Specifications_20260512.pdf
PDF 4 MB Posted
- Solicitation number
- 0000039705
- Issued by
- San Luis Obispo County, San Luis Obispo City, California
About this file
Summary
This is a specifications document and invitation for bid (IFB) issued by the California Military Department (CMD) for the Main Garrison Wastewater Treatment Plant (WWTP) Phase 2 Upgrades located at Camp Roberts, California. The project scope includes wastewater treatment plant upgrades encompassing clearing and site preparation, removal of accumulated sludge, demolition and relocation of existing WWTP components, rehabilitation of existing piping systems, installation of a new membrane bioreactor (MBR) system, sludge handling systems, electrical service upgrades, permeate retention pond construction with HDPE liner installation, and startup testing and commissioning. The prime contractor must possess either a B-General Building Contractor or A-General Engineering license along with a C-22 Asbestos Abatement license or subcontract accordingly. A mandatory pre-bid job walk is scheduled for July 21, 2026, at 1:00 PM at Camp Roberts, Highway 101, San Miguel, California, with prospective bidders required to arrive 15 minutes early and remain for the entire duration. Questions must be submitted to Robert Hawkins at Robert.Hawkins@cmd.ca.gov no later than 5:00 PM on August 11, 2026. Bid submissions are due September 1, 2026, at 2:45 PM via email to PWC@cmd.ca.gov with bid opening scheduled for 3:00 PM the same day.
The specifications document establishes comprehensive contract requirements including detailed project scheduling using Critical Path Method (CPM) with Primavera P6 software, mandatory preconstruction submittals, quality control procedures, and administrative requirements. The facility will remain in continuous operation during construction, and the contractor must coordinate with government entities regarding utility cutovers, environmental procedures, and safety compliance under USACE EM 385-1-1 standards. All contractor and subcontractor personnel require 3Rs Explosives Safety Education Program training completion within 30 calendar days of award. The project involves multiple technical divisions covering concrete, structural steel, plumbing, electrical systems, earthwork, utilities, and specialized wastewater equipment. Mobilization to the jobsite is required within 60 calendar days of contract award, with a project superintendent possessing minimum 10 years' construction experience and at least 5 years as superintendent on similar-sized projects mandatory throughout performance. The contract includes provisions for Red Zone meetings beginning at approximately 75 percent project completion to ensure timely facility turnover and closeout procedures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Report_Waste_Discharge.pdf | ||
| PROCORE_Spec.pdf | ||
| Design_Report_20260416.pdf | ||
| Drawings_20160331.pdf | ||
| QC_Spec_Rev_01.pdf | ||
| IFB_No_130636.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of California Military Department (CMD) Main Garrison Wastewater Treatment Plant (WWTP) Phase 2 Upgrades Camp Roberts California
SPECIFICATIONS
State of California Military Department (CMD)
Main Garrison Wastewater Treatment Plant (WWTP) Phase 2 Upgrades
Camp Roberts WWTP Camp Roberts, California
May 12, 2026
Volume 1 of 1
Divisions 00 through 46
TABLE OF CONTENTS - Page 1
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 List of Drawings
DIVISION 01 – GENERAL REQUIREMENTS
