This file is a Schedule B.3 snow removal specifications document for the State of Michigan, issued under Request for Proposal (RFP) No. 260000002416 for Janitorial, Grounds, and Snow Services at the Davisburg Rest Area in the Metro Region. The specifications detail snow and ice removal requirements as part of a broader service contract. Snow removal must be completed by 7:00 a.m. following any accumulation of 2 inches or more of snow on any given day, including weekends and holidays, with multiple service trips required during heavy snowfall events. The contractor is responsible for clearing entrance ramps, car parking areas, truck parking areas, and exit ramps while ensuring snow is not piled to create vision obstructions or hazards to the public. Snow storage must comply with a provided map or areas designated by the Program Manager, and state law prohibits pushing snow across or onto adjacent roads and shoulders. The contractor must respond to emergency calls for additional snow or ice removal services within one hour of notification and must notify the Program Manager no later than the next day after work is performed.
The specifications establish that contractors must furnish, operate, and maintain all necessary equipment to keep driving surfaces free from ice and snow, and equipment failure does not constitute an acceptable reason for service non-performance. Contractors are prohibited from storing snow removal equipment on state property, and the State assumes no responsibility for theft, vandalism, or damage to contractor equipment. Deicer must be applied using granular or approved liquid products when hard-packed snow or ice remains after snow removal or during periods of freezing precipitation as directed by the Program Manager. The Program Manager retains the right to inspect all equipment for compliance with local, state, and federal codes and may reject equipment that does not meet contract standards. Any accidents or damages must be reported immediately to the Program Manager.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sch B2 Rest Area Grounds Maint specs Davisburg RA.docx | DOCX document | |
| Confidential Treatment Form Davisburg.docx | DOCX document | |
| Standard Contract Terms Davisburg RA.docx | DOCX document | |
| Schedule C - Davisburg Rest Area Final.xlsx | XLSX spreadsheet | |
| Sch B1 Rest Area Janitorial specs Davisburg RA.docx | DOCX document | |
| Sch A Rest Areas Davisburg RA.docx | DOCX document | |
| Proposal Instructions Davisburg RA.docx | DOCX document | |
| Vendor Questions Worksheet Davisburg.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan.gov/MiProcurement
SCHEDULE B.3 – SNOW REMOVAL SPECIFICATIONS
Michigan.gov/MiProcurement
SCHEDULE B.3 – SNOW REMOVAL SPECIFICATIONS
Request for Proposal (RFP) No. 260000002416 Janitorial/Grounds/Snow Services for the Davisburg Rest Area in Metro Region
SNOW AND ICE REMOVAL SPECIFICATIONS
A. General Requirements:
“TIME IS OF THE ESSENCE” in respect to snow and/or ice removal Contract Activities. The Contractor must perform Contract Activities in conformance with the provisions set forth herein and use due diligence to complete the work within the shortest reasonable period of time.
B. Snow Removal on Driving Surfaces
1. Snow removal shall be completed by 7:00 a.m. after each accumulation of 2” or more of snow on any given day including weekends and holidays. In cases of heavy snowfall, multiple service occurrences may be required during the day. Typical service is plowing 2” to 6” of snow accumulation. The Program Manager may request additional service trips to remove snow which has accumulated.
2. Areas for snow removal shall include entrance ramps, car parking areas, truck parking areas, and exit ramps.
3. Snow shall not be piled to cause a vision obstruction or hazard to the public; nor shall it be piled on sidewalks, or sidewalk “cuts”. All snow shall be pushed away from sidewalks and stored in the areas shown on the map (if provided) or in areas designed by the Program Manager.
4. BY STATE LAW no snow shall be pushed across or on to adjacent roads and shoulders.
5. Any accidents or damages on the premises must be reported immediately to the Program Manager.
C. Ice Removal
1. Granular or approved liquid deicer shall be applied anytime hard packed snow or ice remains on pavement after snow removal operation has been completed.
2. Deicer shall be applied during any period(s) of freezing precipitation as directed by the Program Manager.
D. Calls for Additional Services
1. The Program Manager may request additional or emergency snow/ice removal services as needed (drifting snow or other circumstances) and as determined by the Program Manager or designee.
2. The Contractor must respond and be in route to the call out location(s) within one hour of notification from the Program Manager or designee.
E. Work Approval
1. The Contractor must notify the Program Manager or designee no later than the next day after any work is performed.
2. The Contractor shall consult the Program Manager for inspection and tentative approval of work being accomplished, so that in the event of unsatisfactory work, sufficient time will be available for the Contractor to make corrections in a satisfactory manner within the time specified.
F. Equipment
1. The Contractor shall furnish, operate and maintain suitable and adequate equipment necessary to maintain entrance/exit ramps and all parking areas free from ice and snow.
2. The Contractor's snow removal equipment WILL NOT be stored on State property for any reason.
3. Under no circumstances shall the State be responsible for any theft, vandalism, or damage to the Contractor’s equipment.
4. The Program Manager shall have the right to inspect all equipment which is to be used in carrying out the terms of the Contract. Any equipment which does not comply with local, state, and federal codes, or with the Contract, may be rejected.
5. Equipment failure WILL NOT constitute an acceptable reason for failure to provide scheduled service.