Special_Provisions_-_Page_SP-1_to_SP-7.pdf

PDF 259 KB Posted

Attached to
Fort Florida Road Overlay Project
Solicitation number
04-18
Issued by
Volusia County, Florida

About this file

This document comprises the Special Provisions for the Fort Florida Road Overlay Project (Bid No. 04-18) issued by the City of DeBary, Florida, governing the terms and conditions for asphalt pavement overlay work and pavement marking maintenance on Fort Florida Road. The project involves roadway pavement maintenance and restoration of pavement markings, with work limited to overlay activities and restoration of existing drainage patterns and traffic control elements to pre-construction conditions. A pre-paving conference must be held between the contractor and engineer no later than five calendar days after contract execution to review payment procedures, schedules, testing requirements, and establish the Notice-to-Proceed date. Lane closures are restricted to 9 AM to 4 PM with one paved lane of 10-foot width maintained open to traffic at all times, requiring two FDOT-equipped flag persons and adherence to FDOT Standard Index 603 for traffic control. Fort Florida Point Road, a private road serving six residences, requires written notification to residents three days prior to paving with coordination assistance from City staff.

All costs for mobilization, payment bonds, performance bonds, and temporary pavement markings are included in the bid price with no additional compensation available. Liquidated damages of $500 per calendar day apply for work remaining uncompleted after the contract completion date, with no time extensions granted for inclement weather unless rainfall exceeds historical norms as confirmed by the engineer. The contractor must maintain a testing laboratory at its expense for all required testing and sampling per FDOT standards. No escalation or adjustment claims for price increases are permitted, and no assignment of the contract is allowed. The contract documents follow a specific order of precedence beginning with addenda, followed by special provisions, plans, instructions to bidders, general conditions, and FDOT specifications. Storage of materials on City rights-of-way is prohibited except for materials used during daily operations, with the contractor responsible for providing off-site storage facilities and daily material transportation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fort Florida Road Overlay Project

Bid No. 04-18

SP - 1

SPECIAL PROVISIONS

GENERAL NOTES and PAY ITEM NOTES

CITY of DeBary - Bid No. 04-18

FORT FLORIDA ROAD OVERLAY PROJECT

These Special Provisions, General Notes and Pay Item Notes modify, clarify, delete, or supplement the Standard General Conditions of the Contract. These Special Provisions and the latest edition of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction, and Design Standards shall govern the work under this Contract and are included by reference. Refer to Article 16 below for the Order of Precedence of the Contract Documents.

General Notes

Note G1. – TIME IS OF THE ESSENCE FOR ALL WORK UNDER THIS CONTRACT.

Note G2. -All Work is limited to the maintenance of roadway pavement and pavement markings.

Existing drainage patterns and traffic control elements of roadway shall be restored to pre-construction conditions unless otherwise directed by the CITY of DeBary.

Note G3. – All references to CITY included herein shall refer to the CITY of DeBary, Florida.

Note G4. - Maintenance of Traffic, Lane closures are limited to the hours of 9 AM to 4PM unless otherwise approved in writing by the City of DeBary. The Contractor must maintain one paved lane, 10’-0 width, open to traffic at all times during lane closures. Maintenance of traffic for lane closures shall be according to FDOT Standard Index 603 with two FDOT equipped flag persons, at all times.

- End of General Notes -

PAY ITEM NOTES – REFER TO BID FORM

Pay Item Note 1 – Pay Item 101-1, Mobilization - Mobilization for all project sites shall be included in Pay item 101-1. The cost of the Payment and Performance Bonds shall be included in Pay Item 101- 1-1.

Pay Item Note 2 – Pay item 102-1-2 - Ft. Florida Point Road is a private road that serves six (6) homes and dead ends approximately 1000 feet west from its connection to Ft. Florida Road. The Contractor shall maintain vehicle and pedestrian traffic and provide residents and services access to the residences. Each residences shall be notified in writing three (3) days prior to the proposed paving and coordination with residences. City staff will assist the Contractor with notification to residences.

- End of Pay Item Notes -

SP - 2

SPECIAL PROVISIONS

Article 1 - Description of Work

Work included in the Contract as Bid Items are shown on the Bid Form Sheets and as shown on the Pavement Overlay Plan – Page SP-8. All costs to perform the work called for in the Contract Documents are included in the unit prices and the Total Bid Amount in the Proposal submitted by the Contractor.

Any commission or omission shown or implied shall not be cause for deviating from the intent of the Contract Documents. Any modifications of the Contract Documents deemed necessary by the Contractor shall be reported to the CITY. Details of such modifications and the reasons therefore shall be submitted in writing to the Engineer for written approval prior to beginning such modified work.

Article 2 - Insurance

Insurance coverage, limits and other requirements will be in accordance with Section 7-13 of Florida Department of Transportation Specifications for Road and Bridge Construction, latest edition, and as specified in Article 5 of the CITY of DeBary Standard General Conditions. Any discrepancy between the FDOT and the CITY specifications, the CITY’s specifications will govern.

CITY of DeBary shall be listed as additionally insured on Contractor’s Insurance Certificate.

Article 3 - Contract Bonds

The cost of the Payment and Performance Bond shall be included in the Total Bid Amount. Compensation to the Contractor for providing the required Payment and Performance Bonds shall be included in Pay Item 101-1, Mobilization.

The forms included in these contract documents shall be used. NO OTHER FORMS

WILL BE ACCEPTED.

Article 4 - Construction Procedure

The Contractor shall at all times conduct the work in such manner and in such sequence as will insure the least practicable interference with traffic. The Contractor's vehicles and other equipment shall be operated in such manner that they will not be a hazard or hindrance to the traveling public. The Contractor shall not open up work to the prejudice of work already started, and the Engineer may require the Contractor to finish a section on which work is in progress before work is started on any additional section.

SP - 3

The Contractor shall arrange the work and dispose of materials in accordance with the spirit of the Contract Documents and perform the work in proper sequence all as may be approved by the Engineer.

Whenever, in the opinion of the Engineer, any roadway or portion thereof is in an acceptable condition for travel it shall be opened to traffic, as may be directed, and such opening shall not be held to be in any way an acceptance of roadway, or any part of it, or as a waiver of any of the provisions of the Specifications and the Contract Documents. Necessary repairs or renewals made on any section of the roadway opened to travel under instructions of the Engineer, due to defective material or workmanship or due to natural causes, other than ordinary wear and tear, pending completion and acceptance of the roadway, shall be performed by the Contractor without additional compensation.

The Contractor is responsible for maintaining proper drainage during construction.

Existing functioning gutters, pipes, and ditches shall not be obstructed and adjacent premises must be given access as far as practicable. Materials or equipment stored along the roadway shall be placed so as to cause no obstruction to the traveling public.

Article 5 - Barricades, Warnings, and Detour Signs

The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient warning lights, danger signals and signs provide a sufficient number of watchmen to direct the traffic, and take all necessary precautions for the protection of the work and safety of the public. Highways closed to traffic shall be protected by effective barricades on which shall be placed acceptable warning signs and lights.

The Contractor shall erect and maintain acceptable warning and directional signs at all closures (partial or whole), intersections and along the detour routes, directing the traffic around the closed portion or portions of the highway, so that any temporary detour route or routes shall be indicated clearly throughout its or their entire length. All barricades and obstructions shall be illuminated at night and all lights shall be kept burning from sunset until sunrise. All warning and directional signs shall be furnished by the Contractor unless otherwise stipulated.

Article 6 - Maintenance of Traffic and Lane Closure Requirements

Maintenance of traffic shall be in accordance with Section 102, "MAINTENANCE of TRAFFIC", of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction, latest Edition. Traffic Control through Work Zones shall be per the applicable sheets of Florida Department of Transportation Standard Index series 600.

The Contractor shall coordinate all construction that may impede traffic with appropriate CITY representatives and emergency services. The Contractor shall provide public notice, detours, roadways, and crossings to minimize traffic impedance along all public highways.

SP - 4

Lane closures are limited to the hours of 9 AM to 4PM. The Contractor must maintain one paved lane, 10’-0 width, open to traffic at all times during lane closures.

Maintenance of traffic for lane closures shall be according to FDOT Standard Index 603 with two FDOT equipped flag persons, at all times.

Article 7 - Contract Assignment

The successful Bidder will be required to perform the work as a prime contractor. No assignment of the contract will be allowed.

Article 8 - Layout of Work and Surveys

The Engineer will furnish the Contractor with all necessary information relating to lines, grades and locations of the work. The Contractor shall furnish all stakes and necessary labor and shall be responsible for the layout of the work and the establishing of all lines and grades. All layout work may be checked and verified by the Engineer; and the Contractor shall furnish all such necessary materials, equipment, labor and assistance as the Engineer may require. The Contractor is responsible for the safeguarding of survey references and any offset thereto which he might require in the process of his work. The damage, moving or loss of references caused by carelessness of the Contractor will be replaced at the Contractor's expense.

Article 9 - Escalation and/or Adjustment

No claim for escalation or adjustment for any price or rate increases will be considered.

Article 10 - One-Year Correction Period

The Contractor shall at his expense maintain his Contract Bond in effect through the guaranty period and such additional time as the Contractor may be performing work pursuant to his obligations under the guaranty.

Article 11 – Testing

The Contractor will employ, at its expense, a testing laboratory for all testing required under this contract. Asphalt sampling and core locations shall be according to FDOT Standard Specifications and as approved by the CITY of DeBary.

Article 12 – Specifications

The Florida Department of Transportation Standard Specifications for Road and Bridge Construction, latest edition in its entirety will apply to this project, with the exception of the following and other changes, modifications and/or amendments that are included in the Contract Documents.

A. IN GENERAL: Where the word "Department" and "Director" occurs substitute the word "CITY"; delete all references to "Secretary"; delete all

SP - 5

references to "Holiday" and "Working Days"; delete all references to "Value Engineering Incentive".

All references to "Engineer" shall mean the CITY of Debary‘s Consulting Engineer.

B. Method of Payment/Basis of Payment; The units of measurement and the contract unit prices are those indicated in the Bid Form Schedule portion of the proposal form. Such prices and payments shall be full compensation for performing all work necessary to complete the entire project.

Article 13 - "Or Equal" Clause

Direct reference in specifications to any item of material or equipment with or without the words "or equal", shall be interpreted as determining a standard of quality and shall not be construed as limiting competition.

Article 14 - Time of Completion

The time of completion for this project is the date set forth in the Notice-to-Proceed.

No time extensions will be given for inclement weather unless the Contractor can show that rainfall experienced during the contract times is above normal for the same months in previous years as determined by reliable measurement and confirmed by the Engineer's measurements at the site. The number of days of time extension granted under this Article shall be at the sole discretion of the Engineer.

Article 15 - Liquidated Damages

The amount of liquidated damages shall be five hundred dollars ($500.00) per Calendar Day that any work remains uncompleted after the end of the contract time.

Liquidated damages in an amount determined in accordance with the above will be deducted from monies due the Contractor. In the event that no monies are due the Contractor or that the monies due are insufficient, his surety will be held liable for the difference between the amount of the liquidated damages and monies due the Contractor.

Article 16 - Contract Documents - Order of Precedence

A. Addenda B. Special Provisions C. Pavement Overlay Plan - Sheet S-8 D. Instruction to Bidders E General Conditions of the Construction Contract F. Florida Department of Transportation Specifications

SP - 6

Article 17 – Arbitration

There shall be no arbitration process in connection with this project. All claims, disputes and other matters in question between CITY and Contractor shall be decided by a Court with proper jurisdiction in Volusia County, Florida.

Article 18 - Stored Materials

No payment will be made for stored materials.

Article 19 - Alternate Bids

No alternate bids are required.

Article 20 - Pavement Markings

Temporary pavement markings shall be installed immediately following the placement of any surfacing or other activity that obscures existing markings: The replacement of BLUE RPMs in the center of travel lanes adjacent to fire hydrants is to be considered part of the temporary markings and are included in this project. Any cost for the temporary pavement markings will be considered incidental to the cost of the total project. No additional payment shall be made. The Contractor shall take all necessary precautions to protect all pavement markings from damage beyond the actual limits of the work. Any markings that become damaged, physically or by loss of function, shall be replaced by the Contractor to the satisfaction of the Engineer at no cost to the CITY.

Article 21 - Pre-Paving Conference

Prior to the beginning of work, a Pre-Paving Conference will be held between the Contractor and Engineer to review payment procedures, contract forms, schedules, testing; and other pertinent data related to the job. The meeting date and time will be mutually agreed upon, but shall, no case, be later than five (5) calendar days after execution of the contract by all parties thereto. The Contractor shall present the Engineer with a schedule, showing anticipated monthly payments from date of Notice-to-Proceed to Final Completion, at the Pre-Construction Meeting. The date of Notice-to- Proceed with the work will be determined and agreed to at this meeting.

Article 22 - Beginning and Ending Joints

Asphalt pavement restoration shall have start and end joints properly constructed to prevent slipping, raveling and uneven surfaces. Provide milling to provide smooth transition at tie-in of new pavement with existing pavement.

Article 23 – Application for Progress Payment

Applications for Payment shall be referenced to the Contract Pay Items as noted on the Bid Form. Applications for Payment shall include the original contract quantity and unit for each Pay Item and the percent completed. Prior to the initial pay application, the

SP - 7

Contractor shall submit a draft format of the Application for Payment to the CITY for approval. Applications for Payment shall include satisfactory documentation to support the payment. Payment to the Contractor shall be made once for each thirty (30) day period of the contract.

Article 24 – Measurements and Payment

Method of Measurement and Payment for all bid items will be as measured in-place upon acceptance of the Work by the CITY.

Payment for all unit price items will be made for the actual quantities placed and measured.

Article 25 – Public Records

The Contractor shall allow public access to all documents, papers, letters, or other material subject to the provisions of Chapter 119, Florida Statutes, and those made or received by the CITY in conjunction with this Project.

Article 26 – Storage of Equipment and Materials

Storage of construction materials on CITY rights-of-way is not allowed. During daylight operations materials that will be used for that day’s work may be placed on CITY rights-of-way. It is the Contractor’s responsibility to provide materials storage facilities as needed and daily transportation of materials to the site.

The Contractor may store construction equipment on the CITY rights-of-way at locations that are acceptable to the Engineer.

- End of Special Provisions –