This Scope of Work document from the Tennessee Department of Environment and Conservation outlines a complete electrical system replacement project at the Fiery Gizzard State Park Visitor Center located in Monteagle, Tennessee. The project scope encompasses the removal and replacement of the entire building electrical system, including two existing electrical panels, all devices, light fixtures, and wiring throughout the facility. Major work components include installation of a 400-amp 3-phase manual transfer switch, two 200-amp 3-phase main breaker electrical panels, one 125-amp load center, new weather head and service entrance wires, five copper ground rods with bonding and grounding of all non-current-carrying metal parts, 26 LED troffer light fixtures, approximately 76 feet of track lighting in the museum area with motion-activated controls, new circuits for HVAC equipment with four disconnects and surge protective devices, dedicated circuits for water heater, water fountain/bottle filler, security cameras, communications equipment, bathroom vanities, kitchen countertops, front desk, and exterior lighting at multiple entrance locations. The work also includes metal siding replacement at two locations, construction of three new support walls with insulation and drywall finishing, installation of smoke and carbon monoxide detectors, hand dryers, and comprehensive labeling of all electrical components. On-site work shall be performed between December 1, 2026, and January 7, 2027, with a non-mandatory pre-bid meeting to be scheduled. The contractor must possess an active Tennessee Building Contractor license prior to bid submission, and all applicable subcontractors must similarly maintain active licenses throughout the project.
All material substitutions must receive pre-approval prior to bid acceptance, with specified approved brands and pre-approved equals listed for major components including Square-D electrical panels and breakers, Lithonia lighting fixtures, Accuity Brands lighting control systems, and DiversiTech HVAC disconnects. The contractor bears full responsibility for all permits and associated fees, as well as systematic load calculations and circuit tracing of the existing electrical distribution system to identify deficiencies and code violations. Work must comply with state-approved versions of the International Building Code, National Electrical Code, International Residential Code, and National Fire Protection Association standards. The contractor is responsible for site cleanup, repair of any damage caused during construction, and warranty of workmanship for not less than one year from the date of final inspection. Material warranties shall follow manufacturer specifications. A pre-construction conference and final inspection are required, with all invoices submitted no later than ten days after project completion and final acceptance. Facilities Management Regional Manager Mark Harris and Project Manager Adam Kilgore serve as the primary contacts for this project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PreBid_Memo.pdf | ||
| Fiery_Gizzard_S.P._Electrical_System_Replacement.pdf | ||
| Terms_-_Conditions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Visitor Center Electrical System Replacement
Fiery Gizzard State Park
11745 US-41
Monteagle, Tennessee 37356
This request for bids is for a Contract to furnish all material, equipment, supplies, and labor necessary to remove and replace the entire electrical system of the Visitor Center.
General Conditions
1) On-Site work shall be performed between December 1st, 2026, and January 7th, 2027, unless a written exception is granted by the Facilities Management Regional Manager.
2) For this project, the Contractor and applicable subcontractors shall possess an active CE Tennessee Building Contractor license prior to submitting a bid. Failure of the Contractor and applicable subcontractors to provide copies of their appropriate license shall result in the disqualification of the bid. All licenses shall be verified via Tennessee Commerce and Insurance database before project award.
3) The Contractor shall not assign this Contract or enter into a subcontract for this project without prior written approval of Facilities Management. The Contractor’s bid shall include a Declaration of Intended Use of Subcontractor(s) form that clearly states the intent to use a subcontractor, along with their name and license number. Facilities Management reserves the right to reject a bid in whole or a subcontractor, based upon failure to possess an appropriate active TN builder’s license. After project award, any proposed substitution or addition of a subcontractor shall require written Facilities Management acceptance and approval before being allowed on-site or perform any work under this Contract. All subcontractors are required to have an active TN Building Contractor license for the applicable work to be performed before and throughout the project. Any proposed subcontractor failing to meet these requirements is not allowed to perform work on any portion of this project.
4) All work shall comply with State-approved versions of the IBC, standards, regulations, other applicable codes, manufacturer’s recommendation, and best practices. The Contractor is responsible for all permits and associated fees.
5) We are requesting a non-mandatory pre-bid meeting to be held.
