Attachment_0008_Quality_Requirements_SOW.pdf
PDF 117 KB Posted
- Attached to
- M70 Series Cable Assemblies
- Solicitation number
- W52P1J-18-R-0153
About this file
Attachment 0008 Quality Requirements SOW
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY REQUIREMENTS: INSPECTION, ACCEPTANCE, QUALITY ASSURANCE,
AND RELIABILITY
QA001 STATISTICAL PROCESS CONTROL
Part I – General Statistical Process Control Requirements
(a) In addition to the quality requirements of the technical data package, the Contractor shall implement Statistical Process Control (SPC) in accordance with a government accepted SPC Program Plan. Control chart techniques shall be in accordance with the American National Standards Institute (ANSI) B1, B2 and B3. Alternate SPC charting methods may be proposed and submitted to the Government for review.
(b) The SPC Program Plan developed by the contractor shall consist of a general plan and a detailed plan. The plans shall be structured as delineated on the Data Item Description referenced in the DD Form 1423. The general and the detailed plans shall be submitted to the government for review per DD Form 1423 requirements. Notification by the Government of acceptance or nonacceptance of the plans shall be provided in accordance with the timeframes specified on the DD Form 1423.
Once a general plan for a facility has been approved by this Command, the approval remains in effect for subsequent contracts as long as the contractual requirements remain substantially unchanged from contract to contract. Therefore, resubmission of a previously accepted general SPC plan is not required if current SPC contract requirements and Data Item Description (DID) requirements are fulfilled. If this Command has previously accepted the general SPC plan under essentially the same SPC contractual requirements, so indicate by providing the Contracting Officer with the following information:
Date of Acceptance ______________
Contract Number(s) ______________
(c) The contractor is responsible for updating the general plan to current SPC contractual requirements. If errors or omissions are encountered in a previously accepted SPC general plan, opportunities for improvement will be identified by the Government, and corrective action shall be accomplished by the contractor.
(d) A milestone schedule will be submitted for those facilities who do not have, or have never had, a fully implemented SPC program and will not have a fully operational SPC program once production is initiated. The milestones shall provide a time phased schedule of all efforts planned relative to implementation of an SPC program acceptable to the Government. A milestone schedule shall include implementation start and complete dates for those SPC subjects addressed in the Statistical Process Control requirement located in Part II of this section. The milestone schedule shall only include those actions that cannot be accomplished prior to first article or the initiation of production, if a first article is not required. Milestones shall be developed for each commodity identified for SPC application. Milestones shall be submitted through the Government Quality Assurance Representative to the Contracting Officer for review and acceptance. Any deviations from the accepted milestones, to include justification for such deviations, shall be resubmitted through the same channels for review. The Government reserves the right to disapprove any changes to the previously accepted milestones. Notification by the Government of the acceptance or nonacceptance of the milestones shall be furnished to the Contractor by the Contracting Officer.
(e) The Contractor shall review all process and operation parameters for possible application of SPC techniques. This review shall include processes and operations under the control of the prime contractor and those under the control of subcontractor or vendor facilities. A written justification shall be included in the detailed plan for each process and operation parameter that controls or influences characteristics identified as critical, special, or major which have been deemed impractical for the application of SPC techniques. A pamphlet on application of SPC for short production runs is available through the Contracting Officer.
(f) Statistical evidence in the form of control charts shall be prepared and maintained for each process or operation parameter identified in the detailed plan. These charts shall identify all corrective actions taken on statistical signal. During production runs, control charts shall be maintained in such a manner to assure product is traceable to the control charts. At the conclusion of the production run, a collection of charts traceable to the product, shall be maintained for a minimum of 3 years. The control charts shall be provided to the Government for review at any time upon request.
(g) When the process or operation parameter under control has demonstrated both stability and capability, the Contractor may request, in writing, through Administrative Contracting Officer (ACO) and Contracting Officer (CO) channels to the Product
Assurance and Test Directorate, that acceptance inspection or testing performed in accordance with contract requirements be reduced or eliminated. Upon approval by the CO, acceptance shall then be based upon the accepted SPC plan, procedures, practices and the control charts.
(h) The Government will not consider requests for reduction or elimination of 100% acceptance inspection and testing of if any one of the following conditions exist:
(1) The existing process currently utilizes a fully automated, cost effective, and sufficiently reliable method of 100% acceptance inspection or testing for an attribute-type critical parameter or characteristic.
(2) The Contractor utilizes attribute SPC control chart methods for the critical parameter or characteristic.
(3) The critical parameter or characteristic is a first order, single point safety failure mode (nonconformance of the critical parameter or characteristic in and of itself would cause a catastrophic failure).
(i) The Government will only consider reduction or elimination of the 100% acceptance inspection or test requirement for other critical parameters or characteristics if either of the following conditions are met:
(1) The process is in a state of statistical control utilizing variable control chart methods for the critical parameter or characteristic under control and the process performance index (Cpk) is at least 2.0. The Contractor shall maintain objective quality evidence through periodic audits that the process performance index is being maintained for each production delivery.
(2) The critical parameter or characteristic is conclusively shown to be completely controlled by one or more process or operation parameters earlier in the process, and those parameters are in a state of statistical control utilizing variable data, and the product of the probability of the conformance for each earlier parameter associated to the critical characteristic is better than or equal to a value equivalent to that provided by a Cpk of at least 2.0. The Contractor shall maintain objective quality evidence through periodic audits that the process performance indexes are being maintained for each production delivery.
(j) For characteristics other than critical, requests for reduction or elimination of acceptance inspection and testing shall be considered when the process performance index is greater than or equal to a Cpk of 1.33 for variables data.
Requests shall be considered for attributes data when the percent beyond the specification limits is less than or equal to .003 (Cpk=1.33).
(k) Process or operation parameters under reduced or eliminated inspection or testing that undergo a break in production less than 6 months in length, may continue to operate under reduced or eliminated inspection or testing provided there has been no degradation below a Cpk of 1.33 (2.0 for criticals). Any break in production greater than 6 months shall require resubmission of the request for reduction or elimination of inspection or testing through the same channels cited in paragraph (g) above.
(1) Not used.
(m) Immediately following a change to a process or operation parameter under reduced or eliminated inspection, the process capability (Cp) or process performance indexes (Cpk) shall be recalculated and documented for variable data; the grand average fraction defective shall be recalculated for attribute data. If any of these values have deteriorated, immediate notification shall be made to the Government along with the associated documentation. Return to original inspection and test requirements may be imposed as stipulated in paragraph n below.
(n) The Government reserves the right to withdraw authorization to reduce or eliminate final acceptance inspection or testing and direct the Contractor to return to original contract inspection or test procedures at any indication of loss of process control or deterioration of quality.
Part II – Detailed requirements pertaining to plan submittal
In accordance with DD Form 1423 and Part I of this section, the following supplemental information shall be considered and used when designing your general and detailed SPC plans.
1.0 General Management Plan
This section shall define management’s SPC responsibilities and involvement and shall include management’s commitment to continuous process improvement. The plan shall embrace a total commitment to quality and shall be capable of standing on its own merit.
1.1 Policy/Scope:
Describe the Contractor’s policy for applying SPC, including goals and management commitment to SPC.
1.2 Applicable Document:
List documents that are the basis for the contractor’s SPC program (i.e., ANSI standard, textbooks, Government documents).
1.3 SPC Management Structure:
Define the SPC management structure within the organization.
Identify and include interrelationships of all departments involved in SPC (i.e., Production, Quality, Engineering, Purchasing, etc.) Identify by job title or position all key personnel within departments involved in the application of SPC.
Describe which functions are performed by key personnel and when these functions are performed (i.e., include personnel responsible for performing inspections/audits, charting and interpreting data; personnel responsible for determining, initiating and implementing corrective action upon detecting assignable causes, etc.)
1.4 SPC Training:
Identify by job title or position the primary individual responsible for overseeing that SPC training is accomplished.
Describe the qualification program required and in use for all personnel utilizing SPC techniques, including the qualification of trainers. Identify who is to be trained and the type, extent and length of such training (i.e., on-the-job, classroom, etc.).
Identify when refresher training is required and how personnel using SPC techniques are monitored.
1.5 Manufacturing Controls:
Identify the criteria for performing SPC gage capability studies and describe how and when these studies are applied.
Repeatability and accuracy of gages should be addressed.
1.6 Determination of SPC Use:
Describe how the process/operation parameters are determined appropriate for SPC application and explain what actions are taken if SPC is not deemed appropriate for critical, special and major process/operation parameters (i.e., Pareto analysis;
analysis of characteristics with tight tolerances, etc.)
1.7 Process Stability and Capability:
a. Identify the criteria for performing process capability studies and describe how and when these studies are applied.
Describe how the process capability index is calculated and include the frequency of these calculations. Describe what actions are taken as a result of each process capability study.
Describe the contractor’s methodologies when process capability is for variable and attribute data. To determine a capable process, the process/operation parameters shall meet the following requirements:
(1) Variable Data. Process capability (Cp) shall be determined. Process performance index shall be greater than or equal to 1.33 (Cpk). For critical parameters/characteristics, the process performance index shall be greater than or equal to
2.0 (Cpk).
(2) Attribute Data: Process capability/performance shall be the percent beyond the upper/lower specification limit less than or equal to .003 percent (Cpk=1.33).
b. Describe what actions will be taken if process/operation is sub-marginal or marginal. (Cpk less than 1.33 or 2.0 for criticals) or grand average fraction defective is greater than .003 percent).
c. Include analysis of statistical distributions and define all formulas and symbology utilized.
1.8 Control Chart Policy:
a. Type of charts to be used (i.e., x bar/R x bar/S, etc.) and rationale for use; the criteria for selection of sample size, frequency of sampling and rational subgroups.
b. Procedures for establishing and updating control limits, including frequency of adjustments.
c. Criteria for determining out-of-control conditions (i.e., trends, points beyond control limits, etc.) and the corrective action taken; to include failure analysis when the process is unstable or when nonconforming product has resulted from unstable processes. Illustrate out-of-control tests.
d. Describe the method of recording pertinent facts on control charts such as changes in raw materiel, machines, manufacturing methods and environment, and corrective actions taken and describe how control charts are traceable to the product.
1.9 Vendor/Subcontractor Purchase Controls:
Identify whether suppliers are required to utilize SPC and describe the extent the vendor’s policies and procedures are consistent with in-house procedures of the prime contractor.
Describe the following: methods utilized to determine that suppliers have adequate controls to assure defective product is not produced and delivered; the system utilized to audit suppliers, what will be audited and how often; what action will be taken when out-of-control conditions exist at subcontractor/vendor facilities.
1.10 SPC Audit System:
At a minimum, the contractor’s SPC Audit System shall consist of auditing compliance with the planned arrangements specified in the general and detailed SPC plans followed by a review and analysis of the outcome to include implementation of necessary corrective action.
1.11 SPC Records:
Identify various records to be used in support of SPC and describe their use. Identify retention periods.
2.0 Detailed Plan:
This section shall detail specific manufacturing process/operation parameters under control.
2.1 Control of Process/Operation Parameters or Characteristics:
a. Identify the following for each process/operation by name or characteristic under control:
(1) Identify process/operation by name or characteristic and provide rationale for selection; justification for non-selection if the parameter or characteristic is identified as critical, special and/or major.
(2) Describe how the characteristic is produced; the chain of events, type and number of machines involved, location of manufacturing facility, tolerances maintained, etc.
(3) Production and inspection machinery used. Include the production rate, number of shifts and length of shifts plus whether inspection is fully or semi-automatic or manual. If manual, identify the type of gages in use.
(4) Identify the type of charts to be maintained and whether the process/operation is performed in-house or subcontracted out; identify facility/vendor where process/operation parameters are targeted for SPC.
2.2 Reduction or Elimination of Inspection/Test: The Procuring Contracting Officer (PCO) will accept submissions of requests for reduction or elimination of final acceptance inspection/testing when the SPC contract requirements are met.
Each request shall contain and/or address the following: control charts documenting twenty (20) consecutive production shifts or more for the same process/operation parameter under control;
type of control chart utilized; control chart limits and process average or grand average fraction defective (as applicable);
definition of out-of-control condition and corrective actions taken during out-of-control conditions; specification and part number.
QA002 REWORK AND REPAIR OF NONCONFORMING MATERIAL
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR’s disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.
QA003 DESTRUCTIVE TESTING
(a) All costs for destructive testing by the Contractor and items destroyed by the Government are considered as being included in the contract unit price.
(b) Where destructive testing of items or components thereof is required by contract or specification, the number of items or components required to be destructively tested, whether destructively tested or not, shall be in addition to the quantity to the delivered to the Government as set forth in the Contract Schedule.
(c) All pieces of the complete First Article shall be considered as destructively tested items unless specifically exempted by other provisions of this contract.
(d) The Contractor shall not reuse any components from items used in a destructive test during First Article, lot acceptance inprocess testing, unless specifically authorized by the Contracting Officer.
(e) The Government reserves the right to take title to all or any items or components described above. The Government may take title to all or any items or components upon notice to the Contractor. The items or components of items to which the Government takes title shall be shipped in accordance with the Contracting Officer’s instructions. Those items and components to which the Government does not obtain title shall be rendered inoperable and disposed of as scrap by the Contractor.
QA004 MEASUREMENT SYSTEM EVALUATION
(a) Definitions. This paragraph defines specific terms utilized throughout the rest of this section and in the accompanying Contract Data Requirements List (CDRL) and Data Item Description (DID). This aids in clarifying the MSE requirements to Government and contractor personnel.
(1) Acceptance Inspection Equipment (AIE). All equipment (includes AAIE defined below), special and standard, including dimensional gages, measuring equipment, test fixtures, electronic and physical test equipment, and other test equipment used for examination and test of a product to determine conformance to the Technical Data Package (TDP) which may include drawings and specifications (e.g., Detail, Performance, Weapon specifications, and QAPs).
(2) Automated Acceptance Inspection Equipment (AAIE). AIE in which the inspection and acceptance determination of the product is performed, in whole or in part, in an automatic manner.
(3) Contractor Inspection Equipment. Government-approved equipment utilized by the contractor to perform examination and tests to assure conformance to contract requirements.
