.75 | 43,750 | 0 | 9.02 | 45,100 |
| 2900 | Excavation (off-site) | CY | $0.00 | 1,667 | 5.00 | 8,333 | 0 | 5.15 | 8,583 |
| 3000 | Place Top Soil and Prepare for Seeding | SY | $0.00 | 8,333 | 5.00 | 41,667 | 0 | 5.15 | 42,917 |
| 3100 | Hydromulch | SY | $0.00 | 8,333 | 2.20 | 18,333 | 0 | 2.27 | 18,917 |
| 3200 | Install Bermuda Sod | SY | $0.00 | 20,000 | 3.50 | 70,000 | 0 | 3.61 | 72,200 |
| 3300 | Flexterra FGM | SY | $0.00 | 1,667 | 1.50 | 2,500 | 0 | 1.55 | 2,583 |
| 3400 | Scour Stop | SF | $0.00 | 67 | 12.00 | 800 | 0 | 12.36 | 824 |
| ASBESTOS REMOVAL, INCLUDING HAUL, DISPOSAL | |||||||||
| 3500 | Remove Asbestos Insulation from Piping to include Attached Fittings, Valves & accessories, Complete, 1/2" through 6" pipe | LF | $0.00 | 667 | 7.50 | 5,000 | 0 | 7.73 | 5,153 |
| 3600 | Remove Asbestos Insulation from Piping to include Attached Fittings, Valves & accessories, Complete, above 6", pipe | LF | $0.00 | 667 | 8.50 | 5,667 | 0 | 8.76 | 5,840 |
| 3700 | Remove Asbestos Insulation From Duct-work,Complete | SF | $0.00 | 667 | 5.50 | 3,667 | 0 | 5.67 | 3,780 |
| 3800 | Remove Asbestos From Furnaces, Water Tanks, Stacks, Water Heaters and Other Equipment to Include Attached Fittings, Valves & Accessories, Complete | SF | $0.00 | 667 | 9.00 | 6,000 | 0 | 9.27 | 6,180 |
| 3900 | Remove Blown-in Asbestos Insulation from Building Walls and Ceilings | SF | $0.00 | 11,000 | 2.50 | 27,500 | 0 | 2.58 | 28,380 |
| 4000 | Remove Asbestos Type Blown-in Acoustical Insulation | SF | $0.00 | 1,100 | 3.00 | 3,300 | 0 | 3.09 | 3,399 |
| 4100 | Remove Wall Acoustical Plaster w/ ACH, Complete | SF | $0.00 | 1,100 | 4.00 | 4,400 | 0 | 4.12 | 4,532 |
| 4200 | Remove Wall , Hard Veneer Plaster w/ ACH, Complete | SF | $0.00 | 433 | 5.00 | 2,167 | 0 | 5.15 | 2,232 |
| 4300 | Remove Asbestos Cement Board, Complete | SF | $0.00 | 1,100 | 4.00 | 4,400 | 0 | 4.12 | 4,532 |
| 4400 | Remove Asbestos Floor Tile & Carpet Over Floor Tile Complete, w/ Underlayments and Any Floor Overlays to Subfloor, Complete | SF | $0.00 | 10,000 | 3.65 | 36,500 | 0 | 3.76 | 37,600 |
| 4500 | Remove Existing Asbestos Contaminated Soil | CF | $0.00 | 1,333 | 14.00 | 18,667 | 0 | 14.42 | 19,227 |
| 4600 | Clean-up Gross Contaminated Areas | CF | $0.00 | 3,333 | 5.00 | 16,667 | 0 | 5.15 | 17,167 |
| 4700 | Remove Asbestos Contaminated Suspended Ceiling Tile and Grid to Include Disposal | SF | $0.00 | 11,000 | 1.90 | 20,900 | 0 | 1.96 | 21,560 |