6) Only the Facilities Management Project Manager or Facilities Management Regional Manager can approve any alterations, modifications, and substitutions of the specifications or requirements of the project. No additional work shall be authorized unless pre-approved by either the Project Manager or Regional Manager in writing. Park/Hospitality management and staff are not authorized to make any changes, deletions, or additions to the project or accept any portion of the work. This Contract shall be modified only by a written agreement signed by all parties. Any work performed outside of the written scope with any written change orders will be the responsibility of the Contractor or others and not Facilities Management.
All questions, directives, and acceptance shall come only from either the Facilities Management Regional Manager and/or Project Manager.
7) The Contractor shall keep the jobsite clean and safe and leave in a neat and tidy manner.
8) All color selections shall be provided to the Contractor by the Facilities Management Project Manager.
9) All material substitutions must be pre-approved prior to bid acceptance.
10) All materials shall be installed per manufacturers’ recommendation, industry best practice, and applicable code.
11) All dimensions listed are approximate. The Contractor is solely responsible for verifying actual dimensions prior to ordering any materials or bidding. No allowances shall be made due to a bidder neglecting to visit the site and verifying dimensions and conditions.
12) All work performance under this Contract shall be under the full-time direction of the Contractor. The Contractor shall be responsible for work and performance, and damages of any subcontractors and/or independent contractors or laborers hired in connection with the work under this Contract.
General Scope of Work
1) Contractor shall coordinate the demolition and rebuilding to coincide with one another.
2) This project shall be a complete replacement of the entire building’s electrical system from weather head and throughout the building with a use of best trade practices. All existing and new circuits shall be provided with new wire, devices, and all necessary materials to bring up to code and back into service.
3) This project shall be in every aspect a bringing up to code and shall adhere and be complaint with all applicable National Electrical Code (NEC), International Residential Code (IRC) and National Fire Protection Association (NFPA) standards and requirements.
4) All material shall be installed according to the manufacturers’ recommendations and be installed to trade standards.
Description of Demolition or Associated Work
All debris shall be removed from the Park property and disposed of in accordance with all applicable regulations, unless specifically noted.
1) Contractor shall remove the entire electrical system of this building. This includes removal of two (2) electrical panels, all devices, all light fixtures and all wiring of the entire building.
2) Contractor shall remove two (2) conduit bodies and there wires at the penetrations of the public restroom wall. There shall also be an excavation of the ground at this point for a Quazite box to be installed with these wires terminated within it.
3) Contractor shall remove the door/wall that is in front of the existing electrical panels and metal siding at two (2) locations.
4) Contractor shall unwire all necessary equipment and devices to replace its wire and circuits.
5) Contractor shall cut and/or remove wall finishing’s to provide flush/recessed circuits throughout the building.
New Work
Permits and Inspections
1) Contractor is responsible for all necessary permits for this project. This is to include setting up and attending all necessary inspections.
Systematic Locate
2) Contractor shall provide systematic identification, tracing, load calculation and verification of all electrical circuits terminated in and/or fed from the existing two (2) electrical panels. Contractor shall evaluate the existing electrical distribution system and identify any deficiencies, code violations, or corrective actions required to bring the new installation into compliance with all applicable National Electrical Code (NEC) requirements. All information attained of this action step shall be documented and provided to the Project Manager.
Metal Siding Replacement
3) Contractor shall provide and install same type of metal siding and fasteners in two (2) locations. These shall be installed from ground to soffit and fastened in the same orientation as adjacent pieces of metal siding. This also includes contractor applying two (2) coats of paint.
Wall Construction
4) Contractor shall provide and install 2-inch x 4-inch lumber to construct three (3) walls to support the manual transfer switch (outside) and for the support of the electrical panels (inside). These walls shall be on a 16-inch center layout with a bottom and top plate. This shall include sill seal foam gasket, and pressure treated lumber for the bottom plate. Walls shall be anchored to the block walls and each other. Bottom plates shall be anchored to the concrete pad with corrosive resistant 5/8-inch x 8-inch wedge anchors. Walls are to encompass the entire space of width and height up to above ceiling grid.
5) Contractor shall provide and install Rockwool insulation for the exterior wall.
6) Contractor shall provide and install 5/8-inch drywall on the wall where electrical panels are terminated. This shall include a level 4 finish on all seams.
7) Contractor shall provide and apply primer and two (2) coats of paint on all newly hung and finished drywall. The paint color shall be provided by Project Manager.