(4) Commercial Inspection Equipment. Industry-developed inspection equipment of universal application, without limitations to a specific part or item, which is advertised or cataloged as available to the trade or to the public on an unrestricted basis at an established price. Examples follow:
(i) Standard Test Equipment. Multiusage equipment that is specific to a function rather than to an item. It includes such items as hardness testers, tensile strength testers, meters, weighing devices, standard gear testers, ohmmeters, voltmeters, and oscilloscopes.
(ii) Standard Measuring Equipment (SME). Multipurpose equipment and standards used for performing measurements. It includes such items as micrometers, rulers, tapes, height gages, and protractors, etc. Standards include visual inspection equipment such as scratch and dig standards, surface finish comparator, color standards (FED-STD-595), etc.
(5) Nondestructive Testing. The development and application of technical methods to examine materials or components in ways that do not impair future usefulness and serviceability in order to detect, locate, measure and evaluate flaws; to assess integrity, properties and composition; and to measure geometrical characteristics. NDT includes Radiography/Radioscopic, Ultrasonic, Eddy Current, Magnetic Particle, and Liquid Penetrant.
(6) Measurement System Analysis (MSA). Per ASTM E2782 (Standard Guide for MSA), paragraph 3.1.7, MSA is any of a number of specialized methods useful for studying a measurement system and its properties.
(b) Scope. This section establishes requirements for design, supply, performance, and maintenance of AIE used for product inspection and acceptance. In addition, this section establishes requirements for the preparation, submission, and approval of AIE documentation.
(c) AIE. The contractor shall provide all AIE necessary to ensure conformance of components and end-items to contract requirements. AIE shall include inspection, measuring, and test equipment whether Government furnished or contractor furnished (including commercially acquired) along with the necessary specifications and procedures for their use (see ISO 10012, paragraph 6.2.1). The AIE shall not create or conceal defects on the product being inspected. All AIE documentation shall contain sufficient information to permit evaluation of the AIE’s ability to test, verify, and/or measure the applicable characteristics or parameters (see applicable DID referenced in DD Form 1423).
(d) AIE Designs & Government Furnished Gages. AIE designs are of two types – Government designs (see (d)(1)) and contractor designs (see (d)(2)). When applicable, Government designs or Government furnished gages are designated in the TDP/contract;
responsibility for all other AIE is assigned to the contractor.
The designs, associated inspection procedures, and theory of operation shall have the level of detail to demonstrate capability of the proposed AIE to perform the required inspection.
(1) Government AIE Designs. Government AIE designs may consist of detailed drawings necessary for the fabrication and use of the AIE. Unless otherwise specified, the contractor may submit alternate or modified contractor designs of Government AIE designs.
(2) Contractor AIE Designs. Contractor AIE design drawings shall meet the requirements of ASME Y14.100, ASME Y14.5 and ASME Y14.43 and may include commercial inspection equipment.
[“Commercial inspection equipment” is defined as shown in paragraph (a)(4) above. It shall be fully described by catalog listings or other means which provide sufficient information to permit identification and evaluation by the Government and may include illustrations and engineering data.] Designs shall be submitted for any special fixture(s) to be used. Unless otherwise specified, Gage Tolerancing Policy shall be in accordance with ASME Y14.43, “Absolute Tolerancing (Pessimistic Tolerancing).”
(3) Visual Inspection. Visual inspection standards used for the acceptance/rejection of product shall be submitted for approval.
(e) AIE Package Submittals. The contractor shall prepare the AIE package submittal in accordance with the DID referenced in the applicable Contract Data Requirements List (CDRL – DD Form 1423). In addition, the contractor shall adhere to the following requirements:
(1) Designs for Approval. Contractor designs and/or the submission for the use of Government designs shall be approved by the Government. Partial submission of AIE designs is permissible in order to expedite the approval process; however, the response date for design review will be based on the date of the final complete submission of designs.
(2) Correspondence in English. The contractor shall ensure all AIE correspondence and documentation are submitted in English.
(3) Units of Measurement. The units of measurement within the AIE package submittal shall be consistent with the requirements of the Technical Data Package (TDP).
(4) AIE Flow Down. The contractor shall flow down AIE requirements to sub-contractors at any tier who are performing acceptance inspections.
(f) Characteristics for Inspection. AIE documentation for Critical, Special, and Major characteristic inspections shall be submitted to the Government for approval in accordance with (IAW) the CDRL (see DD Form 1423). AIE for Minor characteristic inspections shall be submitted to the Government for approval IAW CDRL (see DD Form 1423) and as required below:
(1) [X] Listed Minor (characteristics displayed on specifications and/or drawings
(2) [ ] Government selected list (as attached or as provided herein):
Click here to enter text.
(3) [ ] Not submitted
(g) Automated Acceptance Inspection Equipment. The AAIE shall accept only conforming material. All characteristics requiring AAIE per the TDP shall utilize inspection equipment with a minimum demonstrated reliability of 99.8% at a 90% confidence level to detect non-conforming material unless otherwise specified below.
