ATTACHMENT A

Amendment A001 To Solicitation No. SWHARC-15-R-0010 Fusion and Operations Center (CEFOP) Construction - Cucuta, Colombia The Solicitation is hereby amended as follows:

I. DUE DATE FOR PROPOSALS:

The due date for delivery of proposals is revised to Tuesday, July 21th, 2015. Consequently, the proposal submission instructions are revised as follows:

1. Due Date: The due date for delivery of the proposals is extended to Tuesday, July 21th, 2015. In order to be accepted, proposals must be received electronically through the FedBizOpps website (www.fedbizopps.gov) no later than 4:00 P.M. local (Fort Lauderdale) time. Any proposal received after the 4:00 P.M. local (Fort Lauderdale) time deadline will not be accepted.

II. PROJECT REQUIEREMENTS:

Solicitation Amendment A001, dated July 14, 2015, included the following revisions to the project requirements:

F.2

FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract immediately upon receiving the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than one-hundred and sixty five (165) calendar days thereafter. The 165 day performance period includes final cleanup of the premises and completion of punch list items. The 165 day performance period does not include the time it will take for the Contractor to submit the required bonds and insurance documentation. A Notice to Proceed with construction will not be issued until such time as the Contracting Officer has received the required bonds and insurance documentation.

The attached SF-1442 and the following documents and drawing attached, hereby amended into the above solicitation, include the above revisions:

· Attachment #1-Specifications is replaced by A001 Attachment#1 Technical Specifications Jul 14.

· Attachment #2- Bidding Chart is replaced by A001 Attachment#2 Bidding Chart Jul 14.

· Attachment #3- Drawings is replaced by A001 Attachment#2 Drawings Jul 14.

· Attachment #7- Submittal Register is replaced by A001 Attachment#7 Submittal Register Jul 14.

· Contractor Questions is replaced by A001 Contractor Questions Jul 14.

· Attached Electrical Drawings FS-102.

Attachment A to Amendment A001 – Solicitation No. SWHARC-15-R-0010 – Fusion and Operations Center (CEFOP) Construction - Cucuta, Colombia