Manual Transfer Switch
8) Contractor shall provide and install two (2) runs of Unistrut. These shall be spaced evenly and mounted to accommodate the manual transfer switch mounting. Exterior rated structural screws shall be used to install Unistrut to wall studs. Fasteners shall be sealed with polyurethane elastomeric sealant.
9) Contractor shall provide and install a 400-amp, 3-phase, manual transfer switch. This shall also include a metal rigid pipe to be installed from manual transfer switch to the new electrical panel. There shall be a sealing of the rigid pipe penetration with a polyurethane elastomeric sealant on exterior and interior sides of the metal siding of the metal rigid pipe.
Weather Head and Service Entrance Wires
10) Contractor shall provide and install a new weather head and new service entrance wires. These shall be sized accordingly by Contractor. This also shall include making all necessary terminations of these wires within the manual transfer switch and electrical panel.
Grounding and Bonding
11) Contractor shall provide and install approximately five (5) new, copper ground rods and their bronze ground rod clamps. Two (2) of these five (5) ground rods shall be for the main breaker load center installed in the Public Restroom closet. These shall be driven below ground grade. All grounding connection wire shall be terminated below ground grade as well. There shall not be a reusing of the existing.
12) Contractor shall provide and install strapping and ½ inch schedule 40 PVC conduit on wall between the manual transfer switch and ground for the ground wire to enter.
This shall be terminated just below the transfer switch and near ground grade for the ground wire to be installed within.
13) Contractor shall provide and install one (1) bronze bridge clamp. It shall be installed just below the manual transfer switch where ground wire exits the PVC conduit to enter the manual transfer switch. This shall have four (4) termination points and also include a plastic cover for the bridge clamp.
14) Contractor shall provide and install grounding and bonding of all non-current-carrying metal parts throughout the building that apply to all applicable National Electrical Code (NEC) requirements.
Electrical Panel’s
15) Contractor shall provide and be responsible for all wire sizing, circuit sizing, load calculations and all wire and conductor terminations of the three (3) electrical panels.
These panels shall have a minimum of twenty percent (20%) of spare breaker space within each panel.
16) Contractor shall provide and install two (2) new, 120/240-volt, 3-phase, 200-amp main breaker electrical panel with a dedicated surge protector and power filter for the
Visitor Center. This shall be a flush/recessed mounted panel.
17) Contractor shall provide and install one (1) new, 120/240-volt, 3-phase, 125-amp load center with a main breaker. This shall be installed in the closet space of the public restrooms. It shall be a surface mount installation, and it shall be a Nema 3R rated panel.
Breakers
18) Contractor shall provide and install all new, necessary, appropriately sized breakers for all three (3) electrical panels.
Conduit
19) Contractor shall provide and install EMT conduit with EMT compression fittings from electrical panels up to their penetration of the ceiling and throughout the interior building, where circuits may need to be surface mounted. All exterior applications shall be RMC conduit. All these areas shall be approved by Project Manager. All these shall be installed to maintain clean straight lines of the conduit, limiting bends as much as possible.
Wiring
20) Contractor shall provide and install new MC cable throughout the entire building to all branch circuits from the three (3) new electrical panels. These shall be sized according to load calculations taken from Contractor. All of these circuits shall be supported and strapped along the metal roof purlins of the building. These wires shall be secured and installed in a manner that is clean and straight branching out to each circuit, location and area.
HVAC
21) Contractor shall provide and install all circuits for the HVAC equipment within EMT conduit with compression fittings from the electrical panel and terminating at disconnects. EMT shall be secured and strapped and installed in a manner that is clean and straight from electrical panel to its termination.
22) Contractor shall provide and install four (4) new disconnects with fuses at the HVAC condenser and evaporator locations. Evaporator disconnects shall be surface mounted with EMT conduit.
23) Contractor shall provide and install four (4) new whips and four (4) new Type 2 Surge
Protective Device at all HVAC equipment and their disconnects.
24) Contractor shall provide and install one (1) 120-volt duplex outlet, weather-resistant mounting blocks/plates/kits and a weatherproof box between the (2) HVAC condenser units. This shall be recessed within the wall. Penetration shall have 1-inch conduit for a wire chase with a polyurethane elastomeric sealant around the penetration.
Water Heater
25) Contractor shall provide and install the circuit for the water heater within EMT conduit with compression fittings from electrical panel and terminating at disconnect.