(1) Reliability of _____% at a _____% Confidence Level for Critical/Special Characteristics
(2) Reliability of _____% at a _____% Confidence Level for Major Characteristics
(3) For inspection of major and minor characteristics where contractor utilizes AAIE when it is not required by the TDP, the AAIE package shall be submitted to the Government for approval.
If the Minor characteristic is not listed in paragraph (f)(2) or not required for submittal in paragraph (f)(3), then the AAIE requirements (e.g., verification, calibration, prove-out, etc.)
of the inspection shall still be performed.
(4) All AAIE packages submitted to the Government for approval shall be in accordance with MIL-A-70625 (Automated Acceptance Inspection Equipment Design, Testing and Approval of). Furthermore, the contractor shall be responsible for producing the acceptance and rejection verification standards/masters representative of the characteristics the AAIE is designed to inspect. The verification standards and frequency of use require Government approval prior to use. When verification standards are used for the VL-VII “sampling plan” per MIL-STD-1916 paragraph 4.4, verification standards and frequency of use shall require Government approval prior to use.
(5) If the AAIE accepts a critical characteristic “reject” standard the contractor shall notify the Government and act in accordance with paragraph (f) of Critical Characteristic Control. In addition, if the AAIE accepts a major and/or minor characteristic “reject” standard the contractor shall act in accordance with paragraph 8.3 of ISO 10012 or paragraph 5.2.3 of
ANSI/NCSL Z540.3.
(6) All AAIE shall be required to pass a Government-approved Acceptance (Prove-Out) Test. The contractor shall conduct this test per the approved test plan and shall submit a test analysis report for approval. See applicable DD Form 1423. This test shall be performed at the contractor’s facilities whose manufacturing system has had the AAIE fully integrated and calibrated as per paragraph (j) of this section. The contractor shall allow Government personnel access to this facility and unobstructed monitoring of this test.
(7) The contractor shall notify the Government prior to a modification and/or relocation of the Government-approved AAIE.
The modified AAIE designs shall be submitted for approval. The modified and/or relocated AAIE shall require submission of the acceptance test plan (prove-out) and results for review and approval prior to use. The modified and/or relocated AAIE shall be in accordance with paragraphs (g)(1) – (g)(6).
(h) Measurement System Analysis (MSA). The contractor is responsible to ensure all AIE is, at a minimum, stable, repeatable, and reproducible for all characteristics. Refer to ASTM E2782 and/or AIAG MSA for guidance. The contractor shall provide objective evidence, including the MSA assessment plan, associated data, and analysis, which demonstrates the AIE is, at a minimum, stable, repeatable, and reproducible for the following characteristics (MSA CDRL):
N/A
Approval of submitted MSA(s) must be granted before the corresponding AIE can be used or continue to be used for acceptance of product. If at any time following approval of the AIE and MSA the AIE is disapproved, then the MSA shall be disapproved. After the resubmitted AIE is approved, the MSA shall be conducted on the approved AIE and resubmitted for approval.
(i) Robust AIE System. The contractor shall ensure the AIE and its use is not negatively affected by any manufacturing/inspection environmental stimuli including, but not limited to production rate, noise, temperature, humidity, and vibration.
(j) AIE Calibration and Verification. The calibration system shall be in accordance with ISO 10012 or ANSI/NCSL Z540.3. All AIE shall be subjected to scheduled calibration intervals to ensure that the equipment will accept only conforming product and reject all non-conforming product for the duration of the approved calibration period. AIE shall be subjected to periodic verification to ensure that the equipment will continue to accept and reject product with the same consistency as it did at the time of its previous calibration.
(k) Non-Destructive Testing (NDT). Contractor shall submit detailed plans for qualifying and certifying NDT personnel and plans for qualification and ongoing use of NDT methods used for inspecting product. If re-qualification of NDT personnel and/or NDT methods is required, then the applicable plans shall be submitted.
(1) Personnel performing NDT examinations shall be qualified and certified in accordance with the standard practices prescribed by NAS 410 (NAS Certification & Qualification of NDT Personnel), ANSI/ASNT-CP-189 (ASNT Standard for Qualification and Certification of NDT Personnel), or SNT-TC-1A (Recommended Practice for Personnel Qualification and Certification in NDT), and additional procedures that may be identified by the Government. Acceptance of product using NDT shall be performed by personnel at a level of qualification consistent with that defined in the applicable standard.
(2) The NDT method(s) shall be applied in accordance with ASTM E 543 (Standard Specification for Agencies Performing Nondestructive Testing) and the current nationally recognized standard practices appropriate to the NDT method(s) employed, such as ASTM E-1742 (Standard Practice for Radiographic Examination) and SAE-AMS-STD-2154 (Inspection, Ultrasonic, Wrought Metals, Process For). Each application technique shall identify the standard(s) utilized. Non-destructive testing includes, but is not limited to, the following types of testing:
Radiography/Radioscopic, Ultrasonic, Eddy Current, Magnetic Particle, and Liquid Penetrant.
