Fort Hood.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Electricity and Ancillary Services-Texas Federal contract opportunity
- Solicitation number
- SP0600-10-R-0419
- Issued by
- Defense Logistics Agency Energy
About this file
Installation Data Sheet
View the file
Other files for this federal contract opportunity
Show all 50
Electricity and Ancillary Services-Texas has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary
| Fort Hood - U.S. Army | ||||||
| Delivery Period: meter read Jan 2011 through the meter read Jan 2013 | ||||||
| *NOTE: Contractor is responsible for checking the TXU Electric Delivery meter reading schedule (http://www.oncorgroup.com/electricity/metering/default.asp) to ensure that accounts are switched on the correct meter read. Please note, Fort Hood line items 4801b and 4801c have January meter reads that occur in December (December 28, 2008). | ||||||
| Line | Meter Read | Total | Demand | |||
| Item | Account | Utility | Rate | Dates | Usage (kWh) | KW |
| 4801a | ESI ID# 10443720004006688 | TXU Electric Delivery | 30 | Jan-09 | 219,391 | 242 |
| BELTON LAKE | Feb-09 | 131,468 | 242 | |||
| Svc Address: | Belton, TX 76513 | Mar-09 | 127,129 | 242 | ||
| 12470V PRIMARY connected directly to local utility | Apr-09 | 91,435 | 242 | |||
| May-09 | 113,328 | 242 | ||||
| Jun-09 | 152,348 | 242 | ||||
| Jul-09 | 163,785 | 242 | ||||
| Aug-09 | 147,724 | 242 | ||||
| Sep-09 | 107,412 | 242 | ||||
| Oct-09 | 93,853 | 242 | ||||
| Nov-09 | 160,260 | 242 | ||||
| Dec-09 | 32,486 | 242 | ||||
| 4801b | ESI ID# 10443720001369461 | TXU Electric Delivery | 30 | Jan-09 | 17,634,885 | 68,285 |
| SOUTH SUBSTATION | Feb-09 | 15,843,997 | 60,779 | |||
| Svc Address: | Killeen, TX 76544 | Mar-09 | 18,567,788 | 60,779 | ||
| 138kv, 3 phase | Apr-09 | 19,253,508 | 60,779 | |||
| May-09 | 24,096,914 | 60,779 | ||||
| Jun-09 | 29,214,592 | 60,779 | ||||
| Jul-09 | 31,810,926 | 60,779 | ||||
| Aug-09 | 31,227,345 | 60,779 | ||||
| Sep-09 | 23,423,609 | 60,779 | ||||
| Oct-09 | 20,709,802 | 60,779 | ||||
| Nov-09 | 17,953,043 | 60,779 | ||||
| Dec-09 | 17,783,953 | 60,779 | ||||
| 4801c | ESI ID# 10443720001369492 | TXU Electric Delivery | 30 | Jan-09 | 7,519,389 | 25,193 |
| WEST SUBSTATION | Feb-09 | 4,347,795 | 29,883 | |||
| Svc Address: | Killeen, TX 76549 | Mar-09 | 4,949,914 | 29,883 | ||
| 138kv, 3 phase | Apr-09 | 4,950,309 | 29,883 | |||
| May-09 | 6,141,007 | 29,883 | ||||
| Jun-09 | 7,447,145 | 29,883 | ||||
| Jul-09 | 8,230,315 | 29,883 | ||||
| Aug-09 | 8,849,989 | 29,883 | ||||
| Sep-09 | 10,054,139 | 29,883 | ||||
| Oct-09 | 8,086,954 | 29,883 | ||||
| Nov-09 | 6,907,403 | 29,883 | ||||
| Dec-09 | 7,446,982 | 29,883 | ||||
| 4801d | ESI ID# 10443720002855787 | TXU Electric Delivery | 30 | Jan-09 | 1,120,955 | 2335 |
| NORTH SUBSTATION | Feb-09 | 1,092,887 | 2335 | |||
| Svc Address: | Hwy 36 W, McGregor, TX 76657 | Mar-09 | 1,166,715 | 2335 | ||
| 66kv, 3 phase | Apr-09 | 1,121,804 | 2335 | |||
| May-09 | 1,536,478 | 2335 | ||||
| Jun-09 | 1,771,868 | 2335 | ||||
| Jul-09 | 1,742,099 | 2335 | ||||
| Aug-09 | 1,721,370 | 2335 | ||||
| Sep-09 | 1,351,354 | 2335 | ||||
| Oct-09 | 889,242 | 2335 | ||||
| Nov-09 | 856,586 | 2335 | ||||
| Dec-09 | 968,656 | 2335 | ||||
| 4801e | ESI ID# 10443720009416007 | TXU Electric Delivery | 44 | Jan-09 | 4,984,394 | 15 |
| Feb-09 | 3,836,107 | 15 | ||||
| Svc Address: | 53100 Clarke Rd.; Killeen, TX 76544 | Mar-09 | 5,955,277 | 15 | ||
| Apr-09 | 5,851,461 | 15 | ||||
| May-09 | 7,455,800 | 15 | ||||
| Jun-09 | 9,139,467 | 2,560 | ||||
| Jul-09 | 9,990,224 | 2,713 | ||||
| Aug-09 | 9,687,497 | 20 | ||||
| Sep-09 | 613,984 | 6,897 | ||||
| Oct-09 | 5,057,495 | 17,079 | ||||
| Nov-09 | 4,335,207 | 20 | ||||
| Dec-09 | 4,942,853 | 20 |
ERCOT SP0600-08-R-0413 Installation Data Sheet - Fort Hood Page &P of &N http://www.comedpowerpath.com/nonrescinfo/calendar.asphttp://www.comedpowerpath.com/nonrescinfo/calendar.asphttp://www.comedpowerpath.com/nonrescinfo/calendar.asphttp://www.comedpowerpath.com/nonrescinfo/calendar.asp
File details come from the government source that posted it. Updated .