AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO.
See Block 14
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE SPE600 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE FACILITY CODE
SPE60014R0410
X
2014 JUL 25
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, X is not extended.
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
12. ACCOUNTING AND APPROPRIATION DATA (If required)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A NAME AND TITLE OF SIGNER (Type or print)
NSN 7540-01-152-8070
Previous edition unusable
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
(a) By completing Items 8 and 15, and returning
DLA ENERGY
8725 JOHN J KINGMAN RD STE 4950
FT BELVOIR VA 22060-6222
USA
15C. DATE SIGNED 16C. DATE SIGNED
D. OTHER (Specify type of modification and authority)
8/15/2014
3. EFFECTIVE DATE
See Attached Continuation Sheet(s).
(X)
CHECK ONE
PAGE OF PAGES
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
SPE600-14-R-0410 Amendment 0001 PJM Large 2014 Page 2 of 2
Solicitation
1. The Standard Form 1449 has been amended to update to reflect the following estimated quantity:
3,518,535,475 kWh.
2. Section A – Solicitation / Contract Form has been amended to add the following note:
NOTE 3: A date for the receipt of prices will be established via a future amendment after the offer due date specified on the Standard Form 1449.
3. Clause B1.08 SUPPLIES TO BE FURNISHED (ELECTRICITY)(DLA ENERGY)(JAN 2012), Paragraph (f) has been amended to revise/add the following notes:
NOTE 6: Fort Meade only:
Due to ongoing privatization efforts, new accounts will be added periodically during contract period of performance as new meters are installed by BGE. It is not anticipated that the overall load for this installation will increase as a result of the additional meters. New accounts will be added in accordance with Clause C800 STATEMENT OF WORK/SPECIFICATIONS, Paragraph (j) ADDING FUTURE ACCOUNTS.
NOTE 9: Costs related to FERC Order 745 shall be a direct pass-through with no markup.
Installation Data Sheet
4. The Installation Data Sheet has been amended to provide the following additional information:
- Summary of usage data for all Fort Meade accounts
- Line Item 0011 – NIH revised to reference First Energy account number 110084629044
- Account numbers for Line Item 0013 – Fort Detrick have been revised.
- Usage data for Line Item 0023 - DLA Distribution Susquehanna accounts 3786079000 and 4202349008
Attachment III – Argonne Pricing Sheet
5. The following paragraph has been amended to remove reference to FERC Order 745 charges:
The energy price is to include all PJM ancillary services and ISO related costs not identified in the pass-through components. This includes transmission entitlement and FERC Order 745 charges. Argonne understands that ComEd zone Reliability Must Run Charges are currently zero. These costs can be listed as a line item charge if they begin to be assessed after the contract is signed.
SPE600-14-R-0410
ANL Pricing Submittal
ATTACHMENT III
ARGONNE NATIONAL LABORATORY (ANL)
PRICING SHEET
CONTRACTOR: _____________________
Contract Term: 24 Months
Fixed Components
24-Month kWh
Est. Contract Peak kWh
237,828,734
Est. Contract Off-Peak kWh
374,329,838
Est. Total kWh
612,158,572
Peak and off-peak hours are based on Commonwealth Edison Company’s (ComEd) definition of Retail Peak Period and Retail Off-Peak Period in its terms and conditions. Retail Peak Period is defined as 9AM to 10PM, Monday through Friday, except on days designated as holidays by the NERC. Retail Off-Peak Period is defined as all hours other than those included in the Retail Peak Period.
A. Fixed Peak Price: _______ cents per kWh
B. Fixed Off-Peak Price: _______ cents per kWh
C. Fixed REC Rate (24 months): _______ cents per kWh
The energy price is to include all PJM ancillary services and ISO related costs not identified in the pass-through components. Argonne understands that ComEd zone Reliability Must Run Charges are currently zero. These costs can be listed as a line item charge if they begin to be assessed after the contract is signed.
Pass-Through Components.
1. Pass-through of PJM transmission costs based on ANL PLC. ANL requests a monthly price based on the following formula:
ANL PLC x Daily Network Transmission Charge x days in the billing period
Monthly invoice price should be pro-rated if transmission rate or ANL PCL changes during a billing period.
2. Pass-through of capacity costs based on ANL PLC. ANL requests a monthly invoice price based on the following formula:
ANL PLC x PJM Capacity Cost x ComEd Scaling Factor x Pool Requirements x Daily Zonal Scaling Factor x Days in the Delivery Period
Monthly invoice price should be pro-rated if PJM price or ANL PCL changes during a billing period.
3. Pass-through of ComEd distribution factor of 0.43%and transmission loss factor of 1.60%*. Current combined loss factor is 2.02%
Separate cost shown for peak and off-peak. Monthly invoice price should be pro-rated if any of the loss rates change during a billing month. The Government is aware that the distribution loss factor changes annually on January 1.
*Argonne expects suppliers to recognize the benefits for the credits obtained for transmission losses, ARR and zonal derates in the Fixed Energy Charge.
4. Illinois Power Agency Alternative Compliance Payment (ACP) Rate for 50% of Renewable Portfolio Standards:
ANL requests a monthly pass-through rate based on the following formula:
Current ACP Rate (kWh) x 50% x ANL Monthly Usage
The other 50% RPS obligation is covered in the fixed REC rate under the fixed price section.
*Argonne is aware that future legislation could modify the current Alternative Compliance Payment method during the January2015 to January 2017 contract period. Argonne will work with selected Contractor in the event a modification is made to the ACP payment.
Summary
LINE ITEM INSTALLATION 12 MONTH CONSUMPTION (kWh) NUMBER OF ACCOUNTS NOTES
0001 Marine Barracks 3,757,332 3
0002 Building 6000, JB Anacostia - Bolling 62,286,510 1
0003 JB Myer-Henderson Hall (Myer) 39,200,000 1 Account is located in Virginia (Dominion)
0004 JB Myer-Henderson Hall (McNair) 24,099,944 3
0005 Walter Reed Army Medical Center 19,120,567 1 6 Month Delivery Period (Dec '14 - Jun '15)
0006 Argonne National Laboratory 306,079,286 1 24 Month Delivery Period (Jan '15 - Jan '17)
0007 DC Naval Research Laboartory 110,731,861 1
0008 US Army Corps of Engineers 8,803,138 17
0009 National Agricultural Library 4,731,320 1
0010 Site 6910 32,455,500 1
0011 National Institutes of Health 19,268,213 6 First Energy account number updated as of Amendment 0001
0012 Fort Detrick - Forest Glen 3,589,632 3
0013 Fort Detrick 3 Account numbers revised as of Amendment 0001. Data will be provided by amendment once received from the utility.
0014 Fort Meade 124,382,927 279 Information updated as of Amendment 0001
0015 VA MD Healthcare 21,673,400 1
0016 Loch Raven 3,545,883 5
0017 MD Naval Research Laboratory 10,246,950 1
0018 Maryland Procurement Office 472,512,050 3
0019 Johns Hopkins Applied Physics Laboratory 5,635,400 1
0020 CSSG 11,925,200 1
0021 DLA Installation Support Columbus 55,279,501 1
0022 Carlisle Barracks 29,562,500 2
0023 DLA Distribution Susquehanna 71,799,803 3 Information updated as of Amendment 0001
0024 Bettis Atomic Power Laboratory 49,878,704 2
0025 Tobyhanna Army Depot 62,690,000 1
0026 Department of Defense 4,194,300 1
TOTAL: 1,557,449,921 343
Note: This sheet is a summary of the historical usage of all installation accounts under this solicitation.
Account specific information can be found under each installation's respective tab.
PJM Large 2014
| Summary Page | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
Marine Barracks
Solicitation Item Number 0001
Marine Barracks
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW) Intern Demand (KW) Off Peak Demand (KW)
1100r 0250391000 PEPCO May-13 100,800 30,000 28,200 42,600 246.0 270.0 228.0
Jun-13 135,600 39,000 36,000 60,600 312.0 318.0 276.0
Svc Address: Will be provided to offerors who submit a technical proposal. Jul-13 171,000 46,800 42,000 82,200 378.0 366.0 318.0
Rate Code: DMGT3 Aug-13 147,000 43,800 40,200 63,000 348.0 330.0 276.0
Sep-13 151,800 40,200 37,200 74,400 348.0 318.0 276.0
Capacity PLC: 324.87 Oct-13 106,800 30,000 27,600 49,200 276.0 270.0 228.0
Tramission PLC: 327.42 Nov-13 91,200 25,800 24,000 41,400 216.0 216.0 198.0
Dec-13 103,200 27,000 25,800 50,400 210.0 228.0 204.0
Jan-14 99,600 25,200 24,600 49,800 216.0 222.0 210.0
Feb-14 95,400 25,200 24,000 46,200 222.0 234.0 222.0
Mar-14 106,800 28,800 28,200 49,800 240.0 240.0 234.0
Apr-14 93,600 27,000 25,800 40,800 228.0 240.0 222.0
Total 1,402,800 388,800 363,600 650,400
Marine Barracks
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW) Intern Demand (KW) Off Peak Demand (KW)
1100s 0251083010 PEPCO May-13 317,823 82,089 76,668 159,066 640.3 620.6 587.3
Jun-13 504,811 205,227 94,357 205,227 661.1 640.3 627.9
Svc Address: Will be provided to offerors who submit a technical proposal. Jul-13 463,303 94,357 106,588 262,358 912.7 627.9 826.1
Rate Code: DMGT1 Aug-13 415,805 99,719 103,941 212,145 744.5 648.4 762.8
Sep-13 582,518 262,358 95,840 224,320 686.6 661.1 655.1
Capacity PLC: 874.44 Oct-13 349,088 106,588 76,384 166,116 534.2 826.1 523.2
Tramission PLC: 886.59 Nov-13 288,208 111,642 53,955 122,611 413.8 922.3 404.8
Dec-13 402,592 212,145 56,128 134,319 403.0 912.7 363.8
This Account currently has 208 kW enrolled in a Demand Response Program Jan-14 288,846 103,941 53,684 131,221 407.0 762.8 389.9
Feb-14 285,349 108,305 52,710 124,334 422.1 762.5 409.0
Mar-14 416,943 224,320 58,122 134,501 411.5 744.5 391.9
Apr-14 264,909 95,840 54,447 114,622 403.0 655.1 404.2
Total 4,580,195 1,706,531 882,824 1,990,840
Marine Barracks
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW) Intern Demand (KW) Off Peak Demand (KW)
1100u 0113631006 PEPCO May-13 0 0 0 0 0.0 0.0 0.0
Jun-13 2,760,000 744,000 687,600 1,328,400 6,408.0 0.0 6,408.0
Svc Address: Will be provided to offerors who submit a technical proposal. Jul-13 600,600 152,400 146,400 301,800 720.0 696.0 696.0
Rate Code: DMGT1 Aug-13 280,800 70,200 67,200 143,400 720.0 696.0 696.0
Sep-13 299,400 75,000 71,400 153,000 768.0 744.0 744.0
Capacity PLC: 671.63 Oct-13 154,800 49,800 50,400 54,600 582.0 606.0 300.0
Tramission PLC: 664.17 Nov-13 138,000 34,200 34,800 69,000 582.0 582.0 582.0
Dec-13 263,400 67,200 60,600 135,600 432.0 444.0 462.0
Jan-14 195,600 46,200 45,600 103,800 426.0 450.0 384.0
Feb-14 186,000 46,200 45,000 94,800 360.0 354.0 366.0
Mar-14 208,800 52,200 49,200 107,400 426.0 444.0 390.0
Apr-14 201,600 52,800 51,600 97,200 426.0 426.0 426.0
Total 5,289,000 1,390,200 1,309,800 2,589,000
| Line Item 0001 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
Building 6000, Bolling AFB
Solicitation Item Number 0002
Building 6000, Bolling AFB
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW) Intern Demand (KW) Off Peak Demand (KW)
1105a 01009-06916 PEPCO Jun-13 5,409,941 1,403,730 1,307,984 2,698,227 9868.3 9826.6 9101.5
Jul-13 6,546,148 1,619,489 1,525,564 3,401,095 10247.8 10370.5 9477.7
Svc Address: Will be provided to offerors who submit a technical proposal. Aug-13 5,151,695 1,383,803 1,293,793 2,474,099 10045.1 10081.1 9316.4
Rate Code: DCHV Sep-13 5,940,485 1,507,067 1,401,163 3,032,255 10128.6 10041.8 9085.0
Oct-13 4,947,763 1,258,815 1,176,677 2,512,271 9109.1 9222.8 8411.8
Capacity PLC: 10084.41 Nov-13 4,777,806 1,209,445 1,147,602 2,420,759 8642.5 8487.4 8200.8
Tramission PLC: 10100.89 Dec-13 5,239,328 1,263,835 1,218,291 2,757,202 8354.5 8326.1 7575.1
Jan-14 5,482,245 1,238,112 1,200,852 3,043,281 8058.6 8024.0 7620.8
This Account currently has 3613 kW enrolled in a Demand Response Program Feb-14 4,487,736 1,104,974 1,054,234 2,328,528 8497.1 8438.0 7833.6
Mar-14 4,840,134 1,284,186 1,225,203 2,330,745 8176.0 8091.7 7686.7
Apr-14 4,533,438 1,194,856 1,126,598 2,211,984 8951.0 8449.2 7952.0
May-14 4,929,791 1,328,505 1,240,207 2,361,079 9630.7 9562.3 8354.5
Total 62,286,510 15,796,817 14,918,168 31,571,525
| Line Item 0002 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
JB Myer-Henderson Hall (Myer)
Solicitation Item Number 0003
JB Myer - Henderson Hall
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
5150a 6086377501 Dominion 04/29/14 2,436,000 1,168,104 1,267,896 1,422
03/28/14 2,240,000 1,112,132 1,127,868 1,260
Svc Address: Will be provided to offerors who submit a technical proposal. 02/27/14 2,324,000 1,126,440 1,197,560 1,228
Rate Code: GS4 01/29/14 2,352,000 1,175,468 1,176,532 1,357
12/30/13 2,688,000 1,295,952 1,392,048 1,487
Capacity PLC: 11/26/13 2,660,000 1,254,148 1,405,852 1,681
Tramission PLC: 10/25/13 2,576,000 1,236,144 1,339,856 2,489
09/26/13 3,136,000 1,308,916 1,827,084 3,039
08/27/13 3,388,000 1,360,996 2,027,004 3,168
07/29/13 4,088,000 1,549,464 2,538,536 3,491
06/27/13 3,332,000 1,398,936 1,933,064 3,136
05/29/13 2,744,000 1,357,188 1,386,812 2,877
04/29/13 2,772,000 1,322,552 1,449,448 2,295
03/28/13 2,464,000 1,217,104 1,246,896 1,907
Total 39,200,000 17,883,544 0 21,316,456
| Line Item 0003 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
JB Myer-Henderson Hall (McNair)
Solicitation Item Number 0004
JB Myer - Henderson Hall
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
1110c 130862717 Pepco 11/13/14 982,453 243,480 221,003 517,970
10/13/14 1,177,704 316,899 282,813 577,992
Svc Address: Will be provided to offerors who submit a technical proposal. 9/13/14 1,127,568 302,335 272,927 552,306
Rate Code: DCHV 8/13/14 1,495,969 379,263 342,482 774,224
7/13/14 1,155,028 322,520 283,215 549,293
Capacity PLC: 2239.79 6/13/14 897,571 250,411 218,501 428,659
Tramission PLC: 2248.28 5/13/14 892,709 236,566 212,125 444,018
4/13/14 842,974 235,058 213,987 393,929
3/13/14 850,050 230,802 205,603 413,645
2/13/14 825,378 213,221 188,981 423,176
1/13/14 952,863 241,596 222,350 488,917
12/12/14 918,400 221,235 204,433 492,732
Total 12,118,667 3,193,386 2,868,420 6,056,861
JB Myer - Henderson Hall (Fort McNair)
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
1110a 108817412 Pepco 11/13/14 389,933 105,696 97,089 187,148
10/13/14 365,756 89,444 82,628 193,684
Svc Address: Will be provided to offerors who submit a technical proposal. 9/13/14 327,996 87,308 79,725 160,963
Rate Code: DCHV 8/13/14 393,439 101,522 93,390 198,527
7/13/14 347,151 95,802 89,297 162,052
Capacity PLC: 829.48 6/13/14 329,735 93,385 85,116 151,234
Tramission PLC: 859.67 5/13/14 382,916 103,741 94,172 185,003
4/13/14 423,580 107,982 99,265 216,333
3/13/14 388,708 106,474 98,849 183,385
2/13/14 419,689 108,414 99,956 211,319
1/13/14 352,650 92,148 85,152 175,350
12/12/14 336,782 90,947 84,131 161,704
Total 4,458,335 1,182,863 1,088,770 2,186,702
JB Myer - Henderson Hall (Fort McNair)
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
1110b 251096012 Pepco 11/13/14 332,223 87,179 84,508 160,536
10/13/14 352,256 82,137 80,374 189,745
Svc Address: Will be provided to offerors who submit a technical proposal. 9/13/14 484,963 126,553 120,343 238,067
Rate Code: DCHV 8/13/14 604,465 152,336 143,509 308,620
7/13/14 531,269 146,369 135,953 248,947
Capacity PLC: 1998.63 6/13/14 571,389 163,939 147,317 260,133
Tramission PLC: 1930.96 5/13/14 728,809 202,199 177,667 348,943
4/13/14 924,809 234,151 210,880 479,778
3/13/14 900,752 252,041 225,129 423,582
2/13/14 937,372 248,376 218,096 470,900
1/13/14 672,041 182,680 163,524 325,837
12/12/14 482,594 127,827 117,565 237,202
Total 7,522,942 2,005,787 1,824,865 3,692,290
| Line Item 0004 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
Walter Reed Army Medical Center
Solicitation Item Number 0005
Walter Reed Army Medical Center
Delivery Period: meter read in December 2014 through meter read in June 2015
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW) Intern Demand (KW) Off Peak Demand (KW)
1115c 0130806227 Pepco Jun-13 1,804,081 386,592 397,041 1,020,448 2408.1 2472.3 2508.5
Jul-13 1,636,243 386,942 397,386 851,915 2408.1 2472.3 2508.2
Svc Address: Will be provided to offerors who submit a technical proposal. Aug-13 2,278,018 536,718 533,089 1,208,211 3852.2 3864.1 3749.9
Rate Code: DCHV Sep-13 2,399,250 544,637 544,054 1,310,559 3852.2 3864.2 3750.0
Oct-13 2,320,513 549,737 548,849 1,221,927 3599.2 3793.2 3637.9
Capacity PLC: 94.82 Nov-13 1,781,904 405,536 408,597 967,771 2945.3 2919.8 2922.0
Tramission PLC: 103.86 Dec-13 1,443,620 305,801 310,961 826,858 2387.9 2377.0 2401.8
Jan-14 1,497,389 323,854 328,395 845,140 2008.2 2004.7 2037.0
Feb-14 1,171,235 252,789 256,682 661,764 1825.3 1820.1 1836.2
Mar-14 1,175,833 266,486 272,216 637,131 1834.6 1850.1 1836.9
Apr-14 930,931 221,480 230,578 478,873 1748.0 1750.8 1779.8
May-14 681,550 146,429 155,130 379,991 1199.5 1102.1 1184.0
Total 19,120,567 4,327,001 4,382,978 10,410,588 1,200 1,102 1,184
| Line Item 0005 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
Argonne National Laboratory
Solicitation Item Number 0006
Argonne National Laboratory
Delivery Period: meter read in January 2015 through meter read in January 2017
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW) Intern Demand (KW) Off Peak Demand (KW)
1705a 0556224009 ComEd 25-Apr-14 24,392,180 9,650,089 14,742,091 39002.72
27-Mar-14 25,512,017 10,169,700 15,342,317 40517.28