(l) Contractor Alternate Inspection Method(s), Modifications and/or Relocation of AIE (Non-Automated) After Government Approval. If the contractor proposes an alternate inspection method and/or modifies the AIE design(s) affecting hardware, software, or procedures after Government approval the intended change(s) shall be submitted to and approved by the Government prior to implementation. If an AIE is relocated and the relocation risks the integrity of the inspection system, notify the Government to determine information needed to assess impact to AIE. See DD Form 1423.
(m) Responsibility for AIE Package Submittal. The contractor shall submit the AIE design documentation package within contractual timeframes per CDRL (See DD Form 1423). The Government will provide approval or disapproval within the timeframe specified in the CDRL. Disapproval of the AIE package will require re-submittal and subsequent Government review in accordance with the CDRL requirements. The AIE package and any required prove-outs must be approved prior to First Article (FA) (if required) or production start-up if FA is not required.
(n) Government’s Right to Disapprove AIE. The Government reserves the right to revoke approval of any AIE that is not satisfying the required acceptance criteria at any time during the performance of this contract. See DD Form 1423.
(o) Navy Furnished Gages. When gages are listed in paragraph (o)(9) below, the Navy Special Interface Gage (NSIG) Requirement paragraphs (o)(1) – (o)(8) shall be satisfied.
(1) The NSIG(s) are provided for verification of selected interface dimensions and do not constitute sole acceptance criteria of production items or relieve the contractor of meeting all drawing/specification requirements under the contract.
(2) The contractor is responsible for contacting the Naval Surface Warfare Center (NSWC), Corona Division at least 45 days prior to FAT (if required) or production, for the delivery of NSIG(s).
(3) NSIG(s) will be forwarded to the contractor for joint use by the Government and the contractor. Government furnished NSIG(s) shall not be used by the contractor(s) or subcontractor(s) as in-process or working gage(s).
(4) For production items that fail to be accepted by the applicable NSIG(s), an alternate inspection method may be submitted for approval.
(5) The contractor may substitute contractor designed and built AIE for the NSIG(s) noted in paragraph (o)(9) below.
However, the designs require Government (Navy) approval and the contractor AIE hardware requires Government (Navy) certification. AIE designs shall be submitted in accordance with CDRL (see DD Form 1423).
(6) The Government (Navy) shall not be responsible for discrepancies or delays in production items resulting through misuse, damage or excessive wear to the NSIG(s).
(7) Calibration and repair of the NSIG(s) shall only be performed as authorized by the NSWC Corona Division. Repair is at no cost to the contractor unless repair is required due to damage to the gages resulting from contractor fault or negligence. Damaged, worn, or otherwise unserviceable NSIG(s) shall be brought to the immediate attention of the CAO and NSWC Corona Division. The contractor shall not make any adjustments, alterations or add permanent markings to NSIG(s) hardware unless specified by the NSIG operating instructions or authorized by the NSWC Corona Division.
(8) Within 45 calendar days after final acceptance of all production items, the NSIG(s) shall be shipped to NSWC Corona Division, ATTN: Receiving Officer, Bldg 575, Gage Laboratory, 1999 Fourth St., Norco, CA 92860-1915. The following shipping and marking specifications are applicable:
(i) Shipping, MIL-STD-2073, “DOD Standard Practice for Military Packaging”
(ii) Marking, MIL-STD-129, “Marking for Shipment and Storage”.
(9) The following NSIG(s) shall be provided and are mandatory for use except as noted by paragraph (o)(5) above.
No NSIGS Required
QA005 FIRST ARTICLE TEST (CONTRACTOR TESTING)
(a) The first article shall consist of:
samples in accordance with QAP M70 Cable Series, Rev
- 06 Sept 2018, which shall be examined and tested in accordance with contract requirements, the item specifications, Quality
Assurance Provisions (QAPS) and all drawings listed in the Technical Data Package.
(b) The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have been produced by the Contractor (including subcontractors) using the technical data package provided by the Government.
(c) The first article shall be inspected and tested by the contractor for all requirements of the drawing(s), the QAP(s), and specification(s) referenced thereon, except for:
(1) Inspections and tests contained in material specifications provided that the required inspection and tests have been performed previously and certificates of conformance are submitted with the First Article Test Report.
(2) Inspections and tests for Military Standard (MS) components and parts provided that inspection and tests have been performed previously and certifications for the components and parts are submitted with the First Article Test Report.
(3) Corrosion resistance tests over 10 days in length provided that a test specimen or sample representing the same process has successfully passed the same test within 30 days prior to processing the first article, and results of the tests are submitted with the First Article Test Report.
(4) Life cycle tests over 10 days in length provided that the same or similar items manufactured using the same processes have successfully passed the same test within 1 year prior to processing the first article and results of the tests are submitted with the First Article Test Report.
(5) Onetime qualification tests, which are defined as a onetime on the drawing(s), provided that the same or similar item manufactured using the same processes has successfully passed the tests, and results of the test are on file at the contractor’s facility and certifications are submitted with the First Article Test Report.
(d) Those inspections which are of a destructive nature shall be performed upon additional sample parts selected from the same lot(s) or batch(es) from which the first article was selected.
(e) A First Article Test Report shall be compiled by the contractor documenting the results of all inspections and tests (including supplier’s and Vendor’s inspection records and certifications, when applicable). The First Article Test Report shall include actual inspection and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specification and QAP requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. The Government Quality Assurance Representative’s (QAR) findings shall be documented on DD Form 1222, Request for and Results of Tests, and attached to the contractor’s test report. Two copies of the First Article Test Report and the DD Form 1222 will be submitted through the Administrative Contracting Officer to the Contracting Officer with an additional information copy furnished to the distribution list per CDRL A008.
(f) Notwithstanding the provisions for waiver of first article, an additional first article sample or portion thereof, may be ordered by the Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of 90 days, or (iii) Whenever a change occurs in place of performance, manufacturing process, material used, drawing, specification or source of supply. When conditions (i), (ii), or (iii) above occurs, the Contractor shall notify the Contracting Officer so that a determination can be made concerning the need for the additional first article sample or portion thereof, and instructions provided concerning the submission, inspection, and notification of results. Costs of the first article testing resulting from production process change, change in the place of performance, or material substitution shall be borne by the Contractor.
QA006 SUPPLEMENTAL WARRANTY INFORMATION
(a) Whenever a request for waiver, deviation, or other change to a requirement in the contract is approved, Contractor responsibilities arising out of provisions of this section are relieved only to the extent of the terms and conditions specified in the approval.
(b) For purpose of identifying the warranted material to facilities receiving it, the following instructions will apply:
(1) For a quantity of warranted material which has been accepted at origin by the Government, the pertinent DD Form 250 (and the pertinent Ammunition Data Card if the card is contractually required) shall bear the following annotation:
“The warranty period of the quantity stated hereon of (enter the item serial/lot number(s) as applicable) begins on (enter the date of acceptance of the quantity) and ends on (enter the date of the end of the warranty period for the quantity).”
(2) For a quantity of warranted material which has not been accepted at origin by the Government, the pertinent DD Form 250 (and the pertinent Ammunition Data Card if the card is contractually required) shall bear the following annotation:
“The warranty period for the quantity stated hereon of (enter item serial/lot number(s) as applicable) begins on the date of the acceptance of the lot and ends (enter the length of the warranty period) days later.”
QA007 AMMUNITION DATA CARDS AND REPORT OF CONTRACTOR
BALLISTIC TESTING
(a) Ammunition Data Cards shall be prepared in accordance with MIL-STD-1168 and shall follow the format required by the world wide web application identified as WARP or Worldwide Ammunition-data Repository Program. Information provided in paragraphs 6.7 through 6.16 of MIL-STD-1168 shall be considered mandatory requirements where all instances of the term “should” are considered to be replaced with the word “shall.” This shall also include, if required on the DD Form 1423, a Report of Contractor Lot Acceptance/Ballistic Testing and Acceptance and Description Sheets (for Propellants and Explosives). WARP will reside within the Munitions History Program (MHP). Additional details on these WARP applications are provided below.
(b) MHP-WARP Access Procedures
(1) Government or Contractor employee with CAC and AKO account:
(a) Click on the MHP hyperlink which is https://mhp.redstone.army.mil/
(b) Enter CAC PIN when prompted
(c) Click on WARP (ADC)
(d) Click on Help
(e) Click on WARP Request Access and follow instructions
(2) Contractor or Government employee without CAC and AKO account: MHP-WARP uses PKI authentication requiring a DoD approved digital certificate as a security measure to protect the integrity of stored data. There are three vendors that have been approved to issue DoD approved certificates per an External Certification Authority (ECA) program. You are required to use one of the approved vendors listed on the following DISA website: http://iase.disa.mil/pki/eca/index.html A nominal fee is charged for each certificate. The Contractor, including any subcontractors, shall assume the responsibility for all costs of obtaining each digital certificate needed.
(3) After the required certificate is obtained:
(a) Click on the MHP-WARP hyperlink:
https://mhpwarp.redstone.army.mil/
(b) Enter ECA password
(c) Click on Help and follow the instructions for obtaining the necessary access
(c) HELP Numbers are as follows:
MHP Access – (256)313-2143; DSN 897-2143 JMC Quality Administrators for WARP issues – (309)782-2697 or (309)782-7107
(d) Worldwide Ammunition-data Repository Program (WARP) An online user’s manual will provide additional help in the development of an ammunition data card. It is recommended that you download and read the user’s manual prior to inputting your initial data card. The user’s manual also contains screen shots, which depict what the inputter will see during the ADC input process.
