S02. Statement of Bid Items.pdf
PDF 118 KB Posted
- Attached to
- Y1DA--Replace Second Floor Flooring Federal contract opportunity
- Solicitation number
- 36C25021B0035
About this file
This memorandum and federal contract opportunity describe a project to replace flooring on the second floor of a Department of Veterans Affairs medical center. The project will remove and replace approximately 7,300 square feet of corridor flooring and base, and includes approximately 2,090 square feet of hazardous material abatement. Interested parties must register at beta.sam.gov to receive solicitation documents on or around April 15th, with bid opening approximately 30 days later. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses, who must meet size standards of $39.5 million or less under NAICS code 236220. The awarded contractor must perform a minimum of 25% of construction work. The project duration is 133 calendar days from notice to proceed, and bonds will be required.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S02. Safety.pdf | ||
| S02. Brand Name or Equal Memo.pdf | ||
| S02. BID ISSUE SUBMISSION - DRAWINGS.pdf | ||
| S02. BID ISSUE SUBMISSION - SPECIFICATIONS.pdf | ||
| S02. Wage Determination.pdf | ||
| S02. Calculation of Self-Performed and Sub-Contracted Work.pdf | ||
| S02. VAMC Health Requirements.pdf | ||
| S02. RFI Form.docx | DOCX document | |
| S02. Bid Opening Instructions.pdf | ||
| S02. Solicitation 36C25021B0035_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Memorandum Veterans Affairs
Date: May 10, 2021
From: Chief, Engineering Service 138 (A)
Subj: Bid Items Replace Second Floor Flooring #541-21-201
To: Network Contracting Activity 10 (NCO10) Attn: Stanley Burdine – Administrative Contracting Officer
Bid Items
Bid Item 1: Base Bid
Description:
This is a multi-phased project that will remove and replace approximately 7,300 square foot of corridor flooring and base on the Second Floor of the main Medical Center. Work includes General trades; no Mechanical or Electrical scope is required. Approximately 2,090 square foot of hazardous material abatement is included in the scope. Work includes all labor, material, equipment and supervision to perform the required construction work on this Project. All work to be done during evenings and weekends.
Duration: 133 days
Glen Zeisset
COR
File details come from the government source that posted it. Updated .