This document contains a safety table of contents for an accident prevention plan and health and safety plan. It outlines sections for signature sheets, background information on the contractor and project, a statement of health and safety policy including goals and objectives, responsibilities and lines of authority, subcontractors and suppliers, safety inspections, incident reporting and investigations, and plans, programs and procedures such as site sanitation and demolition/renovation. The related federal contract opportunity is a solicitation from the Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground for replacement of overhead doors at Solicitation Number W911QY-23-R-1024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE ARMY

US ARMY INSTALLATION MANAGEMENT COMMAND

US ARMY GARRISON DPW

NATICK SOLDIERS SYSTEMS CENTER

15 GENERAL GREENE AVENUE

NATICK MA 01760

1 | P a g e

ACCIDENT PREVENTION PLAN

HEALTH AND SAFETY PLAN

TABLE OF CONTENTS

A. Signature Sheet

1. Plan Preparer

2. Plan Approver

3. Plan Concurrence

B. Background Information

1. Contractor Name

2. Contract Number

3. Project Name

4. Brief Project Description

C. Statement of Health and Safety Policy

1. Contractor’s Written Safety Program Goals

2. Contractor’s Written Safety Program Objectives

D. Responsibilities and Lines of Authority

1. Statement of Ultimate Responsibility

2. Identification and accountability of personnel responsible for safety and health at both the corporate and project level

3. Equivalent Training to the OSHA 30-Hour Classes is Being Presented as Qualification

E. Subcontractors and Suppliers

1. Identification of Subcontractors and Suppliers

2. Safety Responsibilities of Subcontractors and Suppliers

F. Safety and Health Inspections

1. Specific Assignment of Responsibilities

1.a Name(s) of Individual(S) Responsible for Conducting Safety Inspections

G. Incident Reporting and Investigation

1. Exposure Data

1.a Mishap Investigations, Reports and Logs

H. Plans, Programs and Procedures

1. Site Sanitation/Housekeeping Plan

2. Demolition/Renovation Plan

ACCIDENT PREVENTION PLAN
HEALTH AND SAFETY PLAN
TABLE OF CONTENTS
B. Background Information
C. Statement of Health and Safety Policy
D. Responsibilities and Lines of Authority
E. Subcontractors and Suppliers
F. Safety and Health Inspections
G. Incident Reporting and Investigation
H. Plans, Programs and Procedures