S02. BID ISSUE SUBMISSION - DRAWINGS.pdf
PDF 38 MB Posted
- Attached to
- Y1DA--Replace Second Floor Flooring Federal contract opportunity
- Solicitation number
- 36C25021B0035
About this file
This solicitation is for a construction project to replace flooring on the second floor of a Veterans Affairs medical center campus. The project scope includes site preparation and renovation to install 800 square feet of corridor flooring. All labor, equipment, materials and incidentals will be furnished by the contractor, who must perform all work in a manner that maintains safe usage of adjacent spaces for patients, staff and visitors.
The solicitation is a 100% set-aside for service-disabled veteran-owned small businesses and will be issued under authority of Public Law 109-461. Interested parties must register at SAM.gov and Vendor Information Pages to be eligible for award. The project value is between $100,000 and $500,000, bonds are required, and work must be completed within 133 days of notice to proceed. A site visit will be scheduled and the solicitation issued on or around April 15, 2021 with bids due approximately 30 days later. Questions are due in writing by the specified cutoff date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S02. Wage Determination.pdf | ||
| S02. Calculation of Self-Performed and Sub-Contracted Work.pdf | ||
| S02. RFI Form.docx | DOCX document | |
| S02. Bid Opening Instructions.pdf | ||
| S02. Solicitation 36C25021B0035_1.pdf | ||
| S02. Safety.pdf | ||
| S02. Brand Name or Equal Memo.pdf | ||
| S02. Statement of Bid Items.pdf | ||
| S02. BID ISSUE SUBMISSION - SPECIFICATIONS.pdf | ||
| S02. VAMC Health Requirements.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TITLE SHEET & DRAWING
INDEX
10701 EAST BLVD. CLEVELAND, OH. 44106
DEPARTMENT OF VETERANS AFFAIRS MEDICAL CENTER - WADE PARK
Cleveland Veterans Affairs
Medical Center
REPLACE SECOND FLOOR FLOORING
DRAWING INDEX
PROJECT NO. 541-21-201
GI-1 TITLE SHEET & DRAWING INDEX
ARCHITECTURAL
LS-2.1 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 1
LS-2.2 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 2
LS-2.3 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 3
LS-2.4 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 4
LS-2.5 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 5
LS-2.6 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 6
LS-2.7 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 7
LS-2.8 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 8
LS-2.9 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 9
LS-2.10 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 10
LS-2.11 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 11
LS-2.12 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 12
LS-2.13 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 13
LS-2.14 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 14
LS-2.15 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 15
LS-2.16 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 16
LS-2.17 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 17
BID ISSUE SUBMISSION
5.10.21
I. PROJECT LOCATION: CLEVELAND VETERANS AFFAIRS MEDICAL CENTER
10701 EAST BLVD.
CLEVELAND, OHIO
II. DESCRIPTION & USER GROUP CLASSIFICATION OF BLDG
A. NATURE OF PROJECT: REPLACEMENT OF EXISTING FLOORING AND BASE IN 2ND FLOOR
MAIN CORRIDOR & ELEVATOR LOBBIES
B. DESIGN CODES: 2018 NFPA LIFE SAFETY CODE 101, IBC 2018
C. USE GROUP: MIXED USE GROUPS IN HOSPITAL (I-2/S/B) - NO CHANGE PROPOSED
D. CONSTRUCTION TYPE: TYPE I -332, IB - NON-COMBUSTIBLE, PROTECTED
FIRE RATED CONSTRUCTION (LSC A.8.2.1.2)
EXTERIOR BEARING WALLS 3 HRS
INTERIOR BEARING WALLS 3 HRS
STRUCTURAL COLUMNS 3 HRS (SUPPORTING > 1 FLOOR)
2 HRS (SUPPORTING 1 FLOOR ONLY)
2 HRS (SUPPORTING ROOF ONLY)
BEAMS, GIRDERS, TRUSSES 3 HRS (SUPPORTING > 1 FLOOR, COLS., OR BEARING WALLS
2 HRS (ALL OTHERS)
FLOOR-CEILING ASSEMBLIES 2 HRS
ROOF-CEILING ASSEMBLIES 1 12 HRS
INTERIOR NON-BEARING WALLS 0 HRS
EXTERIOR NON-BEARING WALLS 0 HRS
WALL ASSEMBLIES
EXIT ACCESS CORRIDOR WALLS 0 HR SMOKE PARTITIONS
E. PROJECT AREA: 2ND FLOOR MAIN CORRIDOR: 7,300 SF
F. PROJECT AREA OCCUPANT LOAD: NOT APPLICABLE
G. FIRE PROTECTION: EXISTING BUILDING FULLY SPRINKLED AND WILL REMAIN AS A PART OF THIS PROJECT. FIRE
PROTECTION SYSTEM DESIGN NOT IN SCOPE OF WORK
CODE INFORMATION
8.31.20 GI-15.10.21
SITE KEY PLAN
NTS
NORTH
CLEVELAND VAMC
2ND FLOOR KEY PLAN
NTS
NORTH
PROJECT SITE:
2ND FLOOR MAIN
CORRIDOR &
ELEVATOR
LOBBIES
DESIGN DEVELOPMENT SUBMISSION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h
P
M
FULLY SPRINKLERED
Louis Stokes Cleveland
VA Medical Center
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT OF RECORD STAMPCONSULTANTS
321 4 6 7 8 9 10
REPLACE SECOND FLOOR
FLOORING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-201
NICK CARROZZA
CJK KMSRevisions: Date:
E T
G
DE
I
RET
S
HCRA
I
KACZMAR
STANLEY
NO. 4988
T
E R
S
ATE
I
T C
J.
O
O
FO
H
COST ESTIMATING:
MCGUINESS UNLIMITED, INC.
15724 STILLWOOD AVE.
CLEVELAND, OH 44111
P. 440.667.5120
MECH./ELEC. ENGINEERING:
FFE, INC.
110 BOGGS LANE, SUITE 170
SPRINGDALE, OH 45246
P. 513.522.2107
HAZ. MATERIALS ASSESSMENT:
STEPHEN J. SEBESTA & ASSOC., INC.
30628 DETROIT RD. #258
WESTLAKE, OH 44145
P. 216.781.0060
BID ISSUE SUBMISSION
65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20
FINAL CDs SUBMISSION 11.5.20
BID ISSUE SUBMISSION 5.10.21
8.31.20
HAZARDOUS MATERIALS
HA-001 STANDARD DETAILS AND ASBESTOS ABATEMENT
HA-101.1 SECOND FLOOR ASBESTOS ABATEMENT PLAN, PHASE 1 &2
HA-101.2 SECOND FLOOR ASBESTOS ABATEMENT PLAN, PHASE 3 & 4
HA-101.3 SECOND FLOOR ASBESTOS ABATEMENT PLAN, PHASE 5
A-102 OVERALL SECOND FLOOR PHASING PLAN
A-102A OVERALL SECOND FLOOR FINISH PLAN
A-102.1 ENLARGED PHASE PLANS - PHASE 1 & 2
A-102.2 ENLARGED PHASE PLANS - PHASE 3 &4
A-102.3 ENLARGED PHASE PLANS - PHASE 5
A-102.4 ENLARGED PHASE PLANS - PHASE 6 & 7
A-102.5 ENLARGED PHASE PLANS - PHASE 8
A-102.6 ENLARGED PHASE PLANS - PHASE 9 &10
A-102.7 ENLARGED PHASE PLANS - PHASE 11 &12
A-102.8 ENLARGED PHASE PLANS - PHASE13 & 14
A-102.9 ENLARGED PHASE PLANS - PHASE 15 & 16
A-102.10 ENLARGED PHASE PLANS - PHASE 17
A-600 FINISH SCHEDULE AND DETAILS
ELECTRICAL
E-001 LEGEND AND ABBREVIATIONS
ED-0.1A SECOND FLOOR ELECTRICAL REFERENCE PLAN - EAST
ED-01B SECOND FLOOR ELECTRICAL REFERENCE PLAN - WEST
AutoCAD SHX Text
EAST BLVD.
AutoCAD SHX Text
E. 105 ST.
AutoCAD SHX Text
EAST BLVD.
AutoCAD SHX Text
MAGNOLIA DR.
AutoCAD SHX Text
HAZEL DR.
AutoCAD SHX Text
E. 108 ST.
AutoCAD SHX Text
MT. SINAI DR.
AutoCAD SHX Text
MARTIN LUTHER KING DR.
BLOOD
DRAW CAB. &
CHAIR
XXXXXX
X X XX XX X XX X
XX
X X X
X
X X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X
XX
X X
X X
X X
X X
X X
X X
X
X X X X X
X X
X
X X
X X X
X X X
X X
X X X
X X
X
X
X X
X
X X X
A
2D258
A B C D E F
GHIJKL
OIT Telecom/ Data Closet
OIT Telecom/ Data Closet OIT Telecom/
Data Closet
BLOOD
DRAW CAB. &
CHAIR
OIT Telecom/ Data Closet
BATTERY
CABINET
NO.1
UPS
CABINET
NO.1
UPS
CABINET
NO.2
BATTERY
CABINET
NO.2
UTS
NO.1
UTS
NO.2
RSP
NO.1
RSP
NO.2
WOW
VO VSVO SV
V OSV
2B301BA
2S7
FE
F E
FE
F E
FE
F E
FE
F E
F E
DESIGN DEVELOPMENT SUBMISSION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h
P
M
FULLY SPRINKLERED
Louis Stokes Cleveland
VA Medical Center
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT OF RECORD STAMPCONSULTANTS
321 4 6 7 8 9 10
REPLACE SECOND FLOOR
FLOORING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-201
NICK CARROZZA
CJK KMSRevisions: Date:
E T
G
DE
I
RET
S
HCRA
I
KACZMAR
STANLEY
NO. 4988
T
E R
S
ATE
I
T C
J.
O
O
FO
H
COST ESTIMATING:
MCGUINESS UNLIMITED, INC.
15724 STILLWOOD AVE.
CLEVELAND, OH 44111
P. 440.667.5120
MECH./ELEC. ENGINEERING:
FFE, INC.
110 BOGGS LANE, SUITE 170
SPRINGDALE, OH 45246
P. 513.522.2107
HAZ. MATERIALS ASSESSMENT:
STEPHEN J. SEBESTA & ASSOC., INC.
30628 DETROIT RD. #258
WESTLAKE, OH 44145
P. 216.781.0060
BID ISSUE SUBMISSION
65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20
FINAL CDs SUBMISSION 11.5.20
BID ISSUE SUBMISSION 5.10.21
8.31.20
SCALE: 1/16"=1'-0"
SECOND FLOOR - PHASE 1
LIFE SAFETY PLANNORTH
SECOND FLOOR INTERIM LIFE
SAFETY PLAN - PHASE 1
LS-2.15.10.21
LIFE SAFETY LEGEND:
TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA
SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF
CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR
EXISTING 2 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED SMOKE BARRIER
EXISTING O HOUR RATED SMOKE PARTITION
E EXIT
FE
FIRE EXTINGUISHER
EXIT SIGN LOCATION
LIFE SAFETY GENERAL NOTES:
1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING
HEALTH CARE OCCUPANCY" PER NFPA 101 2018.
2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS
3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)
4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.
5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND
COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY
DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY
STANDARDS.
HAZARDOUS ROOM
EXISTING 2 HOUR RATED SMOKE BARRIER
FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"
SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON
COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON
REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"
TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY
BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE
APPROVED BY THE COR.
PROJECT SCOPE BOUNDARY
SOLID WHITE AREA INDICATES
CONSTRUCTION AREA WITHIN SCOPE
OF WORK
GRAY HATCHED AREA INDICATES AREA
OUTSIDE OF SCOPE OF WORK
PHASING DURATION & CONSTRUCTION TIMEFRAMES:
THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING
HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:
PRE-CONSTRUCTION: 60 DAYS
PHASE I: 5 DAYS
PHASE II:
PHASE III:
TOTAL TIMEFRAME: 133 DAYS
THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:
THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):
WORK IN PUBLIC CORRIDORS/WAITING AREAS
WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING
FINISHES
CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS
INFECTION CONTROL CLASS & SAFETY MEASURES:
THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE
BUILDING.
REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26
THROUGHOUT THE ENTIRETY OF THE PROJECT.
PHASE IV:
PHASE V:
PHASE VI:
PHASE VII:
5 DAYS
5 DAYS
5 DAYS
5 DAYS
4 DAYS
4 DAYS
PHASE VIII: 4 DAYS
PHASE IX:
PHASE X:
PHASE XI:
PHASE XII:
PHASE XIII:
PHASE XIV:
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.
CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA
COR.
WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS
PHASE XV: 4 DAYS
PHASE XVI: 4 DAYS
PHASE XVII: 4 DAYS
MISC. OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
ACUTE MEDICINE OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
SLEEP LAB
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
HEMO-ONCOLOGY
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PACU
HOURS: M-F 6:00AM - 5:30 PM
NO WEEKENDS
PULMONARY - HOME OXYGEN
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
CARDIOLOGY - EP/CATH LAB
HOURS: M-F 7:30 AM - 5:30 PM
NO WEEKENDS
ENDOSCOPY
HOURS: M-F 7:30 AM - 5:30 PM
SATURDAY 7 AM - 2 PM
SURGERY - PRE-OP
HOURS: M-F 7:30 AM - 5:00 PM
WEEKENDS: EMERGENCY ONLY
SURGERY - OPERATING SUITE
HOURS: M-F 7:00 AM - 7:00 PM
WEEKENDS: EMERGENCY ONLY
MICU
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
PCU - CURRENT COVID WARD
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
GU
HOURS M-F: 7:30 AM - 4:30 PM
NO WEEKENDS
2B306A 2B3072B306B2B303
2B338A
2B301L
2B301M2B301N
2B301A
2B1502B149
2B146A
2B147
2B146B
2B149
2B413
2B410
2B411
2B1452B1442B143A
2B142 2B141
2B150
2B139
2B137
2B136
2B134
2B132
2B131
2B130
2B129
2B128
2B127
2B125
2B126
2B100B
2B100A
2B301B
2C328 2C326H2C326G2C326F
2C323A
2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C1532C155
2B1242B1232B1222C1362C134 2C134A
2C133B
2C133A
2C133
2C100
2C400B
2C417
2C416
2C400C
2C420
2C415
2C414
2C413
2C411
2C129
2C400A
2C412
2C100B
2C100A
2C157
2C154
2C170
2C171 2D301H
2D301G
2D301F
2D301E
2D301D2D3022D301C 2D3032D304
2D307
2D301A
2D301Q
2D301P
2D301O
2D301N
2C1302C1312D100
2D100A2E314
2E300A
2E313
2E312
2E311
2E310
2E300A 2D100N
2D198
2D197
2D196A
2D196
2D195
2D194
2D193
2D192A
2D192
2D100L
2D163
2D161
2D160
2D159
2E370A
2C1392C1382C137
2D275
ALL DOORS FACING
CORRIDOR TO BE
PROTECTED DURING
CONSTRUCTION
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 1 CONSTRUCTION
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 1 CONSTRUCTION
E
E
DOOR TO REMAIN
AVAILABLE TO STAFF FOR
EMERGENCY USE DURING
CONSTRUCTION PHASE
E
E
TEMPORARY PARTITION
WALL
6'- 5"
CONSTRUCTION AREA
3'-10"
ENDOSCOPY PROJECT - PHASE 1 AREA
VA ACTIVATION STARTING MID-DECEMBER
AutoCAD SHX Text
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
-FD
CHAIR
XXXXXX
X X XX XX X XX X
XX
X X X
X
X X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X
XX
X X
X X
X X
X X
X X
X X
X
X X X X X
X X
X
X X
X X X
X X X
X X
X X X
X X
X
X
X X
X
X X X
A
2D258
A B C D E F
GHIJKL
OIT Telecom/ Data Closet
OIT Telecom/ Data Closet OIT Telecom/
Data Closet
BLOOD
DRAW CAB. &
CHAIR
OIT Telecom/ Data Closet
BATTERY
CABINET
NO.1
UPS
CABINET
NO.1
UPS
CABINET
NO.2
BATTERY
CABINET
NO.2
UTS
NO.1
UTS
NO.2
RSP
NO.1
RSP
NO.2
WOW
VO VSVO SV
V OSV
2B301BA
2S7
FE
F E
FE
F E
FE
F E
FE
F E
F E
DESIGN DEVELOPMENT SUBMISSION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h
P
M
FULLY SPRINKLERED
Louis Stokes Cleveland
VA Medical Center
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT OF RECORD STAMPCONSULTANTS
321 4 6 7 8 9 10
REPLACE SECOND FLOOR
FLOORING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-201
NICK CARROZZA
CJK KMSRevisions: Date:
E T
G
DE
I
RET
S
HCRA
I
KACZMAR
STANLEY
NO. 4988
T
E R
S
ATE
I
T C
J.
O
O
FO
H
COST ESTIMATING:
MCGUINESS UNLIMITED, INC.
15724 STILLWOOD AVE.
CLEVELAND, OH 44111
P. 440.667.5120
MECH./ELEC. ENGINEERING:
FFE, INC.
110 BOGGS LANE, SUITE 170
SPRINGDALE, OH 45246
P. 513.522.2107
HAZ. MATERIALS ASSESSMENT:
STEPHEN J. SEBESTA & ASSOC., INC.
30628 DETROIT RD. #258
WESTLAKE, OH 44145
P. 216.781.0060
BID ISSUE SUBMISSION
65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20
FINAL CDs SUBMISSION 11.5.20
BID ISSUE SUBMISSION 5.10.21
8.31.20
SCALE: 1/16"=1'-0"
SECOND FLOOR - PHASE 2
LIFE SAFETY PLANNORTH
SECOND FLOOR INTERIM LIFE
SAFETY PLAN - PHASE 2
LS-2.25.10.21
LIFE SAFETY LEGEND:
TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA
SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF
CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR
EXISTING 2 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED SMOKE BARRIER
EXISTING O HOUR RATED SMOKE PARTITION
E EXIT
FE
FIRE EXTINGUISHER
EXIT SIGN LOCATION
LIFE SAFETY GENERAL NOTES:
1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING
HEALTH CARE OCCUPANCY" PER NFPA 101 2018.
