(11)_Attachment_K_Project_Specifications.pdf
PDF 3 MB Posted
- Attached to
- Replace Site Primary Electrical Pathway, DLA Distribution Susquehanna, PA Federal contract opportunity
- Solicitation number
- SP3300-15-B-0003
- Issued by
- Defense Logistics Agency Distribution
About this file
Attachment K
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0003_23_July_2015.pdf | ||
| Amendment_0002.pdf | ||
| Site_Visit_Attendance_Sheet.pdf | ||
| Site_Visit_Notes.docx | DOCX document | |
| Amendment_0001.pdf | ||
| (5)_Attachment_E_Deliv_Notification_Form.docm | DOCM document | |
| SB3300-15-B-0003.pdf | ||
| (2)_Attachment_B_Short_Form_Badge_Request.pdf | ||
| (7)_Attachment_G_SF24_-_Bid_Bond.pdf | ||
| (1)_Attachment_A_New_Personnel_Notification_Form.docm | DOCM document | |
| (10)_Attachment_J_Wage_Determinations.pdf | ||
| (13)_Attachment_M_Submittal_Registers.pdf | ||
| (3)_Attachment_C_Long_Form_Badge_Request.pdf | ||
| (9)_Attachment_I_SF25A_(Payment_Bond).pdf | ||
| (12)_Attachment_L_Drawings.pdf | ||
| (4)_Attachment_D_Badge_Renewal.doc | DOC document | |
| (8)_Attachment_H_SF25_(Performance_Bond).pdf | ||
| (6)_Attachment_F_DLA_SP_Camera_Pass_Request_Form.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3969 - Replace Site Primary Electrical Pathway
Project Specifications
Defense Logistics Agency Defense Distribution Center, Susquehanna
New Cumberland, PA
June, 4, 2015 Installation Support (DS-FSI)
3969 - Replace Site Primary Electrical Pathway Specification Table of Contents
SECTION SPECIFICATION TITLE
Pages in Section
Specification Book Page
DIVISION 1 – GENERAL REQUIREMENTS
01 11 00 Summary of Work 6 4 01 14 00 Work Restrictions 9 10 01 32 01.00 10 Project Schedule 14 19 01 33 00 Submittal Procedures 23 33 01 35 26 Government Safety Requirements 18 56 01 35 40.00 20 Environmental Management 7 74 01 45 00.10.20 Quality Control for Minor Construction 9 81 01 50 00 Temporary Construction Facilities and Controls 11 90 01 57 19.00 20 Temporary Environmental Controls 24 101 01 57 20.00 10 Environmental Protection 14 125 01 62 35 Recycled / Recovered / Biobased Materials 2 139 01 78 00 Closeout Submittals 15 141 01 78 23 Operations and Maintenance Data 9 156
DIVISION 2 – EXISTING CONDITIONS
02 41 00 Demolition and Deconstruction 9 165 02 82 14.00 10 Asbestos Hazard Control Activities 38 174
DIVISION 3 – CONCRETE
03 20 00.00 10 Concrete Reinforcing 8 212 03 33 00.00 10 Cast-In-Place Concrete 24 220 03 62 16 Metallic Non-Shrink Grouting 3 244
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07 92 00 Joint Sealants 5 247
DIVISION 26 – ELECTRICAL
26 08 00 Apparatus Inspection and Testing 3 252
26 13 00.00 20 SF6/High-Firepoint Fluids Insulated Pad-Mounted Switchgear 9 255
DIVISION 31 – EARTHWORK
31 05 19 Geotextiles 1 264 31 11 00 Clearing and Grubbing 3 265 31 23 00.00 10 Trenching and Backfill 10 268
3969 - Replace Site Primary Electrical Pathway Specification Table of Contents
31 32 11 Soil Surface Erosion Control 3 278
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 01 16.17 Cold Milling of Bituminous Pavements 3 281 32 11 16.16.10 Subbase for Rigid and Flexible Paving 2 284 32 12 10 Bituminous Tack and Prime Coats 2 286 32 12 16 Hot-Mix Asphalt (HMA) for Roads 2 288 32 17 24.00 10 Pavement Markings 1 290 32 92 19 Seeding 2 291
DIVISION 33 - UTILITIES
33 34 00.00 10 Force Mains 6 293 33 46 16 Subdrainage System 4 299 33 70 02.00 10 Electrical Distribution System, Underground 23 303 33 71 01 Overhead Transmission and Distribution 16 326
3969 – Replace Site Primary Electrical Pathway Defense Distribution Center, Susquehanna Specifications New Cumberland, PA
SECTION 01 11 00 – Summary of Work Page 1 of 6
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E2114 (2008) Standard Terminology for Sustainability Relative to the
Performance of Buildings
GREEN BUILDING INITIATIVE (GBI)
Green Globes (2004) Green Globes (™) US Green Building Rating System
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED NC (2009) Leadership in Energy and Environmental Design(tm) New
Construction Rating System
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E2114, Section 01 57 19.00 20, TEMPORARY ENVIRONMENTAL CONTROLS, and as specified.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Sequence; G
SD-07 Certificates
Energy Performance Rating; G
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
Book Page 4 of 341
SECTION 01 11 00 – Summary of Work Page 2 of 6
The work includes individual projects as described in the Request for Proposal (RFP), and individual projects (as issued by Task Order) under the awarded Task Order Contract, and incidental related work.
1.4.2 Location
The work shall be located at Defense Distribution Center Susquehanna in New Cumberland, PA and for locations within a 20 mile radius of the Installation. Refer to the Contract Drawings provided in the RFP and individual projects (as issued by Task Order) for specific location(s) on site for the work.
1.5 WORK RESCHEDULING
Normal duty hours for work shall be from 0700 to 1530, Monday through Friday excluding all federal holidays. Requests for work off hours shall require written approval from the Contracting Officer no less than 15 working days in advance of the proposed work period unless otherwise noted on the Contract drawings.
1.6 PROJECT ENVIRONMENTAL GOALS
Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporates the principles of sustainability. Specifically:
1.6.2 Independent Verification
1.6.3 EPA Energy Performance Rating
Provide work consistent with drawings in order to meet Energy Star in accordance with design.
1.7 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, the Contractor shall arrange with the Contracting Officer Representative (COR) a Construction Sequence detailing the sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways required to successfully execute the work. This sequence shall be provided in writing and shall be approved by the COR prior to the start of any work. See Section 01 32
01.00 10, Project Schedule for further details.
1.8 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
1.9 ON-SITE PERMITS
Book Page 5 of 341
SECTION 01 11 00 – Summary of Work Page 3 of 6
1.9.1 Utility Outage Requests and Utility Connection Requests
Work shall be scheduled to hold outages to a minimum.
Requests for utility outages and connections shall be made in writing to the COR at least 15 working days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.9.2 Digging, Welding, and Burning Permits
ACTIVITY SUBMISSION DATE SUBMISSION FORM
Digging / Excavation 10 working days prior to work Dig Permit COR will supply when requested.
Confined Space Entry Daily (12 hours maximum) Confined Space Entry Permit
Hot Work Daily Hot Work Permit
Issued by Fire Department when requested.
Utility Outage 15 working days N/A
Permits shall be posted at a conspicuous location in the construction area. Burning of trash or rubbish is not permitted on project site.
1.10 LOCATION OF UNDERGROUND UTILITIES
Contractor is responsible for requesting existing underground utilities be located prior to beginning work. Contractor is also responsible for verifying the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be relocated or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made. See Section 07 78 00, Closeout Submittals for additional information.
1.10.1 Notification Prior to Excavation
Contact PA One Call to have publicly (Utility Company) owned underground utilities located and also submit a Dig Permit through the COR to have privately (Government) owned underground utilities located. Contractor is responsible for maintaining markings provided by both PA One Call and Dig Permit once utilities are marked and throughout construction.
Notify the Contracting Officer Representative to request a Dig Permit at least 10 working days prior to starting excavation work. Damage to existing marked utilities shall be repaired at the contractor’s expense.
Book Page 6 of 341
SECTION 01 11 00 – Summary of Work Page 4 of 6
1.11 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Unless otherwise notified by the Contracting Officer, the Contractor, with his own forces, shall transport all Government furnished equipment / materials described in the Task Order.
The equipment/materials will be transported from the Government storage area to the work site indicated on the Task Order.