(e) Ammunition Data Card Input ADC input allows current contractors and government facilities the capability to create, and submit for approval, ADCs which meet the format requirements of MIL-STD-1168. ADCs are automatically forwarded to the respective Government Agency Responsible for Acceptance (GARA). The GARA in most cases is the Defense Contract Management Agency (DCMA) Quality Assurance Representative (QAR), who reviews contractor input for accuracy and completeness, and after updating the disposition code for the specific lot, submits the ADC to the database. The inputter is granted access only to ADCs identified with its specific manufacturing code. The use of previously inputted ADCs through the TEMPLATE option significantly reduces input effort, while increasing accuracy and consistency of data.
(f) Email Notification WARP provides immediate, automated notification to process participants when actions are required. When the contractor has completed an ADC submission, an email message is routed to the GARA advising that an ADC awaits review and approval. If the GARA approves the ADC as submitted, the ADC is released to the base and an email, with approved data card, is routed back to the originator. If the ADC requires modification or correction to conform with MIL-STD-1168 and contract requirements, an email is provided to the ADC originator advising that corrective action is required prior to approval.
(g) Information Updates It is important that the System Administrators are apprised when a contractor receives a new contract. The contractor shall notify usarmy.ria.jmc.mbx.warp@mail.mil within 30 days after receipt of a new contract. Information to be included shall be the contract number, item, GARA, Manufacturer’s identification symbol and the names of the individuals who will be inputting ADCs into the system. If you are a new contractor and do not have a Manufacturer’s identification symbol, you can obtain one by sending an email to usarmy.ria.jmc.mbx.warp@mail.mil. The email must contain manufacturer’s name, address where performance of the contract will take place, and a point of contact.
(h) Report of Contractor Ballistic/Function Testing Module
(1) In addition to its ADC function, WARP also serves as a repository for reports of contractor ballistic (or functional) testing. Whenever the contract requires contractor performance of ballistic testing, the results of such testing shall be captured by you, the performing contractor, within a specially designed Lot Acceptance Test Report (LATR) module.
(2) Within the LATR module, you are required to provide a report of any contractor ballistic/function testing and to submit the report in electronic format via the WWW. The report must be a .pdf file for the upload process to work.
(i) Acceptance and Description Sheets (for Propellants and Explosives) Module: The WARP application now contains an area for on-screen data entry capturing requirements per MIL-STD-1171 for Acceptance and Description Sheets with respect to contract specified Propellant, Chemical and Explosive constituents.
QA008 2-D BAR CODING
(a) As a logistics measure to improve inventory, accountability, security and control, the supplier is required to provide 2-D Bar Codes in accordance with MIL-STD-129 and MIL-PRF-61002 and as further detailed in Section D of the contract.
(b) An approval of the supplier’s 2-D Bar Code Label is required before each product with a unique national stock number (NSN) or federally recognized number (FRN) shall be presented for acceptance to the Government Quality Assurance Representative.
Prior to formal submission of product to the Government for acceptance, a first time sample of the supplier’s initial 2-D Bar Coding Label, comprising of two (2) each of the exterior pack label and two (2) each of the pallet label, shall be submitted for approval to HQ, US Army Joint Munitions Command, 1 Rock Island Arsenal, ATTN: AMSJM-QAP, Rock Island, IL 61299-6500 to be read by a High Performance Bar Code Verification system.
(c) Within fifteen calendar days, the supplier will be notified electronically of the approval, conditional approval, or disapproval of the submitted 2-D Bar Code Label. A notice of conditional approval shall state any further actions required of the supplier. A notice of disapproval shall cite reasons for the disapproval.
(d) Once approval of the 2-D Bar Code Label is received, the supplier may begin presenting product to the Government for acceptance.
(e) During life cycle management of the product, the Government may randomly perform checks of the integrity and conformity of the 2-D Bar Code labeling that is affixed to the supplier’s product.
(f) The supplier is responsible for all costs associated with correcting 2-D Bar Code labels that do not meet contractual requirements.
QA009 AMMUNITION DATA CARDS
Detailed requirements and guidance for the preparation of Ammunition Data Cards (ADCs) and Ammunition Lot Numbers are contained in MIL-STD-1168, the applicable DD Form 1423 and the Worldwide Ammunition-data Repository Program (WARP) online user’s manual. Detailed requirements for obtaining and using a manufacturer’s identification symbol, which is an integral component of the ammunition lot number, can be found in MIL-STD- 1168 and the WARP user’s manual. Information provided in paragraphs 6.7 through 6.16 of MIL-STD-1168 shall be considered mandatory requirements where all instances of the term “should” are considered to be replaced with the word “shall.”
(a) The contractor shall develop and submit ADCs in accordance with the requirements of this section, MIL-STD-1168, and the user’s manual located on the WARP database.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.