S02. BID ISSUE SUBMISSION - DRAWINGS.pdf

PDF 38 MB Posted

Attached to
Y1DA--Replace Second Floor Flooring Federal contract opportunity
Solicitation number
36C25021B0035
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This solicitation is for a construction project to replace flooring on the second floor of a Veterans Affairs medical center campus. The project scope includes site preparation and renovation to install 800 square feet of corridor flooring. All labor, equipment, materials and incidentals will be furnished by the contractor, who must perform all work in a manner that maintains safe usage of adjacent spaces for patients, staff and visitors.

The solicitation is a 100% set-aside for service-disabled veteran-owned small businesses and will be issued under authority of Public Law 109-461. Interested parties must register at SAM.gov and Vendor Information Pages to be eligible for award. The project value is between $100,000 and $500,000, bonds are required, and work must be completed within 133 days of notice to proceed. A site visit will be scheduled and the solicitation issued on or around April 15, 2021 with bids due approximately 30 days later. Questions are due in writing by the specified cutoff date.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--Replace Second Floor Flooring, newest first.
File Type Posted
S02. Wage Determination.pdf PDF
S02. Calculation of Self-Performed and Sub-Contracted Work.pdf PDF
S02. RFI Form.docx DOCX document
S02. Bid Opening Instructions.pdf PDF
S02. Solicitation 36C25021B0035_1.pdf PDF
S02. Safety.pdf PDF
S02. Brand Name or Equal Memo.pdf PDF
S02. Statement of Bid Items.pdf PDF
S02. BID ISSUE SUBMISSION - SPECIFICATIONS.pdf PDF
S02. VAMC Health Requirements.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TITLE SHEET & DRAWING

INDEX

10701 EAST BLVD. CLEVELAND, OH. 44106

DEPARTMENT OF VETERANS AFFAIRS MEDICAL CENTER - WADE PARK

Cleveland Veterans Affairs

Medical Center

REPLACE SECOND FLOOR FLOORING

DRAWING INDEX

PROJECT NO. 541-21-201

GI-1 TITLE SHEET & DRAWING INDEX

ARCHITECTURAL

LS-2.1 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 1

LS-2.2 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 2

LS-2.3 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 3

LS-2.4 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 4

LS-2.5 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 5

LS-2.6 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 6

LS-2.7 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 7

LS-2.8 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 8

LS-2.9 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 9

LS-2.10 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 10

LS-2.11 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 11

LS-2.12 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 12

LS-2.13 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 13

LS-2.14 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 14

LS-2.15 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 15

LS-2.16 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 16

LS-2.17 SECOND FLOOR INTERIM LIFE SAFETY PLAN - PHASE 17

BID ISSUE SUBMISSION

5.10.21

I. PROJECT LOCATION: CLEVELAND VETERANS AFFAIRS MEDICAL CENTER

10701 EAST BLVD.

CLEVELAND, OHIO

II. DESCRIPTION & USER GROUP CLASSIFICATION OF BLDG

A. NATURE OF PROJECT: REPLACEMENT OF EXISTING FLOORING AND BASE IN 2ND FLOOR

MAIN CORRIDOR & ELEVATOR LOBBIES

B. DESIGN CODES: 2018 NFPA LIFE SAFETY CODE 101, IBC 2018

C. USE GROUP: MIXED USE GROUPS IN HOSPITAL (I-2/S/B) - NO CHANGE PROPOSED

D. CONSTRUCTION TYPE: TYPE I -332, IB - NON-COMBUSTIBLE, PROTECTED

FIRE RATED CONSTRUCTION (LSC A.8.2.1.2)

EXTERIOR BEARING WALLS 3 HRS

INTERIOR BEARING WALLS 3 HRS

STRUCTURAL COLUMNS 3 HRS (SUPPORTING > 1 FLOOR)

2 HRS (SUPPORTING 1 FLOOR ONLY)

2 HRS (SUPPORTING ROOF ONLY)

BEAMS, GIRDERS, TRUSSES 3 HRS (SUPPORTING > 1 FLOOR, COLS., OR BEARING WALLS

2 HRS (ALL OTHERS)

FLOOR-CEILING ASSEMBLIES 2 HRS

ROOF-CEILING ASSEMBLIES 1 12 HRS

INTERIOR NON-BEARING WALLS 0 HRS

EXTERIOR NON-BEARING WALLS 0 HRS

WALL ASSEMBLIES

EXIT ACCESS CORRIDOR WALLS 0 HR SMOKE PARTITIONS

E. PROJECT AREA: 2ND FLOOR MAIN CORRIDOR: 7,300 SF

F. PROJECT AREA OCCUPANT LOAD: NOT APPLICABLE

G. FIRE PROTECTION: EXISTING BUILDING FULLY SPRINKLED AND WILL REMAIN AS A PART OF THIS PROJECT. FIRE

PROTECTION SYSTEM DESIGN NOT IN SCOPE OF WORK

CODE INFORMATION

8.31.20 GI-15.10.21

SITE KEY PLAN

NTS

NORTH

CLEVELAND VAMC

2ND FLOOR KEY PLAN

NTS

NORTH

PROJECT SITE:

2ND FLOOR MAIN

CORRIDOR &

ELEVATOR

LOBBIES

DESIGN DEVELOPMENT SUBMISSION

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

F i l e

P a t h

P

M

FULLY SPRINKLERED

Louis Stokes Cleveland

VA Medical Center

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANTS

321 4 6 7 8 9 10

REPLACE SECOND FLOOR

FLOORING

10701 EAST BLVD. CLEVELAND, OHIO

541-21-201

NICK CARROZZA

CJK KMSRevisions: Date:

E T

G

DE

I

RET

S

HCRA

I

KACZMAR

STANLEY

NO. 4988

T

E R

S

ATE

I

T C

J.

O

O

FO

H

COST ESTIMATING:

MCGUINESS UNLIMITED, INC.

15724 STILLWOOD AVE.

CLEVELAND, OH 44111

P. 440.667.5120

MECH./ELEC. ENGINEERING:

FFE, INC.

110 BOGGS LANE, SUITE 170

SPRINGDALE, OH 45246

P. 513.522.2107

HAZ. MATERIALS ASSESSMENT:

STEPHEN J. SEBESTA & ASSOC., INC.

30628 DETROIT RD. #258

WESTLAKE, OH 44145

P. 216.781.0060

BID ISSUE SUBMISSION

65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20

FINAL CDs SUBMISSION 11.5.20

BID ISSUE SUBMISSION 5.10.21

8.31.20

HAZARDOUS MATERIALS

HA-001 STANDARD DETAILS AND ASBESTOS ABATEMENT

HA-101.1 SECOND FLOOR ASBESTOS ABATEMENT PLAN, PHASE 1 &2

HA-101.2 SECOND FLOOR ASBESTOS ABATEMENT PLAN, PHASE 3 & 4

HA-101.3 SECOND FLOOR ASBESTOS ABATEMENT PLAN, PHASE 5

A-102 OVERALL SECOND FLOOR PHASING PLAN

A-102A OVERALL SECOND FLOOR FINISH PLAN

A-102.1 ENLARGED PHASE PLANS - PHASE 1 & 2

A-102.2 ENLARGED PHASE PLANS - PHASE 3 &4

A-102.3 ENLARGED PHASE PLANS - PHASE 5

A-102.4 ENLARGED PHASE PLANS - PHASE 6 & 7

A-102.5 ENLARGED PHASE PLANS - PHASE 8

A-102.6 ENLARGED PHASE PLANS - PHASE 9 &10

A-102.7 ENLARGED PHASE PLANS - PHASE 11 &12

A-102.8 ENLARGED PHASE PLANS - PHASE13 & 14

A-102.9 ENLARGED PHASE PLANS - PHASE 15 & 16

A-102.10 ENLARGED PHASE PLANS - PHASE 17

A-600 FINISH SCHEDULE AND DETAILS

ELECTRICAL

E-001 LEGEND AND ABBREVIATIONS

ED-0.1A SECOND FLOOR ELECTRICAL REFERENCE PLAN - EAST

ED-01B SECOND FLOOR ELECTRICAL REFERENCE PLAN - WEST

AutoCAD SHX Text

EAST BLVD.