1.12 SALVAGE MATERIAL AND EQUIPMENT
Materials and equipment to be salvaged as identified by the contract documents shall remain the property of the Government. The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area located on the Defense Distribution Center Susquehanna site.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until receipt and acceptance of salvage material by the COR. Salvaged material under the Contractor’s control that is damaged prior to turnover to the Government shall be replaced by the Contractor at Contractor’s expense. Salvage material shall be documented on Form DD 250 and DD250C (continuation if necessary). A copy of this form is attached and shall be made electronically available by the COR. Instructions for the proper preparation of this form can be found at the following link, Part 4:
http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/dfars/DFARSApxF.htm
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not used.
-- End of Section --
Book Page 7 of 341 http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/dfars/DFARSApxF.htm
SECTION 01 11 00 – Summary of Work Page 5 of 6
Book Page 8 of 341
SECTION 01 11 00 – Summary of Work Page 6 of 6
Book Page 9 of 341
01 14 00 – Work Restrictions Page 1 of 9
SECTION 01 14 00
WORK RESTRICTIONS
GENERAL PART 1
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
Defense Logistics Agency
DLA Physical Security Manual
Defense Distribution Center Susquehanna – Installation Access Policy
Defense Distribution Center Susquehanna – Image Capturing Device Policy
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G Completed Contractor and Visitor Badge Request Form – (Long Form); G DDSP Security Information – (Long Form); G Camera Pass Request Form; G
1.3 SPECIAL SCHEDULING REQUIREMENTS
1.3.1 Materials, Equipment, and Personnel
Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
1.3.2 Active facility
The activity at the facility under construction will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
1.3.3 Construction Interruptions
Permission to interrupt any active roads, railroads, and/or parking areas must be requested in writing a minimum of 15 working days prior to the desired date of interruption. In addition, work that will impact existing employee workspaces or material storage areas, etc. shall require a
Book Page 10 of 341
01 14 00 – Work Restrictions Page 2 of 9 minimum additional advance notification not less than (15) working days in advance of the proposed activities. Coordinate all activities through the Contracting Officer Representative.
1.3.4 Scheduling Interruptions
The work under this Contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the Construction Schedule each factor which constitutes a potential interruption to operations.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the activity become familiar with and obey activity regulations including Safety, Fire, Traffic and Security Regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials should be outside of peak traffic hours (0630 to 0800 and after 1530) unless otherwise approved by the Contracting Officer. Wear Hard Hats, Safety Shoes, Reflective Vests, and Eye Protection at all times in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. All Contractor equipment and vehicles must be properly identified with their name and company logo.
1.4.1.1 Subcontractors and Personnel Company Contacts
Provide a list of contact personnel for the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency by the Contracting Officer Representative. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2 Identification Badges and Installation Access
Contractor ID Badges a.
All badges are the property of the United States government. Badges must be displayed at all times while on the installation unless prohibited by safety concerns. Badges will not be photographed or copied and will not be displayed off the installation. Any lost or stolen badges will be reported to the COR and Installation Security immediately. The Contractor will ensure that all badges are returned to the Pass and ID office upon the termination of the contract or individual employees.
All persons, with the exception of delivery truck drivers and persons possessing valid Government Common Access Cards (CACs), entering the Installation must obtain an Identification Badge from Security, Pass and ID. All contractors will receive a badge for the duration of the contract. The construction contractor shall follow the below procedures to obtain and renew Identification Badges for all direct hire and subcontractor employees and visitors:
(1) Complete a Contractor and Visitor Badge Request (noted as Attachment D) for short term passes less than 30 days or DDSP Security Information (noted as Attachment C) for
Book Page 11 of 341
01 14 00 – Work Restrictions Page 3 of 9 long term passes more than 90 days. Copies of these passes are provided at the end of this section.
(2) Submit completed Badge Request forms to the Contracting Officer Representative a minimum of 2 working days prior to arrival on-site.
(3) Electronic copies of these forms are available from the COR. Badge request forms contain Personally Identifiable Information (PII) and must therefore be transmitted over the Internet encrypted. Encrypted forms require a password for access to the form. The COR will provide the password with the encrypted form when the form is delivered for use.
Installation Access b.
(1) Obtaining Contractor ID Badge
Contractor personnel shall enter the Installation at Post #3 off of Old Depot Road and go to the Pass & ID Building located just inside the Installation Entrance. Personnel shall acquire their ID Badges at the Pass & ID Building. The hours of operation for Pass and ID are Monday – Friday (0630-1500), and ID Badge service is available (0630-1430).
Contractor personnel that have not submitted either the Contractor and Visitor Badge Request From or the DDSP Security Information Form (described above) through the COR will not be issued ID Badges or granted access to the Installation.
(2) Privately Owned Vehicles (POVs)
POVs transporting Contractor personnel may enter the Installation via Post 3 off Old Depot Road, provided they are not transporting tools, equipment, or supplies. All persons in Contractor vehicles are required to show ID Badges at the ID Check Stations. All vehicles entering the Installation at Post 3 are subject to random vehicle search procedures.
(3) Contractor and Construction Vehicles
Contractors driving any form of vehicle designed to carry tools, equipment, supplies, or materials necessary for the work are required to enter the installation via Post 4 off of Old York Road (at Normandy Drive). All persons in Contractor vehicles are required to show ID Badges at the Vehicle Search Area. All vehicles entering the Installation at Post 4 are subject to vehicle search procedures.
Construction Deliveries c.
Deliver equipment and materials to the site in an undamaged condition. Material that is deemed to be damaged or defective by the Contracting Officer Representative from manufacturing, during shipment, or while on-site shall be replaced at the Contractor's expense. Equipment and materials that are deemed to be damaged or defective shall be removed and properly disposed of by the Contractor. New equipment and materials shall be utilized to replace rejected materials or equipment.
Book Page 12 of 341
01 14 00 – Work Restrictions Page 4 of 9
Contractors shall receive material and equipment at their own facility and transport this equipment to the Installation and project site themselves. Government is not responsible for damage to material and equipment shipped directly to the Installation. Contractor must be present to accept shipment of material directly to the Installation. Material that is shipped to the main warehouse (Building 2001) can easily be lost in the midst of the large volume of material constantly moving through the receiving warehouse. Material that is shipped to the Installation and subsequently lost shall be replaced at the Contractors expense.
All contractor deliveries shall enter the Installation at Post 4. To avoid delays at Post 4, deliveries should be scheduled to arrive after 0800 whenever possible. The Construction Contractor shall follow the following procedure for all deliveries (including pick-ups at the construction site):
After being processed by DLA Police in the Post 4 Vehicle Search Area, Delivery Vehicles are directed to proceed onto the Installation and into the vehicle holding area where they must wait for an authorized member of the Construction Contractor to escort them from Post 4 to the construction site. The Construction Contractor’s Site Supervisor is responsible for coordinating all material deliveries and providing all required vehicle escorts. Upon completion of material delivery, the Construction Contractor is responsible for escorting the delivery vehicle back to Post 4 to exit the Installation.
Delivery Escort Authorization d.
Personnel that intend to escort deliveries arriving at Gate 4 to the construction site will require special annotation on their contractor badges to enable this activity. Contractors may provide up to 2 names of persons authorized to escort their deliveries on the depot. If the contractor intends to use subcontractors, each sub-contractor is authorized to have one (1) person designated as an escort for their deliveries. To obtain this authorization, place a stamp (electronically added) to the top of either the Contractor and Visitor Badge Request for short term passes, or the DDSP Security Information for long term passes with the words:
“Authorization Request for Construction Delivery Escort”. This stamp should be displayed prominently on the top of the sheet to assure that security personnel do not miss this annotation.
1.4.1.3 Photographs
Cameras may be possessed and operated by authorized persons only. To obtain a Camera Pass, the Contractor must provide the following information to the COR:
Camera Pass Request Form (attached) shall be provided to the contractor by the COR. a.
The COR will validate the Contractor’s request information and forward the Camera Pass Request Form to Installation Security. If approved, the COR will notify the Contractor that a Camera Pass can be obtained at the Pass & ID Building. Camera Pass requests shall be kept to a minimum and limited to Prime Contractor personnel only. A Camera Pass must be in the possession of the person taking the photographs at all times and presented whenever requested by Government personnel. Failure to maintain or loss of Camera Passes must be reported to COR for action. Installation Security will be notified as necessary by the COR. Personnel
Book Page 13 of 341
01 14 00 – Work Restrictions Page 5 of 9 found to be in the possession of photographic equipment without the proper documentation will have their equipment confiscated, contents reviewed and returned upon their departure of the Installation or other arrangements will be made.
