FOR OFFICIAL USE ONLY
DEPARTMENT OF THE ARMY
NETWORK ENTERPRISE CENTER
PLANS, ARCHITECTURE & SERVICE OPERATIONS BRANCH
FORT HOOD, TEXAS 76544
NETWORK ENTERPRISE CENTER
STATEMENT OF REQUIREMENTS
Project
BLDG 38022
Communications Infrastructure Upgrade
FORT HOOD, TEXAS
DEVELOPED BY
NETWORK ENTERPRISE CENTER
2 February 2016
Distribution authorized to US Government agencies and their specified contractors only, for administrative or operational use. Other requests for this document shall be referred to Network Enterprise Center Attn: NEC, Plans Branch, Building 422 27th St, Fort Hood, Texas 76544
FOR OFFICIAL USE ONLY
GENERAL STATEMENT OF REQUIREMENT
Network Enterprise Center (NEC)
General Information:
Communications POC: Angel Rodriguez-Ayala 254(535-2237)
Project ID:
Project title: Admin Facility
General Requirements:
Provide all labor, material, and equipment required to install communications infrastructure to make the facility complete and usable.
Follow all TIA/EIA and RUS standards covering all installation aspects of communications infrastructure. In addition to the industry standards, follow the guidance published by the Network Enterprise Center (NEC) IT Installation Design Guide (IDG) and the Technical Criteria for the Installation Information Infrastructure Architecture I3A.
Perform all required repairs, fixes and adjustments necessary to ensure the installation meets applicable standards.
Specific Requirements:
1.1 Telecommunications Room:
1.1.1 Provide a TR sized in accordance with I3A requirements.
1.1.2 Provide an independent environmental controlled HVAC for the communications room per I3A requirements.
2.1 Duct/Manhole System:
No Requirement exists
3.1 Outside Plant Fiber:
3.1.1 Contractor provide/install 2 fiber jumpers 50’ long with ST to LC terminations from the existing LUI to the new rack location.
3.1.2 Take all measures to protect the FOC (Fiber Optic Cables) and all components currently installed in the buildings from damage during reconstruction efforts.
4.1 Outside Plant Copper:
4.1.1 Contractor shall upgrade in building 38022, 1 each 25 pairs protector unit with 5 pin plug-in protection modules.
4.1.2 Contractor shall terminate 25 pair copper on a circa protector unit.
4.1.3 From the protector unit the contractor shall extended CAT 3 riser cable to the new telecommunications room. Contractor shall install rack mounted 24 port category 6 patch panels and terminate all pairs of the risers, one (1) pair to each of the RJ-45 jacks per NEC IDG requirements.
4.1.4 Ground all OSP telecom equipment utilizing #6 AWG grounding wire in accordance with NFPA 70 and other regulatory and industry standards.
5.1 Building Communications General Installation:
5.1.1 Provide/Install fire retardant backboard painted for mounting required equipment within the communication room. DO NOT
PAINT OVER THE FIRE RETARDANT STAMP.
5.1.2 Contractor shall remove rack from the current location and re-install rack in the new communications room to allow mounting Cat 6 patch panels and electronic devices.
5.1.3 Provide/Install appropriate TMGB and ground all telecom equipment utilizing #6 AWG grounding wire in accordance with NFPA 70 and other regulatory and industry standards.
5.1.4 Provide/Install two dedicated 20A duplex receptacles near the rack location for energizing electronic devices mounted in the rack.
5.1.5 Provide/install Category 6 patch panels sized appropriately for the category 6 cable coming from the various user outlet locations as depicted on DPW floor plans.
5.1.6 Contractor shall install dual cat 6 (blue) drops as shown on DPW floor plan. Route all cat 6 cables to the outlet locations throughout the building utilizing the most cosmetically pleasing approach.
5.1.7 Contractor shall install one single drop wall outlet in the communications room with mounting lugs for wall telephone.
5.1.8 Provide/Install cable management panels in the equipment cabinet or rack for managing cables front and back. Velcro ties shall be used on lieu of plastic Zip ties or electrical tape to secure loose patch cabling.
5.1.9 Provide/Install telecom cable management mounted on the back board and equipment rack for managing cables entering the communications room.
5.1.10 All terminations shall have testing completed per TIA/EIA and NEC IDG requirements.
6.1 Networking and Switching:
6.1.1 Provide/Install dual 8P8C RJ-45 jacks (blue or white) mounted in face plates at all user locations in accordance with DPW floor plan layout.
6.1.2 Provide/Install Category 6 cable runs from each RJ-45 location to the cabinet or rack mounted patch panel and terminate both ends in accordance with TIA/EIA-568-C (T568B) and the NEC IDG requirements.
6.1.3 Label all outlet locations and the communications room patch panel in accordance with the NEC IDG.
6.1.4 Provide/Install above ceiling cable management in the form of cable tray or the appropriate telecommunications J-Hooks. Do not fill beyond 50% fill ratio.
6.1.5 Provide/Install 1” EMT from the user drop locations to 1’ above ceiling. Ensure to have a plastic sleeve installed at the end above the ceiling to prevent cable chafing when installing the category 6.
7.1 Contractor’s requirements: The Contractor will notify government representative when job starts and is completed and ready for quality assurance inspection.
7.1.1 Contractor shall perform a permanent link test on each category six cable and provide electronic and hard copy test reports to the NEC
PM.
8.1 Additional Requirements: The following supplies are to be delivered to Fort Hood NEC Plans and Architecture Branch as part of this project.
QTY 24 Cat 6 Patch Cables 5’ long.
End of Statement: