This is a Quality Control specification document issued by the State of California Military Department for minor construction projects, establishing comprehensive quality control requirements and procedures that contractors must follow. The specification mandates that contractors establish and maintain a Quality Control (QC) program consisting of a dedicated QC Manager, a detailed QC plan, coordination meetings, and three phases of control (preparatory, initial, and follow-up) for each definable feature of work. The QC Manager must possess a minimum of five years of combined experience as a superintendent, inspector, QC manager, project manager, or construction manager on similar construction contracts and must complete Construction Quality Management training. Contractors must submit a QC plan within 15 calendar days of receiving the Notice of Award, and this plan requires government approval before construction commences. The specification establishes mandatory submission deadlines for quality control reports, testing plans, and documentation, with original and one copy of the Contractor Quality Control (CQC) Report due by 10:00 AM the next working day after work is performed. The QC Manager must attend weekly meetings with the superintendent and foreman to review schedules, submittals, and quality issues, and must conduct punch-out inspections, pre-final inspections, and coordinate final acceptance inspections with government representatives.
Testing must be performed by accredited laboratories with appropriate certifications from recognized accreditation authorities including NVLAP, AASHTO, IAS, or the U.S. Army Corps of Engineers Materials Testing Center, with test results clearly marked as "CONFORMS" or "DOES NOT CONFORM" to specifications. The QC Manager must maintain comprehensive documentation including preparatory and initial phase checklists, testing plans and logs, rework items lists, and as-built drawings in three-ring binders organized by specification section and readily available to the government's Quality Assurance Team. All work and testing are prohibited unless the QC Manager is present on site, and the Contracting Officer reserves the right to require removal of personnel and modifications to the QC plan as necessary. The specification applies to both on-site and off-site work and requires notification to the Contracting Officer at least two work days in advance of preparatory phases, two work days in advance of initial phases, and two weeks in advance for off-site work phases. Any proposed changes to the QC organization or personnel require written notification at least seven calendar days prior to implementation and are subject to Contracting Officer approval.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Report_Waste_Discharge.pdf | ||
| PROCORE_Spec.pdf | ||
| Design_Report_20260416.pdf | ||
| Drawings_20160331.pdf | ||
| Specifications_20260512.pdf | ||
| IFB_No_130636.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of California Military Department
SECTION 01 45 00 Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 00
CMD Amended September 2025
QUALITY CONTROL FOR MINOR CONSTRUCTION
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 INFORMATION FOR THE CONTRACTING OFFICER
1.4 QC PROGRAM REQUIREMENTS
1.4.1 Preliminary Work Authorized Prior to Acceptance
1.4.2 Acceptance
1.4.3 Notification of Changes
1.5 QC ORGANIZATION
1.5.1 QC Manager
1.5.1.1 Duties
1.5.1.2 Qualifications
1.5.1.3 Construction Quality Management Training
1.5.2 Alternate QC Manager Duties and Qualifications
1.6 QC PLAN
1.6.1 Requirements
1.7 COORDINATION AND MUTUAL UNDERSTANDING MEETING
1.8 QC MEETINGS
1.9 THREE PHASES OF CONTROL
1.9.1 Preparatory Phase
1.9.2 Initial Phase
1.9.3 Follow-Up Phase
1.9.4 Additional Preparatory and Initial Phases
1.9.5 Notification of Three Phases of Control for Off-Site Work
1.10 SUBMITTAL REVIEW AND APPROVAL
1.11 TESTING
1.11.1 Accreditation Requirements
1.11.2 Laboratory Accreditation Authorities
1.11.3 Capability Check
1.11.4 Test Results
1.12 QC CERTIFICATIONS
1.12.1 Contractor Quality Control Report Certification
1.12.2 Invoice Certification
SECTION 01 45 00 Page 2
1.12.3 Completion Certification
1.13 COMPLETION INSPECTIONS
1.13.1 Punch-Out Inspection
1.13.2 Pre-Final Inspection
1.13.3 Final Acceptance Inspection
1.14 DOCUMENTATION
1.14.1 Quality Control Validation
1.14.2 As-Built Drawings
1.15 NOTIFICATION ON NON-COMPLIANCE
PART 2 PRODUCTS
PART 3 EXECUTION
PROCEDURES FOR INSPECTION
-- End of Section Table of Contents --
SECTION 01 45 00 Page 3
SECTION 01 45 00
QUALITY CONTROL FOR MINOR CONSTRUCTION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health
Requirements Manual
ASTM D3740 (2012a) Minimum Requirements for Agencies
Engaged in the Testing and/or Inspection of Soil and Rock as Using Design and Construction
ASTM E329 (2018) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
SECTION 01 45 00 Page 4
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
QC Plan; G-BO (Governments Building Official)
1.3 INFORMATION FOR THE CONTRACTING OFFICER
Prior to commencing work on construction, the Contractor can obtain a single copy set of the current report forms from the Contracting Officer.