EMT shall be secured and strapped and installed in a manner that is clean and straight from the electrical panel to its termination.
26) Contractor shall provide and install one (1) new disconnect with fuses and one (1) new whip at the water heater location. This shall be surface mounted with EMT conduit.
Circuits and Devices
27) Contractor shall provide and install a complete circuit replacement of all 120-volt and 220-volt circuits throughout the building. These shall terminate at the existing device locations but also shall include all necessary additional device locations, so to adhere to the 6/12 rule and all other applicable National Electrical Code (NEC) requirements.
This shall include all necessary wire, devices and material to complete the circuit. All duplex outlets shall be 20-amp. All outlet boxes shall be recessed within the wall. The devices shall be white in color. All necessary exterior receptacles required by National Electrical Code (NEC) shall follow the call out of the HVAC dedicated service outlet.
28) Contractor shall provide and install approximately twelve (12) 120-volt, 20-amp duplex outlets in specific locations throughout the museum area. These shall be for the interpretive panels. These shall be terminated at approximately 15-inches in height from floor. These locations shall be marked and provided by Project Manager.
Office Desk Outlets
29) Contractor shall provide and install ten (10) double gang boxes with their respective duplex outlets and circuits in specific locations throughout the building. These shall be recessed within the wall. Locations shall be provided by Project Manager.
Smoke and Carbon Monoxide Detectors
30) Contractor shall provide and install all necessary wire and smoke and carbon monoxide detectors throughout the building. They shall be mounted to the acoustic tile metal tracks. These shall be replaceable battery type only device and shall be interconnected.
Water Fountain/Bottle Filler
31) Contractor shall provide and install one (1) dedicated 120/240-volt circuit at the water fountain/bottle filler station. This shall include a junction box terminated above ceiling grid for the wire to pass through, then down through the wall to the equipment. This shall include wiring and re-mounting the equipment.
Troffer Light Fixtures
32) Contractor shall provide and install twenty-four (24) new, 2-foot x 4-foot and two (2) 2-foot x 2-foot LED troffer light fixtures for all areas throughout the building. Troffer lights shall be secured with two (2) 12-gauge safety wires on opposing corners of each fixture attached to the roof structure not the ceiling grid. These locations shall be marked and provided by Project Manager.
33) Contractor shall provide and install acoustic ceiling tiles in locations where existing light fixtures are removed. Contractor shall also provide and install galvanized metal cross tees for two (2) areas for the two (2) 2-foot x 2-foot LED troffer light fixtures.
Museum Light Fixtures
34) Contractor shall provide and install approximately 76-feet of track lighting system throughout the museum area of the building. These shall be mounted to the drop ceilings metal frame and have a minimum of two (2) safety chains for every 4-foot.
These shall be secured to roof framing. These tracks shall have a minimum of three
(3) LED track heads for every 4-foot. There shall be a layout of three (3) separate lighting zones with each having its on lighting control. Lighting control location shall be behind the front desk.
35) Contractor shall provide and install a stand-alone light switch for the mine shaft and the log cabin exhibit. These locations shall be provided by Project Manager.
Lighting Controls
36) Contractor shall provide and install all necessary devices to have all interior lighting
(except employee restroom) on motion activated controls. Programming parameters shall be demonstrated to Park Management. Each office space and area shall have its own standalone lighting control. Other areas shall have specific lighting control location, and this shall be provided by Project Manager.
Exterior Light Fixtures
37) Contractor shall provide and install six (6) weather-resistant mounting blocks/plates/kits for all exterior light fixtures to be installed upon. These shall have built in electrical boxes and shall be dark bronze in color. Penetrations shall have 1-inch conduit for a wire chase with a polyurethane elastomeric sealant around the penetration.
38) Contractor shall provide and install two (2) exterior rated light fixtures at each of the exterior entrances. These shall be mounted to the side of the door at a height the same as front entrance. These shall have photocell and a manual light switch at a specific location that will be provided by Project Manager.
39) Contractor shall provide and install two (2) light fixtures on the exterior wall of the main entrance. These shall be downcast lights terminated at existing light locations.
These shall have photocell and a manual light switch at a specific location that will be provided by Project Manager.
40) Contractor shall provide and install two (2) exterior light fixtures. The locations shall be one (1) in between the restroom doors and one (1) in the breezeway to the public restroom. These shall have photocell and a manual light switch at a specific location that will be provided by Project Manager.