01 00 15 Certifications Page 01 11 00 Summary of Work 01 14 00 Work Restrictions 01 30 00 Administrative Requirements 01 32 01.00 10 Project Schedule 01 33 00 Submittal Procedures 01 35 26 Governmental Safety Requirements 01 35 35 43 Environmental Procedures 01 41 00 Regulatory Requirements 01 42 00 Sources for Reference Publications 01 45 00.00 20 Quality Control 01 50 00 Temporary Construction Facilities and Controls 01 57 19 Temporary Environmental Controls 01 65 00 Product Delivery Requirements 01 74 19 Construction Waste Management and Disposal 01 78 00 Closeout Submittals 01 78 23 Operation and Maintenance Data 01 78 24.00 20 Facility Electronic Operation and Maintenance Support
Information (eOMSI)
DIVISION 2 – EXISTING CONDITIONS
02 41 00 Demolition and Deconstruction 02 82 00 Asbestos Remediation 02 83 00 Lead Remediation
DIVISION 3 – CONCRETE
03 30 00 Cast-In-Place Concrete
DIVISION 5 – METALS
05 12 00 Structural Steel
DIVISION 22 – PLUMBING
22 00 00 Plumbing, General Purpose 22 13 29 Sanitary Sewerage Pumps
TABLE OF CONTENTS - Page 2
DIVISION 26 – ELECTRICAL
26 05 19.00 10 Insulated Wire and Cable 26 05 48 Seismic Protection for Electrical Equipment 26 05 73 Power System Studies 26 08 00 Apparatus Inspection and Testing 26 12 21 Single-Phase Pad-Mounted Transformers 26 20 00 Interior Distribution System 26 28 00.00 10 Motor Control Centers, Switchboards and Panelboards 26 56 00 Exterior Lighting
DIVISION 31 – EARTHWORK
31 00 00 Earthwork 31 11 00 Clearing and Grubbing
DIVISION 32 – EXTERIOR IMPROVEMENTS
31 10 00 Bituminous Concrete Pavement
DIVISION 33 – UTILITIES
33 30 00 Sanitary Sewerage 33 47 13 Pond and Reservoir Liners 33 71 02 Underground Electrical Distribution
DIVISION 46 – WATER AND WASTEWATER EQUIPMENT
46 21 05 Shaftless Spiral Conveyor/Compactor – Headworks® TranspactorTM Type TP
46 21 53 Perforated Plate Fine Screen System 46 53 49 Packaged MBR Treatment Systems 46 75 05 Package Sludge Holding Tank and Dewatering System 46 76 53 Pre-Packaged Screw Press Solids Management System
END OF SECTION
DOCUMENT 00 01 15 - Page 1
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/24
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING
NO.
REVISION
NO.
TITLE
G01 0 INDEX OF DRAWINGS, SITE VICINITY MAP, AND
SITE LOCATION MAP
G02 0 GENERAL NOTES, ABBREVIATIONS, AND LEGEND
G03 0 WASTEWATER TREATMENT PLANT SITE PLAN
G04 0 FLOW PROFILE - LOW FLOW AND PERMEATE
RECIRCULATION
G05 0 FLOW PROFILE - EQUALIZATION TANK
P01 0 WWTP SITE PROCESS FLOW DIAGRAM
P02 0 MBR PROCESS FLOW DIAGRAM
C01 0 EXISTING SITE AND DEMOLITION PLAN (1 OF 2)
C02 0 EXISTING SITE AND DEMOLITION PLAN (2 OF 2)
C03 0 SITE PLAN
C04 0 MEMBRANE BIOREACTOR (MBR) PLAN AND PROFILE
C05 0 DRYPAC PLAN AND PROFILE
C06 0 PERMEATE RETENTION POND PLAN
C07 0 DETAILS AND SECTIONS (1 OF 4)
C08 0 DETAILS AND SECTIONS (2 OF 4)
C09 0 DETAILS AND SECTIONS (3 OF 4)
C10 0 DETAILS AND SECTIONS (4 OF 4)
C11 0 HARDSCAPE PLAN
DOCUMENT 00 01 15 - Page 2
DRAWING
NO.
REVISION
NO.
TITLE
S01 0 STRUCTURAL TITLE SHEET
S02 0 STRUCTURAL SPECIFICATIONS
S03 0 STRUCTURAL SPECIFICATIONS
S04 0 MBR FOUNDATION PLAN
S05 0 MBR MAT SLAB REBAR PLAN
S06 0 MBR CANOPY FRAMING PLAN
S07 0 SLUDGE TANK FOUNDATION PLAN
S08 0 SLUDGE TANK MAT SLAB REBAR PLAN
S09 0 SLUDGE TANK CANOPY FRAMING PLAN
S10 0 STRUCTURAL DETAILS
S11 0 STRUCTURAL DETAILS
S12 0 STRUCTURAL DETAILS
E01 0 ELECTRICAL SYMBOLS, NOTES, AND LEGEND
E02 0 SINGLE LINE DIAGRAM
E03 0 ELECTRICAL SCHEDULES
E04 0 OVERALL ELECTRICAL SITE PLAN
E05 0 SCHEMATIC & CONNECTION DIAGRAMS – SHEET 1
E06 0 SCHEMATIC & CONNECTION DIAGRAMS – SHEET 2
E07 0 COMMUNICATION DIAGRAM
E08 0 CONDUIT BLOCK DIAGRAM
E09 0 ELECTRICAL DETAILS
I01 0 P&ID SYMBOLS AND LEGEND
I02 0 P&ID - SHEET 1
I03 0 P&ID - SHEET 2
I04 0 P&ID - SHEET 3
-- End of Section --
SECTION 01 00 15 - Page 1
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 15
CERTIFICATIONS PAGE
PROJECT TITLE: Main Garrison Wastewater Treatment Plant (WWTP)
AGENCY: California Military Department 9800 Goethe Rd.
