Questions and Responses 08-25-2020.pdf

PDF 68 KB Posted

Attached to
W15QKN-20-Q-5295 - Replace Air Conditioning Units, Baltimore, MD Federal contract opportunity
Solicitation number
W15QKN-20-Q-5295
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

View the file

Other files for this federal contract opportunity

Other files attached to W15QKN-20-Q-5295 - Replace Air Conditioning Units, Baltimore, MD, newest first.
File Type Posted
Additional Questions and Responses W15QKN-20-Q-5295 8-26-2020.pdf PDF
W15QKN-20-Q-5295-0005 (RELEASED).pdf PDF
W15QKN-20-Q-5295-0005 (CONFORMED SOLICITATION).pdf PDF
Questions and Responses 08-24-2020.pdf PDF
W15QKN-20-Q-5295 CONFORMED SOLICITAITON 8-19-20.pdf PDF
W15QKN-20-Q-5295-0004.pdf PDF
W15QKN-20-Q-5295 CONFORMED SOLICITATION.PDF PDF
Questions and Reponses Dated 18 August 2020.pdf PDF
Attachment 0003 - Revised Site Maps Dated 14 August 2020.pdf PDF
Attachment 0002 - Specifications of Work Dated 08-14-2020.pdf PDF
W15QKN-20-Q-5295-0003 (RELEASED).pdf PDF
Attachment 0004 - Site Image Dated 14 August 2020.pdf PDF
W15QKN-20-Q-5295-0002.pdf PDF
Asbestos Inspection Report -MD003-19990908.pdf PDF
Questions and Responses - CSS 19999 MD003 08-06-20.pdf PDF
W15QKN-20-Q-5295-0001.pdf PDF
Attachment 0004 - Site Plan 02.pdf PDF
Attachment 0005 - Davis Bacon Wage Determination MD20200030 06-26-2020.pdf PDF
Attachment 0001 - Contractor Worksheet for Proposal.xls XLS spreadsheet
Attachment 0003 - Site Plan 01.pdf PDF
W15QKN-20-Q-5295 (RELEASED).pdf PDF
Attachment 0002 - Specifications of Work CSS 19999.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Responses CSS #19999 Replace 7 Air Conditioning Units

Baltimore, MD (MD003) Solicitation # W15QKN-20-Q-5295

Dated 08-25-2020

Q1. Without knowing the exact length of refrigerant line set, electrical and control wiring how can the Contractor accurately price out labor and materials per the contract SOW?

R1: The Government cannot provide an exact length of refrigerant line set, electrical and control wiring.

The Contractor is expected to inspect the site during the site visit(s) where services are to be performed to determine a solution based on the existing units.