2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS
3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)
4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.
5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND
COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY
DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY
STANDARDS.
HAZARDOUS ROOM
EXISTING 2 HOUR RATED SMOKE BARRIER
FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"
SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON
COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON
REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"
TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY
BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE
APPROVED BY THE COR.
PROJECT SCOPE BOUNDARY
SOLID WHITE AREA INDICATES
CONSTRUCTION AREA WITHIN SCOPE
OF WORK
GRAY HATCHED AREA INDICATES AREA
OUTSIDE OF SCOPE OF WORK
PHASING DURATION & CONSTRUCTION TIMEFRAMES:
THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING
HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:
PRE-CONSTRUCTION: 60 DAYS
PHASE I: 5 DAYS
PHASE II:
PHASE III:
TOTAL TIMEFRAME: 133 DAYS
THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:
THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):
WORK IN PUBLIC CORRIDORS/WAITING AREAS
WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING
FINISHES
CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS
INFECTION CONTROL CLASS & SAFETY MEASURES:
THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE
BUILDING.
REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26
THROUGHOUT THE ENTIRETY OF THE PROJECT.
PHASE IV:
PHASE V:
PHASE VI:
PHASE VII:
5 DAYS
5 DAYS
5 DAYS
5 DAYS
4 DAYS
4 DAYS
PHASE VIII: 4 DAYS
PHASE IX:
PHASE X:
PHASE XI:
PHASE XII:
PHASE XIII:
PHASE XIV:
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.
CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA
COR.
WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS
PHASE XV: 4 DAYS
PHASE XVI: 4 DAYS
PHASE XVII: 4 DAYS
MISC. OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
ACUTE MEDICINE OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
SLEEP LAB
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
HEMO-ONCOLOGY
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PACU
HOURS: M-F 6:00AM - 5:30 PM
NO WEEKENDS
PULMONARY - HOME OXYGEN
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
CARDIOLOGY - EP/CATH LAB
HOURS: M-F 7:30 AM - 5:30 PM
NO WEEKENDS
ENDOSCOPY
HOURS: M-F 7:30 AM - 5:30 PM
SATURDAY 7 AM - 2 PM
SURGERY - PRE-OP
HOURS: M-F 7:30 AM - 5:00 PM
WEEKENDS: EMERGENCY ONLY
SURGERY - OPERATING SUITE
HOURS: M-F 7:00 AM - 7:00 PM
WEEKENDS: EMERGENCY ONLY
MICU
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
PCU - CURRENT COVID WARD
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
GU
HOURS M-F: 7:30 AM - 4:30 PM
NO WEEKENDS
2B306A 2B3072B306B2B303
2B338A
2B301L
2B301M2B301N
2B301A
2B1502B149
2B146A
2B147
2B146B
2B149
2B413
2B410
2B411
2B1452B1442B143A
2B142 2B141
2B150
2B139
2B137
2B136
2B134
2B132
2B131
2B130
2B129
2B128
2B127
2B125
2B126
2B100B
2B100A
2B301B
2C328 2C326H2C326G2C326F
2C323A
2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C1532C155
2B1242B1232B1222C1362C134 2C134A
2C133B
2C133A
2C133
2C100
2C400B
2C417
2C416
2C400C
2C420
2C415
2C414
2C413
2C411
2C129
2C400A
2C412
2C100B
2C100A
2C157
2C154
2C170
2C171 2D301H
2D301G
2D301F
2D301E
2D301D2D3022D301C 2D3032D304
2D307
2D301A
2D301Q
2D301P
2D301O
2D301N
2C1302C1312D100
2D100A2E314
2E300A
2E313
2E312
2E311
2E310
2E300A 2D100N
2D198
2D197
2D196A
2D196
2D195
2D194
2D193
2D192A
2D192
2D100L
2D163
2D161
2D160
2D159
2E370A
2C1392C1382C137
2D275
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 2 CONSTRUCTION
E
E
E
TEMPORARY PARTITION
WALL
7'- 5"
CO
NS
TR
UC
TI
ON
A
RE
A
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 2 CONSTRUCTION
ALL DOORS FACING
CORRIDOR TO BE
PROTECTED DURING
CONSTRUCTION
DOOR TO REMAIN
AVAILABLE TO STAFF FOR
EMERGENCY USE DURING
CONSTRUCTION PHASE
E
ENDOSCOPY PROJECT - PHASE 1 AREA
VA ACTIVATION STARTING MID-DECEMBER
3'- 8 1
/2"
3'-9 1/2"
AutoCAD SHX Text
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
CHAIR
XXXXXX
X X XX XX X XX X
XX
X X X
X
X X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X
XX
X X
X X
X X
X X
X X
X X
X
X X X X X
X X
X
X X
X X X
X X X
X X
X X X
X X
X
X
X X
X
X X X
A
2D258
A B C D E F
GHIJKL
OIT Telecom/ Data Closet
OIT Telecom/ Data Closet OIT Telecom/
Data Closet
BLOOD
DRAW CAB. &
CHAIR
OIT Telecom/ Data Closet
BATTERY
CABINET
NO.1
UPS
CABINET
NO.1
UPS
CABINET
NO.2
BATTERY
CABINET
NO.2
UTS
NO.1
UTS
NO.2
RSP
NO.1
RSP
NO.2
WOW
VO VSVO SV
V OSV
2B301BA
2S7
FE
F E
FE
F E
FE
F E
FE
F E
F E
DESIGN DEVELOPMENT SUBMISSION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h
P
M
FULLY SPRINKLERED
Louis Stokes Cleveland
VA Medical Center
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT OF RECORD STAMPCONSULTANTS
321 4 6 7 8 9 10
REPLACE SECOND FLOOR
FLOORING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-201
NICK CARROZZA
CJK KMSRevisions: Date:
E T
G
DE
I
RET
S
HCRA
I
KACZMAR
STANLEY
NO. 4988
T
E R
S
ATE
I
T C
J.
O
O
FO
H
COST ESTIMATING:
MCGUINESS UNLIMITED, INC.
15724 STILLWOOD AVE.
CLEVELAND, OH 44111
P. 440.667.5120
MECH./ELEC. ENGINEERING:
FFE, INC.
110 BOGGS LANE, SUITE 170
SPRINGDALE, OH 45246
P. 513.522.2107
HAZ. MATERIALS ASSESSMENT:
STEPHEN J. SEBESTA & ASSOC., INC.
30628 DETROIT RD. #258
WESTLAKE, OH 44145
P. 216.781.0060
BID ISSUE SUBMISSION
65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20
FINAL CDs SUBMISSION 11.5.20
BID ISSUE SUBMISSION 5.10.21
8.31.20
SCALE: 1/16"=1'-0"
SECOND FLOOR - PHASE 3
LIFE SAFETY PLANNORTH
SECOND FLOOR INTERIM LIFE
SAFETY PLAN - PHASE 3
LS-2.35.10.21
LIFE SAFETY LEGEND:
TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA
SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF
CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR
EXISTING 2 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED SMOKE BARRIER
EXISTING O HOUR RATED SMOKE PARTITION
E EXIT
FE
FIRE EXTINGUISHER
EXIT SIGN LOCATION
LIFE SAFETY GENERAL NOTES:
1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING
HEALTH CARE OCCUPANCY" PER NFPA 101 2018.
2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS
3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)
4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.
5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND
COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY
DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY
STANDARDS.
HAZARDOUS ROOM
EXISTING 2 HOUR RATED SMOKE BARRIER
FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"
SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON
COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON
REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"
TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY
BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE
APPROVED BY THE COR.
PROJECT SCOPE BOUNDARY
SOLID WHITE AREA INDICATES
CONSTRUCTION AREA WITHIN SCOPE
OF WORK
GRAY HATCHED AREA INDICATES AREA
OUTSIDE OF SCOPE OF WORK
PHASING DURATION & CONSTRUCTION TIMEFRAMES:
THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING
HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:
PRE-CONSTRUCTION: 60 DAYS
PHASE I: 5 DAYS
PHASE II:
PHASE III:
TOTAL TIMEFRAME: 133 DAYS
THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:
THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):
WORK IN PUBLIC CORRIDORS/WAITING AREAS
WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING
FINISHES
CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS
INFECTION CONTROL CLASS & SAFETY MEASURES:
THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE
BUILDING.
REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26
THROUGHOUT THE ENTIRETY OF THE PROJECT.
PHASE IV:
PHASE V:
PHASE VI:
PHASE VII:
5 DAYS
5 DAYS
5 DAYS
5 DAYS
4 DAYS
4 DAYS
PHASE VIII: 4 DAYS
PHASE IX:
PHASE X:
PHASE XI:
PHASE XII:
PHASE XIII:
PHASE XIV:
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.
CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA
COR.
WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS
PHASE XV: 4 DAYS
PHASE XVI: 4 DAYS
PHASE XVII: 4 DAYS
MISC. OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
ACUTE MEDICINE OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
SLEEP LAB
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
HEMO-ONCOLOGY
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PACU
HOURS: M-F 6:00AM - 5:30 PM
NO WEEKENDS
PULMONARY - HOME OXYGEN
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
CARDIOLOGY - EP/CATH LAB
HOURS: M-F 7:30 AM - 5:30 PM
NO WEEKENDS
ENDOSCOPY
HOURS: M-F 7:30 AM - 5:30 PM
SATURDAY 7 AM - 2 PM
SURGERY - PRE-OP
HOURS: M-F 7:30 AM - 5:00 PM
WEEKENDS: EMERGENCY ONLY
SURGERY - OPERATING SUITE
HOURS: M-F 7:00 AM - 7:00 PM
WEEKENDS: EMERGENCY ONLY
MICU
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
PCU - CURRENT COVID WARD
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
GU
HOURS M-F: 7:30 AM - 4:30 PM
NO WEEKENDS
2B306A 2B3072B306B2B303
2B338A
2B301L
2B301M2B301N
2B301A
2B1502B149
2B146A
2B147
2B146B
2B149
2B413
2B410
2B411
2B1452B1442B143A
2B142 2B141
2B150
2B139
2B137
2B136
2B134
2B132
2B131
2B130
2B129
2B128
2B127
2B125
2B126
2B100B
2B100A
2B301B
2C328 2C326H2C326G2C326F
2C323A
2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C1532C155
2B1242B1232B1222C1362C134 2C134A
2C133B
2C133A
2C133
2C100
2C400B
2C417
2C416
2C400C
2C420
2C415
2C414
2C413
2C411
2C129
2C400A
2C412
2C100B
2C100A
2C157
2C154
2C170
2C171 2D301H
2D301G
2D301F
2D301E
2D301D2D3022D301C 2D3032D304
2D307
2D301A
2D301Q
2D301P
2D301O
2D301N
2C1302C1312D100
2D100A2E314
2E300A
2E313
2E312
2E311
2E310
2E300A 2D100N
2D198
2D197
2D196A
2D196
2D195
2D194
2D193
2D192A
2D192
2D100L
2D163
2D161
2D160
2D159
2E370A
2C1392C1382C137
2D275
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 3 CONSTRUCTION
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 3 CONSTRUCTION
E
E
E
E
TEMPORARY PARTITION
WALL
ALL DOORS FACING
CORRIDOR TO BE
PROTECTED DURING
CONSTRUCTION
91'-8" COMMON PATH OF
TRAVEL DISTANCE
CONSTRUCTION AREA
ENDOSCOPY PROJECT - PHASE 1 AREA
VA ACTIVATION STARTING MID-DECEMBER
3'-9 1/2"
3'- 8 1
/2"
AutoCAD SHX Text
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
CHAIR
XXXXXX
X X XX XX X XX X
XX
X X X
X
X X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X
XX
X X
X X
X X
X X
X X
X X
X
X X X X X
X X
X
X X
X X X
X X X
X X
X X X
X X
X
X
X X
X
X X X
A
2D258
A B C D E F
GHIJKL
OIT Telecom/ Data Closet
OIT Telecom/ Data Closet OIT Telecom/
Data Closet
BLOOD
DRAW CAB. &
CHAIR
OIT Telecom/ Data Closet
BATTERY
CABINET
NO.1
UPS
CABINET
NO.1
UPS
CABINET
NO.2
BATTERY
CABINET
NO.2
UTS
NO.1
UTS
NO.2
RSP
NO.1
RSP
NO.2
WOW
VO VSVO SV
V OSV
2B301BA
2S7
FE
F E
FE
F E
FE
F E
FE
F E
F E
DESIGN DEVELOPMENT SUBMISSION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h
P
M
FULLY SPRINKLERED
Louis Stokes Cleveland
VA Medical Center
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT OF RECORD STAMPCONSULTANTS
321 4 6 7 8 9 10
REPLACE SECOND FLOOR
FLOORING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-201
NICK CARROZZA
CJK KMSRevisions: Date:
E T
G
DE
I
RET
S
HCRA
I
KACZMAR
STANLEY
NO. 4988
T
E R
S
ATE
I
T C
J.