The report forms will consist of the Contractor Production Report, Contractor Production Report (Continuation Sheet), Contractor Quality Control (CQC) Report, CQC Report (Continuation Sheet), Preparatory Phase Checklist, Initial Phase Checklist, Rework Items List, and Testing Plan and Log.
Deliver the following to the Contracting Officer:
a. CQC Report: Original and one copy, by 10:00 AM the next working day after each day that work is performed;
b. Contractor Production Report: Original and one copy by 10:00 AM the next working day after each day that work is performed;
c. Preparatory Phase Checklist: Original attached to the original CQC Report and one copy attached to each copy;
d. Initial Phase Checklist: Original attached to the original CQC Report and one copy attached to each copy;
e. Field Test Reports: One copy, within two working days after the test is performed, attached to the CQC Report;
f. QC Meeting Minutes: One copy, within two working days after the meeting;and
g. QC Certifications: As required by the paragraph entitled "QC Certifications."
SECTION 01 45 00 Page 5
1.4 QC PROGRAM REQUIREMENTS
Establish and maintain a QC program as described in this section. The QC program consists of a QC Manager, a QC plan, a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, and QC certifications and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this contract. The QC program must cover on-site and off-site work and must be keyed to the work sequence. No work or testing may be performed unless the QC Manager is on the work site.
1.4.1 Preliminary Work Authorized Prior to Acceptance
The only work that is authorized to proceed prior to the acceptance of the QC plan is mobilization of storage and office trailers, temporary utilities, and surveying. Written consent is provide by the contracting officer to mobilize prior to acceptance.
1.4.2 Acceptance
Acceptance of the QC plan is required prior to the start of construction.
The Contracting Officer reserves the right to require changes in the QC plan and operations as necessary, including removal of personnel, to ensure the specified quality of work. The Contracting Officer reserves the right to interview any member of the QC organization at any time in order to verify the submitted qualifications.
1.4.3 Notification of Changes
Notify the Contracting Officer, in writing, of any proposed change, including changes in the QC organization personnel, a minimum of seven calendar days prior to a proposed change. Proposed changes must be subject to the acceptance by the Contracting Officer.
1.5 QC ORGANIZATION
1.5.1 QC Manager
1.5.1.1 Duties
Provide a QC Manager at the work site to implement and manage the QC program.
The QC Manager shall be a stand-alone position and have no other duties.
Exception: Building Official (BO) may allow the QC Manager to share duties with the Superintendent or safety officer on projects with a contract value under one million dollars or on single trade, non-complex projects of any value. However, at no time will one person hold more than two duties. This option is at the discretion of the BO. Contractors may request this option during pre-bid RFI’s for bidding purposes.
The QC Manager is required to attend the Coordination and Mutual Understanding Meeting, conduct the QC meetings, perform the three phases of control, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this contract. The QC Manager is responsible for managing and coordinating the three phases of control and documentation performed by others.
SECTION 01 45 00 Page 6
1.5.1.2 Qualifications
An individual with a minimum of 5 years combined experience as a superintendent, inspector, QC Manager, project manager, or construction manager on similar size and type construction contracts which included the major trades that are part of this contract with the technical competency and ability to inspect the work of others. The individual must be familiar with the requirements of the EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.
1.5.1.3 Construction Quality Management Training
In addition to the above experience and education requirements, the QC Manager must have completed the course Construction Quality Management for Contractors and will have a current certificate.
1.5.2 Alternate QC Manager Duties and Qualifications
Designate an alternate for the QC Manager to serve in the event of the designated QC Manager's absence. The period of absence may not exceed two weeks at one time, and not more than 30 workdays during a calendar year.
The qualification requirements for the Alternate QC Manager must be the same as for the QC Manager.
1.6 QC PLAN
Submit a QC plan within 15 calendar days after receipt of Notice of Award.
1.6.1 Requirements
Provide, for acceptance by the Contracting Officer, a QC plan submitted in a three-ring binder that covers both on-site and off-site work and includes the following with a table of contents listing the major sections identified with tabs.
I. QC ORGANIZATION: A chart showing the QC organizational structure and its relationship to the production side of the organization. The QC Manager must report to an officer of the firm and not be subordinate to the Project Superintendent or the Project Manager. The QC Manager, Project Superintendent and Project Manager must work together effectively. Although the QC Manager is the primary individual responsible for quality control, all individuals will be held responsible for the quality of work on the job.
II. NAMES AND QUALIFICATIONS: In resume format, for each person in the QC organization. Include the CQM for Contractors course certification requiredby the paragraph entitled "Construction Quality Management Training".
III. DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONAL: Of each person in the QC organization.
IV. OUTSIDE ORGANIZATIONS: A listing of outside organizations such as architectural and consulting engineering firms that will be employed by the Contractor and a description of the services these firms will provide.
V. APPOINTMENT LETTERS: Letters signed by an officer of the firm appointing the QC Manager and Alternate QC Manager and stating that they are responsible for managing and implementing the QC program as
SECTION 01 45 00 Page 7 described in this contract. Include in this letter the QC Manager's authority to direct the removal and replacement of non-conforming work.
VI. SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER: Procedures for reviewing, approving and managing submittals. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval.
VII. TESTING LABORATORY INFORMATION: Testing laboratory information required by the paragraphs "Accredited Laboratories" or "Testing Laboratory Requirements", as applicable.
VIII. TESTING PLAN AND LOG: A Testing Plan and Log that includes the tests required, referenced by the specification paragraph number requiring the test, the frequency, and the person responsible for each test.
IX. PROCEDURES TO COMPLETE REWORK ITEMS: Procedures to identify, record, track and complete rework items.
X. DOCUMENTATION PROCEDURES: Use Government formats.
XI. LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task, which is separate and distinct from other tasks, has the same control requirements and work crews. The list must be cross-referenced to the Contractor's Construction Schedule and the specification sections. For projects requiring a Progress Chart, the list of definable features of work must include but not be limited to all items of work on the schedule. For projects requiring a Network Analysis Schedule, the list of definable features of work must include but not be limited to all critical path activities.
XII. PROCEDURES FOR PERFORMING THREE PHASES OF CONTROL: For each DFOW provide Preparatory and Initial Phase Checklists. Each list must include a breakdown of quality checks that will be used when performing the quality control functions, inspections, and tests required by the contract documents. The preparatory and initial phases must be conducted with a view towards obtaining quality construction by planning ahead and identifying potential problems.
XIII. PERSONNEL MATRIX: Not Applicable.
XIV. PROCEDURES FOR COMPLETION INSPECTION: See the paragraph entitled
"COMPLETION INSPECTIONS".
XV. TRAINING PROCEDURES AND TRAINING LOG: Not Applicable.
1.7 COORDINATION AND MUTUAL UNDERSTANDING MEETING
During the Pre-Construction conference meeting and prior to the start of construction, discuss the QC program required by this contract. The purpose of this meeting is to develop a mutual understanding of the QC details, including documentation, administration for on-site and off-site work, and the coordination of the Contractor's management, production and the QC personnel. At the meeting, the Contractor will be required to explain how three phases of control will be implemented for each DFOW.
Contractor's personnel required to attend must include the QC Manager, project manager, and superintendent. Minutes of the meeting will be prepared by the QC Manager and signed by both the Contractor and the Contracting Officer. The Contractor must provide a copy of the signed minutes to all attendees. Repeat the coordination and mutual understanding meeting when a new QC Manager is appointed.
1.8 QC MEETINGS
After the start of construction, the QC Manager must conduct QC meetings
SECTION 01 45 00 Page 8 once every week at the work site with the superintendent and
SECTION 01 45 00 Page 9 the foreman responsible for the ongoing and upcoming work. The QC Manager must prepare the minutes of the meeting and provide a copy to the Contracting Officer within two working days after the meeting. As a minimum, the following must be accomplished at each meeting:
a. Review the minutes of the previous meeting;
b. Review the schedule and the status of work and rework;
c. Review the status of submittals;
d. Review the work to be accomplished in the next two weeks and documentation required;
e. Resolve QC and production problems (RFIs, etc.);
f. Address items that may require revising the QC plan; and
g. Review Accident Prevention Plan (APP).
1.9 THREE PHASES OF CONTROL
The three phases of control must adequately cover both on-site and off-site work and must include the following for each DFOW.
1.9.1 Preparatory Phase
Notify the Contracting Officer at least two work days in advance of each preparatory phase. Conduct the preparatory phase with the superintendent and the foreman responsible for the definable feature of work. Document the results of the preparatory phase actions in the daily CQC Report and in the QC checklist. Perform the following prior to beginning work on each definable feature of work:
a. Review each paragraph of the applicable specification sections;
b. Review the contract drawings;
c. Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and approved. Verify receipt of approved factory test results, when required;
d. Review the testing plan and ensure that provisions have been made to provide the required QC testing;
e. Examine the work area to ensure that the required preliminary work has been completed;
f. Examine the required materials, equipment and sample work to ensure that they are on hand and conform to the approved shop drawings and submitted data;
g. Review the APP and appropriate Activity Hazard Analysis (AHA) to ensure that applicable safety requirements are met, and that required Safety Data Sheets (SDS) are submitted; and
h. Discuss specific controls used and the construction methods and the approach that will be used to provide quality construction by planning ahead and identifying potential problems for each DFOW.
SECTION 01 45 00 Page 10
1.9.2 Initial Phase
Notify the Contracting Officer at least two work days in advance of each initial phase. Conduct the Initial Phase with the foreman responsible for that DFOW. Observe the initial segment of the work to ensure that it complies with contract requirements. Document the results of the Initial Phase in the daily CQC Report and in the QC checklist. Perform the following for each DFOW:
a. Establish the quality of workmanship required;
b. Resolve conflicts;
c. Ensure that testing is performed by the approved laboratory; and
d. Check work procedures for compliance with the APP and the appropriate AHA to ensure that applicable safety requirements are met.
1.9.3 Follow-Up Phase
Perform the following for on-going work daily, or more frequently as necessary, until the completion of each DFOW and document in the daily CQC Report and in the QC checklist:
a. Ensure the work is in compliance with contract requirements;
b. Maintain the quality of workmanship required;
c. Ensure that testing is performed by the approved laboratory;
d. Ensure that rework items are being corrected; and
e. Assure manufacturers representatives have performed necessary inspections, if required.
1.9.4 Additional Preparatory and Initial Phases
Additional preparatory and initial phases must be conducted on the same DFOW if the quality of on-going work is unacceptable, if there are changes in the applicable QC organization, if there are changes in the on-site production supervision or work crew, if work on a DFOW is resumed after substantial period of inactivity, or if other problems develop.
1.9.5 Notification of Three Phases of Control for Off-Site Work
Notify the Contracting Officer at least two weeks prior to the start of the preparatory and initial phases.
1.10 SUBMITTAL REVIEW AND APPROVAL
Procedures for submission, review, and approval of submittals are described in Section 01 33 00 SUBMITTAL PROCEDURES.
1.11 TESTING
Except as stated otherwise in the specification sections, perform sampling and testing required under this contract.
SECTION 01 45 00 Page 11
1.11.1 Accreditation Requirements
Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory's scope of accreditation must include the appropriate ASTM standards (i.e.; E 329, C 1077, D 3666, D 3740, E 543) listed in the technical sections of the specifications. Laboratories engaged in Hazardous Materials Testing must meet the requirements of OSHA and EPA.
The policy applies to the specific laboratory performing the actual testing, not just the "Corporate Office."