Only Digital Still Cameras should be used. Cell phones and tablets are NOT authorized under b.
any circumstances for taking photographs.
All images captured on digital cameras must be reviewed by Installation Security prior to removing the Camera from the Installation. Cameras must be brought to the Public Safety Facility, Building 911, on J Avenue at the end of each work day and surrendered to Installation Security Staff for review. Any images found to contain images of unauthorized items or areas will be deleted prior to return to Contractor personnel.
Do not take pictures of Contractor or Government Employee ID Badges, identification signs, c.
certain stored materials (as clarified by the COR), security hardware, fire suppression systems, utilities fixtures, or other areas, facilities, or improvements unless images of such are specifically required by the project.
1.4.1.4 Employee List
The Contractor must provide to the Contracting Officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract
1.4.1.5 Radioactive Materials and Equipment
All testing equipment, containing a radioactive source, must be operated in accordance with an approved radioactive equipment plan. This plan must be submitted to the Contracting Officer and approved prior to bringing the equipment unto the Installation. A different radioactive equipment plan will be required for each different type of equipment, type of radioactive source, or size of radioactive source. A data sheet of for each piece of new radioactive equipment must be submitted to the Contracting Officer. The data sheet must contain the following information:
Name of equipment. a.
Name and address of equipment manufacturer. b.
Type and size of radiation source. c.
The location of the installed radioactive equipment (i.e. building no., floor, code/shop area). d.
1.4.2 Working Hours
Regular working hours must consist of an 8-1/2 hour period, between 0700 and 1530, Monday through Friday, excluding Government holidays.
1.4.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer Representative approval.
Make application 15 working days prior to such work to allow arrangements to be made by the
Book Page 14 of 341
01 14 00 – Work Restrictions Page 6 of 9
Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer Representative. The Contractor shall coordinate its efforts to make all utility cutovers outside normal working hours or on Saturdays, Sundays, to the greatest extent possible to minimize impact to existing operations unless directed otherwise.
1.4.4 Occupied and Existing Buildings
The Contractor may be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer Representative.
The existing buildings and their contents must be kept secure at all times.
1.4.5 Utility Cutovers and Interruptions
1.4.5.1 Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
1.4.5.2 Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
1.4.5.3 Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating (including steam, condensate, and hot water), fire alarm, telecommunication, and compressed air shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
1.4.5.4 Operation of Station Utilities: The Contractor shall be responsible for the operation of control devices in the Installation Utilities System, including water, sewer, electrical, and steam services unless indicated otherwise in the contract documents. The Government will provide supervision and direct which control devices to operate. The Contractor shall not operate control devices except when the COR is present. The Contractor shall notify the COR a minimum of 5 working days prior to the need of when such operation is required.
PRODUCTS PART 2
Not Used
EXECUTION PART 3
Not Used
Book Page 15 of 341
01 14 00 – Work Restrictions Page 7 of 9
AUTHORIZATION REQUEST FOR CONSTRUCTION DELIVERY ESCORT
This electronic stamp is to be provided Only for Escort Requests. See paragraph 14.1.2.d above.
Book Page 16 of 341
01 14 00 – Work Restrictions Page 8 of 9
AUTHORIZATION REQUEST FOR CONSTRUCTION DELIVERY ESCORT
This electronic stamp is to be provided Only for Escort Requests. See paragraph 14.1.2.d above.
Book Page 17 of 341
01 14 00 – Work Restrictions Page 9 of 9
Book Page 18 of 341
Section 01 32 01.00 10 – Project Schedule Page 1 of 14
SECTION 01 32 01.00 10
PROJECT SCHEDULE
GENERAL PART 1
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
1.3 SCHEDULE PREPARER
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports.
PRODUCTS PART 2
Not Used
EXECUTION PART 3
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
3.1.1 Subcontractors and Suppliers
Book Page 19 of 341
Section 01 32 01.00 10 – Project Schedule Page 2 of 14
Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is forward planning and a project monitoring tool.
3.1.2 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. The schedule will provide the basis for all progress payments.
If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.3 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.4 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination that the Contractor is not executing the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update will result in the inability of the Contracting Officer Representative to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract each payment period until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer Representative. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet
Book Page 20 of 341
Section 01 32 01.00 10 – Project Schedule Page 3 of 14 the requirements of this specification will result in the disapproval of the schedule. The level of detailed required in the schedule will be a function of both the complexity of the project and the duration of the project. The schedule shall include the following information as a minimum for any and all projects.
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have activity durations greater than 20 work days. Procurement activities are defined below.
3.3.2.2 Procurement Activities
The schedule must include activities associated with the submittal, approval, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.2.3 Mandatory Tasks
The following tasks must be included and properly scheduled:
a. Submission and approval of O & M manuals (when applicable).
b. Submission and approval of as-built drawings.
c. Submission and approval of 1354 data and installed equipment lists (when applicable).
d. Contractor's pre-final inspection.
e. Correction of punch list from Contractor's pre-final inspection.
f. Government's pre-final inspection.
g. Correction of punch list from Government's pre-final inspection.
Book Page 21 of 341
Section 01 32 01.00 10 – Project Schedule Page 4 of 14
h. Final inspection.
3.3.2.4 Government Activities
Show Government and other agency activities that could impact progress. These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE), and NTP for phasing requirements.
3.3.2.5 Activity Responsibility – Coding (RESP)
Assign responsibility for all activities to the Prime Contractor, Subcontractor, or Government agency responsible for performing the activity. Activities assigned as a Government Responsibility include, but are not limited to: Government approvals, environmental permit approvals by State regulators, GFE and NTP for phasing requirements. All activities not identified as a Government responsibility shall be assigned to the Prime Contractor or Subcontractor responsible to perform the work. Activities shall only have one responsible party. Examples of “other” responsibilities include:
- DOR (for the designer of record)
- ELEC (for the electrical subcontractor)
- GOVT (for DS-FSI).
Unacceptable code values are abbreviations of the names of subcontractors.
3.3.2.6 Activity Work Area – Coding (AREA)
Assign Work Area codes to activities based upon the work area in which the activity occurs.
Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Activities shall not have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.
3.3.2.7 Contract Changes/Requests for Equitable Adjustment (REA) – Coding (MODF)
Add any activity or sequence of activities to the project schedule as a result of a Contract Modification, when approved by the Contracting Officer. Any activity or sequence of activities added to the schedule as a result of alleged construction changes made by the Government shall be added to the current schedule and shall be submitted to the Contracting Officer for approval. Approval to add activities to the project schedule does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. An activity shall not be the result of more than one Contract Change, i.e., every Contract Change shall be scheduled as its own activity or set of activities.
3.3.2.8 Contract Line Item (CLIN) – Coding (BIDI)
Book Page 22 of 341
Section 01 32 01.00 10 – Project Schedule Page 5 of 14
Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN Item Code. CLIN Item code all activities, even when an activity is not cost loaded.
3.3.2.9 Phase of Work – Coding (PHAS)
Assign Phase of Work Code to all activities based upon the phase of work in which the activity occurs. Code activities to either a Design Phase or a Construction Phase. Code fast track design and construction phases proposed by the Contractor to allow filtering and organizing the schedule by fast track design and construction packages. If the contract specifies construction phasing with separately defined performance periods, identify a Construction Phase Code to allow filtering and organizing the schedule accordingly. Each activity shall be identified with a single project phase and have only one Phase of Work code.
3.3.2.10 Category of Work – Coding (CATW)
Assign Category of Work Code to all Activities based upon the category of work to which the activity belongs. Category of Work Code must include, but is not limited to: permits, construction submittals, construction submittal approvals, Acceptance, Procurement, Fabrication, Delivery, Weather Sensitive Installation, Non-Weather Sensitive Installation, Start-Up, Test and Turnover. Assign a Category of Work Code to each activity. Each activity shall have only one Category of Work Code.
3.3.2.11 Definable Features of Work (DFOW) – Coding (FOW1, FOW2, FOW3, …)
Assign a DFOW Code to appropriate activities based on the definable feature of work to which the activity belongs. DFOW is defined in Specification Section 01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION. An activity shall not have more than one FOW Code. Not all activities are required to be FOW Coded. A DFOW is a task which is separate and distinct from other tasks, has the same control requirements, and the same work crews. All DFOWs that have been identified in the Quality Control Plan and shall be identified and scheduled on the Project Schedule.