Svc Address: Will be provided to offerors who submit a technical proposal. 26-Feb-14 25,946,140 10,270,026 15,676,114 40479.36
Rate Code: R67 28-Jan-14 23,915,377 8,921,895 14,993,482 40973.6
26-Dec-13 25,499,199 9,588,560 15,910,639 40445.28
Capacity PLC: 45811.3289 25-Nov-13 28,887,884 11,025,895 17,861,989 40683.36
Tramission PLC: 40084.8088 23-Oct-13 24,661,183 9,635,643 15,025,540 45468.96
26-Sep-13 22,163,068 8,841,835 13,321,233 43454.56
27-Aug-13 28,877,537 11,300,676 17,576,861 45150.72
25-Jul-13 28,417,046 11,070,636 17,346,410 47584.48
25-Jun-13 28,529,736 10,451,190 18,078,546 44773.44
24-May-13 19,277,919 7,988,222 11,289,697 39415.68
Total 306,079,286 118,914,367 187,164,919
| Line Item 0006 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
DC Naval Research Laboratory
Solicitation Item Number 0007
DC Naval Research Laboratory
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW) Intern Demand (KW) Off Peak Demand (KW)
1120a 0251105011 PEPCO 5/1/13 9,098,058 2,395,797 2,280,668 4,421,593 16,804.80 16,234.60 14,970.20
6/1/13 10,711,539 2,710,958 2,577,568 5,423,013 18,086.40 18,028.80 16,634.90
Svc Address: Will be provided to offerors who submit a technical proposal. 7/1/13 13,172,180 3,201,540 3,062,048 6,908,592 19,748.20 19,252.80 17,424.00
Rate Code: DCHV 8/1/13 9,759,329 2,445,517 2,347,691 4,966,121 18,555.80 18,544.30 16,853.80
9/1/13 12,064,824 2,890,610 2,758,428 6,415,786 19,526.40 19,103.00 16,911.40
Capacity PLC: 19649.95 10/1/13 9,554,629 2,355,526 2,244,721 4,954,382 17,481.60 17,282.90 15,678.70
Tramission PLC: 19609.1 11/1/13 8,973,773 2,201,894 2,117,547 4,654,332 15,785.30 15,537.60 14,863.70
12/1/13 9,981,041 2,340,109 2,271,352 5,369,580 15,027.80 14,699.50 14,400.00
1/1/14 9,419,268 2,177,855 2,131,466 5,109,947 14,590.10 14,716.80 13,760.60
2/1/14 9,306,512 2,126,320 2,066,414 5,113,778 14,497.90 14,480.60 13,311.40
3/1/14 8,690,708 2,211,559 2,152,296 4,326,853 14,250.20 14,207.00 13,230.70
4/1/14 0 0 0 0 0.00 0.00 0.00
Total 110,731,861 27,057,685 26,010,199 57,663,977
| Line Item 0007 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
USACE
Solicitation Item Number 0008
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403aa Will be provided to offerors who submit a technical proposal. BG&E 03/13/14 400,600 97,561 73,095 229,944 815
02/13/14 420,100 112,635 81,085 226,380 825
Svc Address: Will be provided to offerors who submit a technical proposal. 01/15/14 385,700 108,429 79,232 198,039 953
Rate Code: Interval GL 12/13/13 348,400 106,733 79,904 161,763 892
11/13/13 346,200 105,486 84,775 155,939 808
Capacity PLC: 1057.782226 6/1/14 10/15/13 179,206 51,145 40,755 87,306 819
Tramission PLC: 1032.690313 1/1/14 09/30/13 199,294 80,289 39,959 79,046 0
09/16/13 484,700 180,609 89,599 214,492 1,077
08/14/13 435,000 175,575 86,888 172,537 1,075
07/16/13 474,200 173,532 86,567 214,101 1,047
06/14/13 184,322 71,286 35,938 77,098 972
05/31/13 251,778 77,369 63,155 111,254 0
05/14/13 392,100 115,745 93,797 182,558 825
04/12/13 351,200 102,537 80,132 168,531 867
Total 4,852,800 1,558,931 1,014,881 2,278,988
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403ac Will be provided to offerors who submit a technical proposal. BG&E 03/13/14 3,612,000 821,505 613,758 2,176,737 5,778
02/13/14 3,790,500 920,940 685,150 2,184,410 5,947
Svc Address: Will be provided to offerors who submit a technical proposal. 01/15/14 4,329,500 924,272 688,911 2,716,317 6,030
Rate Code: Interval P 34KV 12/13/13 3,955,000 925,923 692,122 2,336,955 5,824
11/13/13 3,699,500 915,427 690,287 2,093,786 5,710
Capacity PLC: 5947.037972 6/1/14 10/15/13 1,845,346 439,484 329,883 1,075,979 5,849
Tramission PLC: 6090.943115 1/1/14 09/30/13 1,983,654 611,636 365,728 1,006,290 -
09/16/13 4,396,000 1,235,525 737,169 2,423,306 5,925
08/14/13 3,902,500 1,195,119 711,707 1,995,674 6,056
07/16/13 4,315,500 1,193,412 710,102 2,411,986 5,990
06/14/13 1,761,433 513,088 304,923 943,422 5,950
05/31/13 2,379,067 579,131 438,507 1,361,429 -
05/14/13 4,158,000 960,812 726,937 2,470,251 5,930
04/12/13 3,748,500 865,123 652,774 2,230,603 5,872
Total 47,876,500 12,101,397 8,347,958 27,427,145
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403ad Will be provided to offerors who submit a technical proposal. BG&E 03/13/14 46,213 12,400 9,921 23,892 165
02/13/14 51,260 13,575 9,687 27,998 165
Svc Address: Will be provided to offerors who submit a technical proposal. 01/15/14 55,472 13,455 10,233 31,784 158
Rate Code: 12/13/13 49,024 12,763 10,275 25,986 162
11/13/13 45,404 13,346 10,768 21,290 153
Capacity PLC: 105.582157 6/1/14 10/15/13 22,763 7,344 5,083 10,336 140
Tramission PLC: 104.691702 1/1/14 09/30/13 23,092 8,750 4,215 10,127 -
09/16/13 62,782 19,738 10,826 32,218 128
08/14/13 58,686 19,647 10,684 28,355 129
07/16/13 65,345 20,398 10,880 34,067 125
06/14/13 28,380 9,046 4,975 14,359 119
05/31/13 29,839 8,368 6,896 14,575 -
05/14/13 43,806 12,600 10,247 20,959 134
04/15/13 49,500 13,300 10,500 25,700 155
Total 631,566 184,730 125,190 321,646
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403ae Will be provided to offerors who submit a technical proposal. BG&E 03/12/14 133,800 30,400 23,500 79,900 240
02/12/14 148,900 36,600 27,400 84,900 257
Svc Address: Will be provided to offerors who submit a technical proposal. 01/13/14 157,200 33,800 25,700 97,700 260
Rate Code: GL 12/11/14 137,800 31,800 24,600 81,400 252
11/11/13 130,300 32,300 27,200 70,800 252
Capacity PLC: 256.865521 6/1/14 10/14/13 64,500 15,400 12,600 36,500 329
Tramission PLC: 254.705817 1/1/14 09/30/13 92,400 31,700 15,600 45,100 -
09/11/13 129,200 44,600 22,300 62,300 282
08/13/13 146,800 51,600 25,100 70,100 312
07/12/13 137,700 48,400 23,600 65,700 309
06/12/13 48,200 14,500 7,700 26,000 283
05/31/13 92,300 23,000 20,700 48,600 -
05/10/13 123,700 31,900 28,100 63,700 266
04/10/13 123,100 29,500 24,300 69,300 245
Total 1,665,900 455,500 308,400 902,000
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403af Will be provided to offerors who submit a technical proposal. BG&E 06/13/14 42,149 13,807 8,009 20,333 192
05/31/14 61,651 14,011 10,962 36,678 -
Svc Address: Will be provided to offerors who submit a technical proposal. 05/14/14 101,100 24,036 18,800 58,264 191
Rate Code: INTERVAL GL 04/14/14 111,600 26,407 20,180 65,013 181
03/13/14 90,300 20,885 16,100 53,315 182
Capacity PLC: 175.712464 6/1/14 02/13/14 91,500 22,529 17,285 51,686 168
Tramission PLC: 173.638999 1/1/14 01/15/14 102,600 22,469 17,158 62,973 174
12/13/13 95,400 22,753 17,413 55,234 173
11/13/13 93,600 23,043 17,876 52,681 182
10/15/13 45,340 10,882 8,452 26,006 178
09/30/13 48,860 15,793 8,989 24,078 -
09/16/13 111,600 33,233 18,722 59,645 199
08/14/13 98,700 31,774 18,000 48,926 204
07/16/13 106,800 31,032 17,609 58,159 197
Total 1,201,200 312,654 215,555 672,991
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403ag Will be provided to offerors who submit a technical proposal. BG&E 03/13/14 509,700 116,258 86,457 306,985 950
02/13/14 556,200 136,940 99,445 319,815 1,003
Svc Address: Will be provided to offerors who submit a technical proposal. 01/15/14 596,400 129,148 94,894 372,358 1,019
Rate Code: Interval GL 12/13/13 546,600 128,420 96,015 322,165 909
11/13/13 500,700 121,948 93,990 284,762 850
Capacity PLC: 978.267477 6/1/14 10/15/13 252,127 60,050 46,106 145,971 862
Tramission PLC: 974.712825 1/1/14 09/30/13 263,573 83,790 47,910 131,873 -
09/16/13 617,400 182,447 103,891 331,062 966
08/14/13 559,800 178,207 102,132 279,461 993
07/16/13 621,300 179,611 102,755 338,934 955
06/14/13 243,310 73,801 42,202 127,307 938
05/31/13 328,490 82,933 64,565 180,992 -
05/14/13 555,000 129,094 100,908 324,998 851
04/12/13 523,200 122,679 92,989 307,532 870
Total 6,673,800 1,725,326 1,174,259 3,774,215
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403ah Will be provided to offerors who submit a technical proposal. BG&E 03/13/14 19,368 4,805 2,604 11,959 54
02/13/14 25,093 6,303 3,726 15,064 61
Svc Address: Will be provided to offerors who submit a technical proposal. 01/15/14 23,327 5,185 2,978 15,164 55
Rate Code: GL 12/13/13 18,898 4,474 2,363 12,061 54
11/13/13 12,620 3,159 1,452 8,009 41
Capacity PLC: 17.490456 6/1/14 10/15/13 5,438 1,334 741 3,363 32
Tramission PLC: 17.340668 1/1/14 09/30/13 4,605 1,046 923 2,636 -
9*16/13 11,408 2,810 2,034 6,564 27
08/14/13 10,440 2,654 1,998 5,788 27
07/16/13 10,582 2,487 1,804 6,291 24
06/14/13 4,437 1,075 779 2,583 25
05/31/13 5,689 1,158 787 3,744 -
05/14/13 11,770 2,506 1,330 7,934 55
04/12/13 12,800 2,500 1,500 8,800 55
03/14/13 21,100 5,200 2,800 13,100 52
Total 197,575 46,696 27,819 123,060
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403ai Will be provided to offerors who submit a technical proposal. BG&E 03/06/14 178,300 43,100 33,800 101,400 380
02/06/14 193,300 47,500 37,200 108,600 352
Svc Address: Will be provided to offerors who submit a technical proposal. 01/07/14 193,700 41,200 32,400 120,100 393
Rate Code: GL 12/06/13 182,300 44,100 36,100 102,100 340
11/05/13 158,500 40,100 33,600 84,800 329
Capacity PLC: 320.258614 6/1/14 10/08/13 49,700 12,700 9,900 27,100 390
Tramission PLC: 317.565907 1/1/14 09/30/13 159,800 54,900 27,500 77,400 0
09/05/13 187,000 63,100 32,600 91,300 382
08/07/13 189,900 66,400 34,200 89,300 389
07/08/13 118,800 45,700 18,100 55,000 330
06/07/13 26,800 10,300 4,100 12,400 533
05/31/13 189,800 49,100 40,900 99,800 0
05/06/13 135,700 32,900 28,400 74,400 271
4/4/13 120,600 30,100 24,600 65,900 264
Total 2,084,200 581,200 393,400 1,109,600
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403aj Will be provided to offerors who submit a technical proposal. BG&E 06/13/14 110,921 37,831 21,645 51,445 487
05/31/14 150,979 38,032 30,174 82,773 -
Svc Address: Will be provided to offerors who submit a technical proposal. 05/14/14 245,700 60,255 48,410 137,035 461
Rate Code: INTERVAL GL 04/13/14 256,278 61,532 47,053 147,693 436
03/13/14 222,597 52,845 39,311 130,441 480
Capacity PLC: 502.055322 6/1/14 02/13/14 228,267 58,025 40,905 129,337 514
Tramission PLC: 493.654554 1/1/14 01/15/14 258,900 25,774 18,445 214,681 602
12/13/13 240,000 57,741 43,318 138,941 454
11/13/13 236,700 42,935 35,080 158,685 443
10/15/13 117,764 29,235 22,185 66,344 447
09/30/13 126,436 43,380 23,250 59,806 -
09/16/13 286,800 90,003 49,093 147,704 500
08/14/13 254,700 86,572 46,604 121,524 512
07/16/13 270,300 85,250 45,680 139,370 499
Total 3,006,342 769,410 511,153 1,725,779
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403ak Will be provided to offerors who submit a technical proposal. BG&E 03/13/14 117,052 27,725 20,950 68,377 194
