Solicitation_W9127N21R0008_FOSOSP20.pdf
PDF 8 MB Posted
- Attached to
- Foster Oil Spill Prevention System
- Solicitation number
- W9127N21R0008
About this file
This document provides details for a federal contract solicitation seeking proposals for an Oil Spill Prevention System project at Foster Dam in Oregon. The U.S. Army Corps of Engineers seeks a contractor to introduce a reliable and efficient oil spill prevention system to mitigate the risk of oil and other hydrocarbons negatively impacting the environment. The solicitation will use a request for proposal and best value tradeoff process. The estimated cost of the project is between $1 million to $5 million. This is a 100% small business set-aside utilizing other than full and open competition procedures. The North American Industry Classification code is 237990 and size standard is $36.5 million. Proposals are due by June 29, 2021 and the period of performance is estimated from September 2021 contract award through May 2022 final completion.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation W9127N21R0008
Foster Dam, Linn County, OR
FOSTER DAM OIL SPILL PREVENTION SYSTEM
Project Manual
TOC-1
PROJECT TITLE: FOSTER DAM OIL SPILL PREVENTION SYSTEM
Location: Foster Dam, Linn County, Oregon
Magnitude of Construction: $1,000,000 to $5,000,000
Socio-Economic Considerations: Other Than Full and Open Competition, 100% Small Business Set-Aside
JORDAN M QUANTOCK 503-808-4627
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
28-May-2021
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________29 Jun 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
W9127N
PAGE OF PAGES
1 OF
CODE W9127N
(Title, identifying no., date):
12B. CALENDAR DAYS
01:00 PM (hour)
Sealed envelopes containing offers
USACE PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204-3440
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W9127N21R0008 53
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
Mobilization and Demobilization
FFP
Mobilization and Demobilization in accordance with contract documents FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Job
Powerhouse Sump Modifications
FFP
Powerhouse sump modifications in accordance with contract documents.
FOB: Destination
PSC CD: Z2KA
NET AMT
00 10 00-3
0003 1 Job
Main Unit Transformer Pressure Relief
FFP
Main Unit Transformer Pressure Relief Valve in accordance with contract FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004 1 Job
Oil Water Separator Improvement
FFP
Oil Water Separator Improvement in accordance with contract documents FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005 1 Job
Powerhouse Piping
FFP
Powerhouse piping in accordance with contract documents FOB: Destination
PSC CD: Z2KA
NET AMT
00 10 00-4
0006 1 Job
In-Sump Inspection Report
FFP
In-sump inspection report in accordance with contract documents.
FOB: Destination
PSC CD: Z2KA
NET AMT
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0002 N/A N/A N/A N/A
0003 N/A N/A N/A N/A
0004 N/A N/A N/A N/A
0005 N/A N/A N/A N/A
0006 N/A N/A N/A N/A
00 10 00-5
Section 00 21 00 - Instructions
BIDDER INQUIRY INFORMATION
All inquiries regarding this solicitation are to be submitted via ProjNet‐Bid at https://www.projnet.org/projnet/.
Telephone and email inquiries will not be accepted. ProjNet‐Bid is a web‐based program that allows offerors to post questions regarding the solicitation, and to view all questions by other offerors, and answers by the U.S. Army Corps of Engineers.
No response will be posted to inquiries after the Close of Business on the seventh business day preceding the solicitation due date. All bidders will be held to have reviewed the questions and responses in ProjNet –Bid prior to bid submission. Nothing in the solicitation is changed unless an amendment is sent out.
The Bidder Inquiry Key for this solicitation is: 667SQ7‐SEUU6X
To access the ProjNet‐Bid website the first time:
1) Register.
2) Click Quick Add Key. (The Agency is USACE.)
3) Enter the following information for access:
The Bidder Inquiry Key for this solicitation Valid business contact information
Submit questions or review questions and answers. When an answer is posted to a question, the question and answer is then available for all other bidders to review.
For questions about the ProjNet‐Bid, access the help tab on the ProjNet website.
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 252.215-7008 Only One Offer JUL 2019
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Priced Construction contract resulting from this solicitation.
(End of provision)
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
00 21 00-1
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of provision)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
3.8% (Linn County) 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
00 21 00-2
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Linn County, Oregon
(End of provision)
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
00 21 00-3
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of provision)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
USACE – Portland District
ATTN: CECT-NWP-C
PO BOX 2946
Portland, OR 97208-2946
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
00 21 00-4
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- 15 June 2021 at 10:00am
(c) Participants will meet at-- Foster Dam, Linn County Oregon
(End of provision)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
The Federal Acquisition Regulation, Defense Federal Acquisition Regulation Supplement, and Army Federal Acquisition Regulation Supplement can be found at: https://www.acquisition.gov/
(End of provision)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any DFARS (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
INSTRUCTIONS TO OFFERORS
A. General.
(1) This solicitation is a total small business set-aside. The Government intends to award a single, firm-fixed price construction contract to the responsible offeror whose proposal represents the best value after evaluation in accordance with the evaluation factors in the solicitation. Offerors shall submit a technical proposal and a price proposal. The evaluation results of the non-price and price proposals will determine an awardee.
(2) In the context of this proposal, the “Offeror” refers to the proposed prime contractor.
00 21 00-5
(3) The Government intends to make an award without discussions, but reserves the right to conduct discussions should discussions prove to be necessary or advantageous to the Government. Because the Government does not intend to hold discussions, Offerors are encouraged to include their best pricing in their initial proposal.
(4) All proposals received will stand alone and be considered complete and final. The evaluation board will not consider any information or data incorporated by reference or otherwise referred to. The successful Offeror will be selected solely on the basis of the evaluation factors set forth below. Accordingly, proposals submitted in response to this solicitation should provide clear, complete, concise, and straightforward responses to the evaluation factors. Elaborate proposals, color brochures, and other excesses are discouraged.
(5) Joint Ventures (JV). A joint venture is defined as a legal business entity formed between two or more companies (parties) to undertake the performance activities of a contract together. This does not include other arrangements such as “teaming agreements” or “strategic alliances,” which are not recognized as bona fide joint ventures for the purposes of this solicitation. An Offeror that is a joint venture must submit a copy of its legally binding joint venture agreement signed by an authorized officer from each of the firms comprising the joint venture with the chief executive of each entity identified. If submitting a proposal as a joint venture, the experience and past performance of each of the joint venture partners can be submitted for the joint venture entity. The experience for each joint venture partner will be considered the experience of the joint venture entity. Page and project form limits apply to the joint venture as a whole. Offerors that submit proposals may not change their firm (including Letters of Commitment (LOC) and proposed subcontractors) or their Joint Venture firms, if selected to submit Final Proposal Revisions (FPR).
(6) The successful offeror will be selected solely on the basis of the evaluation factors set forth below. Accordingly, proposals submitted in response to this solicitation should provide clear, complete concise, and straightforward responses to the evaluation factors.
B. Evaluation Factors.
The government will evaluate proposals under the following factors
Experience (Factor 1) Past Performance (Factor 2) Work Plan (Factor 3) Price
All non-price factors are approximately equal in importance. All non-price factors, when combined, are significantly more important than price
00 21 00-6
The Government will use the following definitions when evaluating proposals:
Deficiency – A material failure of a proposal to meet a Government requirement or a combination of weakness in a proposal that increases the risk of a unsuccessful contract performance to an unacceptable level. See FAR 15.001
Significant Weakness – A flaw in a proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001
Weakness – A Flaw in a proposal that increases the risk of unsuccessful contract performance. See FAR 15.001
Strength – An aspect of a proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
Significant Strength – An aspect of a proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
5. SUBMISSION OF PROPOSALS
A. Administrative Details and General Instructions: Proposals are due no later than the time and date specified in Block 13 of Standard Form 1442.
(1) General Proposal Format. The proposal shall be in electronic Portable Document Format, filename extension: “.pdf” and suitable for viewing in Adobe Reader. Offerors shall bookmark and label each electronic PDF to afford easy identification from the Bid table of contents.
Title Page. The electronic proposal must include Offeror’s name and address, phone number and email address, title of the solicitation, solicitation number and date of submittal clearly identified.
Table of Contents. The electronic proposal shall contain a detailed table of contents.
Submission Transmittal. Do not assume submission will be instantaneous. File size and number of files submitted shall be considered. Offeror/Teammate/Subcontractors should allow adequate time for submission completion because the entire Bid (i.e. offerors submission and all teammate/subcontractor(s) independent submissions)
00 21 00-7 must be received by the time and date specified in Block 13 of Standard Form 1442, or SF 30 if applicable.
All information must be confined to the appropriate volume. Each volume of the proposal is expected to contain a table of contents, summary section with a brief abstract of the volume, and the narrative discussion.
Each Volume shall be contained within a separate electronic file.
(2) Proposal Content Limitations.
The Offeror must confine the proposal to relevant information and documentation sufficient to provide an adequate basis for evaluation.
Offerors are responsible for including sufficient details, in a concise manner, to permit a complete and accurate evaluation of the proposal.
The page count is at the discretion of the offeror, however, the proposal may not be more than 25 type written (single page only) pages total. The 25-page limit does NOT include past performance information submitted under Factor 2.
Extraneous information provided in the proposals will not be considered in the evaluations; therefore, the Offeror should provide only information that satisfies the solicitation requirements. Merely restating the specifications without sufficient elaboration demonstrates a lack of understanding of the requirement.
DO NOT cross reference past performance information. It is acceptable to repeat data, project information or experience in more than one non-price area as long as it satisfies the requirements of the factor.
Proprietary information must be clearly marked.
B. Content of Proposals: All proposals must be prepared in two volumes: A technical proposal (Volume I), a price proposal (Volume II). Each of the volumes shall be separate and complete in itself so that evaluation of one may be accomplished independently from evaluation of the other. The technical proposal (Volume I) must not contain reference to price. The narrative and content structure of the proposal shall follow the format shown under Volume I below. Offerors who fail to submit a complete proposal may be excluded and thus receive no further consideration for award.
(1) Technical Proposal, Volume I: Provide one (1) electronic proposal in Portable Document Format. Filename extension “.pdf” and suitable for viewing in Adobe Reader. Volume I shall consist of information for the three (3) factors, listed in tabular form, as noted below. Repeating or restating the specifications without sufficient elaboration will be determined to show a lack of understanding of the requirement.
00 21 00-8
Volume I – Technical (Non-Price) Factors and Sub-factors:
Tab 1 - Factor 1 - Experience
Tab 2 - Factor 2 – Past Performance
Tab 3 - Factor 3 – Work Plan
(2) Price Proposal, Volume II: Provide one (1) electronic proposal in Portable Document Format. Filename extension “.pdf” and suitable for viewing in Adobe Reader. Provide pricing and complete all line items on Standard Form 1442 (SF 1442). The Price Proposal must be prepared in accordance with the following and must include:
Tab 1 - SF1442, Solicitation, Offer, and Award.
The SF1442 shall be filled out completely by the Offeror and signed by an official that is authorized to bind the company. The Offeror shall also acknowledge all amendments to the solicitation in accordance with the instructions on the Standard Form 30 or Block 19 of SF1442.
Tab 2 – Section 00 10 00, Proposal Price / Bid Schedule.
The Offeror shall fully complete this section.
Tab 3 - Representations, Certifications and other Statements of Offerors.
The Offeror shall complete all representations and certifications in Section 00 45 00 and also ensure current registration and completed/updated Annual Representations and Certifications on the System for Award Management (SAM) website https://www.sam.gov/SAM/
Tab 4 - Bid/Offer Guarantee. The requirement that an original and copy(ies) be submitted as found in block 13A of the SF1442 is satisfied through the electronic submission. Additionally, electronic submission of the bid guarantee, when a bid guarantee is required, is due with the bid submission (mailing a bid guarantee is not allowed).
Submission of Proposals: Offeror shall submit its Bid via email to Jordan Quantock, Jordan.m.quantock@usace.army.mil, and Kristina Morrow, Kristina.K.Morrow@usace.army.mil. Offerors should enter a description for every file submitted. For files over 20 megabytes (MB) the offeror shall break the file into smaller files sent via separate emails, each marked to identify which number the email is relative to the total number of emails submitted (i.e. “one of four”). Once all of the emails submitted have been received, the Government will confirm receipt via return email. If an offeror submits multiple bids, the Government will only consider the last bid submitted prior to the bid due date and time.
00 21 00-9
HARD COPY SUBMISSIONS WILL NOT BE CONSIDERED.
6. EVALUATION FACTORS
Volume I – Technical (Non-Price) Submission Requirements and Evaluation Method:
FACTOR 1 (TAB 1) – Experience
Submission Requirements:
The offeror shall submit information for at least two (2) and no more than three (3) projects that best demonstrate the Offeror’s experience performing projects similar in size, scope, and complexity to the work required by the solicitation. Each project must be completed or be substantially completed within the last five (5) years.
Information submitted for each project must include the information outlined in Offeror’s Experience Form, Attachment A.
Substantially complete is defined as being 75% complete by the date that proposals are due. If an Offeror submits a project that it represents is “substantially complete,” the Offeror must reasonably explain why the project is considered at least 75% complete. If an Offeror submits an ongoing project without providing an accompanying reasonable explanation that explains how the project is at least 75% complete, the Government reserves the right to reject the project.
A maximum of three (3) projects will be evaluated. If an Offeror disregards these instructions and submits more than three projects, only the first three projects listed will be evaluated for meeting the requirements. Offeror’s should describe each project with enough detail to ensure that the Government can meaningfully assess whether the projects submitted meet the minimum evaluation criteria outlined below.
Instructions on the use of major subcontractors to demonstrate experience:
Offeror’s may use the past experience of major subcontractors to demonstrate experience. A major subcontractor is defined as a subcontractor that the offeror proposes to perform 25% or more of the work required under the solicitation. If the offeror submits experience of major subcontractors, the offeror must submit a letter of commitment from the subcontractor on the letterhead of the firm to be subcontracted. The letter of commitment must be signed by an authorized individual from the subcontractor who is proposed to perform the work. If a letter of commitment is not submitted, the experience will not be considered.
Evaluation method:
00 21 00-10
The Government will rate this factor using the combined technical/risk rating as follows:
COLOR RATING DESCRIPTION
Blue Outstanding
Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Purple Good
Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate
Green Acceptable
Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Red Unacceptable
Proposal does not meet the requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable
TECHNICAL RISK RATING METHOD
ADJECTIVAL RATING DESCRIPTION
Low
Proposal may contain weakness(es) which have little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor effort and normal Government monitoring will likely be able to overcome any difficulties
Moderate
Proposal contains a significant weakness or combination of weaknesses which may potentially cause disruption of schedule, increased cost or degradation of performance.
Special contractor emphasis and close Government monitoring will likely be able to overcome any difficulties.
High
Proposal contains a significant weakness or a combination of weaknesses which is likely to cause significant disruption os schedule, increased cost or degredation of performance.
Is unlikely to overcome any difficulties, even with special contractor emphasis and close Government monitoring.
Unacceptable Proposal contains a material failure or a combination of significant weaknesses that increases the risk of unsuccessful performance to an unacceptable level.
00 21 00-11
In determining strengths and weaknesses, the Government will consider the following:
The extent to which the offeror’s submitted projects include oil water separator installation and/or waste water treatment systems that involved installation of industrial pumps and piping, including controls similar to the requirements of this solicitation. NOTE: Projects that include oil water separators are more similar to the requirements of this solicitation than projects including other similar systems.
The extent to which the offeror’s submitted projects involved the following:
a. Performing welding, mechanical, plumbing, electrical work and installation of platforms and ladders in permit-required confined spaces;
b. Structural concrete cutting, coring, and repair;
c. Installation of pre-case structures;
d. Installation and programming of hydrocarbon monitors;
e. Repair or service of nitrogen blanketed Class 2 step up oil filled power transformers; and
f. Working in a hydropower powerhouse.
FACTOR 2 (TAB 2) – Past Performance
Submission Requirements:
The offeror shall provide past performance information for each project listed by the offeror under Factor 1 - Experience
If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal.
If there is not a completed CPARS evaluation, the offeror shall submit a Past Performance Questionnaire (PPQ) for the project. See Attachment A. Do not submit a PPQ when a completed CPARS is available.
o If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment A), which will provide contract and client information for the respective project(s).
o Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Jordan Quantock, via email at prior to proposal closing date. The offerors shall instruct the clients to refer to the solicitation number in the subject line.
o The PPQs are Source Selection materials. All successfully submitted PPQs will receive an e-mail confirmation upon receipt. If the offeror does not receive the confirmation, it is their responsibility to follow up to ensure the government has received the information.
Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted past performance information in the past
00 21 00-12 performance evaluation.
Offerors may provide explanation on problems encountered on past projects and the corrective actions taken by the offeror.
In addition to the above, the Government may review other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the PPIRS (Past Performance Information Retrieval System) including CPARS (Contractor Performance Assessment Reporting System), using all CAGE/DUNS (Commercial and Government Entity Code/ Data Universal Numbering System) numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), FAPIIS (Federal Awardee Performance and Integrity Information System), Electronic Subcontract Reporting System (eSRS), or other databases; telephone interviews with organizations familiar with the offeror’s performance, Government personnel with personal knowledge of the offeror’s performance capability, and any other known sources not provided by the offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
Evaluation Method:
The Government seeks a contractor who maintains a strong commitment to customer satisfaction and superior performance. It is the offeror’s responsibility to affirmatively document these qualities in his technical proposal. In doing so, be mindful that “past performance” and “experience” are not identical. Experience measures what the offeror has done and how, many times, or for how long the offeror have done it. Past performance, however, measures how well the offeror has performed.
The past performance evaluation results is an assessment of the offeror’s probability of meeting the minimum past performance solicitation requirements. This assessment is based on the offeror’s record of relevant and recent past performance information that pertain to the project outlined in the solicitation requirements.
There are three aspects to the past performance evaluation: recency, relevancy, and quality.
The first aspect is to evaluate whether the Offeror’s past performance is recent, and relevant or not relevant to the solicitation requirements. For this solicitation, recent projects are those projects:
Completed or substantially completed (as defined above) within five (5) years of the date that proposals are due.
00 21 00-13
The second aspect is to determine how relevant the Offeror’s past performance projects are to the solicitation requirements. There are four (4) levels of relevancy as shown in the table below.
PAST PERFORMANCE RELEVANCY
RATING DESCRIPTION
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant
Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
In assessing the relevancy of the offeror’s past performance, the government will consider the following:
The extent to which a submitted project included oil water separator installation and/or waste water treatment systems that involved installation of industrial pumps and piping, including controls similar to the requirements of this solicitation. NOTE: Projects that include oil water separators are more similar to the requirements of this solicitation than projects including other similar systems.
The extent to which the offeror’s submitted projects involved the following:
a. Performing welding, mechanical, plumbing, electrical work and installation of platforms and ladders in permit-required confined spaces;
b. Structural concrete cutting, coring, and repair;
c. Installation of pre-case structures;
d. Controls involving programmatic logic controllers (PLC)
e. Repair or service of nitrogen blanketed Class 2 step up oil filled power transformers; and
f. Working in a hydropower powerhouse.
More relevant past performance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance.
The third aspect of the past performance evaluation is to determine how well the contractor performed on its past performance projects. The Government will evaluate the offeror’s past performance to ensure previous work performance satisfactorily met the contract requirements, performance schedules, prescribed quality of work, safety requirements, and other customer expectations on these projects. If any performance
00 21 00-14 issues are identified, the Government will consider the number, type, and severity of the problems and effectiveness of corrective actions taken.
The Government reserves the right to obtain or verify offeror’s past performance information from references and other sources available to the Government.
Based on a consideration of those three aspects, the Government will assign a final Performance Confidence Assessment Rating for this factor. The Government will review the past performance information and determine the quality and usefulness as it applies to performance confidence assessment. In conducting a performance confidence assessment, each offeror shall be assigned one of the ratings using he table below.
PERFORMANCE CONFIDENCE ASSESSMENT
RATING DESCRIPTION
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
The offeror may not be evaluated favorably or unfavorably in the factor of past performance.
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
In the case of an offeror without a record of relevant past performance of for which information on past performance is not available, the offeror will not be evaluated favorably or unfavorably on past performance, and therefore may receive a “Neutral Confidence” rating.
FACTOR 3 (TAB 3) – Work Plan
Submission requirements:
The offeror shall submit a Work Plan that demonstrates the offeror’s approach to performing the required work as outlined in the specifications.
00 21 00-15
The Work Plan must include, at a minimum:
Gantt Chart: Submit a project schedule in Gantt shart format using the critical path method (MS Project or Primavera software). Provide enough detail and tasks to adequately cover the scope of the project and the activities required to successfully describe and complete the project as required by the solicitation.
Narrative: Submit a narrative detailing the plan (means and methods) for completing the work, meeting the schedule, and the challenges and site constraints that may be encountered during construction. Describe the proposed mitigation measures for the identified challenges and constraints to successfully complete the major features of work described below. Detail how the offeror can support accelaerating work if it were to encounter delays in the work schedule.
For each of the following features of work, identify who is performing the work (offeror or a subcontractor).
o Sump pumps, piping, and controls;
o Pre-cast OWS structure o Oil/Water separator install;
o Powerhouse piping and hydrocarbon monitor;
o Sump access safety improvements;
o Transformer pressure relief valve replacement.
Evaluation method:
The Government will evaluate this factor using the combined technical/risk rating as follows:
COLOR RATING DESCRIPTION
Blue Outstanding
Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Purple Good
Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate
Green Acceptable
Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Red Unacceptable Proposal does not meet the requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful
00 21 00-16 performance is unacceptable. Proposal is unawardable
TECHNICAL RISK RATING METHOD
ADJECTIVAL RATING DESCRIPTION
Low
Proposal may contain weakness(es) which have little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor effort and normal Government monitoring will likely be able to overcome any difficulties
Moderate
Proposal contains a significant weakness or combination of weaknesses which may potentially cause disruption of schedule, increased cost or degradation of performance.
Special contractor emphasis and close Government monitoring will likely be able to overcome any difficulties.
High
Proposal contains a significant weakness or a combination of weaknesses which is likely to cause significant disruption os schedule, increased cost or degredation of performance.
Is unlikely to overcome any difficulties, even with special contractor emphasis and close Government monitoring.
Unacceptable Proposal contains a material failure or a combination of significant weaknesses that increases the risk of unsuccessful performance to an unacceptable level.
In determining the strengths and weaknesses, the Government will consider the following when evaluating the offeror’s Work Plan:
The extent to which the offeror’s schedule has realistic durations for each required work task and includes work task sequencing in a logical order;
The extent to which the offeror’s Work Plan demonstrates the offeror’s understanding of the scope of work and the challenges to be encountered during construction;
The extent to which the offeror’s Work Plan demonstrates an understanding of challenges and constraints due to site location and logistics related to working in the powerhouse sump.
Volume II - Price.
The Price Proposal will be evaluated to determine fairness and reasonableness. For evaluation purposes, the total evaluated price will be calculated by adding the total price for all optional items to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the options.
The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing
00 21 00-17 exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
00 21 00-18
Section 00 45 00 - Representations and Certifications
CLAUSES INCORPORATED BY REFERENCE
52.204-26 Covered Telecommunications Equipment or Services-- Representation.
OCT 2020
252.204-7008 Compliance With Safeguarding Covered Defense Information Controls
OCT 2016
CLAUSES INCORPORATED BY FULL TEXT
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2020)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.
(2) The small business size standard is $39.5 million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
( ) Paragraph (d) applies.
( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this…