3.3.2.12 Three Phase Inspection Requirements
Before and during the project, quality control shall be maintained through the inspection requirements set forth in Section 01 45 00.10 20, QUALITY CONTROL FOR MINOR
CONSTRUCTION.
3.3.3 Scheduled Project Work Activity Calendar
The schedule interval shall extend from NTP date to the required contract completion date.
The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor. Schedule activities on a calendar to which the activity logically belongs.
Weather sensitive installation activities are to be noted as such on the project schedule.
Original durations must account for anticipated normal adverse weather. Activities may be
Book Page 23 of 341
Section 01 32 01.00 10 – Project Schedule Page 6 of 14 assigned to a 7 day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. The Government will interpret all work periods not identified as non-work periods on the project schedule as meaning the Contractor intends to perform work during those periods.
3.3.3.1 Project Start Date
The schedule shall start no earlier than the date on which the Notice To Proceed (NTP) was acknowledged. Include as the first activity in the project schedule an activity called "Start Project"(or NTP). Actual work will not start until schedule has been approved by the COR.
3.3.3.2 Schedule Constraints and Open Ended Logic
Constrain completion of the last activity in the schedule by the contract completion date.
The schedule shall have no constrained dates other than those specified in the contract.
There shall only be 2 open ended activities:
a. Start Project (or NTP) with no predecessor logic
b. End Project with no successor logic.
3.3.3.3 Early Project Completion
In the event that the project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.
3.3.4 Interim Completion Dates
Constrain contractually specified interim completion dates to show negative float when the calculated early finish date of the last activity in that phase is later than the specified interim completion date.
3.3.4.1 Start Phase
Include as the first activity for a project phase an activity called "Start Phase X" where "X" refers to the phase of work. The "Start Phase X" activity shall have an Earliest Start "ES" constraint date equal to the date on which the NTP was acknowledged and a zero day duration.
3.3.4.2 End Phase
Book Page 24 of 341
Section 01 32 01.00 10 – Project Schedule Page 7 of 14
Include as the last activity for a project phase an activity called "End Phase X" where "X" refers to the phase of work. The "End Phase X" activity shall have a Latest Finish "LF" constraint date equal to the specified completion date for that phase and a zero day duration.
3.3.4.3 Phase "X" Hammock
Include a hammock type activity for each project phase called "Phase X" where "X" refers to the phase of work. A hammock activity is a group of related schedule activities that, for reporting purposes, is shown as a single aggregate activity on the project schedule. The "Phase X" hammock activity shall be logically tied to the earliest and latest activities in the phase.
3.3.5 Default Progress Data Disallowed
Do not automatically update Actual Start and Finish dates with default mechanisms that may be included in the scheduling software. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process shall match those dates provided from Contractor Quality Control Reports. Failure of the Contractor to document the AS and AF dates on the Daily Quality Control report for every in-progress or completed activity, and failure to ensure that the data contained on the Daily Quality Control reports is the sole basis for schedule updating shall result in the disapproval of the Contractor's updated schedule and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes. Updating of the percent complete and the remaining duration of any activity shall be independent functions. Disable program features which calculate one of these parameters from the other.
3.3.6 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of- Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer Representative. Propose logic corrections to eliminate all out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Correct out of sequence progress that continues for more than two update cycles by logic revision, as approved by the Contracting Officer Representative.
3.3.7 Negative Lags and Start to Finish Relationships
Lag durations contained in the project schedule shall not have a negative value. Do not use Start to Finish (SF) relationships.
3.3.8 Calculation Mode
Schedule calculations shall retain the logic between predecessors and successors even when the successor activity starts and the predecessor activity has not finished. Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") will not be allowed.
3.3.9 Milestones
Book Page 25 of 341
Section 01 32 01.00 10 – Project Schedule Page 8 of 14
The schedule must include milestone activities for each significant project event (as appropriate for the specific project) including but not limited to:
a. Milestone activities for each fast track design package released for construction
b. Design complete
c. Permanent power complete
d. Testing complete.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data CD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS.
3.4.1 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval no later than the Preconstruction Meeting.
The schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. The Initial Schedule shall be at a reasonable level of detail as determined by the Contracting Officer. The approved Initial Project Schedule will be used for payment purposes. Completely cost load the Initial Project Schedule to balance the contract award CLINS shown on the Schedule of Values.
The Initial Project Schedule must include all of the required Plan and Program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan. Include the entire construction effort with as much detail as is known at the time but, as a minimum, include all construction start and completion milestones, and detailed construction activities. Initial project schedule should show how planned construction activities are constrained by Government acceptance of the submissions and all other specified Program and Plan approvals. Show all meetings in the initial project schedule. Including monthly or biweekly project reviews (frequency as identified in the contract documents).
3.4.2 Periodic Schedule Updates
Based on the result of the meeting, specified in SCHEDULE UPDATE MEETINGS, submit periodic schedule updates. These submissions will enable the Contracting Officer to assess Contractor's progress. If the Contractor fails or refuses to furnish the information and project schedule data, which in the judgment of the Contracting Officer or authorized representative is necessary for verifying the Contractor's progress, the Contractor shall be deemed not to have provided an estimate upon which progress payment may be made.
Update the schedule to include detailed construction activities.
3.4.3 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11, Appendix A. This exact structure is mandatory, even if some fields are not used.
Book Page 26 of 341
Section 01 32 01.00 10 – Project Schedule Page 9 of 14
A template SDEF compatible schedule backup file (sdef.prx) is available on the QCS website: http://rms.usace.army.mil/. The SDEF format is as follows:
SDEF Format Field Activity Code Length Description
1 WRKP 3 Workers per Day 2 RESP 4 Responsible Party (e.g. GC, subcontractor, USACE) 3 AREA 4 Area of Work 4 MODF 6 Modification or REA number 5 BIDI 6 Bid Item (CLIN) 6 PHAS 2 Phase of Work 7 CATW 1 Category of Work 8 FOW1 10 Feature of Work (used up to 10 characters in length) 9 FOW2 10 Feature of Work (used up to 20 characters in length) 10 FOW3 10 Feature of Work (used up to 30 characters in length)
3.5 SUBMISSION REQUIREMENTS
Submit the following items for the Initial Schedule and every Periodic Schedule Update throughout the life of the project:
3.5.1 Submissions – Electronic Format
Provide Initial Schedule and Periodic Schedule updates in PDF format. Electronic files may be mailed on data CD or provided via email (preferred). Schedule updates of shall be provided throughout the life of the project. Label each CD indicating the type of schedule (Initial or Update – indicate date), full contract number, Data Date and file name. Each schedule shall have a unique file name as determined by the Contractor. Email updates shall include the same information within the note for the purpose of tracking updates through the life of the project.
3.5.2 Approved Changes Verification
Include only those project schedule changes in the schedule submission that have been previously approved by the Contracting Officer.
3.5.3 Update Reports
3.5.3.1 Schedule Update Reports
The Contractor shall provide schedule updates no less than once a month (if necessary) and more frequently if warranted by project complexity, changes in project scope, or if requested by the Contracting Officer. Frequency of reporting shall be defined in the contract documents.
Book Page 27 of 341 http://rms.usace.army.mil/
Section 01 32 01.00 10 – Project Schedule Page 10 of 14
3.5.3.2 Daily Reports
Daily report shall be assembled and submitted to the Contracting Officer Representative on a weekly basis. The daily report shall include the following reported daily:
a. A list of all activities sorted according to activity number.
b. Project Milestone Dates
Show milestone dates on the project schedule for start of project, any contract required interim completion dates, and contract completion date.
c. Critical Path
Clearly show the critical path on the project schedule.
3.5.3.3 Banding
Organize activities as directed to assist in the understanding of the activity sequence.
Typically, this flow will group activities by category of work, work area and/or responsibility.
3.6 PERIODIC SCHEDULE UPDATE MEETINGS
Conduct periodic schedule update meetings at least monthly. See contract document required frequency of these meetings. The Contract Officer may call more frequent meetings if warranted by schedule delays or other project related issues. The schedule update meeting shall be run by the Contractor.
Meetings shall occur within five days of the proposed schedule update and after the Contractor has updated the schedule with Government concurrence regarding actual start dates, actual finish dates, remaining durations and percent complete for each activity it intend to status.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .