Sample Contract - IFB CCB Electrical 202580397 (v2025-07-29).pdf
PDF 215 KB Posted
- Attached to
- City & County Building Electrical Upgrades
- Solicitation number
- 50012
- Issued by
- Denver County, Denver City, Colorado
About this file
This is an Invitation for Bid (IFB) contract between the City and County of Denver and an unspecified contractor for electrical panel repairs, upgrades, and maintenance at the City and County Building. The contract involves furnishing all labor, tools, supplies, equipment, and materials necessary to complete electrical work as described in the Scope of Work. The contract term and specific start and end dates are to be filled in, with the understanding that time is of the essence and the work must be completed within specified timeframes. The contractor will be responsible for providing skilled workers, obtaining necessary permits, maintaining work site conditions, protecting property, ensuring safety, and complying with all applicable laws and regulations.
The maximum contract amount will be determined and inserted into the document, with payment contingent upon satisfactory completion of work and submission of detailed invoices. The contract includes provisions for prevailing wage requirements, with workers to be paid no less than the prevailing wages and fringe benefits in effect on the bid date. Insurance requirements are extensive, including commercial general liability, automobile liability, and workers' compensation coverage. The contractor will be responsible for all costs associated with transportation, disposal of non-hazardous waste, and compliance with environmental and safety regulations. The contract also includes specific provisions for potential liquidated damages, termination conditions, and detailed indemnification requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit C - COI Template.pdf | ||
| Exhibit D - Prevailing Wage Schedules.pdf | ||
| Exhibit B - Pricing Matrix.xlsx | XLSX spreadsheet | |
| Bid Document_IFB #50012.pdf | ||
| Exhibit A - SOW - CCB Electrical Upgrades - Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB Sample Contract – CCB Electrical Upgrades 1
GENRL-202580397-00
AGREEMENT:
CCB Electrical Upgrades
THIS AGREEMENT (this “Agreement”) is by and between the CITY AND COUNTY OF
DENVER, a municipal corporation of the State of Colorado (the “City”), and
_______________________, a [State of formation] [type of entity (e.g., limited liability company)], whose address is _____________________________ (the “Contractor”).
RECITALS
1. The City has identified a need for a qualified contractor to perform work directed by the
City. The work will generally consist of electrical panel repairs, upgrades, and maintenance at the City and County Building.
2. The City solicited and received bids for such services, and Contractor was the lowest qualified, responsive and responsible bidder in response to the Invitation for Bid.
3. The Contractor is willing, able and has the present capacity to perform all of the repair services required by this Contract.
AGREEMENT
In consideration of the mutual covenants contained in this Contract, and subject to the terms and conditions stated in this Contract, the Parties agree as follows:
1. WORK TO BE PERFORMED.
A. Work: The Contractor shall furnish all labor, tools, supplies, equipment, materials and everything necessary for and required to do, perform and complete all of the work described in the
Scope of Work, Exhibit A (the “Work”). The Contractor shall perform the Work in a highly skilled manner consistent with the performance standards and technical requirements set forth in Exhibit A and in accordance with the rates attached hereto as Exhibit B. The Contractor shall diligently prosecute the Work to completion using its best efforts, highly skilled work effort and attention. The Contractor shall be solely responsible for all means, methods, and techniques of performance, protection of property and safety. The
Contractor shall be responsible to the City for the acts and omissions of the Contractor’s employees and any other persons performing any of the work or furnishing materials.
B. Oversight: The Executive Director of General Services (the “Executive Director”) is the City's representative responsible for authorizing and approving the work performed under this
Contract. The Director hereby designates the Director of Facilities Management (the “Director”) as the authorized representative for the purpose of designating a project manager, and administering, coordinating and initially approving the Work and services provided by the Contractor. The project manager shall report to the Director, and shall be responsible for the day-to-day administration, coordination, and approval or acceptance of the Work, except for those approvals or acceptances identified herein as requiring Director action. The Director expressly reserves the right to designate another authorized representative to perform on his/her behalf upon written notice to the Contractor.
C. Cooperation and Coordination: The Contractor shall make every reasonable effort to fully coordinate the Work with any City agency or any person or firm under contract with the
City doing work that affects the Contractor’s Work. The Contractor agrees to allow the City to review any
IFB Sample Contract – CCB Electrical Upgrades 2 of the procedures used by it in doing the Work and to make available for inspection all notes and other documents used in performing the Work.
D. Inspection of the Work: Persons who are employees of the City or who are under contract to the City will be assigned to inspect and test the Work. These persons may perform any tests and observe the Work to determine whether or not materials used, manufacturing and construction processes and methods applied, and equipment installed satisfy the requirements of the technical specifications, all other Agreement requirements, and the Contractor’s warranties and guarantees. The
Contractor shall permit these inspectors unlimited access to the Work and provide means of safe access to the Work, which cost shall be included in the Contractor’s price for the Work. In addition, the
Contractor shall provide whatever access and means of access are needed to off-site facilities used to store or manufacture materials and equipment to be incorporated into the Work and shall respond to any other reasonable request to further the inspector's ability to observe or complete any tests. Such inspections shall not relieve the Contractor of any of its quality control responsibilities or any other obligations under the
Contract. All inspections and all tests conducted by the City are for the convenience and benefit of the
City. These inspections and tests do not constitute acceptance of the materials or Work tested or inspected, and the City may reject or accept any Work or materials at any time prior to the inspections, whether or not previous inspections or tests were conducted by the inspector or a City representative.