Sacramento, CA 95827
LOCATION: Main Garrison Wastewater Treatment Plant, Camp Roberts, California
CIVIL ENGINEER STRUCTURAL
ENGINEER
ELECTRICAL ENGINEER
SECTION 01 11 00 - Page 1
SECTION 01 11 00
SUMMARY OF WORK
02/24
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Salvage Plan; G,
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes wastewater treatment plant upgrades, associated site work and incidental related work.
a. Clearing, grubbing, site preparation and installation of site controls.
b. Remove accumulated sludge from the existing sludge drying beds and existing sludge digesters (storage tanks) and dispose of as directed by the COR.
c. Abandon, relocate, and/or demolish existing wastewater treatment plant (WWTP) components to allow for installation of membrane bioreactor system(s), sludge handling system, and associated components.
d. Rehabilitate existing 24-inch WW bypass (slip line or other approved equal).
e. Abandon and remove existing 24-inch dia. RCP from diversion chamber to secondary clarifier.
SECTION 01 11 00 - Page 2
f. Repurpose existing secondary clarifier as MBR equalization tank with upstream low-flow equalization tank by-pass pump station.
g. Install new 24-inch dia. HDPE gravity line from diversion chamber to low-flow pump station and from low-flow pump station to equalization tank.
h. Install new equalization tank pump station.
i. Trench excavation and installation of new pipeline(s).
j. Surface restoration in areas of trenching (match existing conditions where appropriate).
k. Install new MBR system, sludge handling system, and associated piping and concrete pads.
l. Install new electrical service and subsurface electrical line(s) providing power to the new MBR system and associated components.
m. Grade permeate retention pond and install HDPE liner system. Excess cut shall be utilized as backfill, as appropriate, or stockpiled at the Camp Roberts landfill borrow area, or as directed by the cor.
n. Install new permeate retention pond pump station.
o. Connect MBR control panel(s) to main WWTP control panel.
p. Install wiring associated with MBR and WWTP control panels.
q. Upgrade the electrical utility service to accommodate new system load(s).
r. Perform startup testing and commissioning requirements as specified in the CONTRACT DOCUMENTS.
1.3 Location
The work is located at the Camp Roberts Main Garrison Wastewater Treatment Plant, to the east of the 101-Freeway, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.4 OCCUPANCY OF PREMISES
The facility will remain in continuous operation during the performance of work under this Contract.
SECTION 01 11 00 - Page 3
1.5 EXISTING WORK
Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.6 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 2 work days prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered.
Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.7 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 5 miles of the construction site.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in
SECTION 01 11 00 - Page 4 the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 14 00 - Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 5: 05/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, including delivery vehicles, are clearly identified with their company name.
SECTION 01 14 00 - Page 2
Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours will consist of an 8 1/2 hour period established by the Contracting Officer, between Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 3 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in accordance with requirements of EM 385-1-1.
1.3.4 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
SECTION 01 14 00 - Page 3
1.4 ARMY AND ARMY NATIONAL GUARD REQUIREMENTS AND RESTRICTIONS
1.4.1 3Rs Explosive Safety Education Training Certificate
All Contractor and subcontractor employees requiring access to Army or Army National Guard installations, facilities, and areas for the performance of a contract or subcontract must complete the 3Rs (Recognize, Retreat, Report) Explosives Safety Education Program training. Complete the training within 30 calendar days after the date of receipt of a written notice of award. The Contractor is responsible for ensuring that all subcontractor employees complete the training before access to the installation is required for performance of the subcontract. The Contractor is also responsible for ensuring that all contractor and subcontractor employees renew the training annually for the duration of the performance period of the contract or subcontract. Submit certificates of completion for each Contractor and subcontractor employee subject to this requirement to the Contracting Officer’s Representative (COR) or to the Contracting Officer, if a COR is not assigned, within 5 calendar days after completion of training. 3Rs Explosives Safety Education Program training is available at the following website:
https://www.denix.osd.mil/uxo/3rs-training/.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
https://www.denix.osd.mil/uxo/3rs-training/
SECTION 01 30 00 - Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in
SECTION 01 30 00 - Page 2
JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice one set of digital photographs in the agency construction management system of record, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch with the submission in the agency construction management system of record as a digital file. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years of experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 20 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the jobsite at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
SECTION 01 30 00 - Page 3
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time or excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION CONFERENCE
Prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.7.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled Red Zone Meetings beginning at approximately 75 percent of project completion.
Include the following in the facility Turnover effort:
SECTION 01 30 00 - Page 4
1.8.1 Red Zone Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.
b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity.
Submit the modified Red Zone Checklist to the Contracting Officer.
The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
1.8.2 Meetings
a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer. At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.
e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
1.9 MOBILIZATION
Mobilize to the jobsite within 60 calendar days after contract award.
Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.
PART 2 PRODUCTS
SECTION 01 30 00 - Page 5
PART 3 EXECUTION
SECTION 01 32 01.00 10 - Page 1
SECTION 01 32 01.00 10
PROJECT SCHEDULE
08/23, CHG 1: 08/24
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
AACE 84R-13 (2015) Planning and Accounting for Adverse Weather
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 67-17 (2017) Schedule Delay Analysis
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (2017) Administration -- Project Schedules
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G, Preliminary Project Schedule; G, Initial Project Schedule; G, Periodic Schedule Update; G, SECTION 01 32 01.00 10 - Page 2
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules for projects of similar size and complexity to this contract, using Primavera P6. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government uses Primavera P6. Ensure exported schedule files are compatible with the version of P6 used by the Government.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required SDEF file must be created and supported by the software manufacturer.
Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system. Verify at the SEKO meeting which version of P6 is in use by the Government. Export the schedule in a version of P6 no newer than that used by the Government.
Other Than Primavera
If the Contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
SECTION 01 32 01.00 10 - Page 3
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute to developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward-planning tool as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.1.1 Scheduling Expectations Kickoff Meeting(SEKO)
In conjunction with the post award conference or pre-construction conference the Government and the Contractor will hold a separate and distinct Scheduling Expectations Kickoff Meeting(SEKO). The intent of this meeting is for the Government to review with the contractor the requirements of the scheduling specification, communicate the Government’s expectations regarding schedule development and management, and answer any questions the Contractor may have regarding the schedule requirements.
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN. Match the progress payment "Pay Period Thru" date in RMS to the schedule data date.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Activities with negative cost loading are not allowed. Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Cost Loading of Submittals
No costs are to be assigned to activities for the preparation, review, or approval of submittals, except as described under paragraph COST LOADING OF CLOSEOUT ACTIVITIES, paragraph AS-BUILT DRAWINGS, and paragraph O&M MANUALS.
SECTION 01 32 01.00 10 - Page 4
3.2.3 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial, or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Non-procurement activities Original Durations (OD) are not to exceed 20 workdays or 30 calendar days.
3.3.3 Procurement Activities
Include in the schedule activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Activities
Include the following activities in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission of mechanical/electrical/information systems layout drawings.
SECTION 01 32 01.00 10 - Page 5
c. Submission and approval of O & M manuals.
d. Submission and approval of as-built drawings.
e. Submission and approval of DD1354 data and installed equipment lists.
f. Submission and approval of testing and air balance (TAB).
g. Submission of TAB specialist design review report.
h. Submission and approval of fire protection specialist.
i. Submission and approval of Building Commissioning Plan, Controls testing plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
These activities may include but are not limited to: air and water balancing, building commissioning -functional performance testing, controls testing, and performance verification testing. Include other systems testing, if required. Include additional commissioning requirements noted elsewhere in the Contract as required in the schedule and discuss during the SEKO meeting, noted in paragraph SCHEDULING EXPECTATIONS KICKOFF MEETING (SEKO).
j. Contractor's pre-final inspection.
k. Correction of punch list from Contractor's pre-final inspection.
l. Government's pre-final inspection.
m. Correction of punch list from Government's pre-final inspection.
n. Final inspection.
3.3.5 Government Activities
Show in schedule, Government and other agency activities that could impact progress. These activities include, but are not limited to, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
SECTION 01 32 01.00 10 - Page 6
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements
Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
SECTION 01 32 01.00 10 - Page 7
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings. Activities cannot have more than one Work Area Code.
Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Number (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
c. Code proposed fast-track design and construction phases proposed to allow filtering and organizing the schedule by fast-track design and construction packages.
SECTION 01 32 01.00 10 - Page 8
d. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00.00 20 QUALITY CONTROL. An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or affect network logic are prohibited. No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case-by-case basis.
Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If
SECTION 01 32 01.00 10 - Page 9 the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.
Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Adverse Weather
Ensure anticipated adverse weather is accounted for in the Project Schedule.
AACE 84R-13 provides methodologies for techniques in planning for adverse weather. The preferred methodology is the use of a weather calendar. If a method other than a weather calendar is proposed, discuss the reason during the SEKO meeting.
3.3.9 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
If a weather calendar is used its implementation and execution is to be in accordance with AACE 84R-13
3.3.10 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" is to have no predecessor logic, and the last activity -"End Project" is to have no successor logic. Except as noted above, each activity must have at least a start-to-start or finish-to-start relationship with its predecessor and a finish-to-finish or finish-to-start relationship with its successor.
SECTION 01 32 01.00 10 - Page 10
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.11 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.12 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule.
Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.13 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.14 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.15 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb or create float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
SECTION 01 32 01.00 10 - Page 11
3.3.16 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not allowed.
3.3.17 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management. Budgeted cost of activity is to be reduced by the amount needed to correct deficiency. The activity referenced in paragraph COST LOADING of CLOSEOUT ACTIVITIES must have its budgeted cost increased by this amount.
3.3.18 Remaining Duration
Update the remaining duration for each activity based on the number of estimated workdays it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete. The remaining durations for unstarted activities are not to be less than their original durations.
3.3.19 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, whichever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.
SECTION 01 32 01.00 10 - Page 12
O & M Manuals
Cost load the "Submission and approval of O & M manuals" activity not less than $20,000. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.
3.3.20 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and hours) and the Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data reports and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4.1 Preliminary Project Schedule Submission
Within 15 calendar days after the NTP is acknowledged, submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and
SECTION 01 32 01.00 10 - Page 13
Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Code activities that are summary in nature, after the first 90 calendar days, with the following activity codes: Bid Item (CLIN) code (BIDI), Responsibility Code (RESP), and Feature of Work code (FOW)..
3.4.2 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.
3.4.3 Periodic Schedule Updates
Update the Project Schedule on a regular basis, monthly at a minimum.
Provide a draft Periodic Schedule Update for review at the schedule update meetings as prescribed in the paragraph PERIODIC SCHEDULE UPDATE MEETINGS.
These updates will enable the Government to assess Contractor's progress.
a. Update information including Actual Start Dates (AS), Actual Finish Dates (AF), Remaining Durations (RD), and Percent Complete. Updated information is subject to the approval of the Government at the meeting.
b. AS and AF dates must match the date(s) reported on the Contractor's Quality Control Report for an activity start or finish.
3.5 SUBMISSION REQUIREMENTS
Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:
3.5.1 Electronic Scheduling Data
Provide electronic scheduling data containing the current project schedule and all previously submitted schedules in the format of the scheduling software (e.g. .xer). Also include the Narrative Report and all required Schedule Reports. The electronic file is to identify the type of schedule (Preliminary, Initial, Update), full contract number, Data Date and schedule file name. Each schedule must have a unique file name and use project
SECTION 01 32 01.00 10 - Page 14 specific settings. The file naming convention is to be determined at SEKO meeting.
3.5.2 Narrative Report
Provide a Narrative Report with each schedule submission. The Schedule Narrative Report is a "stand alone" report in PDF or Word format. Title the report "Schedule Narrative Report". Show the Report date, schedule name, and contract number on the first page. Indicate who is responsible for the schedule update and narrative report. Provide a brief description of the Project Scope. The Narrative Report is expected to communicate to the Government the thorough analysis of the schedule output and the plans to compensate for problems, either current or potential, which are revealed through that analysis. Include the following information at a minimum in the Narrative Report:
a. Identify and discuss the work scheduled to start in the next update period.
b. Describe activities along the critical path in addition to activities on the next float path after the critical path.
c. Describe current and anticipated problem areas, delaying factors and their impact, and an explanation of corrective actions taken or required to be taken. Identify the party responsible for delay, if applicable.
d. Identify and explain why activities, based on their calculated late dates, should have either started or finished during the update period but did not.
e. Identify…