Questions and Answers 11 Aug 23.pdf

PDF 159 KB Posted

Attached to
Liebert Dual-Cool HVAC System Federal contract opportunity
Solicitation number
FA282323Q0048
Issued by
Department of the Air Force Materiel Command Test Center

About this file

This document contains questions and answers regarding solicitation FA282323Q0048 from the Department of the Air Force for a Liebert dual-cool HVAC system. The solicitation seeks the purchase and installation of a commercial HVAC unit to replace an existing unit. The contractor will be responsible for all electrical work, controls setup, and coordinating with the facility manager. The response date was extended to August 25, 2023 at 11:00am CDT. Davis-Bacon wage determinations apply. This is considered a commercial purchase and standard commercial terms will govern any contractual issues or damages. Bidders are advised to wait one week after the closing date before following up about bid results. The point of contact is TSgt Paul McLean at paul.mclean@us.af.mil or DSN 882-3194 for any additional questions.

View the file

Other files for this federal contract opportunity

Other files attached to Liebert Dual-Cool HVAC System, newest first.
File Type Posted
Solicitation Amendment FA282323Q00480001 SF 30.pdf PDF
Addendum to FAR 52.212-2.pdf PDF
Service Contract Act WD 2015-4531.pdf PDF
SOW_20230717.pdf PDF
SV Base Access Memo.docx DOCX document
Attachment Cover Sheet.pdf PDF
Brand Name Justification4_Redacted.pdf PDF
Davis-Bacon Act WD FL20230217.pdf PDF
FA282323Q0048 - Site Visit Letter.pdf PDF
Addendum to FAR 52 212-1 and FAR 52 212-3 (NOV 2021).pdf PDF
Solicitation - FA282323Q0048.pdf PDF
TRD_20230717.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

AIR FORCE TEST CENTER (AFTC)

EGLIN AIR FORCE BASE, FLORIDA

11 August 2023

MEMORANDUM FOR RECORD

SUBJECT: Solicitation FA282323Q0048 Questions and Answers

1. For this project there will need to be significant electrical upgrades. Who is responsible for electrical upgrades for new equipment?

a. The contractor shall provide all labor and materials for electrical requirements.

2. The equipment will have to be down for a certain period of time will we need to provide temporary cooling?

a. No, the government will coordinate temporary cooling as required. Start date will need to provide for planning purposes.

3. Who is responsible for controls and programming if necessary?

a. The Contractor shall be responsible for the controls set up and liaison with the facility manager to schedule the fire alarm system disconnect and reconnect.

4. Does the new unit require to be on UPS?

a. No, the CRU is not on the UPS but is connected to the backup generator system.

5. Can the response date be extended to August 25th?

a. The government has determined an extension of this solicitation to 25 August

2023 at 11:00am CDT is acceptable.

6. Is there a completion date specified and are there any liquidated damages if project is not completed by specified date?

a. Requested completion date is identified in Delivery Schedule of the SF1449 solicitation document. This is a commercial purchase and commercial contract terms and conditions will apply in the seeking of damages in the event of delivery dates being missed.

DEPARTMENT OF THE AIR FORCE

AIR FORCE TEST CENTER (AFTC)

EGLIN AIR FORCE BASE, FLORIDA

7. Requesting confirm the August 14 at 11:00am EDT close of solicitation.

a. Close date and time of solicitation will be extended to 25 August 2023 at 11:00am

CDT as reference in Question 5.

8. Requesting confirmation of construction cost estimate or a construction cost range for the project.

a. This requirement is a commercial commodity purchase including installation.

Davis-Bacon Act wage determination and applicable construction clauses have and will be included in the solicitation and award to cover work to be completed.

However as this is not a construction requirement, a ROM or cost estimate will not be provided.

9. Requesting confirmation of planholders list/bidders list or non-mandatory pre-bid attendance list.

a. As stated, this requirement is for a commercial equipment purchase and installation. There is no planholders list/bidders list or non-mandatory pre-bid attendance list.

10. Requesting confirmation of any addenda that have been released.

a. There have been no prior amendments to the solicitation.

11. Requesting confirmation of best time to follow up for bid results.

a. Please allow at least one-week post-solicitation close before following up to provide time for the government to evaluate offers.

12. For any additional questions, contact TSgt Paul McLean at email paul.mclean@us.af.mil or DSN 882-3194.

PAUL R. MCLEAN, TSGT, USAF

Contract Specialist

2023-08-11T13:26:29-0500
MCLEAN.PAUL.RICHARD.1470199438