1.11.2 Laboratory Accreditation Authorities
Laboratory Accreditation Authorities include the National Voluntary Laboratory Accreditation Program (NVLAP) administered by the National Institute of Standards and Technology, the American Association of State Highway and Transportation Officials (AASHTO), International Accreditation Services, Inc. (IAS), U. S. Army Corps of Engineers Materials Testing Center (MTC), the American Association for Laboratory Accreditation (A2LA), the Washington Association of Building Officials (WABO) (Approval authority for WABO is limited to projects within Washington State), and the Washington Area Council of Engineering Laboratories (WACEL) (Approval authority by WACEL is limited to projects within the NAVFAC WASH and Public Works Center Washington geographical area).
1.11.3 Capability Check
The Contracting Officer retains the right to check laboratory equipment in the proposed laboratory and the laboratory technician's testing procedures, techniques, and other items pertinent to testing, for compliance with the standards set forth in this contract.
1.11.4 Test Results
Cite applicable Contract requirements, tests or analytical procedures used. Provide actual results and include a statement that the item tested or analyzed conforms or fails to conform to specified requirements. If the item fails to conform, notify the Contracting Officer immediately.
Conspicuously stamp the cover sheet for each report in large red letters "CONFORMS" or "DOES NOT CONFORM" to the specification requirements, whichever is applicable. Test results must be signed by a testing laboratory representative authorized to sign certified test reports.
Furnish the signed reports, certifications, and other documentation to the Contracting Officer.
1.12 QC CERTIFICATIONS
1.12.1 Contractor Quality Control Report Certification
Each CQC Report must contain the following statement: "On behalf of the Contractor, I certify that this report is complete and correct and equipment and material used and work performed during this reporting period is in compliance with the contract drawings and specifications to the best of my knowledge except as noted in this report."
SECTION 01 45 00 Page 12
1.12.2 Invoice Certification
Furnish a certificate to the Contracting Officer with each payment request, signed by the QC Manager, attesting that as-built drawings are current and attesting that the work for which payment is requested, including stored material, is in compliance with contract requirements.
1.12.3 Completion Certification
Upon completion of work under this contract, the QC Manager must furnish a certificate to the Contracting Officer attesting that "the work has been completed, inspected, tested and is in compliance with the contract."
1.13 COMPLETION INSPECTIONS
1.13.1 Punch-Out Inspection
Near the completion of all work or any increment thereof established by a completion time stated in the Contract clause "Commencement, Prosecution, and Completion of Work," or stated elsewhere in the specifications, the QC Manager must conduct an inspection of the work and develop a punch list of items which do not conform to the approved drawings and specifications.
Include in the punch list any remaining items of the "Rework Items List", which were not corrected prior to the Punch-Out inspection. The punch list must include the estimated date by which the deficiencies will be corrected. A copy of the punch list must be provided to the Contracting Officer. The QC Manager or staff must make follow-on inspections to ascertain that all deficiencies have been corrected. Once this is accomplished, the Contractor must notify the Government that the facility is ready for the Government "Pre-Final Inspection".
1.13.2 Pre-Final Inspection
The Government and QC manager will perform this inspection to verify that the facility is complete and ready to be occupied. A Government pre-final punch list may be developed as a result of this inspection. The QC Manager must ensure that all items on this list are corrected prior to notifying the Government that a "Final" inspection with the customer can be scheduled. Any items noted on the "Pre-Final" inspection must be corrected in a timely manner and must be accomplished before the contract completion date for the work or any particular increment thereof if the project is divided into increments by separate completion dates.
1.13.3 Final Acceptance Inspection
The QC Manager, the superintendent, or other Contractor management personnel and the Contracting Officer will be in attendance at this inspection. Additional Government personnel may be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the "Pre-Final Inspection". Notice must be given to the Contracting Officer at least 14 days prior to the final inspection. The notice must state that all specific items previously identified to the Contractor as being unacceptable will be complete by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the contract clause "Inspection of Construction".
1.14 DOCUMENTATION
SECTION 01 45 00 Page 13
Maintain current and complete records of on-site and off-site QC program operations and activities. The forms identified under the paragraph "INFORMATION FOR THE CONTRACTING OFFICER" must be used. Reports are required for each day work is performed. Account for each calendar day throughout the life of the contract. Every space on the forms must be filled in. Use N/A if nothing can be reported in one of the spaces. The superintendent and the QC Manager must prepare and sign the Contractor Production and CQC Reports, respectively. The reporting of work must be identified by terminology consistent with the construction schedule. In the "remarks" section in this report which will contain pertinent information including directions received, problems encountered during construction, work progress and delays, conflicts or errors in the drawings or specifications, field changes, safety hazards encountered, instructions given and corrective actions taken, delays encountered and a record of visitors to the work site. For each remark given, identify the Schedule Activity No. that is associated with the remark.
1.14.1 Quality Control Validation
Establish and maintain the following in a series of three ring binders.
Binders must be divided and tabbed as shown below. These binders must be readily available to the Government's Quality Assurance Team during all business hours.
a. All completed Preparatory and Initial Phase Checklists, arranged by specification section.
b. All milestone inspections, arranged by Activity/Event Number.
c. A current up-to-date copy of the Testing and Plan Log with supporting field test reports, arranged by specification section.
d. Copies of all contract modifications, arranged in numerical order.
Also include documentation that modified work was accomplished.
e. A current up-to-date copy of the Rework Items List.
f. Maintain up-to-date copies of all punch lists issued by the QC Staff on the Contractor and Sub-Contractors and all punch lists issued by the Government.
1.14.2 As-Built Drawings
The QC Manager is required to review the as-built drawings, required by Section 01 78 00 CLOSEOUT SUBMITTALS, are kept current on a daily basis and marked to show deviations, which have been made from the Contract drawings. Ensure each deviation has been identified with the appropriate modifying documentation, e.g. PC number, modification number, RFI number, etc. The QC Manager must initial each deviation or revision. Upon completion of work, the QC Manager must submit a certificate attesting to the accuracy of the as-built drawings prior to submission to the Contracting Officer.
1.15 NOTIFICATION ON NON-COMPLIANCE
The Contracting Officer will notify the Contractor of any detected non-compliance with the foregoing requirements. The Contractor must take immediate corrective action. If the contractor fails or refuses to correct the non-compliant work, the Contracting Officer will issue a non compliance notice. Such notice, when delivered to the Contractor at the
SECTION 01 45 00.10 20 Page 14 work site, must be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor must make no part of the time lost due to such stop orders the subject of claim for extension of time, for excess costs, or damages.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
COMPLETION INSPECTIONS
PROCEDURES FOR INSPECTION
3.1 All Inspections including Special Inspections will be requested by the contractors QC manager to the governments Inspector of Record(IOR)/QA.
Inform the IOR no less then 48 hours prior to the time inspection is requested via the system of record used to manage the project(Procore, Bim360, Email etc). QC shall perform quality control inspection prior to requesting inspection from the government. The following documents shall accompany all inspection requests to be valid.
a. Map and location of the work that is to be inspected
b. Preparatory Phase Checklist
c. Initial Phase Checklist
d. Pictures of the work (a reasonable amount to illustrate the work)
e. Specification sections for the work being inspected
f. A written and signed inspection request on company letterhead from the
QC stating "the work has been completed, was inspected and is in compliance with the contract documents"
-- End of Section –
SECTION 01 45 00.10 20 Page 15
Photo 1
Photo 2
Photo 3
From: QC Name Date: (Todays Date)
TO: CA Mil Dept.- IOR Name
Request inspection on: Date / Time
Details: Request government inspection of the rough electrical lighting located in the front lobby, restrooms, and outer lobby. Work to be inspected is highlighted on the map below.
Below are photographs of the work to be inspected
Specification section attached
Preparatory Phase checklist attached
Initial Phase checklist attached
Electrical Subcontractor verifies work is ready for inspection Signature
“QC Verification statement:” The work has been completed, was inspected and is in compliance with the contract documents Signature
Company Letterhead
4296/2B (9/98) SHEET 1 OF 2
PREPARATORY PHASE CHECKLIST
(CONTINUED ON SECOND PAGE)
CONTRACT NO DEFINABLE FEATURE OF WORK
SPEC SECTION
SCHEDULE ACT NO.
DATE
INDEX #
GOVERNMENT REP
NOTIFIED
HOURS IN ADVANCE: YES NO
NAME POSITION COMPANY/GOVERNMENT
REVIEW SUBMITTALS AND/OR SUBMITTAL REGISTER. HAVE ALL SUBMITTALS BEEN APPROVED? YES NO
IF NO, WHAT ITEMS HAVE NOT BEEN SUBMITTED?
ARE ALL MATERIALS ON HAND? YES NO
IF NO, WHAT ITEMS ARE
MISSING?
CHECK APPROVED SUBMITTALS AGAINST DELIVERED MATERIAL. (THIS SHOULD BE DONE AS MATERIAL ARRIVES.)
COMMENTS:
ARE MATERIALS STORED PROPERLY? YES NO
IF NO, WHAT ACTION IS TAKEN?
REVIEW EACH PARAGRAPH OF SPECIFICATIONS.
DISCUSS PROCEDURE FOR ACCOMPLISHING THE
WORK.
CLARIFY ANY DIFFERENCES.
ENSURE PRELIMINARY WORK IS CORRECT AND PERMITS ARE ON FILE.
IF NOT, WHAT ACTION IS TAKEN?
PR
EL
IM
IN
AR
Y
W O
R K
PE
RM
IT
S
M
AT
ER
IA
L
ST
O
RA
G E
SP
EC
IF
IC
AT
IO
N S
SU
B
M
IT
TA
LS
R
SO
N N
EL
P
RE
SE
NT
4296/2B (9/98) SHEET 2 OF 2
IDENTIFY TEST TO BE PERFORMED, FREQUENCY, AND BY
WHOM.
WHEN REQUIRED?
WHERE REQUIRED?
REVIEW TESTING PLAN.
HAS TEST FACILITIES BEEN
APPROVED?
ACTIVITY HAZARD ANALYSIS APPROVED? YES NO
REVIEW APPLICABLE PORTION OF EM 385-1-1.
COMMENTS DURING MEETING.
OTHER ITEMS OR REMARKS:
QC MANAGER DATE
O
TH
ER
IT
EM
S
RE
M
AR
KS
EE
TI
N
G C
O M
M
EN
TS
SA
FE
TY
TE
ST
IN
G
4296/2C (9/98) SHEET 1 OF 1
INITIAL PHASE CHECKLIST SPEC SECTION DATE
CONTRACT NO DEFINABLE FEATURE OF WORK SCHEDULE ACT NO. INDEX #
SO
N
N
EL
P
RE
SE
NT
GOVERNMENT REP NOTIFIED HOURS IN ADVANCE: YES NO
NAME POSITION COMPANY/GOVERNMENT
PR
C
ED
U
CO
PL
IA
N
CE
IDENTIFIY FULL COMPLIANCE WITH PROCEDURES IDENTIFIED AT PREPARATORY. COORDINATE PLANS, SPECIFICATIONS, AND SUBMITTALS.
PR
EL
IM
IN
AR
Y W
RK
ENSURE PRELIMINARY WORK IS COMPLETE AND CORRECT. IF NOT, WHAT ACTION IS TAKEN?
W
RK
M
AN
SH
IP
ESTABLISH LEVEL OF WORKMANSHIP.
WHERE IS WORK
LOCATED?
IS SAMPLE PANEL REQUIRED? YES
WILL THE INIITAL WORK BE CONSIDERED AS A SAMPLE? YES
(IF YES, MAINTAIN IN PRESENT CONDITION AS LONG AS POSSIBLE AND DESCRIBE LOCATION OF
SAMPLE)
NO
SO
LU
TI
O
N
RESOLVE ANY DIFFERENCES.
C
H
EC
K S
AF
ET
Y REVIEW JOB CONDITIONS USING EM 385-1-1 AND JOB HAZARD ANALYSIS
TH
ER
OTHER ITEMS OR REMARKS
QC MANAGER
4296/2 (9/98) SHEET 1 OF 1
CONTRACTOR QUALITY CONTROL REPORT
(ATTACH ADDITIONAL SHEETS IF NECESSARY)
DATE
REPORT
NO
PHASE CONTRACT NO CONTRACT TITLE
PR
EP
A
RA
TO
RY
WAS PREPARATORY PHASE WORK PREFORMED TODAY? YES NO
IF YES, FILL OUT AND ATTACH SUPPLEMENTAL PREPARATORY PHASE CHECKLIST.
Schedule
Activity No. Definable Feature of Work Index #
IN
IT
IA
L
WAS INITIAL PHASE WORK PREFORMED TODAY? YES NO
IF YES, FILL OUT AND ATTACH SUPPLEMENTAL INITIAL PHASE CHECKLIST.
