The document provided is a set of Special Terms and Conditions for a goods and nonprofessional services contract opportunity issued by the Commonwealth of Virginia. The contract involves the retention of records for 5 years, the award of a contract on a cost per acre basis to the lowest responsive and responsible bidder, and the ability for the agency to cancel the contract with 60 days' written notice. The contract also includes provisions related to eVA, bid prices, the bid acceptance period, subcontracting, site damage repairs, and final inspection requirements.
The contract specifies that bid prices must be provided in the form of firm unit prices, and that the contract may be terminated by the contractor after the initial 12 months with 60 days' written notice. The document does not provide information about any set-asides, incumbent contractors, funding sources, or other salient commercial details.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL TERMS AND CONDITIONS
GOODS AND NONPROFESSIONAL SERVICES
1. AUDIT: The contractor shall retain all books, records, and other documents relative to this contract for five (5) years after final payment, or until audited by the Commonwealth of Virginia, whichever is sooner. The agency, its authorized agents, and/or state auditors shall have full access to and the right to examine any of said materials during said period.
2. AWARD OF CONTRACT: The Commonwealth will make the award(s) on cost per acre basis to the lowest responsive and responsible bidder. The purchasing office reserves the right to conduct any test it may deem advisable and to make all evaluations. The Commonwealth also reserves the right to reject any or all bids, in whole or in part, to waive informalities and to delete items prior to making the award, whenever it is deemed in the sole opinion of the procuring public body to be in its best interest.
3. CANCELLATION OF CONTRACT: The purchasing agency reserves the right to cancel and terminate any resulting contract, in part or in whole, without penalty, upon 60 days written notice to the contractor. In the event the initial contract period is for more than 12 months, the resulting contract may also be terminated by the contractor, without penalty, after the initial 12 months of the contract period upon 60 days written notice to the other party. Any contract cancellation notice shall not relieve the contractor of the obligation to deliver and/or perform on all outstanding orders issued prior to the effective date of cancellation.
4. eVA ORDERS AND CONTRACTS: The solicitation/contract will result in 1 purchase order with the applicable eVA transaction fee assessed.
5. BID PRICES: Bid shall be in the form of a firm unit price for each item during the contract period.
6. BID ACCEPTANCE PERIOD: Any bid in response to this solicitation shall be valid for 30 days. At the end of the days the bid may be withdrawn at the written request of the bidder. If the bid is not withdrawn at that time it remains in effect until an award is made or the solicitation is canceled.
7. SUBCONTRACTS: No portion of the work shall be subcontracted without prior written consent of the purchasing agency. In the event that the contractor desires to subcontract some part of the work specified herein, the contractor shall furnish the purchasing agency the names, qualifications and experience of their proposed subcontractors. The contractor shall, however, remain fully liable and responsible for the work to be done by its subcontractor(s) and shall assure compliance with all requirements of the contract.
8. WORK SITE DAMAGES: Any damage to existing utilities, equipment or finished surfaces resulting from the performance of this contract shall be repaired to the Commonwealth’s satisfaction at the contractor’s expense.
9. FINAL INSPECTION: At the conclusion of the work, the contractor shall demonstrate to the authorized owner’s representative that the work is fully operational and in compliance with contract specifications and codes. Any deficiencies shall be promptly and permanently corrected by the contractor at the contractor’s sole expense prior to final acceptance of the work.