O
O
FO
H
COST ESTIMATING:
MCGUINESS UNLIMITED, INC.
15724 STILLWOOD AVE.
CLEVELAND, OH 44111
P. 440.667.5120
MECH./ELEC. ENGINEERING:
FFE, INC.
110 BOGGS LANE, SUITE 170
SPRINGDALE, OH 45246
P. 513.522.2107
HAZ. MATERIALS ASSESSMENT:
STEPHEN J. SEBESTA & ASSOC., INC.
30628 DETROIT RD. #258
WESTLAKE, OH 44145
P. 216.781.0060
BID ISSUE SUBMISSION
65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20
FINAL CDs SUBMISSION 11.5.20
BID ISSUE SUBMISSION 5.10.21
8.31.20
SCALE: 1/16"=1'-0"
SECOND FLOOR - PHASE 4
LIFE SAFETY PLANNORTH
SECOND FLOOR INTERIM LIFE
SAFETY PLAN - PHASE 4
LS-2.45.10.21
LIFE SAFETY LEGEND:
TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA
SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF
CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR
EXISTING 2 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED SMOKE BARRIER
EXISTING O HOUR RATED SMOKE PARTITION
E EXIT
FE
FIRE EXTINGUISHER
EXIT SIGN LOCATION
LIFE SAFETY GENERAL NOTES:
1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING
HEALTH CARE OCCUPANCY" PER NFPA 101 2018.
2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS
3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)
4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.
5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND
COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY
DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY
STANDARDS.
HAZARDOUS ROOM
EXISTING 2 HOUR RATED SMOKE BARRIER
FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"
SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON
COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON
REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"
TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY
BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE
APPROVED BY THE COR.
PROJECT SCOPE BOUNDARY
SOLID WHITE AREA INDICATES
CONSTRUCTION AREA WITHIN SCOPE
OF WORK
GRAY HATCHED AREA INDICATES AREA
OUTSIDE OF SCOPE OF WORK
PHASING DURATION & CONSTRUCTION TIMEFRAMES:
THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING
HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:
PRE-CONSTRUCTION: 60 DAYS
PHASE I: 5 DAYS
PHASE II:
PHASE III:
TOTAL TIMEFRAME: 133 DAYS
THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:
THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):
WORK IN PUBLIC CORRIDORS/WAITING AREAS
WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING
FINISHES
CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS
INFECTION CONTROL CLASS & SAFETY MEASURES:
THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE
BUILDING.
REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26
THROUGHOUT THE ENTIRETY OF THE PROJECT.
PHASE IV:
PHASE V:
PHASE VI:
PHASE VII:
5 DAYS
5 DAYS
5 DAYS
5 DAYS
4 DAYS
4 DAYS
PHASE VIII: 4 DAYS
PHASE IX:
PHASE X:
PHASE XI:
PHASE XII:
PHASE XIII:
PHASE XIV:
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.
CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA
COR.
WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS
PHASE XV: 4 DAYS
PHASE XVI: 4 DAYS
PHASE XVII: 4 DAYS
MISC. OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
ACUTE MEDICINE OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
SLEEP LAB
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
HEMO-ONCOLOGY
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PACU
HOURS: M-F 6:00AM - 5:30 PM
NO WEEKENDS
PULMONARY - HOME OXYGEN
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
CARDIOLOGY - EP/CATH LAB
HOURS: M-F 7:30 AM - 5:30 PM
NO WEEKENDS
ENDOSCOPY
HOURS: M-F 7:30 AM - 5:30 PM
SATURDAY 7 AM - 2 PM
SURGERY - PRE-OP
HOURS: M-F 7:30 AM - 5:00 PM
WEEKENDS: EMERGENCY ONLY
SURGERY - OPERATING SUITE
HOURS: M-F 7:00 AM - 7:00 PM
WEEKENDS: EMERGENCY ONLY
MICU
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
PCU - CURRENT COVID WARD
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
GU
HOURS M-F: 7:30 AM - 4:30 PM
NO WEEKENDS
2B306A 2B3072B306B2B303
2B338A
2B301L
2B301M2B301N
2B301A
2B1502B149
2B146A
2B147
2B146B
2B149
2B413
2B410
2B411
2B1452B1442B143A
2B142 2B141
2B150
2B139
2B137
2B136
2B134
2B132
2B131
2B130
2B129
2B128
2B127
2B125
2B126
2B100B
2B100A
2B301B
2C328 2C326H2C326G2C326F
2C323A
2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C153
2C155
2B1242B1232B1222C1362C134 2C134A
2C133B
2C133A
2C133
2C100
2C400B
2C417
2C416
2C400C
2C420
2C415
2C414
2C413
2C411
2C129
2C400A
2C412
2C100B
2C100A
2C157
2C154
2C170
2C171 2D301H
2D301G
2D301F
2D301E
2D301D2D3022D301C 2D3032D304
2D307
2D301A
2D301Q
2D301P
2D301O
2D301N
2C1302C1312D100
2D100A2E314
2E300A
2E313
2E312
2E311
2E310
2E300A 2D100N
2D198
2D197
2D196A
2D196
2D195
2D194
2D193
2D192A
2D192
2D100L
2D163
2D161
2D160
2D159
2E370A
2C1392C1382C137
2D275
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 4 CONSTRUCTION
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 4 CONSTRUCTION
E
E
E
E
CONSTRUCTION AREA
TEMPORARY PARTITION
WALL
ENDOSCOPY PROJECT - PHASE 1 AREA
VA ACTIVATION STARTING MID-DECEMBER
3'- 8 1
/2" 3'-10"
AutoCAD SHX Text
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
CHAIR
XXXXXX
X X XX XX X XX X
XX
X X X
X
X X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X
XX
X X
X X
X X
X X
X X
X X
X
X X X X X
X X
X
X X
X X X
X X X
X X
X X X
X X
X
X
X X
X
X X X
A
2D258
A B C D E F
GHIJKL
OIT Telecom/ Data Closet
OIT Telecom/ Data Closet OIT Telecom/
Data Closet
BLOOD
DRAW CAB. &
CHAIR
OIT Telecom/ Data Closet
BATTERY
CABINET
NO.1
UPS
CABINET
NO.1
UPS
CABINET
NO.2
BATTERY
CABINET
NO.2
UTS
NO.1
UTS
NO.2
RSP
NO.1
RSP
NO.2
WOW
VO VSVO SV
V OSV
2B301BA
2S7
FE
F E
FE
F E
FE
F E
FE
F E
F E
DESIGN DEVELOPMENT SUBMISSION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h
P
M
FULLY SPRINKLERED
Louis Stokes Cleveland
VA Medical Center
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT OF RECORD STAMPCONSULTANTS
321 4 6 7 8 9 10
REPLACE SECOND FLOOR
FLOORING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-201
NICK CARROZZA
CJK KMSRevisions: Date:
E T
G
DE
I
RET
S
HCRA
I
KACZMAR
STANLEY
NO. 4988
T
E R
S
ATE
I
T C
J.
O
O
FO
H
COST ESTIMATING:
MCGUINESS UNLIMITED, INC.
15724 STILLWOOD AVE.
CLEVELAND, OH 44111
P. 440.667.5120
MECH./ELEC. ENGINEERING:
FFE, INC.
110 BOGGS LANE, SUITE 170
SPRINGDALE, OH 45246
P. 513.522.2107
HAZ. MATERIALS ASSESSMENT:
STEPHEN J. SEBESTA & ASSOC., INC.
30628 DETROIT RD. #258
WESTLAKE, OH 44145
P. 216.781.0060
BID ISSUE SUBMISSION
65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20
FINAL CDs SUBMISSION 11.5.20
BID ISSUE SUBMISSION 5.10.21
8.31.20
SCALE: 1/16"=1'-0"
SECOND FLOOR - PHASE 5
LIFE SAFETY PLANNORTH
SECOND FLOOR INTERIM LIFE
SAFETY PLAN - PHASE 5
LS-2.55.10.21
LIFE SAFETY LEGEND:
TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA
SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF
CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR
EXISTING 2 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED SMOKE BARRIER
EXISTING O HOUR RATED SMOKE PARTITION
E EXIT
FE
FIRE EXTINGUISHER
EXIT SIGN LOCATION
LIFE SAFETY GENERAL NOTES:
1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING
HEALTH CARE OCCUPANCY" PER NFPA 101 2018.
2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS
3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)
4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.
5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND
COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY
DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY
STANDARDS.
HAZARDOUS ROOM
EXISTING 2 HOUR RATED SMOKE BARRIER
FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"
SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON
COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON
REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"
TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY
BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE
APPROVED BY THE COR.
PROJECT SCOPE BOUNDARY
SOLID WHITE AREA INDICATES
CONSTRUCTION AREA WITHIN SCOPE
OF WORK
GRAY HATCHED AREA INDICATES AREA
OUTSIDE OF SCOPE OF WORK
PHASING DURATION & CONSTRUCTION TIMEFRAMES:
THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING
HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:
PRE-CONSTRUCTION: 60 DAYS
PHASE I: 5 DAYS
PHASE II:
PHASE III:
TOTAL TIMEFRAME: 133 DAYS
THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:
THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):
WORK IN PUBLIC CORRIDORS/WAITING AREAS
WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING
FINISHES
CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS
INFECTION CONTROL CLASS & SAFETY MEASURES:
THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE
BUILDING.
REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26
THROUGHOUT THE ENTIRETY OF THE PROJECT.
PHASE IV:
PHASE V:
PHASE VI:
PHASE VII:
5 DAYS
5 DAYS
5 DAYS
5 DAYS
4 DAYS
4 DAYS
PHASE VIII: 4 DAYS
PHASE IX:
PHASE X:
PHASE XI:
PHASE XII:
PHASE XIII:
PHASE XIV:
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
4 DAYS
TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.
CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA
COR.
WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS
PHASE XV: 4 DAYS
PHASE XVI: 4 DAYS
PHASE XVII: 4 DAYS
MISC. OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
ACUTE MEDICINE OFFICES
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
SLEEP LAB
HOURS: M-F 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
HEMO-ONCOLOGY
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
PULMONARY - STAFF
HOURS M-F: 7:00 AM - 3:30 PM
NO WEEKENDS
PACU
HOURS: M-F 6:00AM - 5:30 PM
NO WEEKENDS
PULMONARY - HOME OXYGEN
HOURS M-F: 7:00 AM - 5:30 PM
NO WEEKENDS
CARDIOLOGY - EP/CATH LAB
HOURS: M-F 7:30 AM - 5:30 PM
NO WEEKENDS
ENDOSCOPY
HOURS: M-F 7:30 AM - 5:30 PM
SATURDAY 7 AM - 2 PM
SURGERY - PRE-OP
HOURS: M-F 7:30 AM - 5:00 PM
WEEKENDS: EMERGENCY ONLY
SURGERY - OPERATING SUITE
HOURS: M-F 7:00 AM - 7:00 PM
WEEKENDS: EMERGENCY ONLY
MICU
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
PCU - CURRENT COVID WARD
HOURS: 24 HOURS A DAY
7 DAYS A WEEK
GU
HOURS M-F: 7:30 AM - 4:30 PM
NO WEEKENDS
2B306A 2B3072B306B2B303
2B338A
2B301L
2B301M2B301N
2B301A
2B1502B149
2B146A
2B147
2B146B
2B149
2B413
2B410
2B411
2B1452B1442B143A
2B142 2B141
2B150
2B139
2B137
2B136
2B134
2B132
2B131
2B130
2B129
2B128
2B127
2B125
2B126
2B100B
2B100A
2B301B
2C328 2C326H2C326G2C326F
2C323A
2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C1532C155
2B1242B1232B1222C1362C134 2C134A
2C133B
2C133A
2C133
2C100
2C400B
2C417
2C416
2C400C
2C420
2C415
2C414
2C413
2C411
2C129
2C400A
2C412
2C100B
2C100A
2C157
2C154
2C170
2C171 2D301H
2D301G
2D301F
2D301E
2D301D2D3022D301C 2D3032D304
2D307
2D301A
2D301Q
2D301P
2D301O
2D301N
2C1302C1312D100
2D100A2E314
2E300A
2E313
2E312
2E311
2E310
2E300A 2D100N
2D198
2D197
2D196A
2D196
2D195
2D194
2D193
2D192A
2D192
2D100L
2D163
2D161
2D160
2D159
2E370A
2C1392C1382C137
2D275
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 5 CONSTRUCTION
ALL EXISTING EGRESS
PATHS TO REMAIN
UNAFFECTED DURING
PHASE 5 CONSTRUCTION
E
E
E
STAIR DOOR NOT IN USE
DURING PHASE. VA TO
ISSUE ILSM AS REQUIRED
ALL DOORS FACING
CORRIDOR TO BE
PROTECTED DURING
CONSTRUCTION
TEMPORARY PARTITION
WALL
TEMPORARY PARTITION
WALL
ENDOSCOPY PROJECT - PHASE 1 AREA
VA ACTIVATION STARTING MID-DECEMBER
3'- 8"
3'-9 1/2"
AutoCAD SHX Text
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SR
AutoCAD SHX Text
SL
AutoCAD SHX Text
-FD
AutoCAD SHX Text
SL
CHAIR
XXXXXX
X X XX XX X XX X
XX
X X X
X
X X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X
XX
X X
X X
X X
X X
X X
X X
X
X X X X X
X X
X
X X
X X X
X X X
X X
X X X
X X
X
X
X X
X
X X X
A
2D258
A B C D E F
GHIJKL
OIT Telecom/ Data Closet
OIT Telecom/ Data Closet OIT Telecom/
Data Closet
BLOOD
DRAW CAB. &
CHAIR
OIT Telecom/ Data Closet
BATTERY
CABINET
NO.1
UPS
CABINET
NO.1
UPS
CABINET
NO.2
BATTERY
CABINET
NO.2
UTS
NO.1
UTS
NO.2
RSP
NO.1
RSP
NO.2
WOW
VO VSVO SV
V OSV
2B301BA
2S7
FE
F E
FE
F E
FE
F E
FE
F E
F E
DESIGN DEVELOPMENT SUBMISSION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h
P
M
FULLY SPRINKLERED
Louis Stokes Cleveland
VA Medical Center
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT OF RECORD STAMPCONSULTANTS
321 4 6 7 8 9 10
REPLACE SECOND FLOOR
FLOORING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-201
NICK CARROZZA
CJK KMSRevisions: Date:
E T
G
DE
I
RET
S
HCRA
I
KACZMAR
STANLEY
NO. 4988
T
E R
S
ATE
I
T C
J.
O
O
FO
H
COST ESTIMATING:
MCGUINESS UNLIMITED, INC.
15724 STILLWOOD AVE.
CLEVELAND, OH 44111
P. 440.667.5120
MECH./ELEC. ENGINEERING:
FFE, INC.
110 BOGGS LANE, SUITE 170
SPRINGDALE, OH 45246
P. 513.522.2107
HAZ. MATERIALS ASSESSMENT:
STEPHEN J. SEBESTA & ASSOC., INC.
30628 DETROIT RD. #258
WESTLAKE, OH 44145
P. 216.781.0060
BID ISSUE SUBMISSION
65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20
FINAL CDs SUBMISSION 11.5.20
BID ISSUE SUBMISSION 5.10.21
8.31.20
SCALE: 1/16"=1'-0"
SECOND FLOOR - PHASE 6
LIFE SAFETY PLANNORTH
SECOND FLOOR INTERIM LIFE
SAFETY PLAN - PHASE 6
LS-2.65.10.21
LIFE SAFETY LEGEND:
TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA
SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF
CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR
EXISTING 2 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED FIRE BARRIER
EXISTING 1 HOUR RATED SMOKE BARRIER
EXISTING O HOUR RATED SMOKE PARTITION
E EXIT
FE
FIRE EXTINGUISHER
EXIT SIGN LOCATION
LIFE SAFETY GENERAL NOTES:
1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING
HEALTH CARE OCCUPANCY" PER NFPA 101 2018.
2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS
3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)
4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.
5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND
COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY
DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY
STANDARDS.
HAZARDOUS ROOM
EXISTING 2 HOUR RATED SMOKE BARRIER
FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"
SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON
COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON
REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"
TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY
BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE
APPROVED BY THE COR.
PROJECT SCOPE BOUNDARY
SOLID WHITE AREA INDICATES
CONSTRUCTION AREA WITHIN SCOPE
OF WORK
GRAY HATCHED AREA INDICATES AREA
OU…