E. Warranties; Correction of Work: The Contractor warrants that all parts, materials, components, equipment, systems and other items incorporated into the Work (collectively, “Items”) shall be new, unless otherwise specified, and suitable for the purpose used, and will be of good quality, free from faults and defects, and in keeping with common industry standards and that said Items shall be properly installed or incorporated into the Work in accordance with manufacturer’s specifications and standard practices for said Items, and all of this shall be in conformance with the specifications and requirements of this Contract. The Contractor’s warranty shall be effective for a one-year period following the completion of the Work and shall be extended for one year following any repair, replacement, or corrective action required under the warranty. The Contractor, when requested, shall furnish the Director with satisfactory evidence of the kind and quality of Items proposed to be incorporated into the Work. At any time while this Contract is in effect or during the warranty period, the Contractor shall, at no cost to the City, promptly investigate, repair, replace, or otherwise correct any of its workmanship and/or Items in the Work that contain fault(s) or defect(s), whether such failure(s) are observed by the City or the
Contractor, and promptly repair, replace, otherwise correct any damage to any personal or real property owned by the City or another person resulting from said fault(s) or defect(s) or from the repair, replacement, or correction of the fault(s) or defect(s).
F. Title: The Contractor warrants that it has full title to all items incorporated into the
Work, that its transfer of such title to the City is rightful and free and clear from all security interests, liens, claims, or encumbrances whatsoever, and that the Contractor will defend such title against all persons claiming the whole or part of any Item, at no cost to the City.
G. Time is of the Essence: The Work is time sensitive. The Contractor acknowledges and affirms that it is imperative that the Contractor exercise due diligence and actively and expeditiously undertake all measures necessary: 1) in initiating, making good progress, and completing the Work
Project, all within the timeframes specified in this Agreement, and 2) in promptly and fully correcting or completing any Work noted in a Notice of Deficiency. Failure or refusal by the Contractor to initiate, make good progress, or timely complete the Work may result, at the discretion of the Director, in termination of this Agreement, or in assessment of liquidated damages under Section 5 of this Contract.
IFB Sample Contract – CCB Electrical Upgrades 3
H. Subcontracting: Except as approved by the Executive Director in advance and in writing, the Contractor shall not subcontract with another contractor to perform the Work. The Contractor is prohibited from hiring any subcontractor currently debarred by the City in accordance with section 20-
77 of the Denver Revised Municipal Code.
2. METHODS OF WORK.
A. Resources, Personnel, and Time Commitment: The Work shall be promptly commenced and actively prosecuted with the optimum complement of workers and equipment in order to complete the Work in an effective and expeditious manner. The Contractor shall furnish all labor, tools, supplies, equipment, materials and everything necessary for and required to perform and complete the
Work. The Work shall be undertaken by workers skilled, proficient, and experienced in the trades required by this Agreement and shall be performed in an orderly and responsible manner in accordance with recognized standards and the plans and specifications contained in this Agreement or provided to the
Contractor by the City. If the City reasonably believes that the Work is not proceeding satisfactorily or timely because the Contractor has not utilized an adequate number of qualified and skilled personnel or workers or provided sufficient tools, supplies, equipment, or materials, then the City may require the
Contractor, at no additional cost to the City, to utilize additional qualified and skilled personnel or workers or provide additional tools, supplies, equipment, or materials to perform the Work in a manner reasonably acceptable to the City.
B. Permits and Licenses: Any tasks specified under this Contract that require the employment of licensed or registered personnel shall be performed by licensed or registered personnel.
The Contractor shall obtain, at its own expense, and maintain all permits or licenses, including any prescribed governmental authorizations or approvals, required for the performance of the Work and shall demonstrate, if requested, what actions the Contractor has taken to comply with the required permits, licenses, authorizations or approvals.
C. Work Site Conditions: Work sites and nearby locations shall be kept clean and neat. Equipment, vehicles, and materials no longer needed at the site shall be promptly removed from the site, and any such items lawfully stored for use on the site shall be so placed and secured as to protect the public health and safety. All scraps, debris, trash, excess soil, and other waste materials shall be regularly removed and properly disposed of. Disposal in solid waste containers provided by the City is prohibited unless written authorization is obtained.
D. Protection of Property: The Contractor shall assume full responsibility and expense for the protection of all public and private property, including but not limited to structures, pathways, sprinkler systems, water lines, sewers, and other utilities, both above and below ground, at or near the site or sites of the Work or at any other location affected by the prosecution of the Work or the transportation or utilization of workers, equipment, or materials in connection with the Work. The
Contractor shall provide, in a timely manner and in advance, written notice to: 1) the City department having charge of any property, right of way, or utility affected by the Work; 2) any utility having charge of any utility affected by the Work; and 3) any private property owner whose property or improvements will be affected by the Work, and shall make all necessary arrangements with such City department, utility, or private property owner for the removal and replacement or the protection of such property. The
Contractor shall arrange and obtain any utility locations required by law or necessary to protect utilities or underground facilities on public or private property and shall be liable for any failure to obtain or comply with such utility locations. To the extent that any permit or license is required by a City department or other governmental entity for any work on public property, said permit or license shall be obtained and
IFB Sample Contract – CCB Electrical Upgrades 4 paid for by the Contractor in advance of performing the Work and shall be complied with in the performance of the Work. If the Contractor or its employees, agents, or subcontractors destroy or damage any property, public or private, the Contractor shall promptly repair or replace such property, to the reasonable satisfaction of the Department, before the City will accept or pay for the Work performed. If the Contractor fails to make such repairs or replacement, the Director may, at the Director’s discretion, undertake such repair or replacement and deduct the cost of the same from amounts payable to the
Contractor under this Agreement.
