TRD_20230717.pdf

PDF 1 MB Posted

Attached to
Liebert Dual-Cool HVAC System Federal contract opportunity
Solicitation number
FA282323Q0048
Issued by
Department of the Air Force Materiel Command Test Center

About this file

This technical requirements document specifies requirements for a dual-cool HVAC system with remote condenser to replace an existing chilled-water system at Eglin Air Force Base. The new system must have a maximum dimension of 9' L x 3' W x 6'9" H for the HVAC unit and secure a remote condenser to a concrete pad no larger than 10' L x 5' W. It must withstand local environmental conditions, have smoke and moisture sensors with alarms, and use digital scroll compressors and variable speed fans. The system must provide 070 kW of cooling capacity at specified conditions. Installers must be EPA Section 608 certified and the equipment must meet ASHRAE standards. The interface and documentation must allow for easy configuration, monitoring, installation and troubleshooting. Onsite training will be provided upon acceptance.

The related federal contract opportunity is a solicitation from the Department of the Air Force Materiel Command Test Center to provide a Liebert dual-cool HVAC system meeting the above technical requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Liebert Dual-Cool HVAC System, newest first.
File Type Posted
Solicitation Amendment FA282323Q00480001 SF 30.pdf PDF
Questions and Answers 11 Aug 23.pdf PDF
SV Base Access Memo.docx DOCX document
Addendum to FAR 52.212-2.pdf PDF
Service Contract Act WD 2015-4531.pdf PDF
SOW_20230717.pdf PDF
Addendum to FAR 52 212-1 and FAR 52 212-3 (NOV 2021).pdf PDF
Solicitation - FA282323Q0048.pdf PDF
Attachment Cover Sheet.pdf PDF
Brand Name Justification4_Redacted.pdf PDF
Davis-Bacon Act WD FL20230217.pdf PDF
FA282323Q0048 - Site Visit Letter.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Requirements Document (TRD) Dual-cool (Chilled-Water and Refrigerant Coil) HVAC System with Remote Condenser.

July 17, 2023

Purpose:

The purpose is to remove and replace an existing chilled-water HVAC system with a new dual-cool (chilled-water and refrigerant coil) HVAC system with remote condenser. This is required to provide redundancy and better protect a 360-battery 1.2kW uninterruptible power supply and power distribution unit from overheating in the event of power surges or outages.

Specifications:

Maximum dimension of HVAC unit is 9’ L x 3’ W x 6’9” H.

Remote condenser must secure to concrete pad no larger than 10’ L x 5’ W.

Construction and Environmental Considerations: External units must be able to withstand local environmental elements i.e., wind, salt air, operating temperature range, humidity tolerance, and other factors suitable for Eglin AFB.

HVAC unit must have smoke and moisture sensors with unit alarm.

HVAC unit must have digital scroll compressors.

Condenser unit must have variable speed fans.

Power Specifications: Input Supply Voltage: 460 Volt, 3 Phase, 60 H.

PerformanceCapacity: Nominal 070 kW (20 Ton) Air Cooled Upflow System with a net sensible cooling capacity of 72°F, 50% R.

Certification and Compliance:

HVAC technicians must be certified under the Environmental Protection Agency's Section 608 of the Clean Air Act.

Equipment must comply with American Society of Heating, Refrigerating and Air-Conditioning Engineers certification standards.

User Interface: Equipment must have a human machine interface for easy configuration and monitoring.

Documentation: Comprehensive documentation and user guides for installation, configuration, and troubleshooting as built information.

Technical Support: Must respond within 24 hours of notification for technical support if system fails within warranty period.

Training: Provide training for 2 personnel on day of acceptance. Training will consist of use, troubleshooting, modes and general maintenance requirements.

07/17/2023