02/13/14 122,543 28,477 21,321 72,745 195
Svc Address: Will be provided to offerors who submit a technical proposal. 01/15/14 127,632 26,014 19,597 82,021 190
Rate Code: GL 12/13/13 110,687 24,665 18,408 67,614 197
11/13/13 110,630 26,810 20,292 63,528 203
Capacity PLC: 164.996717 6/1/14 10/15/13 66,227 15,798 11,986 38,443 203
Tramission PLC: 163.596472 1/1/14 09/30/13 57,152 16,215 10,220 30,717 -
09/16/13 143,362 40,217 23,895 79,250 203
08/14/13 124,613 37,592 22,362 64,659 205
07/16/13 132,473 36,012 21,552 74,909 188
06/14/13 55,552 16,335 9,316 29,901 195
05/31/13 66,491 16,347 11,564 38,580 -
05/14/13 108,345 26,852 20,465 61,028 183
04/15/13 119,700 26,100 20,400 73,200 195
Total 1,462,459 365,159 252,328 844,972
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403al Will be provided to offerors who submit a technical proposal. BG&E 03/13/14 61,934 16,572 13,492 31,870 162
02/13/14 70,505 18,856 14,483 37,166 168
Svc Address: Will be provided to offerors who submit a technical proposal. 01/15/14 77,930 19,095 15,227 43,608 182
Rate Code: GL 12/13/13 70,409 18,117 15,276 37,016 162
11/13/13 61,491 16,722 15,309 29,460 154
Capacity PLC: 153.707257 6/1/14 10/15/13 29,152 8,790 6,777 13,585 200
Tramission PLC: 152.421042 1/1/14 09/30/13 30,431 12,891 6,064 11,476 0
09/16/13 71,090 30,287 13,036 27,767 204
08/14/13 66,411 30,002 12,739 23,670 197
07/16/13 71,906 30,545 12,927 28,434 194
06/14/13 31,183 12,410 5,706 13,067 206
05/31/13 35,902 10,140 10,079 15,683 0
05/14/13 59,158 16,781 15,869 26,508 149
04/15/13 69,800 17,100 15,100 37,600 161
Total 807,302 258,308 172,084 376,910
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403d Will be provided to offerors who submit a technical proposal. BG&E 03/06/14 257,400 62,323 49,812 145,265 474
02/06/14 287,100 73,572 57,647 155,881 469
Svc Address: Will be provided to offerors who submit a technical proposal. 01/07/14 303,000 66,097 51,771 185,132 470
Rate Code: Interval GL 12/06/13 288,900 70,526 56,098 162,276 501
11/06/13 292,500 74,318 60,482 157,700 514
Capacity PLC: 628.131048 6/1/14 10/07/13 39,796 8,838 6,953 24,005 591
Tramission PLC: 626.658891 1/1/14 09/30/13 262,604 84,008 44,482 134,114 -
09/06/13 340,500 113,083 60,559 166,858 572
08/06/13 328,800 111,891 59,910 156,999 620
07/08/13 346,500 105,355 56,307 184,838 603
06/07/13 66,695 20,529 11,017 35,149 603
05/31/13 275,305 71,323 58,939 145,043 -
05/06/13 313,500 76,684 63,465 173,351 569
04/04/13 269,100 64,601 52,147 152,352 474
Total 3,671,700 1,003,148 689,589 1,978,963
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403r Will be provided to offerors who submit a technical proposal. BG&E 03/13/14 66,800 17,274 11,780 37,746 164
02/13/14 78,500 21,225 13,929 43,346 191
Svc Address: Will be provided to offerors who submit a technical proposal. 01/15/14 78,800 9,016 6,363 63,421 179
Rate Code: Interval GL 12/13/13 69,300 17,910 13,230 38,160 150
11/13/13 55,000 10,621 9,338 35,041 129
Capacity PLC: 155.489651 6/1/14 10/15/13 22,160 6,088 5,090 10,982 164
Tramission PLC: 151.816104 1/1/14 09/30/13 26,340 11,397 4,975 9,968 -
09/16/13 61,600 25,003 10,452 26,145 168
08/14/13 56,500 24,543 10,387 21,570 172
07/16/13 60,200 24,275 10,549 25,376 178
06/14/13 23,242 9,869 4,340 9,033 161
05/31/13 39,058 10,950 9,409 18,699 -
05/14/13 75,700 18,295 14,571 42,834 141
04/12/13 62,300 16,581 12,608 33,111 253
Total 775,500 223,047 137,021 415,432
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Demand (KW)
2403v Will be provided to offerors who submit a technical proposal. BG&E 03/04/14 4,120,200 934,579 698,015 2,487,606 6,586
02/04/14 4,678,800 1,080,611 802,283 2,795,906 6,505
Svc Address: Will be provided to offerors who submit a technical proposal. 01/03/14 4,376,400 975,945 724,338 2,676,117 6,381
Rate Code: Interval P 13KV 12/04/13 4,431,000 1,037,937 775,971 2,617,092 6,568
11/04/13 4,825,800 1,107,621 826,327 2,891,852 6,898
Capacity PLC: 6892.467354 6/1/14 10/03/13 314,237 104,056 78,443 131,738 6,747
Tramission PLC: 7066.802383 1/1/14 09/30/13 4,062,163 1,198,158 717,210 2,146,795 -
09/04/13 5,119,800 1,429,794 856,948 2,833,058 7,073
08/02/13 4,779,600 1,395,338 839,470 2,544,792 7,112
07/03/13 4,397,400 1,299,870 783,777 2,313,753 7,134
06/05/13 633,636 130,040 78,312 425,284 6,940
05/31/13 4,523,964 1,061,289 796,574 2,666,101 -
05/02/13 4,611,600 1,129,563 833,141 2,648,896 6,982
04/02/13 4,380,600 1,008,238 749,442 2,622,920 6,774
Total 55,255,200 13,893,039 9,560,251 31,801,910
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403z Will be provided to offerors who submit a technical proposal. BG&E 02/25/14 353,100 83,383 67,080 202,637 649
01/28/14 410,100 95,652 76,130 238,318 671
Svc Address: Will be provided to offerors who submit a technical proposal. 12/26/13 398,100 93,993 75,009 229,098 670
Rate Code: Interval GL 11/25/13 374,400 93,117 76,555 204,728 709
10/28/13 371,432 90,644 75,373 205,415 766
Capacity PLC: 841.393539 6/1/14 09/30/13 80,668 25,344 13,956 41,368 -
Tramission PLC: 823.566999 1/1/14 09/25/13 412,800 133,301 72,237 207,262 822
08/27/13 455,100 147,679 80,488 226,933 784
07/26/13 465,300 155,181 83,558 226,561 832
06/25/13 327,584 101,580 55,379 170,625 786
05/31/13 57,616 19,686 16,733 21,197 -
05/28/13 437,100 104,583 87,141 245,376 770
04/24/13 359,700 87,068 72,739 199,893 731
03/26/13 344,100 86,640 69,976 187,484 600
Total 4,847,100 1,317,851 922,354 2,606,895
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403am Will be provided to offerors who submit a technical proposal. BG&E 04/24/14 329,400 80,168 63,648 185,584 629
03/25/14 309,900 76,670 60,112 173,118 586
Svc Address: Will be provided to offerors who submit a technical proposal. 02/25/14 311,700 73,469 58,219 180,012 599
Rate Code: Interval GL 01/28/14 354,300 81,880 63,210 209,210 556
12/26/13 340,500 81,994 63,140 195,366 573
Capacity PLC: 703.353976 6/1/14 11/25/13 303,300 76,032 60,209 167,059 612
Tramission PLC: 699.076307 1/1/14 10/28/13 302,021 74,283 57,859 169,879 627
09/30/13 64,879 20,358 11,246 33,275 -
09/25/13 337,200 110,932 58,466 167,802 823
08/27/13 386,400 130,018 68,039 188,343 703
07/26/13 402,900 135,290 73,228 194,382 700
06/25/13 286,935 90,601 48,647 147,687 729
05/31/13 51,765 17,926 15,731 18,108 -
05/28/13 375,600 90,267 74,450 210,883 726
Total 4,156,800 1,139,888 776,204 2,240,708
United States Army Corps of Engineers
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2403an Will be provided to offerors who submit a technical proposal. BG&E 04/21/14 871,500 199,397 152,029 520,074 1,611
03/20/14 822,150 207,825 150,034 464,291 1,743
Svc Address: Will be provided to offerors who submit a technical proposal. 02/20/14 894,600 211,437 150,357 532,806 1,794
Rate Code: Interval P 13KV 01/23/14 1,047,900 237,415 169,482 641,003 1,758
12/20/13 918,750 222,586 161,379 534,785 1,659
Capacity PLC: 1516.727911 6/1/14 11/20/13 778,050 200,804 151,765 425,481 1,510
Tramission PLC: 1517.442698 1/1/14 10/22/13 520,636 130,676 103,450 286,510 1,500
09/30/13 247,964 69,867 39,249 138,848 -
09/21/13 861,000 287,914 157,406 415,680 1,631
08/21/13 799,050 275,049 149,787 374,214 1,534
07/23/13 922,950 293,156 157,740 472,054 1,712
06/21/13 596,751 192,297 107,517 296,937 1,600
05/31/13 294,699 75,434 60,384 158,881 -
05/22/13 911,400 226,332 182,033 503,035 1,514
Total 10,487,400 2,830,189 1,892,612 5,764,599
| Line Item 0008 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
National Agricultural Library
Solicitation Item Number 0009
MD National Agricultural Library
Delivery Period: meter read in December 2014 through meter read in December 2016 Meter Read Date Total On Peak Interm Peak Off Peak On Peak Demand Interm Peak Demand Off Peak Demand
Line Item Account Utility kWh kWh kWh kWh
2404a 5000 1620 07 PEPCO Jun-13 453,354 114,757 106,705 231,892 878.4 858.5 885.3
Jul-13 488,582 127,192 116,873 244,517 1031.9 1014.1 939.2
Svc Address: Will be provided to offerors who submit a technical proposal. Aug-13 517,609 130,024 120,087 267,498 1032.3 1027.3 921.3
Rate Code: Interval GT Sep-13 454,153 117,721 109,224 227,208 1000.1 818.0 740.9
Oct-13 437,143 117,150 110,312 209,681 967.9 873.8 761.4
Capacity PLC: 1285.37 Nov-13 389,060 89,480 85,938 213,642 731.3 693.2 661.7
Tramission PLC: 1285.22 Dec-13 342,034 85,819 81,582 174,633 708.9 717.6 628.2
Jan-14 374,311 87,231 84,271 202,809 694.8 697.8 641.9
Feb-14 315,015 79,673 75,670 159,672 667.1 575.8 573.7
Mar-14 295,774 73,622 70,262 151,890 692.0 696.2 507.0
Apr-14 350,895 90,744 85,249 174,902 754.8 674.8 553.1
May-14 313,390 82,107 78,279 153,004 728.4 697.6 636.6
Total 4,731,320 1,195,520 1,124,452 2,411,348
| Line Item 0009 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
Site 6910
Solicitation Item Number 0010
Site 6910
Delivery Period: meter read in December 2014 through meter read in December 2016
Line Item Account Supplier Choice ID Utility Meter Read Date Total kWh Usage kWh On Peak kWh Intern Peak kWh Off Peak Peak Demand (KW)
2406a Will be provided to offerors who submit a technical proposal. BG&E 03/20/14 2,394,000 610,230 479,357 1,304,413 4,473
02/20/14 2,366,000 572,859 445,901 1,347,240 4,443
Svc Address: Will be provided to offerors who submit a technical proposal. 01/23/14 2,845,500 654,116 506,631 1,684,753 4,385
Rate Code: Interval P 34KV 12/20/13 2,492,000 621,878 485,713 1,384,409 4,488
11/20/13 2,464,000 629,645 503,836 1,330,519 4,508
Capacity PLC: 5259.201041 6/1/14 10/22/13 1,883,582 475,173 384,057 1,024,352 4,816
Tramission PLC: 5414.610446 1/1/14 09/30/13 870,918 246,625 134,314 489,979 -
09/21/13 2,964,500 983,252 532,481 1,448,767 5,867
08/21/13 2,796,500 944,080 516,104 1,336,316 5,615
07/23/13 3,195,500 1,013,833 536,961 1,644,706 6,056
06/21/13 1,910,504 623,102 337,088 950,314 5,617
05/31/13 938,496 241,711 194,827 501,958 -
05/22/13 2,898,000 724,154 588,714 1,585,132 4,896
04/19/13 2,436,000 606,849 493,888 1,335,263 5,035
Total 32,455,500 8,947,507 6,139,872 17,368,121
| Line Item 0010 | Installation Data Sheet |
| SPE600-14-R-0410 | &P of &N |
NIH
Solicitation Item Number 0011
National Institute of Health
Delivery Period: meter read in December 2014 through meter read in December 2016 Meter Read Date Total On Peak Interm Peak Off Peak On Peak Demand Interm Peak Demand Off Peak Demand
Line Item Account Utility kWh kWh kWh kWh
2410q 2009385259 PEPCO May-13 205,144 56,224 48,967 99,953 569.6 546.2 470.3
Jun-13 266,615 77,154 58,420 131,041 677.6 689.7 641.0
Svc Address: Will be provided to offerors who submit a technical proposal. Jul-13 332,073 85,236 69,272 177,565 735.1 718.8 689.4