All (3) Storage Rooms
41) Contractor shall provide and install these duplex outlets recessed within the wall and be terminated at a height approximately 48-inches from floor.
Communications and Data Equipment
42) Contractor shall provide and install one (1) dedicated 120-volt circuit for communication and data. This shall include two (2) double gang boxes and respective duplex outlets at two (2) locations in proximity to accommodate the existing equipment.
Security Cameras
43) Contractor shall provide and install one (1) double-gang box and its respective duplex outlets for security cameras. These shall be recessed within the wall and terminated in proximity to accommodate the existing equipment.
Bathroom
44) Contractor shall provide and install one (1) dedicated 120-volt circuit at bathroom vanity. This shall be recessed within the wall.
45) Contractor shall provide and install one (1) exhaust fan/light combo and one (1) vanity light fixture. The exhaust fan/light combo shall be terminated near shower stall and the vanity light being wall mounted and centered over the vanity in the bathroom.
Exhaust fan/light combo and vanity light shall all have separate switch controls for their function. These switch controls shall be manual operated switches.
Kitchen
46) Contractor shall provide and install two (2) dedicated 120-volt circuits and double gang boxes with duplex outlets every 16-inches along all countertops and terminated at appropriate height. These shall be recessed within the wall.
47) Contractor shall provide and install one (1) dedicated 120-volt circuit at the microwave/range hood combo location. This shall be terminated within the above cabinet. It shall be recessed within the cabinet/wall.
Front Desk
48) Contractor shall provide and install one (1) dedicated 120-volt circuit and three (3) double gang boxes at the front desk. These shall be recessed within the countertop knee wall with one (1) above countertop and two (2) below countertop.
49) Contractor shall provide and install one (1) dedicated 120-volt circuit to the front desk area for a space heater. This shall be a single gang box with a 20-amp duplex outlet.
This shall be recessed within the countertop knee wall below countertop.
Main Entrance Foyer
50) Contractor shall provide and install a recessed TV box kit and its circuit at the TV location in the foyer. This shall be installed to be hidden behind the TV and also it shall include a pulling of a string and leaving it accessible in ceiling space for future pull of data cables.
Public Restrooms
51) Contractor shall provide and install two (2) dedicated 120-volt circuits to the adult changing stations.
52) Contractor shall provide and install two (2) dedicated 120-volt circuits and two (2) hand dryers to the public restrooms. Location shall be provided by Project Manager.
53) Contractor shall provide and install a Quazite box at the two (2) existing LB penetrations. This shall include contractor installing the wire leaving the building and waterproofing the entrance of these wires entering the Quazite box.
Lift Station
54) Contractor shall provide and install one (1) dedicated 120-volt circuit weather-resistant mounting blocks/plates/kits and device at lift station. This shall be recessed within the wall.
This shall include a lockable double gang weatherproof box. Penetration shall have 1-inch conduit for a wire chase with a polyurethane elastomeric sealant around the penetration.
Face Plates
55) Contractor shall provide and install face plates on all outlets and switches. These shall be white in color.
Labeling
56) Contractor shall provide identification labeling for each electrical panel, all circuit breakers, all junction box cover plates, all disconnects and the acoustic ceiling tiles where junction boxes are located.
Finishings Repair
57) Contractor shall provide and install all necessary material and supplies to return any and all wall finishings back to its original state. This includes interior and exterior of the building. This shall include but not be limited to a level 4 drywall finishing and replacement of paneling. Some finishing may require painting, and this shall include primer and two (2) coats of paint.
Testing and Commissioning
58) Contractor shall field verify all existing circuits in phasing, voltage, continuity, insulation resistance and grounding before energizing.
59) Contractor shall provide documentation of test reports, inspection reports, product data, maintenance manuals, and load calculations of all circuits to Project Manager.
60) Contractor shall provide a demonstration of the system operation to Park Representative and Project Manager during the initial energizing of the system. This shall also include testing and commissioning the manual transfer switch with generator and providing training for staff in the operation and functionality.
61) Contractor shall submit all manufacturers’ warranties.
