Sol_12445525R0007.pdf

PDF 352 KB Posted

Attached to
Little Rough Run and Cold Run Culvert Replacement Federal contract opportunity
Solicitation number
12445525R0007
Issued by
Department of Agriculture Forest Service

About this file

This document is a solicitation for a construction contract to replace two box culverts in the Monongahela National Forest. The United States Department of Agriculture Forest Service is seeking a contractor to replace the Little Rough Run and Cold Run box culverts on Forest Road 76, located approximately 8 miles east of Richwood, West Virginia. The project involves in-water construction work to be completed under low flow conditions (70 cubic feet per second) between July and October, with a project value between $250,000 and $500,000.

The solicitation requires offerors to submit both technical and price proposals, with evaluation based on a tradeoff process that considers past performance, instream construction experience, and equipment suitability. Key submission requirements include a project list detailing similar past culvert and instream construction projects, an equipment list, and completed representations and certifications. The contract is anticipated to be awarded as a firm fixed-price contract, with performance period from May 27, 2025 to November 14, 2025. Proposals must be submitted electronically by June 18, 2025, with the government expecting to make an award without discussions but reserving the right to conduct negotiations if necessary.

View the file

Other files for this federal contract opportunity

Other files attached to Little Rough Run and Cold Run Culvert Replacement, newest first.
File Type Posted
Att 01_Schedule of Items (20320).docx DOCX document
Att 02_SOW (240916).pdf PDF
Att 04_Wage Rates (250214).pdf PDF
Att 03_Plans (240916).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1145405

USDA-FS CSA EAST 13

1720 PEACHTREE ST NW

STE 876S

ATLANTA GA 30309-2449

Paul Boucher

Contract Specialist paul.boucher@usda.gov

PAUL BOUCHER

1x 05/19/2025

12445525R0007

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

The contractor shall provide all labor, materials, and applicable incidentals to replace the Little Rough run, and Cold Run box culverts on FR-76, in accordance with all contract terms, conditions, specifications, plans, and other attachments.

All in water work will occur under low flow conditions (70 cubic feet per second), between July and October.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

14 0 calendar days and complete it within ________________ ________________ calendar days after receiving

06/18/2025

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA-FS CSA EAST 13

1720 PEACHTREE ST NW

STE 876S

ATLANTA GA 30309-2449

DEBRA K. BRINN

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 37

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

12445525R0007

Delivery: 11/14/2025

Delivery Location Code: 3434

USDA FOREST SERVICE

MONONGAHELA NATIONAL FOREST

200 SYCAMORE ST

ELKINS WV 26241-3962 US

Period of Performance: 05/27/2025 to 11/14/2025

0001 LITTLE ROUGH RUN SEE ATTACHMENT 01

0002 COLD RUN SEE ATTACHMENT 01

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No: 12445525R0007 Little Rough Run and Cold Run Culvert Replacement

FAC 2025-03 January 17, 2025

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 TECHNICAL SPECIFICATIONS

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

G.2 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

G.3 INVOICING

G.4 INCIDENTAL PAYMENT ITEMS

G.5 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 INSURANCE COVERAGE

H.2 ORDER OF PRECEDENCE

H.3 PRODUCT SUBSTITUTION

H.4 LANDSCAPE PRESERVATION AND HAZARDOUS MATERIALS

H.5 HAZARDOUS CONDITIONS SAFETY PLAN

H.6 SPECIAL EQUIPMENT CLEANING REQUIREMENTS

H.7 FINAL CLEANUP

H.8 PROTECTION OF CULTURAL RESOURCES

H.9 PAYMENT FOR MATERIALS DELIVERED OFF THE SITE

PART II--CONTRACT CLAUSES

FAC 2025-03 January 17, 2025

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF

OFFERORS OR RESPONDENTS

K.1 PROVISIONS

K.2 OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

L.1 PROVISIONS

L.2 INSTRUCTIONS

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROVISIONS

M.2 PROPOSAL EVALUATION

M.3 TECHNICAL EVALUATION FACTORS

M.4 PRICE EVALUATION

FAC 2025-03 January 17, 2025

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

See attachment 01 Schedule of Items, contained in Section J.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

The contractor shall provide all labor, materials, and applicable incidentals to replace the Little

Rough run, and Cold Run box culverts on FR-76, in accordance with all contract terms conditions, specifications, plans, and other attachments.

All in water work will occur under low flow conditions (70 cubic feet per second), between July and October.

C.2 PROJECT LOCATION

The projects are located on the Gauley Ranger District of the Monongahela National Forest, approximately 8 miles East of Richwood, WV.

Directions to Cold Run Culvert Replacement:

FROM THE GAULEY RANGER STATION, DRIVE EAST ON ROUTE 39 19.9 MILES TO

FR 102 SOUTH FORK CRANBERRY RIVER (CRANBERRY GLADES BOTANICAL

AREA). FOLLOW FR 102 SOUTH FORK CRANBERRY RIVER PAST THE CRANBERRY

GLADES BOARDWALK TO THE GATE ON FR 102 2.4 MILES. ONCE THROUGH THE

GATE, THE WORK SITE IS 9.3 MILES NORTH OF THE GATE.

Directions to Little Rough Run Culvert replacement:

FROM THE GAULEY RANGER STATION, DRIVE EAST ON ROUTE 39 19.9 MILES TO

FR 102 SOUTH FORK CRANBERRY RIVER (CRANBERRY GLADES BOTANICAL

AREA). FOLLOW FR 102 SOUTH FORK CRANBERRY RIVER PAST THE CRANBERRY

GLADES BOARDWALK TO THE GATE ON FR 102 2.4 MILES. ONCE THROUGH THE

GATE, THE WORK SITE IS 10.7 MILES NORTH OF THE GATE.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

Between $250,000 and $500,000.

C.4 TECHNICAL SPECIFICATIONS

This project uses the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14), U.S. Customary Units; available by reference and download from https://hlh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf.

Standard and Supplemental Specifications for FP-14 shown in the specification listing contained in the attachments are applicable to this contract. All specifications not included in the specifications listing but referenced by listed specifications, are applicable.

https://hlh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf

FAC 2025-03 January 17, 2025

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

FAR 52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

FAR 52.211-18 Variation in Estimated Quantity (APR 1984) FAR 52.236-15 Schedules for Construction Contracts (APR 1984) FAR 52.242-14 Suspension of Work (APR 1984)

FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within fourteen (14) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than11/14/2025. The time stated for completion shall include final cleanup of the premises.

(End of clause)

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

AGAR 452.204-70 Modification for Contract Closeout

G.2 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

The contracting Officer will designate a Contracting Officer's Representative(COR) at the time of award. The COR is responsible for administering the performance of work under this contract.

In no event, however, will any understanding, agreement, modification, change order, or other

FAC 2025-03 January 17, 2025 matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

On all matters that pertain to the contract terms the contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the contracting officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal for a contract claim.

G.3 INVOICING

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). All invoices are to be submitted online via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/. If your company does not have an existing IPP account, one will be generated, using the Government Business Point Of Contact listed in your SAM profile. Some initial set-up tasks may need to be completed before submitting your first invoice: information can be found at https://www.ipp.gov/vendors/.

G.4 INCIDENTAL PAYMENT ITEMS

The intent of the contract is to provide for the complete performance of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items.

All other work and materials will be considered as incidental to and included in the payment for items shown.

G.5 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts The Contract Price includes the total amount for premiums that the Contractor attributes to the furnishing of performance and payment bonds required by the contract. Reimbursement for bond premiums under the clause at FAR 52.232-5, Payments Under Fixed-Price Construction, shall not cover any amount therefor not included in the contract price.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 INSURANCE COVERAGE

Pursuant to FAR clause FAR 52.228-5, Insurance-Work on a Government Installation paragraph (a), Contractors shall present evidence and maintain, as a minimum, the amounts of insurance coverage indicated below:

(1) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If https://www.ipp.gov/vendors/

FAC 2025-03 January 17, 2025 occupational diseases are not compensable under those statutes, they must be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 must be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(2) General Liability. The Contractor must have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(3) Automobile Liability. The Contractor must have automobile liability insurance written on a comprehensive form of policy. The policy must provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States must provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

H.2 ORDER OF PRECEDENCE

Any inconsistency in this solicitation or contract, not already addressed by FAR 52.215-8, shall be resolved by giving precedence in the following order:

1. Schedule (excluding the specifications)

2. Representations and Certifications

3. Instructions to Offerors

4. Special Contract Requirements

5. Contract Clauses (excluding the specifications and drawings)

6. Special Project and Supplemental Specifications

7. Standard Specifications

8. Drawings, figured dimensions over scaled dimensions

9. Drawings, large scale over small scale

10. Drawings - Schedules on drawings over notations on drawings

11. Shop Drawings

12. Other Documents, Exhibits, and Attachments

H.3 PRODUCT SUBSTITUTION

Any modification of items, designs, materials, products or equipment (including Government- Furnished property) made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award has been made. No approvals will be made prior to award.

H.4 LANDSCAPE PRESERVATION AND HAZARDOUS MATERIALS

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, FAC 2025-03 January 17, 2025 disposed of, or incorporated in the work as directed by the Contracting Officer. The Contractor shall make all reasonable attempts to preserve the scenic and natural environment within and adjacent to this construction project.

(b) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, lakes, reservoirs, and other surface waters.

(1) Wash water or waste from concrete, aggregate or other operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(2) Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

(c) No petroleum products or other hazardous substances shall be released on or into land or rivers, streams, impoundments or other waters, or into natural or manmade channels leading thereto or therefrom. Servicing of all equipment shall be done only in the areas approved by the Contracting Officer. The Contractor shall transport off government lands all waste oil, vehicle oil filters (drained of free-flowing oil), and oily rags and shall dispose of such materials in accordance with applicable State and Federal regulations.

(1) If the total on-site oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare and implement a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer. This plan shall include notification of appropriate state and local officials, the Contracting Officer and other appropriate agencies.

(2) At all on-site work areas (including Contractor storage, transfer, fueling, mixing sites, etc., for oil, oil products or any hazardous materials), the Contractor shall take appropriate preventive measures to ensure that any release of hazardous products does not enter any stream or other waters of the United States or any of the individual States and shall conform to the federal, state and local regulations. Planned spill containment locations in stream courses shall be established prior to commencement of work activities. These locations will be reviewed by the Contracting Officer or representative. When deemed appropriate; additional planned preventive measures shall be established for review by the Contracting Officer or representative.

(3) The Contractor, acting independently, shall immediately take action to notify the appropriate agencies including the Contracting Officer, and to contain and clean up, without expense to the Government, all petroleum products or other hazardous substance releases which are on or in the vicinity of the project and which are caused by the Contractor's employees, directly or indirectly.

The Contractor shall have the necessary materials on site to contain a spill which may occur on land or within live streams as appropriate for any potential flow conditions likely to occur. This may require absorbent pads and/or booms or other containment devices. In the event the Government determines that additional resources beyond those of the Contractor's are required, the Contractor may be held liable for all damages and costs including, but not limited to additional labor, subsistence, equipment, supplies and transportation deemed necessary by the Government for the containment and clean-up of petroleum products or other hazardous substance releases caused by Contractor's employees or resulting from or related to construction operations.

(4) The Contractor shall notify the Contracting Officer of any hazardous materials to be used on

FAC 2025-03 January 17, 2025 the job and shall have Material Safety Data Sheets (MSDS) for those materials available on the job.