Activity No. Definable Feature of Work Index #
FO
LL
O W
-U P
WORK COMPLIES WITH CONTRACT AS APPROVED DURING INITIAL PHASE? YES NO
WORK COMPLIES WITH SAFETY REQUIREMENTS? YES NO
Schedule Activity No.
Description of Work, Testing Performed & By Whom, Definable Feature of Work, Specification Section, Location and List of Personnel Present
REWORK ITEMS IDENTIFIED TODAY (NOT CORRECTED BY CLOSE OF BUSINESS) REWORK ITEMS CORRECTED TODAY (FROM REWORK ITEMS LIST)
Activity No. Description Schedule Activity No. Description
REMARKS (Also Explain Any Follow-Up Phase Checklist Item From Above That Was Answered "NO"), Manuf. Rep On-Site, etc.
Activity No. Description
On behalf of the contractor, I certify that this report is complete and correct and equipment and material used and work performed during this reporting period is in compliance with the contract drawings and specifications to the best of my knowledge except as noted in this report. AUTHORIZED QC MANAGER AT SITE DATE
REWORK ITEMS LIST
4296/3 (9/98) SHEET 1 of 1
Contract No. and Title: Enter Contract # and Title Here
Contractor: Enter Contractor's Company Name Here
NUMBER
IDENTIFIED
DESCRIPTION
CONTRACT
REQUIREMENT
(Spec. Section and Par. No., Drawing No.
and Detail No., etc.)
ACTION TAKEN
BY QC MANAGER
RESOLUTION
COMPLETED
TESTING PLAN AND LOG
4296/4 (9/98) SHEET 1
CONTRACT NUMBER
Enter Contract # Here
PROJECT TITLE AND LOCATION
Enter Contract Title and Location Here
CONTRACTOR
Enter Contractor's Company Name Here
SPECIFICATION
SECTION
AND
PARAGRAPH
NUMBER
ITEM
OF
WORK
TEST REQUIRED
ACCREDITED/
APPROVED
LAB
SAMPLED BY
TESTED BY
LOCATION
OF TEST
COMPLETED
FORWARDED
TO
CONTR. OFF.
REMARKS
YES
ON
SITE
OFF
SITE
RESPONSIBILITIES/AUTHORITY OF THE QC MANAGER
1. Appointing letter to the QC manager shall detail his/her authority and responsibility to act for the contractor and outline his/her duties, responsibilities and authority. He/she shall have no job-related responsibilities other than QC unless specifically permitted in the specification.
2. He/she shall be on the site at all times during progress of the work, with complete authority to take any action necessary to ensure conformance with the contract requirements. In the event of his/her absence, approved backup shall be on the site.
3. Authority to immediately stop any segment of work which does not comply with the contract plans and specifications and direct the removal and replacement of any defective work.
4. Conduct daily inspection of work performed for compliance with plans and specifications.
5. Certify daily that all materials and equipment delivered/installed in the work comply with contract plans and specifications. Certify daily that all work performed on the construction site and off the construction site conforms to plans and specifications. Report any deficiencies and remedial action planned and taken.
6. Supervise and coordinate the inspection and tests made by the members of the Quality Control Organization, including subcontractors.
7. Assure QC staff is adequate to meet its responsibilities.
8. Maintain a copy of the Building Official approved QC Plan on file at the jobsite complete with up-to-date approved revisions/filled-in log of submittals. Maintain at the jobsite an up-to-date QC Submittal Register (provided in the specification) showing the status of all submittals required by the contract.
9. Maintain at the jobsite a testing plan showing status of all tests required by the contracts. Ensure that all tests required are performed and report the results of same. Indicate whether test results show the item tested conforms to contract requirements or not.
10. Authority to remove any individual from the site who fails to perform his/her work in a skillful and workmanlike manner or his/her work does not comply with the contract plans and specifications.
11. QC manager does not have authority to deviate from plans and specifications without prior approval, in writing, from the ROICC.
12. Ensure that the contractor's Quality Control Organization is adequately staffed with qualified personnel to perform all the detailed inspections and testing specified in the plans and specifications.
13. Maintain at the jobsite the up-to-date QC Rework Items List.
ATTACHMENT A