Approved Brands and Specifics (or Pre-approved Equal)
Item Approved Brand or Pre-Approved Equal
Specific Requirements
Lumber 2 by Material, Non-Pressure Treated For Studs and Top Plate, Pressure Treated for Bottom Wall Plates
Sill Seal Foam Gasket
Everbilt or Equal 3½-inches in Width
Wedge Anchors Redhead or Equal Corrosive Resistant 5/8-inch x 8-inch
Insulation Rockwool Comfortbatt, R-15
Drywall Georgia Pacific or Equal
Gold Bond, 5/8-in, Fire-Shield, Fire Resistant, Type X Drywall Panel
Primer Sherwin Williams Multi-Purpose, Interior/Exterior Latex Primer Sealer
Drywall Paint Sherwin Williams Low-VOC, Latex, Flat
Metal Siding Same as Existing
Metal Siding Paint Sherwin Williams Park Brown
Unistrut Unistrut 1 5/8-inch, 12 Gauge Metal Strut Channel, Slotted Back, Pre-Galvanized Zinc
Manual Transfer Switch
Square D 400-amp, 3-Phase, Exterior, Manual, Double Throw, NEMA type 3R, Primary On-Off-On Secondary, Weatherproof with Exterior Rated Fittings
Weather Head Southwire or Equal Clamp-On, Aluminum
Polyurethane Elastomeric Sealant
Sika Mfr. Model # 107777 1A Medium Bronze 1-Part Polyurethane Non-Sag Elastomeric Sealant, Paintable
Ground Rods 5/8-inch x 8-foot, Copper
Ground Rod Clamps
Southwire or Equal Bronze Material
Bridge Clamp Arlington or Equal Bronze, UV-Rated Plastic Cover, 4-Termination Points
Electrical Panels (A&B)
Square-D Flush Mount, 200-amp with Main Breaker, 3- Phase, 120/240-Volt
Electric Panel (C)
Square-D Surface Mount, Nema 3R, 125-amps with Main Breaker, 3-Phase, 120/240-volt
Breakers Square-D Matching to Panels
Conduit EMT for Interior RMC for Exterior
Wire Southwire or Equal MC Copper Cable
HVAC
Disconnects
DiversiTech Series # DDS Pull Out Handle, Blown Fuse Indicator, NEMA type 3R Fused Disconnect w/ Side Open Door
Whips DiversiTech or Equal Non-Metallic Conduit, NPT Liquid Tight Fittings
Water Heater Disconnect
DiversiTech Series # DDS Pull Out Handle, Blown Fuse Indicator, NEMA type 3R Fused Disconnect w/ Side Open Door
All Duplex Outlets Leviton, Hubbell, Legrand
20-Amp, 120-volt, Tamper Resistant, Grounded, White In Color
Smoke & Carbon Monoxide Detectors
Kidde Model # 30CUAR Style 9th Edition, Smoke & Carbon Monoxide Combo, 120-volt, Photoelectric & Electrochemical Sensor Type, Hardwired, (2) AA Battery Backup
Troffer Light Fixtures
Lithonia Lighting Series 2BLT4 and 2BLT2 2-foot x 4-foot, 2-foot x 2-foot, 120-volt, LED, CCT/LED Color Tunable, Dimmable, Recessed, Curved and Smooth Diffusers with Trim Rings, Wireless nLight Controls
Acoustic Ceiling Tile
Armstrong Ceilings 2-foot x 4-foot, Texture and Finish To Match Existing
Track Lighting Systems
Juno Lighting Trac-Master, T-Series, Black Finish, LED, 30–45 Degree, Adjustable Heads, Narrow Beam, Adjustable CCT/Color, 1200-Lumens
Power Supply Accuity Brands nPS 80, nLight System Power Supply Series, 120-volt
Wall Pod Accuity Brands nPODM DX Series, On/Off and On/Off plus Raise/Lower, White in Color, nLight System
Occupancy Sensor
Accuity Brands nCM xx RJB Family, nCM 10 Lens option, Ceiling Mount, White in Color, nLight System
All Exterior Lights Lithonia Lighting Model # WMCL4
LED, Wall Pack, Lumens 2,433, Switchable CCT- 30K, 40K, and 50K, 120-Volt, Integrated Photocell, Finish Dark Bronze
Mounting Boxes Built-in Electrical Boxes, Finish Dark Bronze
Exhaust Fan/Light Combo
Broan Nu-Tone Model # BEL8 Roomside Series, 80 CFM, 1.5 Sones, Bathroom Exhaust Ventilation Fan with LED, Light Energy Star
Vanity Light Kichler Model # 45973OZ Avery, Wall Mount, 24-inches, 3-Light, Olde Bronze Vintage, Clear Seeded Glass
TV Box Kit Legrand Model # TV3WTVSSW
Hand Dryer Excel Dryer Model # XL-SB-110/120V XLERATOR XL-SB, 110/120-volt, Automatic, High Speed, Brushed Stainless Steel Cover
Wall Guard Alpine or Equal 31.8-inches x 15.8-inches, Stainless Steel, 3M Adhesive Strips
Lift Station Outlet Box
GE Model # U012010GRP Lockable, Double Gang, two (2) Duplex’s, 20 Amp, Galvanized Steel, Dark Green Color, Nema 3R Enclosure
Face Plates White in Color
Ceiling Markers www.emedco.com or Equal
Red, Installed Upon the Acoustic Ceiling Metal Grid
Specific Instructions
Additional Terms and Conditions
1) All aspects of this job shall be left in a finished condition: All finish work, interior and exterior walls and trim, finish painting, caulking and final cleanup are included in this Contract.
2) The Contractor shall be responsible for determining where all utilities are on the job site and care should be taken to protect the utilities from any damage caused by the demolition/construction. This shall include any underground utilities around the job site area.
If damage occurs, it shall be repaired within a twenty-four (24) -hour period from the time damage occurs.
3) The Contractor shall perform work on regular time and shall invoice work time and material not to exceed the quoted price. Any variance in quote shall be addressed only with a representative of the Facilities Management Regional Office before any additional work is undertaken or materials ordered.
4) Work shall be scheduled to avoid any interference with normal operation of the Park as much as possible. During the construction period, coordinate construction schedules and operations with the Park Manager. Work shall be conducted during the normal business hours of Monday through Friday, 8:00 a.m. to 4:30 p.m., unless an alternate schedule is approved by Facilities Management.
5) The successful Contractor shall schedule and attend a pre-construction conference where a pre-construction form shall be signed by Facilities Management, Contractor and Park Manager or Park representative before work can begin. The Contractor shall also schedule and attend a final inspection where a final inspection form shall be signed by Facilities
Management, Contractor and Park Manager or Park representative before final invoice shall be paid.
6) The Contractor shall protect areas adjacent to his work and shall be required to repair any damage they may cause. The Contractor shall protect work of other trades. The Contractor shall correct any painting related damage by cleaning, repairing, or replacing, and refinishing as directed by Facilities Management. The Contractor shall leave residences and other buildings in a habitable manner after hours by securing unfinished openings.
7) Workmanship shall be warrantied for not less than one (1) year from date of final inspection.
Materials shall be warrantied as per manufacturer’s warranty.
8) Unless otherwise indicated, all materials, equipment, and supplies shall be new and in good condition, UL listed when applicable, and all work accomplished in a manner acceptable to Facilities Management.
9) Clean up of the project site shall be the responsibility of the Contractor. The Contractor shall assure that job site is clean of nails, debris, etc., at end of each day to ensure safety. The Contractor shall clean up and haul away all scrap when work is completed to an approved location off state property.
10) At all times, the Contractor shall have a copy of project specifications, permits, and Certificate of Insurance on-site.
11) The Contractors and all subcontractors are not authorized to day laborers or temporary labor on this project without the express written permission of Facilities Management.
12) Note: Before the Contract resulting from this Invitation to Bid is signed, the apparent successful proposer shall be registered with the Department of Revenue for the collection of
Tennessee sales and use tax. The State shall not approve a Contract unless the proposer provides proof of such registration. The foregoing is a mandatory requirement of an award of a Contract pursuant to this solicitation.
13) Invoice shall be submitted for payment not before project completion and final project acceptance but also no later than ten (10) days after project completion and acceptance. A copy of the invoice shall be submitted to: Becky Johns, Middle TN Regional Office - Facilities Management 2000 Jackson Hill Rd. Burns, TN 37029, (615) 981-6285, becky.johns@tn.gov
14) Facilities Management Regional Contacts for this project are:
Regional Manager: Mark Harris, (615) 218-7697, mark.harris@tn.gov
Project Manager: Adam Kilgore, (615) 238-1230, adam.kilgore@tn.gov