This scope of work document outlines repair and deferred maintenance services required at the historic Nike Missile Site located within the Golden Gate National Recreation Area in Marin County, California. The National Park Service seeks a general contractor to provide all labor, materials, equipment and transportation necessary to complete nine contract line item numbers involving repairs to various buildings and structures at the site. Work includes rehabilitating the Missile Assembly Building flagpole, removing and replacing two bays of the Missile Loading Rack System A, painting and repairs to the Main Sentry Station, mothballing the Missile Loading Rack System B, repairs to perimeter and exclusion area fencing, replacing the roof on the Generator Building, and painting and repairs to the Missile Warhead and Flammable Storage buildings. The contractor must follow all safety, environmental and historic preservation requirements and submit a quality control plan for approval. The period of performance is not specified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE INTERIOR

NATIONAL PARK SERVICE

GOLDEN GATE NATIONAL RECERATION AREA

FORT MASON, SAN FRANCISCO, CA 94123

SCOPE OF WORK FOR A GENERAL CONTRACTOR TO REPAIR AND CORRECT

DEFERRED MAINTENANCE AT NIKE SITE:

MISSILE ASSEMBLY BLDG FLAGPOLE FA963; MISSILE LOADING RACK SYSTEM

A REPLACEMENT FA969; MAIN SENTRY STATION BLDG REPAIRS FA970;

MISSILE LOADING RACK SYSTEM B MOTHBALL FA 971; PERIMETER FENCE

REPAIRS; GENERATOR BLDG ROOF FA 966; MISSILE WARHEAD BLDG REPAIRS

FA967; FLAMMABLE STORAGE BLDG FA 972 ROOF & RODENT PROOFING

AT FORT BARRY/SAUSALITO, CALIFORNIA

1.0 GENERAL

Project Identification: The project is located at the NATIONAL REGISTER OF HISTORIC PLACES LISTED NIKE MISSILE LAUNCH SITE within the Golden Gate National Recreation Area, Marin County, CA. The work of this contract shall consist of the construction project tasks described below for the referenced project. In this document, the construction project shall be referred to as “the Project.”

Contracting Officer’s Representative: The Contracting Officer’s Representative (COR) is designated by the Contracting Officer (CO) and shall serve as the primary POC for all technical matters. The COR is also responsible for the approval of submittals, progress payments, and acceptance and rejection of work. The COR for this project is Jason Hagin, Fort Mason Bldg 201, San Francisco, CA 94123, (415) 561-4973, Jason_Hagin@nps.gov.

1.1 BACKGROUND:

Nike Missile Site SF-88L is a nationally significant Cold War era property on the National Register of Historic Places. It is the best-preserved Nike missile launcher site in the nation, and the site in the National Park System that best represents the Cold War historic theme and context. The site presently houses more than $40 million worth of cultural resource objects and equipment, including a majority of Nike missiles left in the United States (all of which are inert).

The damp, marine environment of the seaside location requires an intensive program of cyclic maintenance in order to avoid serious and irreversible damage to this nationally significant resource and very popular visitor attraction. When in operation, there were 120 soldiers whose duties involved constant care of the site and its delicate equipment, and we must devote at least a fraction of this effort to its continued unimpaired preservation.

RFP No. 140P8621R0013 Section J - Attachment No. 002

The Missile Assembly Building Flagpole (FA963) is operational, and consists of a custom fabricated steel base comprised of two 2”x6” steel channels welded to a 2’-0” x 2’0” ¼” thick steel base plate and including an integral weighted steel tube flagpole that can be bent to the ground by a pivot pin in the steel base. The flagpole needs to be disassembled, preserving hardware if feasible or replacing it to match existing character and technical performance, and the base structure prepared, repaired in the shop using welded patches and limited replacements, then hot-dipped galvanized and reinstalled. The flagpole requires field metal treatment to address rust, and then needs to be reinstalled in the base and erected to a vertical position, ready for operation.

The Missile Loading Rack System at Magazine A (FA969) consists of modular steel trusses with two parallel tracks about 30 inches above ground and are used to convey missiles to and from the launch assemblies. The two main components of the loading racks are a support assembly and a side truss assembly. The support assemblies stand on adjustable leg base and column assemblies, which are anchored with threaded rods, designed to accommodate uneven ground, and include support columns that are secured to the side truss with headless bent pins. The top chord of the side trusses bears on the support assemblies and are also secured with headless bent pins. Many components of the loading rack system at Magazine A are rusted, deteriorated and in need of repairs. To the extent of available funding, currently installed components need to be disassembled and removed (16 Side Truss assemblies, up to 8 Support Assemblies, and up to 16 leg base and column assemblies);

replacement support assembly, side truss assembly, leg bases and column support components supplied by the Government need to be reinstalled to comprise a re-assembled Loading Rack System in good condition that can again convey missiles to the launchers.

Installation of new epoxy dowel anchors and leveling bolts (up to 64 locations) must be included to accommodate the slope of finish grade. There is an OPTION Metal Painting & Repairs scope to prepare and paint the Magazine A Elevator doors, and their adjacent associated metal and concrete features.

The main entry Sentry Station (FA970) is a 142 sq. ft (5’-5” x 7’-5”) concrete block guardhouse building constructed in 1959. The exterior of the building, including three windows and one door needs to be painted (230 sf); the roof trims and flashings need repairs and door needs to be rodent-proofed.

The Missile Loading Rack System at Magazine B (FA971) is a similar system to the Magazine A System located at the adjacent missile magazine. It is in poor condition and in need of mothball treatment. Many components of the loading rack system at Magazine B are rusted, deteriorated and in need of replacement. To the extent of available funding (labor, materials and equipment estimate), spare parts and parts identified by the COR as “very poor condition to be removed” shall be removed and disposed, including (quantity) (3) Side Assembly; (6) Side Truss; (2) Expansion Assembly; (2) Magazine Elevator Doors. Haul and dispose of stockpiled and miscellaneous rubbish, including e-waste: (35 yards). Dispose of one abandoned fiberglass portable toilet unit. And as directed by the CO, replace miscellaneous existing wood blocking with new plastic lumber nominal 6x6 blocks cut to length as required for the following items stored on site: (quantity) (2) elevator doors; (2) radar units; (3) rocket motor units; include allowance for (5) spare parts. Dispose of existing wood blocks.

The Perimeter Fence and Exclusion Area Fence needs to be repaired with an allowance for new replacement 45º arms, and 920 linear feet of three-strand barbed wire needing to be re-hung (total both fence lines).

The Generator Building (FA966) is an 820 sq. ft (20’-0” x 41’-0”) concrete block building constructed in 1965. A new modified bitumen roof with cap sheet and gravel topping to match the existing (820 sf), including replacement and painting of new metal roof flashings (122 lf), trims and appurtenances, and including stabilization, reinstallation and painting of metal ventilators, is needed.

The Missile Warhead Building (FA967) is a 784 sq. ft. concrete block building 20’-0” x 40’-0” with metal rolling doors at either end constructed in 1959. Historic exterior vapor lights need repairs (3 units); metal gutters and downspouts need repairs (16 lf); a small section of concrete block at the roof needs repair (8 sf); exterior of the building needs to be repainted (2400 sf).

The Flammable Storage Building (FA972) is a 54 sq. ft (7’-3” x 7’-3”) concrete block storage building constructed in 1961. A new modified bitumen roof with cap sheet and gravel topping to match the existing (64 sf), including replacement and painting of new metal roof flashings (36 lf), trims and appurtenances, and the door needs to be rodent-proofed. There is an OPTION for repairs to roof framing and fascia, and painting the exterior of the building (230 sf).

1.2 SCOPE:

A. Contractor shall furnish all necessary supervision, labor, tools, parts, material, equipment, appurtenances and transportation for the “Repair and Correct Deferred Maintenance at Historic Nike Site Project.” The Project is located in Fort Barry in the Marin Headlands near Rodeo Beach in The Golden Gate National Recreation Area (GGNRA), Sausalito, Marin County, California as specified herein.

B. Contract documents provided by the Contracting Officer will include archive drawings, site photographs and initial bid site walk through. This information will be made available from Jason Hagin, Historical Architect, Contracting Officer’s Representative (COR), Building 101 Fort Mason, (415) 561-4973, E-mail: Jason_Hagin@nps.gov

1.3 PROJECT DESCRIPTION

The Contractor shall provide all supervision, labor, tools, parts, material, equipment and transportation to complete the following project work items (the Contractor shall take into account the site conditions in project planning and submittal of the proposal and at minimum provide water and electrical power as required for the project - toilet facilities are provided nearby the work site and a portable toilet is available for use at the site):

CLIN 1 Missile Assembly Building Flagpole Rehab & Repair (FA963): Disassemble on site, preserving hardware if feasible or replacing it to match existing character and technical performance. Remove and repair flagpole base in the shop using welded patches and limited replacements, hot dip galvanize, and reinstall (unpainted) using new galvanized epoxy anchor bolts to replace existing. Perform field metal treatment to address rust and paint the metal flagpole; reinstall in the repaired base and erect to a vertical position; make all repairs necessary to ready for operation and use.

Fig. 1 – Missile Assembly Building Flagpole

CLIN 2 Loading Rack System A (FA969) Remove Existing & Replace 2 Bays:

Disassemble and remove existing loading rack system components consisting of 16 Side Truss assemblies, up to 8 Support Assembles, and 16 leg base and column assemblies.

Prepare site for installation of epoxy dowel anchors for replacement column leg bases by core- drilling out the historic lead anchors and reuse hole for new anchors if feasible – if not feasible for reuse then fill the core hole with non-shrink grout colored to match adjacent surface, rotate base 45 degrees from original position and prepare for install of new epoxy anchors (64 locations of original anchors). Install new ½” galvanized threaded rod with 6” epoxy embed (64 locations). Re-assemble loading rack system on newly installed epoxy anchors, consisting of 16 Side Truss assemblies, 8 Support Assembles, and 16 leg base and column assemblies provided by the Government.

Fig. 2A Loading Rack System A Looking South

Fig. 2B - Loading Rack System Component Diagram

CLIN 3 Main Sentry Station Painting & Repairs (FA970) (5’-5”W x 7’-5”L x 9-0”H):

Install metal door sweep, metal threshold and repair wood door stop to rodent-proof the building entry door. Repair wood roof facia, metal flashing and miscellaneous wood trims and roof framing. Remove loose and flakey lead-based paint on building exterior. Repaint building exterior.

Fig. 3 – Sentry Station Looking North

CLIN 4 Loading Rack System B (FA971) Mothball: As directed by CO, remove and dispose of Rack System spare part in very poor condition: (3) Side Assembly; (6) Side Truss;

(2) Expansion Assembly; (2) Magazine Elevator Doors. Haul and dispose of stockpiled and miscellaneous rubbish, including e-waste: (35 yards). Dispose of abandoned fiberglass portable toilet unit. As directed by CO, replace miscellaneous existing wood blocks with new plastic lumber nominal 6x6 blocks cut to length as required: (2) elevator doors; (2) radar units; (3) rocket motor units; allowance for (5) spare parts. Dispose of existing wood blocks.

Fig. 4 Loading Rack System B Looking East

CLIN 5 Perimeter & Exclusion Area Fence Repairs: Repair/replace existing 3-strand barbed wire (barbed wire only - no work on chain link panels). Include an allowance for hanger arms and miscellaneous hardware. Basis of estimate is 920 linear feet of 3-strand, galvanized, 12.5 ga., 4 point, 5" spaced barbed wire.

Fig. 5A Perimeter Fence Looking West

Fig. 5B Exclusion Area Fence Looking West

CLIN 6 Generator Building Roof (FA 966) (20’-0” x 41’-0”): Demolish existing and install new BUR with gravel surface including all flashings and trims to match existing -reuse existing ventilator units.

Fig. 6. – Generator Building Looking West

CLIN 7 Missile Warhead Building (FA967) Painting & Repairs (20’-0”Wx40’-0”Lx14’-0”H):

Repair exterior vapor lights. Repair metal gutters and downspouts. Repair broken concrete block at southeast roof corner. Remove loose and flakey lead-based paint on building exterior. Repaint building exterior.

Fig. 7 – Warhead Building Looking South

CLIN 8 Flammable Storage Building (FA972) Roof Replacement (7’-5”W x 7’-5”L x 9- 0”H): Demolish existing and install new Built-Up Roof (BUR) with gravel surface including all flashings and trims to match existing.

Fig. 8 Flammable Storage Building Looking West

CLIN 9 OPTION: Flammable Storage Building (FA972) Painting & Repairs (7’-5”W x 7’-5”L x 9-0”H): OPTION: Install metal door sweep, metal threshold and repair wood door stop to rodent-proof the building entry door. Repair wood roof facia, metal flashing and miscellaneous wood trims and roof framing. Remove loose and flakey lead-based paint on building exterior. Repaint building exterior.

CLIN 10 OPTION: Elevator A Doors (FA969) Painting: OPTION: Remove loose and flakey lead-based paint on steel magazine elevator doors, adjacent metal plates and concrete curbing, steel magazine double entry doors, and (2) steel hatches. Paint steel magazine elevator doors, adjacent metal plates and concrete curbing, steel magazine double entry doors, and (2) steel hatches.

Fig. 11 – Elevator B Doors for Illustration Only (Elevator A Doors FA 969 Similar)

1.3.1 GENERAL NOTES AND SPECIFICATIONS:

The quality of workmanship, quality and the type of materials, and the details of construction shall conform to all applicable portions of the highest standards except where requirements of the drawings and specifications are in excess thereto, in which case the drawings and specifications shall take precedence.

Materials and accessories, and equipment with model numbers, catalog numbers, and descriptions are shown on the drawings. Shop drawings, catalog cuts, etc., shall be submitted for approval by the Contracting Officer’s Representative (COR).

Note that the Nike Site will remain open to visitors at the hours posted, and at other hours as may be necessary for the operation of the historic site.

The contractor shall not close or obstruct walkways, or passages unnecessarily, and will not place, nor store, material in walkways, in the courtyard general or in passageways.

The contractor shall take precautions to protect all park visitors and park staff members from injury and safety hazard, as well as protect all of those portions of the structure which are not being worked on from any sort of damage. Any damage which does occur will be repaired by the Contractor at no cost to the government.

Existing coatings are presumed to be lead-based paint.

1.3.1.1 DEMOLITION AND SALVAGE

The contractor shall furnish labor and materials to complete the demolition indicated, as specified herein, or both.

Items to be demolished – generally, but not restricted to this list:

1. Lumber, trims and roofing materials associated with roofing replacement;

2. Miscellaneous metals

3. As required selective demolition for repairs of existing features noted above.

4. As required with prior approval by COR for limited replacements of existing features noted above.

If the contractor has any doubts concerning the demolition, or the extent of demolition, he shall contact the COR for confirmation (or otherwise) of the parts to be demolished.

The contractor shall execute demolition work to ensure that adjacent portions of the resource are not damaged from falling debris or other causes.

Remove as it accumulates, excess debris, except as otherwise specified, resulting from demolition operations. Do not store or permit debris to accumulate on site. If the contractor fails to remove excess debris promptly, the NPS reserves the right to cause same to be removed at the contractor’s expense.

Contractor shall follow NPS Waste Management specifications provided by the Contracting Officer. Lead based paint contaminated waste management must be coordinated with the NPS Environmental Protection specialist and as directed by the COR.

1.3.1.2 FERROUS METALS

The contractor shall deliver, store, handle metals to prevent damage to whatever nature, and clean finished metal work surfaces free from stains, markings defects of any kind.

Mild steel – hot rolled mild steel, 0.15% to 0.25% carbon range

Structural steel – ASTM, A36/A36M. Accessories and connections for steel, unless otherwise required: Steel.

Welding rods – ASTM, A233.

Galvanized steel shapes – galvanized in accordance with ASTM, A525 or superseding and prevailing ASTM standard.

1.3.1.3 WELDING AND EQUIPMENT

American Welding Society’s “Code for Welding in Building Construction,” subject to applicable laws and ordinances.

Fabrication and Welders: licensed operators.

Welding not otherwise covered herein: Conform to best modern practice, adequate strength, durability, with jointing made tight, flush, in true planes with base metals, clean, smooth.

1.3.1.4 METAL TREATMENTS

Field Metal Work & Metal Painting: Metal repairs done in the field and including limited metal replacement with field welding as required; Power Tool Cleaning -SSPC/SP3; Prior to painting clean and remove visible and soluble surface contaminants per SSPC/SP1.

Spot Prime rusty metal with Devoe Pre Prime 167 100% Solids Epoxy Sealer or approved equal.

Second coat Devoe Bar Rust 235 Surface Tolerant Epoxy Coating or approved equal.

Finish with two coats Devoe Devthane 378H aliphatic urethane semigloss finish or approved equal; color provided by the Government.

Shop Metal Work: Hot dip galvanizing-after repairs and/or new fabrications and before painting, ferrous metals: Clean thoroughly to remove completely any oil, grease, dirt; pickle in hot dilute solution of sulfuric acid to insure removal of mill scale and other foreign matter;

rinse thoroughly in clear water; air dry; dip in bath of molten prime virgin zinc; ASTM, A123; coating: adherent; smooth; and free from uncoated spots. Zinc coating weight per square foot of actual surface: Average of not less than 2.0 ounces.

1.3.1.5 MISCELLANEOUS METAL PAINTING

Surface preparation prior to painting shall be as recommended by Steel Structures Painting Council (SSPC). Oil, grease, or salts shall be removed by solvent cleaning as outlined in Specifications SSPC-SP 1. Rust and loose mill scale shall be removed by hand tool cleaning in accordance with SSPC-SP 3.

Spot Prime rusty metal with Devoe Pre Prime 167 100% Solids Epoxy Sealer or approved equal.

Second coat Devoe Bar Rust 235 Surface Tolerant Epoxy Coating or approved equal.

Finish with two coats Devoe Devthane 378H aliphatic urethane semigloss finish or approved equal; color provided by the Government.

Use, Kelly Moore, Tnemec, Benjamin Moore, Sherwin Williams or approved equal product.

1.3.1.6 WOOD REPAIRS AND REPLACEMENTS

The contractor shall deliver, store, handle lumber to prevent damage to whatever nature, and clean finished woodwork surfaces free from stains, markings defects of any kind.

Lumber – American Softwood Lumber Standard PS-20-86.

Moisture Content: 19 percent maximum (dry) at time of manufacture for lumber 2 inches or less in thickness.

Surfacing: S4S, unless otherwise specified.

Species: Redwood or cedar

Window Sash, Fascia, Trim and Miscellaneous Appearance Lumber: Provide species as noted and grades for items to be finish painted

Wood restoration consolidants and epoxy repair filler compounds shall be high quality and shrink-free; Abatron LiquidWood, WoodEpox or approved equal.

1.3.1.7 WOOD PAINTING

Oil, grease, or salts shall be removed by solvent cleaning. Remove sap on wood surfaces by scraping and washing with turpentine. Sand all interior wood before priming.

Seal all knots or resinous areas with knot sealer and allow to dry at least 2 hours before priming. Fill all gouges, dents, and small openings in interior wood with plastic wood tinted for stained or natural appearance. Allow plastic wood to dry before painting.

Back prime backs, edges, and ends of interior and exterior wood.

Adjust natural finishes as necessary to obtain a like appearance on veneers and solid stock.

Finish interior stained work to a furniture smooth surface.

General Painted Wood – Exterior:

Low Luster;

1st coat: 255 AcryShield 100% Acrylic Stain Blocking Primer 2nd coat: 1245 AcryShield 100% Acrylic Low Sheen, color to match existing 3rd coat: 1245 AcryShield 100% Acrylic Low Sheen, color to match existing

Use, Tnemec, Benjamin Moore, Sherwin Williams, Kelly Moore or equal product.

1.3.1.8 CONCRETE/MASONRY PAINTING

Oil, grease, or salts shall be removed by solvent cleaning.

General Painted Concrete/Masonry – Exterior:

Low Luster;

1st coat: 295 Kel Bond Universal Primer 2nd coat: 1245 AcryShield 100% Acrylic Low Sheen, color to match existing 3rd coat: 1245 AcryShield 100% Acrylic Low Sheen, color to match existing

Use, Tnemec, Benjamin Moore, Sherwin Williams, Kelly Moore or equal product.

1.3.1.9 BUILT UP ROOFING

The built-up roofing system shall be equal to Johns-Manville Corporation Specification No. 4GNG, which has been used as a basis for this general specification. Other systems will be considered as an approved equal.

Remove existing built-up roofing, install new built-up roofing.

Install new flashing as required for performance of work, and as required to complete the work;

paint to match existing surfaces.

Touch-up paint on any wood, gutters and down spouts and miscellaneous appurtenances to match existing surfaces.

• Materials: All materials shall be furnished by, or approved by, manufacturer of the roofing system.

• Sheathing Paper: As recommended by manufacturer.

• Felts Base Felt: Glasbase; Finishing Felt: GlasPly.

• Bitumen: ASTM D3 12-84, Type III.

• Gravel or Slag: ASTM D1863-83. Match existing

• Cant Strip: Asphalt impregnated fiberboard, size as shown, as manufactured by

Celotex Corporation, Tampa, Florida, or approved equal.

• Base Flashing: ANSI/ASTM B370, cold rolled temper, weighing a minimum of

16 oz. per square foot.

• Fasteners: Nails with annular or spiral threads, driven through tin caps if the heads are less than 1 inch in diameter, or staples power driven through tin caps. Nails shall not penetrate eaves or overhangs leaving points exposed, use longest fastener possible without breaking through exposed overhang sheathing.

• Gravel Stops: Shall be 26-gauge galvanized steel, sheet, zinc coated.

• Other Exposed Metals: ANSI/ASTM A527-80. Steel, sheet, zinc coated galvanized), lock forming quality. Zinc coating designation, ASTM A525-83, G90.

INSPECTION: Determine that deck surfaces are in suitable condition or report unsuitable surfaces to Contracting Officer.

FIRST FELT: Apply felt horizontally, starting at the low edge. Working up the slope, lap each felt 2 inches over the preceding one. Nail laps at 9 inches on center. Down the longitudinal center of each felt, nail two rows approximately 11 inches apart. Place nails in each row 18 inches on center and offset the second row so that each nail is centered between nails of the first row. In addition, nail a 3” wide flat metal (galvanized) strap every 3 feet on base felt to the roof sheathing. Nail the metal strap at 6” on centers securely to the roof sheathing.

ROOF FLASHING: Install new pre-formed metal flashing on all vents, skylights and other protrusions on the roof. Replace drip edge flashing to cover and protect joints in wood fascia boards at corners. Replace all existing flashing with new galvanized flashing, painted to match existing adjacent surfaces.

BITUMEN: Apply bitumen between felts within the equiviscous temperature range determined by the bitumen manufacturer. Mop uniformly over the entire surface just before placing each layer of felt. Felt shall not touch felt.

SECOND, THIRD, AND FOURTH FELTS: Starting at the low edge, apply one 12-inch-wide, then over that one 24-inch-wide, then over both a full 36-inch-wide felt. Apply following felts full width overlapping the preceding felt by 24-2/3 inches in such a manner that at least three plies of felt cover the base felt at any point. Nail each felt at approximately 9-inch centers adjacent to the back edge. Broom each felt so that it is firmly and uniformly set without voids into hot bitumen.

SURFACING: Flood the surface with bitumen, and while it is hot, embed gravel or slag.

Complete installation of built-up roofing system, including aggregate surface, up to line of termination of day’s work.

1.4 WORK SEQUENCE

A. The Work will be conducted in such a manner to provide the least possible interference to occupant access in the area and that causes no damage to historic cultural or natural resources.

1.5 PUBLIC ACCESS AND SAFETY

1.5.1 During the course of this project, the Contractor shall at all times:

A. Conduct operations to ensure public safety and the least inconvenience to the public.

B. Maintain access for National Park Service administrative and other official business throughout the construction phase.

C. During working hours, secure areas that are under construction from visitors.

D. Leave construction area in a condition that is safe for visitors on weekends, holidays, and other times when contract work is not in progress.

1.6 CONTRACTOR USE OF PREMISES

A. Emergencies: Emergency telephone numbers must be posted at all phones at the job site:

Fire/Emergency Medical Service/Police – 911 or (415) 561-5656.

NOTE: This site is outside of most cellular service.

B. Site & Features Protection: The Nike Missile Site lies within a National Register Historic District. Because of its significance, all parties are to take all measures necessary during the performance of the work to maintain and protect the historic fabric of the site. Contractor supplied padlocks shall be provided at gates to allow access for the duration of the Project.

Plan and perform all work with extreme care to ensure that no building or site features are damaged. Note that all features to remain in place, whether historic or non-historic, should be protected during construction.

C. Occupied Sites & Structures: This surrounding site will be open to visitation throughout construction. Contractor must provide temporary enclosures, barricades, signage, etc. as required to protect adjacent occupied spaces and public areas such as building facilities and materials, etc. from dust, noise and debris associated with performing the work.

D. Hours of Work: Work must be performed between 7:00 am and 5:00 pm, Monday through Friday. Requests to work outside designated hours must be given in writing a minimum of two (2) working days prior to scheduling and must be approved in writing by Contracting Officer’s Representative.

E. Fire Safety - Construction activities are to be conducted in accordance with NFPA 241, Standard for Safeguarding Construction, Alternation and Demolition Operations. Smoking must be prohibited at or in the vicinity of hazardous operations or combustible/flammable materials. Smoking must be permitted only in a designated area. Provide 2A:10B:C fire extinguishers with current State Fire Marshall tags affixed to them in all work/office areas.

Combustible materials must not be allowed to accumulate on site. Store all fuels and flammable liquids in a commercially available flammable storage locker, at least 50 feet from any structure. Have storage lock-up clearly marked "FLAMMABLES" "KEEP FIRE

AWAY".

F. Vehicle Refueling: Motorized equipment will be operated so that exhausts do not discharge against combustible materials. Refueling on-site is prohibited.

G. Hot Work Permit: A hot work permit is required for any torch cutting, welding or heat gun work. No open flame torch work will be allowed. The permit will be issued by the NPS Fire Inspection office to the Contractor and will be good through completion of work. The Contractor will be responsible for ensuring that all workers and subcontractors follow permit conditions. Contact the GOGA Fire Inspection and Prevention Office (415-289-1813) a minimum of three days prior to the date the hot work permit is needed to avoid delays in work.

H. Stop Work Orders. GGNRA reserves the right to stop work at any time for emergencies/safety violations, and NEPA and NHPA violations. Emergency and safety stop work orders may be issued directly by GGNRA Safety Officer and/or GGNRA Public Safety personnel (law enforcement/fire). All other stop work orders will be issued through the project POCs (GGNRA).

I. Construction Camp: Establishment of a camp within the park will not be permitted. The work site (including containment area) will be closed to the public during construction.

However, maintain access for National Park Service administrative and other official business throughout the construction phase. Confine storage of materials to the work site.

Contractor must at all times conduct his operations to ensure the least inconvenience to the visiting public.

J. Preservation of Natural Features - Vegetation: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government. Provide temporary barriers to protect existing trees and plants and root zones. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer’s Representative and remove agreed-on roots and branches that interfere with construction. Do not fasten ropes, cables, or guys to existing trees.

K. Preservation of Natural Features - Wildlife: Do not approach, disturb, harass or feed wildlife.

L. Environmental Protection: Properly clean up, mitigate and remedy, if necessary, all spills of petroleum products, hazardous materials, or other chemical or biological products released from the construction from construction vehicles or stationary sources. Immediately report to the Contracting Officer’s Representative any spill of petroleum products or a hazardous material. Report the spill to the appropriate federal, state and local authorities, if the spill is of a reportable quantity. Separate work area, including material sources, by the use of a dike or other suitable barrier that prevents petroleum products, chemicals or other liquid or solid material from entering the waters of the U.S.

1.7 GOVERNMENT FURNISHED MATERIALS.

A. The Government will furnish Missile Loading Rack System A components including 16 Side Truss assemblies, up to 8 Support Assembles, and up to 16 leg base and column assemblies, and associated Rack System parts as required. The Government will not furnish any other supplies, materials or equipment to the Contractor for the Project.

1.8 CONTRACTOR ACCESS AND USE OF THE SITE

A. Contractor shall maintain control of the site during the period of construction by creating perimeter control through fences or other means specified and approved by the Project Manager.

B. Contractor shall provide OSHA and other required postings regarding safety at the site

C. All Contractor employees and subcontractor employees shall be advised of the rules and regulations of the National Park Service.

1.9 CLEANUP

A. The Contractor shall at all times keep the work area including the storage areas to be used from unnecessary accumulation of waste material and rubbish. All Contractor generated waste material and rubbish shall be removed upon completion of the work from the premises and disposed of properly in accordance with all Local, Municipal, State and Federal regulations.

B. Upon completion of work, the Contractor shall ensure that the Project area is in a clean, neat and orderly condition satisfactory to the Project Manager.

1.10 PARKING

A. Parking for Contractor’s vehicles shall be in designated spaces as directed by the COR.

1.11 UTILITIES

A. The Contractor is advised that there no potable water available in the general area of the work site. Contractor shall provide water and electrical power as required for the project -toilet facilities are provided nearby the work site and a portable toilet is available for use at the site

1.12 OPERATING HOURS

A. Regular work hours shall be between 7:30 AM and 4:30 PM, Monday through Friday, excluding Saturdays, Sundays, and Official Government holidays.

B. If the Contractor intends on working outside of the regular work hours noted prior approval must by COR is required.

1.13 FIELD VERIFICATION

A. Contractor shall perform field verification of all existing conditions affecting the work associated with this contract before ordering of parts, materials and equipment.

1.14 KEY CONTRACTOR PERSONNEL.

A. For the duration of this contract, the Contractor shall appoint a Supervisor and/or Point of Contact and provide the contact information to the COR.

1.15 GOVERNMENT POINTS OF CONTACT

1.15.1 The following are the Government Points of Contact for this contract:

Contracting Officer: Kyle Dansika (559) 565-3180 Office, E-mail: Kyle_Daniska@nps.gov

Contracting Officer’s Representative: Jason Hagin, Historical Architect, Building 101 Fort Mason, (415) 561-4973, E-mail: Jason_Hagin@nps.gov

2.0 SAFETY AND ACCIDENT PREVENTION:

2.1. The contractor shall formulate and submit a written safety and health plan for acceptance by the Government. The written plan shall include the details of the contractor's safety organization, responsibilities, method of program implementation, and how hazards and deficiencies shall be identified and corrected. It shall detail employee's responsibilities for:

protection of Government property and safety of others, employee's responsibilities for reporting all mishaps, and establish procedures for reporting or correcting unsafe conditions, hazards, or practices. The plan shall also contain mishap notification and reporting procedures. The contractor shall have a central POC for safety and health related issues and the POC shall be identified in writing.

2.2. The contractor shall ensure employees have safety education when engaged in activities involving Government facilities, personnel, or equipment.

2.3 The contractor shall immediately notify NPS Safety Officer of all accidents/incidents involving employee use of and/or damage/injury to facilities, equipment, or personnel.

2.4 The contractor shall require their personnel to wear safety shoes/boots IAW OSHA standards

2.5 The contractor shall provide all required personal protection equipment, (e.g. respirators, hearing protection, eye protection, gloves, steel-toed boots, aprons, masks, face shields, reflective vests, etc. IAW OSHA Standards.)

3.0. ENVIRONMENTAL REQUIREMENTS

3.1 The Contractor shall comply with all federal, state, and local environmental laws, and NPS policies and regulations to include but not limited to Resource Conservation, Safe Water Drinking Act (SWDA), the Clean Air Act (CAA), and Federal Facilities Compliance Act

(FFCA).

3.2 The use, handling, storage, and disposal of all toxic, hazardous, special or radiological wastes/materials shall be in accordance with all local, State, Federal, and NPS Environmental Regulations and procedures; and coordinated with the NPS Environmental Safety Programs Office and as directed by the COR. Contractor personnel shall be trained by the Contractor on proper procedures to include spill response and clean up.

3.3 Environmental Management Plan. The Contractor shall provide a complete environmental plan to assure compliance with all environmental statutes and regulations. One copy of the plan shall be provided to the COR for submittal to the park Safety Officer at contract start and as changes occur.

3.4 Vehicles and equipment. All vehicles, tools, equipment and boots entering the project area must be clean of noxious weeds and free from oil leaks and are subject to inspection.

Wash all construction vehicles, tools and equipment thoroughly remove all dirt, plant, and other foreign material prior to entering the project. Particular attention must be shown to the under carriage and any surface where soil containing exotic seeds may exist. These efforts are critical to prevent the introduction and establishment of non-native plant species into the project area. Make arrangements for the CO to inspect each piece of equipment before entering the project.

4.0 QUALITY CONTROL PLAN

All work of the project shall conform to the Secretary of the Interior’s Standards for the Treatment of Historic Properties and meet or exceed applicable sections and requirements of the 2016 California Historical Building Code. The quality of all work and the performance of all furnishings, fixtures and equipment shall be the responsibility of the Contractor. Tests, inspections, and related actions by independent third-party inspectors must be included in the Contractor's quality assurance and control procedures to facilitate compliance with the Contract Document requirements and as needed to ensure compliance with the Building Code.

Contractor shall submit to the COR a “Quality Control Plan” for review and approval. The Quality Control Plan shall include:

1. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

2. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

3. Methods of performing, documenting, and enforcing quality control of all work, including examples of construction progress and quality control reports.

4. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

4.1 CONTRACTOR PRODUCTION AND QUALITY CONTROL REPORTS

Contractor shall complete standard format daily construction progress reports and weekly quality control reports. Contractor shall submit the reports electronically in a timely manner to the COR.

5.0 SUBMITTAL AND APPROVAL PROCEDURES

A. All submittals must be transmitted using National Park Service form DSC-1(CS), dated 11/95. No action will be taken on a submittal item unless accompanied by the transmittal form. As specified in the individual sections, forward submittals to Contracting Officer’s Representative at least 30 days before need for approval. Unless a different number is specified, submit 1 reproducible original and 2 copies of each shop drawing, 2 copies of manufacturer's catalog sheets (product data sheets), 1 specimen of each sample, and 2 copies of all other submittals requested.

B. Shop Drawings: Include the following information with each copy of shop drawings:

Date; Date of revisions (when applicable); Details of fabrication, assembly and erection including connections and engagement to contiguous work; Materials used; All required dimensions. The term "by others" must not be used. All work to be performed by others must be identified by Contractor or subcontractor name, discipline, or trade.

C. Samples: Samples must be large enough to illustrate clearly the functional characteristics and full range of color, texture, or pattern.

D. Manufacturers' Catalog Sheets: Submit only pertinent pages; mark each copy of standard printed data to identify specific products proposed for use.

E. Manufacturer's Installation Instructions: When contract documents require compliance with manufacturer's printed instructions, provide one complete set of instructions for COR and keep another complete set of instructions at the project site until substantial completion.

F. COR reserves the right to require submittals in addition to those called for in individual sections.

G. Approved Equals: For each item proposed as an "approved equal," submit supporting data, including the following: Samples as appropriate; Comparison of the characteristics of the proposed item with that specified; Changes required in other elements of the work because of the substitution; Name, address, and telephone number of vendor; Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists - Describe availability of maintenance service, and state source of replacement materials.

H. A request for approval constitutes a representation that Contractor: Has investigated the proposed item and determined that it is equal or superior in all respects to that specified; Will provide the same warranties for the proposed item as for the item specified; Has determined that the proposed item is compatible with interfacing items; Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution; Waives all claims for additional expenses that may be incurred as a result of the substitution.

I. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements.

Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal must contain only data specific to that individual submittal.

J. Submittal Identification: Contracting Officer may provide a project identification stamp which must be applied by the Contractor. Identification must include the park name-package number, project title, contract number, and transmittal number. All sets of shop drawings, manufacturer's catalog sheets, samples, and other documents submitted to the Contracting Officer’s Representative must have the identification information stamped on the submittal.

Identification information must be applied to the bottom right margin on each page.

Identification information on samples must be applied to the most readily visible area on the sample or on tags attached to sample.

K. Submittal Numbering: Number each submittal consecutively. For re-submittals use the original submittal number, plus a letter suffix beginning with A. Additional re-submittals of the same item must contain the original number with the next consecutive letter.

L. Contracting Officer’s Representative's Review: Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor's approval. Any work done or orders for materials or services placed before approval must be at the Contractor's own risk.

After reviewing submittals, the Contracting Officer’s Representative will return one copy of form DSC-1(CS) and one copy of applicable (marked up) submittal sheets to the Contractor.

Shop drawing review notations will be returned on the reproducible original shop drawing.

All other submitted items will be retained. The Contractor is responsible for producing additional copies for his/her own use. The returned submittal will be marked in one of three ways as defined below:

APPROVED: Acceptable with no corrections.

APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear, and no further review is required. The Contractor must address all review comments when proceeding with the work.

DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer’s Representative will identify the reasons for disapproval. The Contractor must revise and resubmit with changes clearly identified.

4.0 INVOICING

Vendor shall submit invoices via www.ipp.gov.

END OF SECTION

Oil, grease, or salts shall be removed by solvent cleaning. Remove sap on wood surfaces by scraping and washing with turpentine. Sand all interior wood before priming.
Seal all knots or resinous areas with knot sealer and allow to dry at least 2 hours before priming. Fill all gouges, dents, and small openings in interior wood with plastic wood tinted for stained or natural appearance. Allow plastic wood to dry bef...
Back prime backs, edges, and ends of interior and exterior wood.
Adjust natural finishes as necessary to obtain a like appearance on veneers and solid stock. Finish interior stained work to a furniture smooth surface.
General Painted Wood – Exterior:
Oil, grease, or salts shall be removed by solvent cleaning.
General Painted Concrete/Masonry – Exterior:

File details come from the government source that posted it. Updated .