Questions and Responses 08-24-2020.pdf

PDF 123 KB Posted

Attached to
W15QKN-20-Q-5295 - Replace Air Conditioning Units, Baltimore, MD Federal contract opportunity
Solicitation number
W15QKN-20-Q-5295
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

View the file

Other files for this federal contract opportunity

Other files attached to W15QKN-20-Q-5295 - Replace Air Conditioning Units, Baltimore, MD, newest first.
File Type Posted
Additional Questions and Responses W15QKN-20-Q-5295 8-26-2020.pdf PDF
W15QKN-20-Q-5295-0005 (CONFORMED SOLICITATION).pdf PDF
W15QKN-20-Q-5295-0005 (RELEASED).pdf PDF
Questions and Responses 08-25-2020.pdf PDF
W15QKN-20-Q-5295 CONFORMED SOLICITAITON 8-19-20.pdf PDF
W15QKN-20-Q-5295-0004.pdf PDF
W15QKN-20-Q-5295 CONFORMED SOLICITATION.PDF PDF
Questions and Reponses Dated 18 August 2020.pdf PDF
Attachment 0003 - Revised Site Maps Dated 14 August 2020.pdf PDF
Attachment 0004 - Site Image Dated 14 August 2020.pdf PDF
W15QKN-20-Q-5295-0003 (RELEASED).pdf PDF
Attachment 0002 - Specifications of Work Dated 08-14-2020.pdf PDF
Asbestos Inspection Report -MD003-19990908.pdf PDF
W15QKN-20-Q-5295-0002.pdf PDF
Questions and Responses - CSS 19999 MD003 08-06-20.pdf PDF
W15QKN-20-Q-5295-0001.pdf PDF
Attachment 0003 - Site Plan 01.pdf PDF
W15QKN-20-Q-5295 (RELEASED).pdf PDF
Attachment 0002 - Specifications of Work CSS 19999.pdf PDF
Attachment 0004 - Site Plan 02.pdf PDF
Attachment 0005 - Davis Bacon Wage Determination MD20200030 06-26-2020.pdf PDF
Attachment 0001 - Contractor Worksheet for Proposal.xls XLS spreadsheet
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Responses CSS #19999 Replace 7 Air Conditioning Units

Baltimore, MD (MD003) Solicitation # W15QKN-20-Q-5295

Dated 08-24-2020

Q1: Will the customer consider Heat Pumps on the same platforms or does the Government just want strictly Air Condition Split Systems?

R1: The Government is strictly requesting Air conditioning split systems.

Q2. Are new concrete pad(s) required?

R2: No.

Q3. Are lock boxes required for the wall mounted programmable thermostats?

R3: No.

Q4. How many remote-control devices are required per DSS?

R4: One (1).

Q5. What is the warranty period?

R5: Manufacturer’s warranty.

Q6. Is there a scope of work for the spacepak replacements?

R6: Please review Attachment 0002 – Specifications of Work Dated 08-14-2020.

Q7. Per Amendment 003 – “QUESTIONS AND RESPONSES DATED18 AUGUST 2020” –

QUESTION Q24C: Is it the government’s intention to replace all the electrical wiring and electrical components serving this equipment? Or is it the government’s intention to use the existing electrical components as needed and to increase only if the new equipment’s specifications require it.

A24C. It is the Government’s intention to replace the electrical components associated with each unit.

This answer is confusing and could grossly impact the overall cost of the project. PLEASE CLARIFY AS

TO THE GOVERNMENT’S TRUE INTENTION.

Q7: Does the government want the wire, conduit, disconnects, breakers, etc. (associated existing electrical components) replaced?

R7: Yes, it is the Government’s intention to replace the electrical components associated with each unit.

Q8: If government want the wire, conduit, disconnects, breakers, etc. (associated existing electrical components) replaced, can more drawings be provided? . Please confirm if any ELECTRICAL DRAWINGS are available to properly trace all circuits as to their origin. To do this in a site visit would take many hours of investigation. Or in a more typical replacement situation, use the existing electrical components as needed and to increase or replace only if the new equipment’s specifications require it or a testing failure.

R8: There are no additional drawings to be provided.