H.5 HAZARDOUS CONDITIONS SAFETY PLAN

The following conditions have been identified as inherently hazardous to a degree that failure to take the proper precautions could lead to serious injury or loss of life. This listing shall not be construed as all inclusive. The Contractor shall provide a written job-specific hazard analysis and safety plan that addresses and conforms to the requirements of 29 CFR 1910 and 1926 and the clause entitled Accident Prevention (FAR 52.236-13) included herein. Appropriate actions shall be taken by the Contractor to implement this plan during performance and to take all other necessary steps to mitigate the dangers from hazards.

• Tree felling

• Temporary excavation / deep trenching / slope stability

• Fall hazard from work heights exceeding six feet

• Equipment operation

• Confined space entry

• Fire hazards

• Hazardous materials handling

• Mechanical hazards such as pulleys, springs etc.

H.6 SPECIAL EQUIPMENT CLEANING REQUIREMENTS

All earth moving equipment (loaders, excavators, dump trucks, etc.) moved to the job site shall be cleaned of weeds and their seeds prior to each entrance onto the National Forest lands.

Cleaning shall consist of the removal of all dirt, grease, debris and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose. Equipment shall be made available for visual inspection by the Forest Service prior to entering Forest Service lands.

The Contractor shall advise of a proposed date for mobilization. Inspections will take place at mutually agreeable in route locations in advance of entry onto National Forest lands. Special care shall be taken to assure removal of noxious weeds and their seeds.

The Contractor shall take special care under this contract to prevent contamination of water at the work sites with any petroleum residues from mechanical equipment operations. This shall include daily inspection and cleaning as appropriate.

H.7 FINAL CLEANUP

Contractor shall remove and dispose of all of its own trash and refuse from the contract area.

Material to be removed includes, but is not limited to, camp refuse such as tin cans, aluminum foil, glass, paper, garbage, used engine oil, oil filters, oil cans, grease cartridges, etc. The Contractor shall also remove and dispose of upon completion of the road construction, all stakes, old culverts, flagging and similar debris within the project area. This cleanup is a subsidiary item for which no special payment will be made. All debris shall be disposed of off National Forest Land and in accordance with State and Local disposal requirements.

H.8 PROTECTION OF CULTURAL RESOURCES

Location of known historic or prehistoric sites, buildings, objects and properties related to

FAC 2025-03 January 17, 2025

American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C. 470) and the Archaeological Resources Protection Act of 1969 (PL 96-95 and 36 CFR 261.9(e)) shall be identified on the ground by the Forest Service.

Forest Service may unilaterally modify, or cancel, this contract to protect an area, object of antiquity, artifact or similar object which is, or may be, entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified. Discovery of such areas or objects by either party shall be promptly reported to the other party.

Contractor shall protect (for each Individual Project Task Order the Contracting Officer will specify items for protection) all known and identified historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture against destructions, obliteration, removal or damage during Contractor’s Operations. In accordance with 36 CFR 296.14(c), the Contractor shall bear costs of restoration, provided that such payment shall not relieve the Contractor from civil or criminal remedies otherwise provided by law.

Wheeled or track-laying equipment shall not be operated within such areas, except on roads.

Unless agreed otherwise, trees will not be felled into such areas.

H.9 PAYMENT FOR MATERIALS DELIVERED OFF THE SITE

As provided in FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, material acquired for incorporation into the project, and stored off site by the Contractor, may, at the option of the Contracting Officer, be included in progress payments. Prior to payment, such material will be subject to Government inspection and must be stored separately from other materials, and be identified as, "PROPERTY OF THE UNITED STATES, Project Name and Contract Number." In addition, the Contractor shall furnish the Government with a right of ingress and egress to the property together with right of removal.

FAC 2025-03 January 17, 2025

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR): https://www.acquisition.gov/browse/index/far (Clauses are located at FAR part 52 and begin with 52)

Department of Agriculture Acquisition Regulation (AGAR):https://www.acquisition.gov/agar (Clauses are located at AGAR part 452 and begin with 452)

Deviations to clauses may be viewed at: USDA FAR Class Deviations

FAR 52.202-1 Definitions (JUN 2020) FAR 52.203-3 Gratuities (APR 1984) FAR 52.203-5 Covenant against Contingent Fees (MAY 2014) FAR 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) FAR 52.203-7 Anti-Kickback Procedures (JUN 2020) FAR 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper

Activity (MAY 2014) FAR 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) FAR 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN

2020) FAR 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower

Guidance to contractor employees) FAR 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) FAR 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(JUN 2020)

FAR 52.204-13 System for Award Management Maintenance (OCT 2018) FAR 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) FAR 52.204-19 Incorporation by Reference of Representations and Certifications (DEC

2014) FAR 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (NOV

2021) FAR 52.204-23 Prohibition on Contracting for Hardware, Software, and Services

Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/far/part-52 https://www.acquisition.gov/agar https://www.acquisition.gov/agar/part-452-solicitation-provisions-and-contract-clauses https://www.usda.gov/about-usda/general-information/staff-offices/departmental-administration/office-contracting-and-procurement-ocp/usda-far-class-deviations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK

FAC 2025-03 January 17, 2025

FAR 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)

FAR 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) FAR 52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition (Dec

2023) FAR 52.209-6 Protecting the Government's Interest when Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment, or Voluntarily Excluded (JAN 2025)

FAR 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

FAR 52.215-2 Audit and Records -- Negotiation (JUN 2020) FAR 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) FAR 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) FAR 52.219-8 Utilization of Small Business Concerns (JAN 2025) FAR 52.219-28 Postaward Small Business Program Rerepresentation (JAN 2025) FAR 52.222-3 Convict Labor (JUN 2003) FAR 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation

(MAY 2018)

FAR 52.222-6 Construction Wage Rate Requirement (AUG 2018) FAR 52.222-7 Withholding of Funds (MAY 2014) FAR 52.222-8 Payrolls and Basic Records (JUL 2021) FAR 52.222-9 Apprentices and Trainees (JUL 2005) (DEVIATION FEB 2025) FAR 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) FAR 52.222-11 Subcontracts (Labor Standards) (MAY 2014) FAR 52.222-12 Contract Termination - Debarment (MAY 2014) FAR 52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations (MAY 2014) FAR 52.222-14 Disputes Concerning Labor Standards (FEB 1988) FAR 52.222-15 Certification of Eligibility (MAY 2014) FAR 52.222-35 Equal Opportunity for Veterans (JUN 2020) FAR 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) FAR 52.222-37 Employment Reports on Veterans (JUN 2020) FAR 52.222-40 Notification of Employee Rights Under National Labor Relations Act

(DEC 2010)

FAR 52.222-50 Combating Trafficking in Persons (NOV 2021) FAR 52.222-54 Employment Eligibility Verification (JAN 2025) FAR 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026

(JAN 2022)

FAR 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) FAR 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts

(MAY 2024) (DEVIATION FEB 2025)

FAR 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2024) FAR 52.223-23 Sustainable Products & Services (MAY 2024) (DEVIATION FEB 2025) FAR 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) FAR 52.226-7 Drug-Free Workplace (MAY 2024)

FAC 2025-03 January 17, 2025

FAR 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving

(MAY 2024)

FAR 52.227-1 Authorization and Consent (JUN 2020) FAR 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN

2020) FAR 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) FAR 52.228-2 Additional Bond Security (OCT 1997) FAR 52.228-5 Insurance – Work on a Government Installation (JAN 1997) FAR 52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION MAY

2023) FAR 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) FAR 52.228-14 Irrevocable Letter of Credit (NOV 2014) FAR 52.228-15 Performance and Payment Bonds -- Construction (JUN 2020)

(DEVIATION MAY 2023)

FAR 52.229-3 Federal, State, and Local Taxes (FEB 2013) FAR 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) FAR 52.232-17 Interest (MAY 2014) FAR 52.232-23 Assignment of Claims (MAY 2014) FAR 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) FAR 52.232-33 Payment by Electronic Funds Transfer – System for Award Management

(OCT 2018)

FAR 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) FAR 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR

2023) FAR 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) FAR 52.233-3 Protest after Award (AUG 1996) FAR 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) FAR 52.236-2 Differing Site Conditions (APR 1984) FAR 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) FAR 52.236-5 Material and Workmanship (APR 1984) FAR 52.236-6 Superintendence by the Contractor (APR 1984) FAR 52.236-7 Permits and Responsibilities (NOV 1991) FAR 52.236-8 Other Contracts (APR 1984) FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) FAR 52.236-10 Operations and Storage Areas (APR 1984) FAR 52.236-11 Use and Possession Prior to Completion (APR 1984) FAR 52.236-12 Cleaning Up (APR 1984) FAR 52.236-13 Accident Prevention (NOV 1991) FAR 52.236-17 Layout of Work (APR 1984) FAR 52.236-21 Specifications and Drawings for Construction (FEB 1997) FAR 52.236-26 Preconstruction Conference (FEB 1995) FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by

American Security Drone Act-Covered Foreign Entities (NOV 2024) FAR 52.242-13 Bankruptcy (JUL 1995) https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf

FAC 2025-03 January 17, 2025

FAR 52.243-4 Changes (JUN 2007) FAR 52.244-2 Subcontracts (JUN 2020) FAR 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN

2025) (DEVIATION FEB 2025)

FAR 52.246-21 Warranty of Construction (MAR 1994) FAR 52.248-3 Value Engineering – Construction (OCT 2020) FAR 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR

2012)-Alternate I (SEP 1996) FAR 52.249-10 Default (Fixed-Price Construction) (APR 1984) FAR 52.253-1 Computer Generated Forms (JAN 1991)

FAR 52.225-9 Buy American Act-Construction Materials (OCT 2022)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.

However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost https://www.acquisition.gov/far/part-2#FAR_2_101

FAC 2025-03 January 17, 2025 of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.

Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners.

Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of https://www.acquisition.gov/far/part-25#FAR_25_105

FAC 2025-03 January 17, 2025 coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. Chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

None

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505 https://www.acquisition.gov/far/part-12#FAR_12_505

FAC 2025-03 January 17, 2025 content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

FAC 2025-03 January 17, 2025

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1 Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2 Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

FAC 2025-03 January 17, 2025

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]

(End of clause)

FAR 52.236-4 Physical Data (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surface observations.

(b) Weather conditions typical for this area indicate the following normal work season and fire season:

Normal work season: May through October

Restricted work season: November through April (due to heavy precipitation)

Normal fire season: March 1 – May 31, October 1 – Dec 31

(c) Transportation facilities providing access to the site are identified elsewhere herein.

(End of clause)

FAR 52.252-6 Authorized Deviations in Clauses (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.

(b) The use in this solicitation or contract of any Agriculture Acquisition Regulation (48 CFR 4) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.

(End of clause)

FAC 2025-03 January 17, 2025

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

1 Schedule of Items 2 Pages 2025/03/20 2 SOW 12 pages 2024/09/16 3 Plans 31 Pages 2024/09/16 4 Wage Rates

(WD# WV20250098, Webster County) 8 Pages 2025/02/14

FAC 2025-03 January 17, 2025

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER

STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

FAR 52.204-29 Federal Acquisition Supply Chain Security Act Orders—Representation and Disclosures (Dec 2023)

FAR 52.236-28 Preparation of Proposals – Construction (OCT 1997)

FAR 52.204-8 Annual Representations and Certifications (JAN 2025) (DEVIATION FEB 2025)

(a) (1) The North American Industry Classification System (NAICS) code for this acquisition is 237310 Highway, Street, and Bridge Construction.