| 4800 | Remove Carpet Glued to Concrete or Wood with Asbestos Contaminated Mastic to Include Disposal | SF | $0.00 | 6,667 | 2.75 | 18,333 | 0 | 2.84 | 18,933 |
| 4900 | Remove and Dispose of Asbestos Containing Roof Felt and Mastic (up to 3 Layers) | SF | $0.00 | 667 | 3.00 | 2,000 | 0 | 3.09 | 2,060 |
| 5000 | Remove and Dispose of Asbestos Containing Roof Flashing | LF | $0.00 | 2,000 | 2.50 | 5,000 | 0 | 2.58 | 5,160 |
| 5100 | Remove and Dispose of Asbestos Containing Glazing and Puty | SF | $0.00 | 667 | 8.00 | 5,333 | 0 | 8.24 | 5,493 |
| LEAD-BASED PAINT REMOVAL | |||||||||
| 5200 | Lead-Based Paint Removal | SF | $0.00 | 1,333 | 11.00 | 14,667 | 0 | 11.33 | 15,107 |
| 5300 | Mold Remediation | SF | $0.00 | 1,333 | 2.00 | 2,667 | 0 | 2.06 | 2,747 |
| 5400 | Initial Asbestos, Lead-Based Pain, Mold Building Survey: | $0.00 | |||||||
| 5400-1 Building Up to 5000 SF | EA | $0.00 | 5 | 2,200.00 | 11,000 | 0 | 2,266.00 | 11,330 | |
| 5400-2 Building Greater Than 5000SF, Up to 10,000 SF | EA | $0.00 | 8 | 2,400.00 | 20,000 | 0 | 2,472.00 | 20,600 | |
| 5400-3 Building Greater Than 10,000 SF, Up to 20,000 SF | EA | $0.00 | 3 | 3,000.00 | 8,000 | 0 | 3,090.00 | 8,240 | |
| 5400-4 Building Greater Than 20,000 SF | EA | $0.00 | 1 | 3,800.00 | 2,533 | 0 | 3,914.00 | 2,609 | |
| 5500 | Construction/Post-Construction Asbestos Sample Testing | EA | $0.00 | 2 | 500.00 | 833 | 0 | 515.00 | 858 |
| 5600 | Unpriced Unit Items (10%) | ||||||||
| DO NOT BID ON THIS LINE ITEM. THIS LINE ITEM WILL ONLY BE USED FOR PROJECTS WHERE NO PRE-PRICED LINE ITEMS EXIST ELSEWHERE IN THE BID SCHEDULE. IT WILL BE NEGOTIATED AT TIME OF OCCURRENCE. | |||||||||
| 5700 | Bond (2.5% of Total) | LS | $0.00 | 1 | |||||
| 5800 | Asbestos Fees | EA | $0.00 | 20 | 75.00 | 1,500 | 0 | 75.00 | 1,500 |
| 5900 | As-Built Drawings | EA | $0.00 | 10 | 2,300.00 | 23,000 | 0 | 2,369.00 | 23,690 |
| TOTAL | 987,943 | 0 | 1,018,574 |
OPTION YR 2
| ALL LINE ITEMS SHALL BE BASED ON SPECIFICATIONS AND ALL ATTACHMENTS. | |||||||||||
| LINE ITEM# | WORK DESCRIPTION | UNIT | Unit Price | Actual Quantity | Proposal BY Unit Price | Proposal Base Year | TOTAL | Proposal OY Unit Price | Proposal Option Year | PROP. TOTAL COST | Option Yr 2 TOTAL COST |
| $2,006,517.67 | $0.00 |
| 100 | Dismantle, Demo, Removal of One Story Wooden Structure | SF | $0.00 | 50,000 | 5.42 | 271,000 | 0 | 5.59 | 279,500 |
| 200 | Dismantle, Demo, Removal of Two Story Wooden Structure | SF | $0.00 | 6,667 | 6.49 | 43,267 | 0 | 6.69 | 44,600 |
| 300 | Dismantle, Demo, Removal of One Story Masonry Structure | SF | $0.00 | 3,333 | 5.77 | 19,233 | 0 | 5.95 | 19,833 |
| 400 | Dismantle, Demo, Removal of Metal Building with Exterior Walls | SF | $0.00 | 10,667 | 2.59 | 27,627 | 0 | 2.67 | 28,480 |
| 500 | Dismantle, Demo, Removal of Metal Structures with No Exterior Walls | SF | $0.00 | 2,333 | 2.20 | 5,133 | 0 | 2.27 | 5,297 |
| 600 | Dismantle, Removal, Service Disconnect of Relocatable Structures, include removal of huricane tiedowns and grounding | SF | $0.00 | 16,667 | 0.80 | 13,333 | 0 | 0.83 | 13,833 |
| 700 | For Building With No Interior Walls, Deduct | SF | $0.00 | 1,667 | 0.20 | 333 | 0 | 0.21 | 350 |
| 800 | Minimum Labor/Equipment Charge | EA | $0.00 | 20 | 250.00 | 5,000 | 0 | 257.50 | 5,150 |
| SELECTIVE DEMOLITION, UTILITIES AND COMMUNICATIONS, INCLUDE HAUL, SALVAGE | |||||||||
| 900 | Remove Existing Aerial Primary or Secondary Conductors | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| 1000 | Remove Existing Pole Through 60', Include Accessories | EA | $0.00 | 7 | 950.00 | 6,333 | 0 | 978.50 | 6,523 |
| 1100 | Demo Down Guy Wire to Include Apparatus | EA | $0.00 | 5 | 400.00 | 2,000 | 0 | 412.00 | 2,060 |
| 1200 | Remove Pole-Mounted Transformer, 1 Phase, Up to 100 kVA | EA | $0.00 | 3 | 1,750.00 | 5,833 | 0 | 1,802.50 | 6,008 |
| 1300 | Remove Pad-Mounted Transformer, 1 Phase, Up to 200 kVA | EA | $0.00 | 3 | 1,500.00 | 5,000 | 0 | 1,545.00 | 5,150 |
| 1400 | Remove Pad-Mounted Transformer, 3 Phase, Up to 300 kVA | EA | $0.00 | 2 | 1,800.00 | 3,600 | 0 | 1,854.00 | 3,708 |
| 1500 | Demo Man-hole/ Hand-hole | EA | $0.00 | 5 | 700.00 | 3,500 | 0 | 721.00 | 3,605 |
| 1600 | Remove Outside Communication Line | LF | $0.00 | 1,000 | 3.00 | 3,000 | 0 | 3.09 | 3,090 |
| 1700 | Disconnect and move SIPR safe | EA | $0.00 | 2 | 1,600.00 | 2,667 | 0 | 1,648.00 | 2,747 |
| 1800 | Place Flowable Fill in Abandoned Pipe, 2"-4" | LF | $0.00 | 1,000 | 3.00 | 3,000 | 0 | 3.09 | 3,090 |
| 1900 | Place Flowable Fill in Abandoned Pipe, +4"-8" | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| SELECTIVE DEMOLITION, SITE, INCLUDE HAUL, SALVAGE | |||||||||
| 2000 | Pavement Removal, Bituminous, to 4" thickness | SY | $0.00 | 16,667 | 2.80 | 46,667 | 0 | 2.89 | 48,167 |
| 2100 | Pavement Removal, Bituminous, Additional 1" | SY | $0.00 | 1,333 | 2.00 | 2,667 | 0 | 2.06 | 2,747 |
| 2200 | Pavement Removal. Sidewalk, 4" Typ. | SY | $0.00 | 3,333 | 4.00 | 13,333 | 0 | 4.12 | 13,733 |
| 2300 | Pavement Removal, Concrete, to 6" Thickness | SY | $0.00 | 2,667 | 5.75 | 15,333 | 0 | 5.93 | 15,813 |
| 2400 | Pavement Removal, Concrete, +6" to 12" Thickness | SY | $0.00 | 1,000 | 10.00 | 10,000 | 0 | 10.30 | 10,300 |
| 2500 | Curbs, Concrete, Reinforced | LF | $0.00 | 1,000 | 5.00 | 5,000 | 0 | 5.15 | 5,150 |
| 2600 | Remove Fencing Post & Fabric, Barbwire, Gates, Up to 7' Tall | LF | $0.00 | 1,333 | 5.50 | 7,333 | 0 | 5.67 | 7,560 |
| 2700 | Remove Fencing Post & Fabric, Barbwire, Gates, Greater Than 7' Tall | LF | $0.00 | 333 | 8.00 | 2,667 | 0 | 8.24 | 2,747 |
| SITE REESTABLISHMENT | |||||||||
| 2800 | Fill, Compact, Grading | CY | $0.00 | 5,000 | 8.75 | 43,750 | 0 | 9.02 | 45,100 |
| 2900 | Excavation (off-site) | CY | $0.00 | 1,667 | 5.00 | 8,333 | 0 | 5.15 | 8,583 |
| 3000 | Place Top Soil and Prepare for Seeding | SY | $0.00 | 8,333 | 5.00 | 41,667 | 0 | 5.15 | 42,917 |
| 3100 | Hydromulch | SY | $0.00 | 8,333 | 2.20 | 18,333 | 0 | 2.27 | 18,917 |
| 3200 | Install Bermuda Sod | SY | $0.00 | 20,000 | 3.50 | 70,000 | 0 | 3.61 | 72,200 |
| 3300 | Flexterra FGM | SY | $0.00 | 1,667 | 1.50 | 2,500 | 0 | 1.55 | 2,583 |
| 3400 | Scour Stop | SF | $0.00 | 67 | 12.00 | 800 | 0 | 12.36 | 824 |
| ASBESTOS REMOVAL, INCLUDING HAUL, DISPOSAL | |||||||||
| 3500 | Remove Asbestos Insulation from Piping to include Attached Fittings, Valves & accessories, Complete, 1/2" through 6" pipe | LF | $0.00 | 667 | 7.50 | 5,000 | 0 | 7.73 | 5,153 |
| 3600 | Remove Asbestos Insulation from Piping to include Attached Fittings, Valves & accessories, Complete, above 6", pipe | LF | $0.00 | 667 | 8.50 | 5,667 | 0 | 8.76 | 5,840 |
| 3700 | Remove Asbestos Insulation From Duct-work,Complete | SF | $0.00 | 667 | 5.50 | 3,667 | 0 | 5.67 | 3,780 |
| 3800 | Remove Asbestos From Furnaces, Water Tanks, Stacks, Water Heaters and Other Equipment to Include Attached Fittings, Valves & Accessories, Complete | SF | $0.00 | 667 | 9.00 | 6,000 | 0 | 9.27 | 6,180 |
| 3900 | Remove Blown-in Asbestos Insulation from Building Walls and Ceilings | SF | $0.00 | 11,000 | 2.50 | 27,500 | 0 | 2.58 | 28,380 |
| 4000 | Remove Asbestos Type Blown-in Acoustical Insulation | SF | $0.00 | 1,100 | 3.00 | 3,300 | 0 | 3.09 | 3,399 |
| 4100 | Remove Wall Acoustical Plaster w/ ACH, Complete | SF | $0.00 | 1,100 | 4.00 | 4,400 | 0 | 4.12 | 4,532 |
| 4200 | Remove Wall , Hard Veneer Plaster w/ ACH, Complete | SF | $0.00 | 433 | 5.00 | 2,167 | 0 | 5.15 | 2,232 |
| 4300 | Remove Asbestos Cement Board, Complete | SF | $0.00 | 1,100 | 4.00 | 4,400 | 0 | 4.12 | 4,532 |
| 4400 | Remove Asbestos Floor Tile & Carpet Over Floor Tile Complete, w/ Underlayments and Any Floor Overlays to Subfloor, Complete | SF | $0.00 | 10,000 | 3.65 | 36,500 | 0 | 3.76 | 37,600 |
| 4500 | Remove Existing Asbestos Contaminated Soil | CF | $0.00 | 1,333 | 14.00 | 18,667 | 0 | 14.42 | 19,227 |
| 4600 | Clean-up Gross Contaminated Areas | CF | $0.00 | 3,333 | 5.00 | 16,667 | 0 | 5.15 | 17,167 |
| 4700 | Remove Asbestos Contaminated Suspended Ceiling Tile and Grid to Include Disposal | SF | $0.00 | 11,000 | 1.90 | 20,900 | 0 | 1.96 | 21,560 |
| 4800 | Remove Carpet Glued to Concrete or Wood with Asbestos Contaminated Mastic to Include Disposal | SF | $0.00 | 6,667 | 2.75 | 18,333 | 0 | 2.84 | 18,933 |
| 4900 | Remove and Dispose of Asbestos Containing Roof Felt and Mastic (up to 3 Layers) | SF | $0.00 | 667 | 3.00 | 2,000 | 0 | 3.09 | 2,060 |
| 5000 | Remove and Dispose of Asbestos Containing Roof Flashing | LF | $0.00 | 2,000 | 2.50 | 5,000 | 0 | 2.58 | 5,160 |
| 5100 | Remove and Dispose of Asbestos Containing Glazing and Puty | SF | $0.00 | 667 | 8.00 | 5,333 | 0 | 8.24 | 5,493 |
| LEAD-BASED PAINT REMOVAL | |||||||||
| 5200 | Lead-Based Paint Removal | SF | $0.00 | 1,333 | 11.00 | 14,667 | 0 | 11.33 | 15,107 |
| 5300 | Mold Remediation | SF | $0.00 | 1,333 | 2.00 | 2,667 | 0 | 2.06 | 2,747 |
| 5400 | Initial Asbestos, Lead-Based Pain, Mold Building Survey: | $0.00 | |||||||
| 5400-1 Building Up to 5000 SF | EA | $0.00 | 5 | 2,200.00 | 11,000 | 0 | 2,266.00 | 11,330 | |
| 5400-2 Building Greater Than 5000SF, Up to 10,000 SF | EA | $0.00 | 8 | 2,400.00 | 20,000 | 0 | 2,472.00 | 20,600 | |
| 5400-3 Building Greater Than 10,000 SF, Up to 20,000 SF | EA | $0.00 | 3 | 3,000.00 | 8,000 | 0 | 3,090.00 | 8,240 | |
| 5400-4 Building Greater Than 20,000 SF | EA | $0.00 | 1 | 3,800.00 | 2,533 | 0 | 3,914.00 | 2,609 | |
| 5500 | Construction/Post-Construction Asbestos Sample Testing | EA | $0.00 | 2 | 500.00 | 833 | 0 | 515.00 | 858 |
| 5600 | Unpriced Unit Items (10%) | ||||||||
| DO NOT BID ON THIS LINE ITEM. THIS LINE ITEM WILL ONLY BE USED FOR PROJECTS WHERE NO PRE-PRICED LINE ITEMS EXIST ELSEWHERE IN THE BID SCHEDULE. IT WILL BE NEGOTIATED AT TIME OF OCCURRENCE. | |||||||||
| 5700 | Bond (2.5% of Total) | LS | $0.00 | 1 | |||||
| 5800 | Asbestos Fees | EA | $0.00 | 20 | 75.00 | 1,500 | 0 | 75.00 | 1,500 |
| 5900 | As-Built Drawings | EA | $0.00 | 10 | 2,300.00 | 23,000 | 0 | 2,369.00 | 23,690 |
| TOTAL | 987,943 | 0 | 1,018,574 |
File details come from the government source that posted it. Updated .