E. Safety: The Contractor is responsible for the health and safety of every person on or at the Work site and shall take all necessary and appropriate precautions and actions to protect such persons from injury, death or loss. The Contractor shall be responsible for being fully familiar with and complying with all applicable City, state, or federal laws, ordinances, rules and regulations, requirements and guidelines, including the Occupational Safety and Health Act and any regulations or directives adopted thereunder (“Safety Laws”). The Contractor shall promptly notify the City in writing of any violations of said Safety Laws, along with copies of any injury reports, and any citations, orders, or warnings issued by governmental agencies in the enforcement of said Safety Laws. The Contractor shall provide and properly locate all necessary protective devices and safety precautions, including warning signs, barricades, or other devices or precautions as required by Safety Laws or the City. For all operations requiring the placement and movement of equipment or materials, the Contractor shall observe and exercise, and shall direct its employees or agents to observe and exercise, all appropriate and prudent caution so as to avoid injury to persons or damage to property and to minimize annoyance to or undue interference with the movement of the public and the performance of City functions. All ladders, scaffolding, or other devices used to reach objects not otherwise accessible, shall be of sound construction, firm and stable and shall be maintained in good, operable condition. All such equipment shall be moved, placed, shifted, and removed from work areas in such a manner as to provide maximum safety to persons and property and cause the least possible interference with the normal usage of such areas by the public and City personnel.
F. Disposal of Non-Hazardous Waste at DADS: In accordance with the Landfill
Agreement made between the City and Waste Management of Colorado, Inc., the Contractor will be required to haul dedicated loads (non-hazardous entire loads of waste) to the Denver-Arapahoe Disposal
Site (“DADS”) for disposal. DADS is located at Highway 30 and Hampden Avenue in Arapahoe County, Colorado. The City will pay all fees associated with such disposal but the Contractor shall be responsible for the costs of transporting the loads. Non-hazardous waste is defined as those substances and materials not defined or classified as hazardous by the Colorado Hazardous Waste Commission pursuant to C.R.S.
§25-15-207, as amended from time to time, and includes construction debris, soil and asbestos. Proposals shall not use Gun Club Road between I-70 and Mississippi Avenue as a means of access to DADS.
G. Prohibition on Use of CCA-Treated Wood Products: The use of any wood products pressure-treated with chromated copper arsenate (CCA) is prohibited. Examples of CCA-treated wood products include wood used in play structures, decks, picnic tables, landscaping timbers, fencing, patios, walkways and boardwalks.
H. Waiver of Part 8 of Article 20 of Title 13, Colorado Revised Statutes: The
Contractor specifically waives all the provisions of Part 8 of Article 20 of Title 13, Colorado Revised
Statutes regarding defects in the Work under this Agreement.
I. Liens and Other Encumbrances: The Contractor shall not permit any mechanic’s or materialman’s liens or any other liens to be imposed and remain for more than ninety (90) days upon
IFB Sample Contract – CCB Electrical Upgrades 5 any City-owned property, or any part thereof, by reason of any worker labor performed or materials or equipment furnished by any person or legal entity to or on behalf of the Contractor, either pursuant to
C.R.S. § 38-26-107 or by any other authority. The Contractor shall promptly pay when due all bills, debts, and obligations incurred in connection with this Agreement and shall not permit the same to become delinquent. The Contractor shall not permit any lien, mortgage, judgment, execution or adjudication of bankruptcy which will in any way impair the rights of the City under this Agreement. The Contractor will indemnify and save harmless the City for the extent of any and all payments, interests, and penalties resulting from failure to comply with this section. The Contractor’s obligations set out in this section shall survive the termination of this Agreement.
J. Environmental Compliance: The Contractor shall obtain all necessary federal, state, and local environmental permits and comply with all applicable federal, state, and local environmental permit requirements relating to the Work. The Contractor shall comply with all applicable local, state, and federal environmental guidelines, rules, regulations, statutes, laws, and orders
(collectively, “Environmental Requirements”), including but not limited to Environmental Requirements regarding the storage, use, transportation, and disposal of Hazardous Materials and regarding releases or threatened releases of Hazardous Materials to the environment. The term “Hazardous Materials” shall mean asbestos and asbestos-containing materials, special wastes, polychlorinated biphenyls (PCBs), any petroleum products, natural gas, radioactive source material, pesticides, any hazardous waste as defined at 42 U.S.C. § 6903(5) of the Solid Waste Disposal Act, any hazardous substance as defined at 42 U.S.C.
§ 9601(14) of the Comprehensive Environmental Response, Compensation and Liability Act, and chemical substance as defined at 15 U.S.C.§ 2602(2) of the Toxic Substances Control Act, and any guidelines issued and rules or regulations promulgated pursuant to such statutes or any other applicable federal or state statute.
K. Attorney’s Fees: Colorado Revised Statute 38-26-107 requires that in the event any person or company files a verified statement of amounts due and unpaid in connection with a claim for labor and materials supplied on this project the City shall withhold from payments to the Contractor sufficient funds to insure the payment of any such claims. Should the City and County of Denver be made a party to any lawsuit to enforce such unpaid claims or any lawsuit arising out of or relating to such withheld funds, the Contractor agrees to pay to the City its costs and reasonable attorney’s fee which cost shall be included as a Cost of the Work. Because the City Attorney Staff does not bill the City for legal services on an hourly basis, the Contractor agrees a reasonable fee shall be computed at the rate of two hundred dollars per hour of City Attorney time.
L. Environmental Sustainability: The Contractor shall demonstrate commitment to and experience in environmental sustainability and public health protection practices applicable to its line of services including, but not limited to, construction waste recycling and energy efficiency. The
Contractor shall work to reduce landfill waste by recycling and/or salvaging recyclable materials. Where applicable, vendor shall procure and install fixtures and equipment that reduce energy use.
3. TERM. This Agreement will commence on __________, ______, and will expire on
__________________, _____ (the “Term”). Subject to the Director’s prior written authorization, the
Contractor shall complete any Work in progress as of the expiration date and the Term will extend until the Work is completed or earlier terminated by the Director. The parties agree that in the performance of the terms, conditions, and requirements of this Agreement by the Contractor, time is of the essence.
4. COMPENSATION AND PAYMENT.
A. Maximum Contract Amount: The Maximum Contract Amount to be paid by the
IFB Sample Contract – CCB Electrical Upgrades 6
City to the Contractor for satisfactory completion of all Work authorized by the City and performed by the Contractor under this Agreement shall in no event exceed the sum of __________________________
DOLLARS AND __________ CENTS ($_________.___), unless this Agreement is modified to increase said amount by a duly authorized and written amendment to this Agreement executed by the Parties in the same manner as this Agreement. The Maximum Contract Amount stated herein is not intended, and shall not be construed, as a promise or guarantee to the Contractor that the final price payable to the Contractor for all of the authorized Work will equal the Maximum Contract Amount.
B. Conditions of Payment: Payment shall be made upon satisfactory completion of the Work or as set out in the Scope of Work. The request for payment submitted by the Contractor must fully document and itemize the Work rendered and all equipment, supplies, materials, labor, and other authorized and actually incurred costs. The request for payment shall affirmatively represent that: i) all of the Work has been fully performed and completed and any Deficiency Notice has been satisfied; ii) no claims, liens, or amounts owed to employees, suppliers, or materialmen are outstanding and all requirements and conditions of section 13 below have been fully complied with; iii) all rights, title and interests to the materials or improvements provided or installed as the result of the Work have transferred to the City; and iv) no interest or encumbrance of any kind associated with the Work will be asserted, has been acquired, or will be made by the Contractor or any other person or entity. If the request for payment does not contain these representations, the representations are hereby deemed to contain them. The request for payment must be approved by the Director in writing in order to be eligible for compensation under this Agreement. Any payment may be reduced by any liquidated damages assessed by the Director under sub-section 5.D.2 below.
C. Subject to Appropriation; No Multiple Year Obligation: It is understood and agreed that any payment obligation of the City hereunder, whether direct or contingent, shall extend only to funds appropriated by the Denver City Council for the purpose of this Agreement, encumbered for the purpose of this Agreement and paid into the Treasury of the City. The Contractor acknowledges that (i) the City does not by this Agreement irrevocably pledge present cash reserves for payments in future fiscal years, and (ii) this Agreement is not intended to create a multiple-fiscal year direct or indirect debt or financial obligation of the City.
D. Amendments: The Contractor acknowledges that the City is not obligated to execute an amendment to this Agreement, and that any work performed by Contractor beyond that specifically described or allowed under this Agreement or without a fully and properly executed amendment to this Agreement is performed at the Contractor’s risk and without authorization under this
Agreement.
5. TERMINATION & REMEDIES.
A. Termination for Convenience of the City: The Director, upon giving twenty (20) calendar days written notice (unless a longer period is given), may terminate this Agreement, in whole or part, when it is in the best interest of the City as determined by the Director. To the extent that the
Contractor has initiated or completed Work for which the Contractor has not yet been compensated in accordance with this Agreement, appropriate compensation for all such authorized Work shall be paid to the Contractor in accordance with this Agreement.
B. Termination, With Cause, by the City: The occurrence of any one or more of the following shall constitute a breach of this Agreement (“Breach”), for which the Director may, at the
Director’s option, either terminate this Agreement, with cause, upon written notice to the Contractor:
IFB Sample Contract – CCB Electrical Upgrades 7
1) The Contractor fails or refuses, within three (3) calendar days of being notified, to expeditiously and actively undertake or substantially or timely perform its responsibilities and obligations or fails or refuses to make adequate progress in performing its responsibilities and obligations under this Agreement, including the due diligence obligations set forth in Section 1 of this Agreement or the Work methods under Section 2 of this Agreement, provided that the failure or refusal to undertake, make good progress, or complete the Work is not due to matters beyond the Contractor’s control such as weather disaster or persistent bad weather, floods, or other acts of God, civil unrest, acts of the public enemy, national calamity, or strike at a manufacturer or supplier for the Work Project;
2) There is substantial evidence that it has been or will be impossible for the
Contractor to perform the Work required due to matters within the Contractor’s control such as voluntary bankruptcy, strikes, boycotts, and labor disputes involving Contractor’s employees or closure or suspension of operations by regulatory order of a governmental entity or an order of a court due to violations or infractions by the Contractor or Contractor’s employees;
3) The Contractor has persistently or flagrantly failed to perform the Work or failed to timely perform the Work or to comply with the specifications and requirements as set forth in the
Statement of Work in Exhibit A to this Agreement;
4) The Contractor has submitted one or more requests for payment under this
Agreement that are fraudulent or persistently or flagrantly erroneous or misleading;
5) The Contractor has made an assignment or transfer of, or subcontracted, its responsibilities and obligations under this Agreement without obtaining the Director’s written consent or not in conformance with this Agreement;
6) The Contractor fails to obtain, renew, replace, or maintain the insurance coverage required by this Agreement or causes or is at fault for damage to property or injury to persons that is not covered or not adequately covered by insurance and the Contractor fails to remedy the situation to the satisfaction of the Director;
7) The Contractor fails to obtain or properly and timely maintain any financial assurances required by this Agreement;
8) Any lien is filed against City property because of any act or omission of the
Contractor and is not timely discharged, unless the Contractor furnishes to the City such bond or other financial assurance reasonably acceptable to the Director to protect the interests of the City;
9) The Contractor has failed to obtain or maintain any required permit or license or has utilized personnel or workers not licensed or registered as required by law;
10) The Contractor has failed to deliver title or warranties or has failed to honor warranties as required by this Agreement;
11) The Contractor fails, within three (3) calendar days of being notified, to comply with, or fails to compel its subcontractors to comply with, the prevailing wage requirements or other City ordinances applicable to the type and nature of Work being performed under this Agreement;
or
12) The Contractor or any of its officers or employees are convicted, plead nolo contendere, enter into a formal contract in which they admit guilt, enter a plea of guilty, or otherwise admit culpability to criminal offenses of bribery, kickbacks, collusive bidding, bid-rigging, antitrust, fraud, undue influence, theft, racketeering, extortion or any offense of a similar nature, in connection with the
IFB Sample Contract – CCB Electrical Upgrades 8
Contractor’s business.
C. Compensation: Upon termination of this Agreement by the City, with cause, under
Sub-section 5.B above, the Contractor shall be compensated for the Work that the Director determines to have been satisfactorily completed, except that the City shall be entitled to keep any unpaid amount owing to the Contractor to the extent that said amount or some portion of said amount is needed to compensate the City for: 1) liquidated damages, if specified under sub-section 5.E below; 2) the costs of releasing any liens or satisfying any claims related to the Work; and 3) the costs of paying a new contractor for those services necessary to complete or rectify the Work or to repair or replace any damaged or lost property caused by the Breach. The Contractor shall have no claim of any kind whatsoever against the City for any termination with cause, except for compensation for the Work satisfactorily performed as described herein.
D. Remedies.
1) Termination: For any termination with cause of this Agreement, the City shall have the right to any or all of the following remedies through the courts or other means of legal recourse available to the City: a) cancellation of this Agreement; b) actual damages or costs caused by
Breach of the Contractor; and c) recovery of costs incurred by the City itself in paying for the release of liens related to the Work or in completing or rectifying the Work or in retaining and compensating another contractor to complete or rectify the Work, to the extent not covered in sub-section 5.C. above. In any legal action brought by the Contractor, the Contractor shall not be entitled to recover any more than the full amount, not previously paid, of any Work executed with and performed in whole or part by the
Contractor. The City and the Contractor understand and agree that the rights of specific performance and to incidental, consequential, or punitive damages have been hereby expressly waived and released by both
Parties.
2) Liquidated Damages: If the Director determines, for a Breach under Sub-section 5.B above, not to terminate this Agreement but to apply liquidated damages as provided in this paragraph, the Contractor shall be liable to the City for liquidated damages in the amount of five hundred dollars ($500.00) per day, calculated from the day that the Director issues notice to the Contractor of a
Breach under sub-section 5.B through a) the day before the Breach is remedied, or b) the day before a new
Work Order or contract is executed with another contractor to perform the Work, as so determined by the
Director. The Contractor and City hereby acknowledges and agrees that it would be impractical and extremely difficult to estimate the damages which the City might incur for said breach, and that, in the interest of assuring that the Work is timely and properly performed, the liquidated damages provided herein is the most fair and reasonable way to compensate the City for any delay or inadequate performance without termination of this Agreement or litigation.
6. WHEN RIGHTS AND REMEDIES NOT WAIVED. In no event will any payment or other action by the City constitute or be construed to be a waiver by the City of any breach of covenant or default that may then exist on the part of the Contractor. No payment, other action, or inaction by the City when any breach or default exists will impair or prejudice any right or remedy available to it with respect to any breach or default. No assent, expressed or implied, to any breach of any term of this Agreement constitutes a waiver of any other breach.
7. INDEPENDENT CONTRACTOR. The Contractor is an independent contractor retained to perform services for limited periods of time. Neither the Contractor nor any of its employees are employees or officers of the City under Chapter 18 of the Denver Revised Municipal Code, or for any purpose whatsoever. The Contractor is responsible for the operational management, errors and omissions
IFB Sample Contract – CCB Electrical Upgrades 9 of the Contractor’s employees, agents, and subcontractors. Without limiting the foregoing, the Contractor understands and acknowledges that the Contractor and the Contractor’s employees, agents and subcontractors: a) are not entitled to workers’ compensation benefits through the City; b) are not entitled to unemployment insurance benefits unless unemployment compensation coverage is provided by the
Contractor or some other entity besides the City; and c) are obligated to pay federal and state taxes on any monies earned pursuant to this Agreement. Furthermore, it is understood and agreed that nothing in this
Agreement is intended, or shall be construed, to constitute a joint venture between the Parties.
8. INSURANCE.
A. General Conditions: The Contractor agrees to secure, at or before the time of execution of this Agreement, the following insurance covering all operations, goods or services provided pursuant to this Agreement. The Contractor shall keep the required insurance coverage in force at all times during the term of this Agreement, including any extension thereof, and during any warranty period. The required insurance shall be underwritten by an insurer licensed or authorized to do business in Colorado and rated by A.M. Best Company as “A-VIII" or better. Each policy shall require notification to the City in the event any of the required policies be canceled or non-renewed before the expiration date thereof.
Such written notice shall be sent to the parties identified in the Notices section of this Agreement. Such notice shall reference the City contract number listed on the signature page of this Agreement. Said notice shall be sent thirty (30) days prior to such cancellation or non-renewal unless due to non-payment of premiums for which notice shall be sent ten (10) days prior. If such written notice is unavailable from the insurer, the Contractor shall provide written notice of cancellation, non-renewal and any reduction in coverage to the parties identified in the Notices section by certified mail, return receipt requested within three (3) business days of such notice by its insurer(s) and referencing the City’s contract number. The
Contractor shall be responsible for the payment of any deductible or self-insured retention. The insurance coverages specified in this Agreement are the minimum requirements, and these requirements do not lessen or limit the liability of the Contractor. The Contractor shall maintain, at its own expense, any additional kinds or amounts of insurance that it may deem necessary to cover its obligations and liabilities under this Agreement.
B. Proof of Insurance: The Contractor may not commence services or work relating to this Agreement prior to placement of coverages required under this Agreement. The Contractor certifies that the certificate of insurance attached as Exhibit C, preferably an ACORD form, complies with all insurance requirements of this Agreement. The City requests that the City’s contract number be referenced on the certificate of insurance. The City’s acceptance of a certificate of insurance or other proof of insurance that does not comply with all insurance requirements set forth in this Agreement shall not act as a waiver of the Contractor’s breach of this Agreement or of any of the City’s rights or remedies under this Agreement. The City’s Risk Management Office may require additional proof of insurance, including but not limited to policies and endorsements.
C. Additional Insureds: For Commercial General Liability, Auto Liability and
Excess Liability/Umbrella (if required), the Contractor and subcontractor’s insurer(s) shall include the
City and County of Denver, its elected and appointed officials, employees and volunteers as additional insured.
D. Waiver of Subrogation: For all coverages required under this Agreement, the
Contractor’s insurer shall waive subrogation rights against the City.
E. Subcontractors and Subconsultants: All subconsultants, subcontractors, independent contractors, suppliers or other entities providing goods or services required by this Agreement
IFB Sample Contract – CCB Electrical Upgrades 10 shall be subject to all of the requirements herein. The Contractor shall require all of its subcontractors and subconsultants of any tier to provide insurance coverage in types and amounts required by the Contractor, but in amounts of at least $1,000,000 Commercial General Liability, Business Auto Liability insurance of
$1,000,000 combined single limit, statutory Workers’ Compensation coverage, and $1,000,000 professional liability for any subcontractor performing design or engineering work. The Contractor agrees to provide proof of insurance for all such subcontractors, subconsultants, independent contractors, suppliers or other entities upon request by the City.
F. Workers’ Compensation and Employer’s Liability Insurance: The Contractor shall maintain the coverage as required by statute for each work location and shall maintain Employer’s
Liability insurance with limits of $100,000 per occurrence for each bodily injury claim, $100,000 per occurrence for each bodily injury caused by disease claim, and $500,000 aggregate for all bodily injuries caused by disease claims.
G. Commercial General Liability: The Contractor shall maintain a Commercial
General Liability insurance policy with minimum limits of $1,000,000 for each bodily injury and property damage occurrence, $2,000,000 products and completed operations aggregate (if applicable), and
$2,000,000 policy aggregate.
H. Automobile Liability: The Contractor shall maintain Automobile Liability with minimum limits of $1,000,000 combined single limit applicable to all owned, hired and non-owned vehicles used in performing services under this Agreement.
9. DEFENSE AND INDEMNIFICATION.
A. The Contractor hereby agrees to defend, indemnify, reimburse and hold harmless the City, its appointed and elected officials, agents and employees for, from and against all liabilities, claims, judgments, suits or demands for damages to persons or property arising out of, resulting from, or relating to the work performed under this Agreement (“Claims”), unless such Claims have been specifically determined by the trier of fact to be the sole negligence or willful misconduct of the City. This indemnity shall be interpreted in the broadest possible manner to indemnify the City for any acts or omissions of the Contractor or its subcontractors either passive or active, irrespective of fault, including the City’s concurrent negligence whether active or passive, except for the sole negligence or willful misconduct of the City.
B. The Contractor’s duty to defend and indemnify the City shall arise at the time written notice of the Claim is first provided to the City regardless of whether Claimant has filed suit on the Claim. The Contractor’s duty to defend and indemnify the City shall arise even if the City is the only party sued by claimant and/or claimant alleges that the City’s negligence or willful misconduct was the sole cause of claimant’s damages.
C. The Contractor will defend any and all Claims which may be brought or threatened against the City and will pay on behalf of the City any expenses incurred by reason of such Claims including, but not limited to, court costs and attorney fees incurred in defending and investigating such
Claims or seeking to enforce this indemnity obligation. Such payments on behalf of the City shall be in addition to any other legal remedies available to the City and shall not be considered the City’s exclusive remedy.
D. Insurance coverage requirements specified in this Agreement shall in no way lessen or limit the liability of the Contractor under the terms of this indemnification obligation. The Contractor shall obtain, at its own expense, any additional insurance that it deems necessary for the City’s protection.
IFB Sample Contract – CCB Electrical Upgrades 11
E. This defense and indemnification obligation shall survive the expiration or termination of this Agreement.
10. FINANCIAL ASSURANCES. Reserved.
11. COLORADO GOVERNMENTAL IMMUNITY ACT. The Parties hereto understand and agree that the City is relying upon, and has not waived, the monetary limitations and all other rights, immunities and protection provided by the Colorado Governmental Act, § 24-10-101 et seq., C.R.S.
12. TAXES, CHARGES AND PENALTIES. The City is not liable for the payment of taxes, late charges or penalties of any nature, except for any additional amounts that the City may be required to pay under the City’s prompt payment ordinance D.R.M.C. § 20-107, et seq. The Contractor shall promptly pay when due, all taxes, bills, debts and obligations it incurs performing the services under this Agreement and shall not allow any lien, mortgage, judgment or execution to be filed against City property.
13. COMPLIANCE WITH ALL LAWS. The Contractor shall perform or cause to be performed all services in full compliance with all applicable laws, rules, regulations and codes of the
United States, the State of Colorado; and with the Charter, ordinances, rules, regulations and Executive
Orders of the City and County of Denver.
14. COMPLIANCE WITH DENVER WAGE LAWS. To the extent applicable to the
Contractor’s provision of work hereunder, the Contractor shall comply with, and agrees to be bound by, all rules, regulations, requirements, conditions, and City determinations regarding the City’s Minimum
Wage and Civil Wage Theft Ordinances, Sections 58-1 through 58-26 D.R.M.C., including, but not limited to, the requirement that every covered worker shall be paid all earned wages under applicable state, federal, and city law in accordance with the foregoing D.R.M.C. Sections. By executing this Agreement, the Contractor expressly acknowledges that the Contractor is aware of the requirements of the City’s
Minimum Wage and Civil Wage Theft Ordinances and that any failure by the Contractor, or any other individual or entity acting subject to this Agreement, to strictly comply with the foregoing D.R.M.C.
Sections shall result in the penalties and other remedies authorized therein.
15. EXAMINATION OF RECORDS AND AUDITS. Any authorized agent of the City, including the City Auditor or his or her representative, has the right to access, and the right to examine, copy and retain copies, at City’s election in paper or electronic form, any pertinent books, documents, papers and records related to Contractor’s performance pursuant to this Agreement, provision of any goods or services to the City, and any other transactions related to this Agreement. The Contractor shall cooperate with City representatives and City representatives shall be granted access to the foregoing documents and information during reasonable business hours and until the latter of three (3) years after the final payment under this Agreement or expiration of the applicable statute of limitations. When conducting an audit of this Agreement, the City Auditor shall be subject to government auditing standards issued by the United
States Government Accountability Office by the Comptroller General of the United States, including with respect to disclosure of information acquired during the course of an audit. No examination of records and audits pursuant to this paragraph shall require the Contractor to make disclosures in violation of state or federal privacy laws. The Contractor shall at all times comply with D.R.M.C. 20-276.
16. ASSIGNMENT; SUBCONTRACTING. The Contractor shall not voluntarily or involuntarily assign any of its rights or obligations, or subcontract performance obligations, under this
Agreement without obtaining the Executive Director’s prior written consent. Any assignment or subcontracting without such consent will be ineffective and void, and will be cause for termination of this
Agreement by the City. The Executive Director has sole and absolute discretion whether to consent to any
IFB Sample Contract – CCB Electrical Upgrades 12 assignment or subcontracting, or to terminate this Agreement because of unauthorized assignment or subcontracting. In the event of any subcontracting or unauthorized assignment: (i) the Contractor shall remain responsible to the City; and (ii) no contractual relationship shall be created between the City and any sub-consultant, subcontractor or assign.
17. NO THIRD-PARTY BENEFICIARY. Enforcement of the terms of this Agreement and all rights of action relating to enforcement are strictly reserved to the parties. Nothing contained in this
Agreement gives or allows any claim or right of action to any third person or entity. Any person or entity other than the City or the Contractor receiving services or benefits pursuant to this Agreement is an incidental beneficiary only.
18. NO AUTHORITY TO BIND CITY TO CONTRACTS. The Contractor lacks any authority to bind the City on any contractual matters. Final approval of all contractual matters that purport to obligate the City must be executed by the City in accordance with the City’s Charter and the Denver
Revised Municipal Code.
19. AGREEMENT AS COMPLETE INTEGRATION-AMENDMENTS. This Agreement is the complete integration of all understandings between the parties as to the subject matter of this
Agreement. No prior, contemporaneous or subsequent addition, deletion, or other modification has any force or effect, unless embodied in this Agreement in writing. No oral representation by any officer or employee of the City at variance with the terms of this Agreement or any written amendment to this
Agreement will have any force or effect or bind the City.
20. SEVERABILITY. Except for the provisions of this Agreement requiring appropriation of funds and limiting the total amount payable by the City, if a court of competent jurisdiction finds any provision of this Agreement or any portion of it to be invalid, illegal, or unenforceable, the validity of the remaining portions or provisions will not be affected, if the intent of the parties can be fulfilled.
21. CONFLICT OF INTEREST.
A. No employee of the City shall have any personal or beneficial interest in the services or property described in this Agreement. The Contractor shall not hire, or contract for services with, any employee or officer of the City that would be in violation of the City’s Code of Ethics, D.R.M.C.
§2-51, et seq. or the Charter §§ 1.2.8, 1.2.9, and 1.2.12.
B. The Contractor shall not engage in any transaction, activity or conduct that would result in a conflict of interest under this Agreement. The Contractor represents that it has disclosed any and all current or potential conflicts of interest. A conflict of interest shall include transactions, activities or conduct that would affect the judgment, actions or work of the Contractor by placing the Contractor’s own interests, or the interests of any party with whom the Contractor has a contractual arrangement, in conflict with those of the City. The City, in its sole discretion, will determine the existence of a conflict of interest and may terminate this Agreement if it determines a conflict exists, after it has given the
Contractor written notice describing the conflict.
22. NOTICES. All notices required by the terms of this Agreement must be hand delivered, sent by overnight courier service, mailed by certified mail, return receipt requested, or mailed via United
States mail, postage prepaid, if to Contractor at the address first above written, and if to the City at:
By Contractor to: Executive Director of General Services
201 West Colfax Avenue, Dept. 601
Denver, Colorado 80202
IFB Sample Contract – CCB Electrical Upgrades 13
Notices hand delivered or sent by overnight courier are effective upon delivery. Notices sent by certified mail are effective upon receipt. Notices sent by mail are effective upon deposit with the U.S. Postal
Service. The parties may designate substitute addresses where or persons to whom notices are to be mailed or delivered. However, these substitutions will not become effective until actual receipt of written notification.
23. DISPUTES. All disputes between the City and the Contractor arising out of or regarding this Agreement will be resolved by administrative hearing pursuant to the procedure established by
D.R.M.C. § 56- 106(b)-(f). For the purposes of that administrative procedure, the City official rendering a final determination shall be the Executive Director as defined in this Agreement.
24. GOVERNING LAW; VENUE. This Agreement will be construed and enforced in accordance with applicable federal law, the laws of the State of Colorado, and the Charter, Revised
Municipal Code, ordinances, regulations and Executive Orders of the City and County of Denver, which are expressly incorporated into this Agreement. Unless otherwise specified, any reference to statutes, laws, regulations, charter or code provisions, ordinances, executive orders, or related memoranda, includes amendments or supplements to same. Venue for any legal action relating to this Agreement will be in the
District Court of the State of Colorado, Second Judicial District (Denver District Court).
25. NO DISCRIMINATION IN EMPLOYMENT. In connection with the performance of work under this Agreement, the Contractor may not refuse to hire, discharge, promote, demote, or discriminate in matters of compensation against any person otherwise qualified, solely because of race, color, religion, national origin, ethnicity, citizenship, immigration status, gender, age, sexual orientation, gender identity, gender expression, marital status, source of income, military status, protective hairstyle, or disability. The Contractor shall insert the foregoing provision in all subcontracts.
26. USE, POSSESSION OR SALE OF ALCOHOL OR DRUGS. The Contractor shall cooperate and comply with the provisions of Executive Order 94 concerning the use, possession or sale of alcohol or drugs. Violation of this provision or refusal to cooperate with implementation of the policy can result in the City barring the Contractor from City facilities or participating in City operations.
27. PREVAILING WAGE REQUIREMENTS.
A. The Contractor shall comply with, and agrees to be bound by, all requirements, conditions and City determinations regarding the Payment of Prevailing Wages Ordinance, Sections 20-
76 through 20-79, D.R.M.C. including, but not limited to,…