Rate Code: 2A6 Aug-13 252,606 74,462 57,568 120,576 629.4 642.9 623.2
Sep-13 280,589 73,110 59,391 148,088 646.4 617.8 634.4
Capacity PLC: 742.04 Oct-13 120,217 29,706 28,069 62,442 363.3 361.9 380.9
Tramission PLC: 736.05 Nov-13 137,436 27,600 33,265 76,571 349.6 380.9 511.2
Dec-13 130,156 30,523 31,290 68,343 267.1 253.2 249.0
Jan-14 127,527 27,216 28,690 71,621 243.5 253.2 267.1
Feb-14 104,241 23,282 25,173 55,786 243.5 253.2 267.1
Mar-14 141,268 30,624 32,311 78,333 222.6 232.1 228.3
Apr-14 0 0 0 0 0.0 0.0 0.0
Total 2,097,872 535,137 472,416 1,090,319
National Institute of Health
Delivery Period: meter read in December 2014 through meter read in December 2016 Meter Read Date Total On Peak Interm Peak Off Peak On Peak Demand Interm Peak Demand Off Peak Demand
Line Item Account Utility kWh kWh kWh kWh
2410r 2009385333 PEPCO May-13 261,669 85,241 65,176 111,252 694.4 693.6 576.5
Jun-13 271,646 79,235 64,635 127,776 759.6 731.7 545.0
Svc Address: Will be provided to offerors who submit a technical proposal. Jul-13 368,396 95,829 82,471 190,096 707.2 702.4 688.4
Rate Code: 2A6 Aug-13 258,875 72,438 60,776 125,661 593.5 582.0 590.5
Sep-13 295,782 77,446 64,359 153,977 628.9 622.2 577.8
Capacity PLC: 741.86 Oct-13 100,029 23,755 22,833 53,441 300.2 294.9 308.7
Tramission PLC: 732.13 Nov-13 89,140 21,189 21,369 46,582 226.4 226.6 223.2
Dec-13 105,394 23,426 23,920 58,048 187.3 187.7 189.6
Jan-14 92,683 20,014 20,737 51,932 141.9 143.9 146.0
Feb-14 99,343 22,020 22,504 54,819 218.9 248.2 240.0
Mar-14 94,554 21,213 21,713 51,628 167.2 169.0 169.0
Apr-14 74,411 17,215 18,224 38,972 162.5 163.2 163.0
Total 2,111,922 559,021 488,717 1,064,184
National Institute of Health
Delivery Period: meter read in December 2014 through meter read in December 2016 Meter Read Date Total On Peak Interm Peak Off Peak On Peak Demand Interm Peak Demand Off Peak Demand
Line Item Account Utility kWh kWh kWh kWh
2410w 2024 2092 11 PEPCO May-13 168,371 57,821 44,875 65,675 555.1 562.5 624.3
Jun-13 149,330 50,277 38,692 60,361 417.1 437.1 399.5
Svc Address: Will be provided to offerors who submit a technical proposal. Jul-13 160,094 53,032 40,175 66,887 557.9 543.6 491.8
Rate Code: 2A6 Aug-13 144,336 50,687 39,264 54,385 562.2 604.9 570.5
Sep-13 163,741 55,024 41,118 67,599 510.3 445.7 486.0
Capacity PLC: 406.3 Oct-13 168,242 56,495 41,587 70,160 532.8 579.5 579.9
Tramission PLC: 406.43 Nov-13 172,748 49,418 43,441 79,889 579.9 607.0 618.3
Dec-13 279,996 85,346 67,562 127,088 619.4 675.3 679.5
Jan-14 284,329 69,301 64,508 150,520 679.5 659.0 631.8
Feb-14 226,597 59,413 54,668 112,516 679.5 658.5 629.2
Mar-14 342,752 89,833 87,171 165,748 663.1 697.3 721.9
Apr-14 0 0 0 0 0.0 0.0 0.0
Total 2,260,536 676,647 563,061 1,020,828
National Institute of Health
Delivery Period: meter read in December 2014 through meter read in December 2016 Meter Read Date Total On Peak Interm Peak Off Peak On Peak Demand Interm Peak Demand Off Peak Demand
Line Item Account Utility kWh kWh kWh kWh
2410x 2018394110 PEPCO May-13 251,821 72,377 65,125 114,319 584.3 576.2 552.5
Jun-13 369,806 89,685 80,268 199,853 700.9 683.6 682.6
Svc Address: Will be provided to offerors who submit a technical proposal. Jul-13 432,386 103,558 96,045 232,783 729.8 722.9 720.4
Rate Code: MMGTL Aug-13 437,064 108,820 102,935 225,309 838.6 786.6 767.2
Sep-13 372,690 94,932 88,585 189,173 718.9 719.9 700.0
Capacity PLC: 406.3 Oct-13 275,885 64,903 61,079 149,903 630.4 569.6 629.3
Tramission PLC: 406.43 Nov-13 257,725 61,017 59,598 137,110 484.7 478.4 488.5
Dec-13 292,827 65,113 64,970 162,744 453.7 456.5 474.4
Jan-14 249,604 54,573 54,941 140,090 394.9 454.6 476.2
Feb-14 242,616 50,622 50,718 141,276 358.4 356.0 388.3
Mar-14 193,313 47,013 47,913 98,387 355.0 338.9 334.4
Apr-14 182,291 42,001 43,034 97,256 414.7 310.9 353.2
Total 3,558,028 854,614 815,211 1,888,203
National Institute of Health
Delivery Period: meter read in December 2014 through meter read in December 2016 Meter Read Date Total On Peak Interm Peak Off Peak On Peak Demand Interm Peak Demand Off Peak Demand
Line Item Account Utility kWh kWh kWh kWh
2410y 2011268857 PEPCO May-13 99,941 28,345 26,372 45,224 195.0 193.0 155.5
Jun-13 100,816 25,261 23,682 51,873 190.7 189.2 156.7
Svc Address: Will be provided to offerors who submit a technical proposal. Jul-13 97,632 26,501 24,613 46,518 189.0 193.4 152.6
Rate Code: MMGTL Aug-13 108,062 29,294 26,975 51,793 190.5 188.5 151.6
Sep-13 90,439 24,847 23,101 42,491 183.5 183.3 150.5
Capacity PLC: 177.82 Oct-13 64,135 16,669 15,647 31,819 143.0 139.4 111.3
Tramission PLC: 175.63 Nov-13 65,164 17,370 15,955 31,839 138.2 138.1 113.4
Dec-13 77,855 20,527 18,759 38,569 141.3 143.1 114.9
Jan-14 64,135 16,680 15,223 32,232 133.3 131.5 110.8
Feb-14 32,789 7,941 7,697 17,151 102.3 105.8 88.3
Mar-14 27,624 6,550 6,394 14,680 60.3 57.1 47.9
Apr-14 21,505 4,979 5,119 11,407 51.6 46.3 59.6
Total 850,097 224,964 209,537 415,596
National Institute of Health
Delivery Period: meter read in December 2014 through meter read in December 2016 Meter Read Date Total On Peak Interm Peak Off Peak On Peak Demand Interm Peak Demand Off Peak Demand
Line Item Account Utility kWh kWh kWh kWh
2410z 11 00 84 6290…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .