SATPC0042297 Tab 04 4 SOW.pdf
PDF 174 KB Posted
- Attached to
- FDRF Camera Systems Upgrade
- Solicitation number
- 80NSSC26941061Q
About this file
This is a Statement of Work (SOW) for upgrading the Flight Dynamics Research Facility (FDRF) camera system at NASA Langley Research Center in Hampton, Virginia.
The contractor shall remove five existing Panasonic cameras (two compact, two PTZ, and one camcorder) and retain seven pieces of Government-Furnished Equipment including an equipment rack, Blackmagic VideoHub, four Blackmagic HyperDeck Recorders, Blackmagic MultiView 16, Christie Monitoring Displays, and two Panasonic AG-HMR10 Recorder/Players. The upgrade requires installation of two 4K60 12G-SDI compact cameras with 27x optical zoom, two UHD 4K60 PTZ cameras with 30x optical zoom, and one 4K professional camcorder with 24x zoom. Associated infrastructure includes replacement of coaxial cabling with RG6 12G-SDI cabling, new CATx control cabling with RS-232 adapters for joystick integration, two 12G-SDI equalizers/extenders for signal extension beyond 30 meters, one PTZ joystick controller, and one remote terminal switch. The contractor must provide all programming and configuration for camera routing, preset management, PTZ control, basic user interface development, and system commissioning. Deliverables include system integration and testing verification of camera operation, video routing, recording functionality, signal integrity, and compatibility with retained Government equipment. Upon completion, the contractor shall provide onsite operator training covering basic camera operation, PTZ controller operation, recording system overview, startup and shutdown procedures, and basic troubleshooting. The delivery location is 20 Langley Blvd, Hampton, VA 23666, Building 2105 Mail Stop 343, with a four-week material lead time. Project acceptance requires installation of all equipment, verification of functionality, completion of operational testing, delivery of training, and Government acknowledgement of compliance with the SOW.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SATPC0042297 Tab 04 4 SOW (Revised).pdf | ||
| SATPC0042297 Tab 07 Capability Statement.pdf | ||
| SATPC0042297 Tab 06 RDSS..pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
NASA Langley Research Center (LaRC)
Flight Dynamics Research Facility (FDRF) Camera System Upgrade
1. Objective
Provide all labor, materials, equipment, engineering, programming, integration, testing, and training necessary to upgrade the camera acquisition and control system supporting the NASA Langley Research Center FDRF in Hampton, Virginia. The objective of this project is to replace existing camera equipment with new 4K-capable video capture and control technologies while maintaining integration with designated Government-Furnished Equipment (GFE).
2. Scope of Work
2.1 Removal of Existing Equipment
Disconnect, remove, and turn over to the Government the following existing equipment:
• Two (2) Panasonic Compact Cameras
• Two (2) Panasonic PTZ Cameras
• One (1) Panasonic Tracker Camcorder
All removed equipment shall be handled in accordance with Government property management procedures and delivered to the designated Government representative.
2.2 Retention and Reuse of Government-Furnished Equipment
The following GFE shall remain in service and be integrated into the upgraded camera system:
• Existing Equipment Rack
• Blackmagic VideoHub
• Four (4) Blackmagic HyperDeck Recorders
• Blackmagic MultiView 16
• Christie Monitoring Displays
• Two (2) Panasonic AG-HMR10 Recorder/Players
Inspect, test, and reconnect retained GFE as required for integration within the upgraded system.
2.3 Camera System Upgrade
Furnish and install the following equipment and associated infrastructure:
Compact Camera Replacement
• Install two (2) 4K60, 12G-SDI compact cameras with 27x optical zoom on the existing C-strut mounting structure.
• Replace existing coaxial cabling with new RG6 12G-SDI cabling.
• Utilize existing CATx cabling for PoE power delivery.
• Install new CATx control cabling and RS-232 adapters for joystick control integration.
Signal Extension
• Install two (2) 12G-SDI equalizers/extenders to support reliable signal transport exceeding 30 meters.
PTZ Camera Replacement
• Install two (2) UHD 4K60 PTZ cameras with 30x optical zoom.
• Replace existing coaxial cabling with new RG6 12G-SDI cabling.
• Utilize existing CATx cabling for PoE power.
• Provide new CATx control cabling and RS-232 adapters for joystick controller integration.
Camcorder Replacement
• Install one (1) 4K professional camcorder with 24x zoom capability.
• Provide one (1) remote terminal switch for quick play/stop functionality.
• Utilize existing HDMI infrastructure for video transport.
Camera Control
• Install one (1) PTZ joystick controller capable of controlling all installed cameras.
2.4 Programming and Control
Provide all programming and system configuration required for operation of the camera system.
Programming services shall include:
• Camera routing and control configuration
• Preset management
• PTZ control functionality
• Basic user interface development and configuration
• System commissioning and operational verification
Any advanced programming, specialized automation, custom integrations, or functionality beyond the defined project scope shall be subject to separate review and pricing.
2.5 System Integration, Testing, and Commissioning
Configure, integrate, test, and commission all installed equipment.
Testing shall verify:
• Camera operation and image quality
• Video routing and switching functionality
• Recording system operation
• Camera control functionality
• Signal integrity across all installed cabling
• Compatibility with retained Government-Furnished Equipment where feasible
All newly installed camera equipment shall support 4K video signal operation.
2.6 Training
Upon completion of installation and commissioning activities, Provide onsite operator training for designated Government personnel. Training shall include:
• Basic camera operation
• PTZ controller operation
• Recording system overview
• System startup and shutdown procedures
• Basic troubleshooting procedures
3. Deliverables
At project completion, the contractor shall provide:
• Removal and turnover of retired camera equipment
• Fully installed and operational camera system
• Functional integration of designated Government-Furnished Equipment
• System testing and commissioning
• Operator training for designated personnel
• Manufacturer documentation and connection accessories supplied with installed equipment
• Delivery location is 20 Langley Blvd Hampton, VA 23666. Building 2105 Mail Stop
• Lead time for materials is four weeks
4. Assumptions
• Government personnel shall provide access to the facility during normal working hours.
• Existing power, network, and facility infrastructure required to support the installation shall be available and operational.
• Existing CATx pathways and infrastructure are suitable for reuse.
• Government-Furnished Equipment identified for reuse shall be serviceable and operational.
• Any required IT approvals, network configurations, or cybersecurity requirements shall be provided by the Government.
• No structural, electrical, or construction modifications are included unless
Shanna Patterson Highlight
Shanna Patterson Highlight specifically identified herein.
5. Acceptance Criteria
The project shall be considered complete upon:
1. Installation of all specified equipment.
2. Verification of camera, routing, recording, and control functionality.
3. Completion of operational testing and commissioning.
4. Delivery of operator training.
5. Government acknowledgement that the installed equipment performs in accordance with this Statement of Work.
| 2. Scope of Work |
| 2.2 Retention and Reuse of Government-Furnished Equipment |
| 2.3 Camera System Upgrade |
| Compact Camera Replacement |
| Signal Extension |
| PTZ Camera Replacement |
| Camcorder Replacement |
| Camera Control |
| 2.4 Programming and Control |
| 2.5 System Integration, Testing, and Commissioning |
| 2.6 Training |
| 3. Deliverables |
| 4. Assumptions |
| 5. Acceptance Criteria |