AutoCAD SHX Text

E. 105 ST.

AutoCAD SHX Text

EAST BLVD.

AutoCAD SHX Text

MAGNOLIA DR.

AutoCAD SHX Text

HAZEL DR.

AutoCAD SHX Text

E. 108 ST.

AutoCAD SHX Text

MT. SINAI DR.

AutoCAD SHX Text

MARTIN LUTHER KING DR.

BLOOD

DRAW CAB. &

CHAIR

XXXXXX

X X XX XX X XX X

XX

X X X

X

X X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X

XX

X X

X X

X X

X X

X X

X X

X

X X X X X

X X

X

X X

X X X

X X X

X X

X X X

X X

X

X

X X

X

X X X

A

2D258

A B C D E F

GHIJKL

OIT Telecom/ Data Closet

OIT Telecom/ Data Closet OIT Telecom/

Data Closet

BLOOD

DRAW CAB. &

CHAIR

OIT Telecom/ Data Closet

BATTERY

CABINET

NO.1

UPS

CABINET

NO.1

UPS

CABINET

NO.2

BATTERY

CABINET

NO.2

UTS

NO.1

UTS

NO.2

RSP

NO.1

RSP

NO.2

WOW

VO VSVO SV

V OSV

2B301BA

2S7

FE

F E

FE

F E

FE

F E

FE

F E

F E

DESIGN DEVELOPMENT SUBMISSION

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

F i l e

P a t h

P

M

FULLY SPRINKLERED

Louis Stokes Cleveland

VA Medical Center

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANTS

321 4 6 7 8 9 10

REPLACE SECOND FLOOR

FLOORING

10701 EAST BLVD. CLEVELAND, OHIO

541-21-201

NICK CARROZZA

CJK KMSRevisions: Date:

E T

G

DE

I

RET

S

HCRA

I

KACZMAR

STANLEY

NO. 4988

T

E R

S

ATE

I

T C

J.

O

O

FO

H

COST ESTIMATING:

MCGUINESS UNLIMITED, INC.

15724 STILLWOOD AVE.

CLEVELAND, OH 44111

P. 440.667.5120

MECH./ELEC. ENGINEERING:

FFE, INC.

110 BOGGS LANE, SUITE 170

SPRINGDALE, OH 45246

P. 513.522.2107

HAZ. MATERIALS ASSESSMENT:

STEPHEN J. SEBESTA & ASSOC., INC.

30628 DETROIT RD. #258

WESTLAKE, OH 44145

P. 216.781.0060

BID ISSUE SUBMISSION

65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20

FINAL CDs SUBMISSION 11.5.20

BID ISSUE SUBMISSION 5.10.21

8.31.20

SCALE: 1/16"=1'-0"

SECOND FLOOR - PHASE 1

LIFE SAFETY PLANNORTH

SECOND FLOOR INTERIM LIFE

SAFETY PLAN - PHASE 1

LS-2.15.10.21

LIFE SAFETY LEGEND:

TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA

SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF

CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR

EXISTING 2 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED SMOKE BARRIER

EXISTING O HOUR RATED SMOKE PARTITION

E EXIT

FE

FIRE EXTINGUISHER

EXIT SIGN LOCATION

LIFE SAFETY GENERAL NOTES:

1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING

HEALTH CARE OCCUPANCY" PER NFPA 101 2018.

2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS

3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)

4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.

5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND

COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY

DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY

STANDARDS.

HAZARDOUS ROOM

EXISTING 2 HOUR RATED SMOKE BARRIER

FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"

SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON

COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON

REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"

TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY

BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE

APPROVED BY THE COR.

PROJECT SCOPE BOUNDARY

SOLID WHITE AREA INDICATES

CONSTRUCTION AREA WITHIN SCOPE

OF WORK

GRAY HATCHED AREA INDICATES AREA

OUTSIDE OF SCOPE OF WORK

PHASING DURATION & CONSTRUCTION TIMEFRAMES:

THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING

HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:

PRE-CONSTRUCTION: 60 DAYS

PHASE I: 5 DAYS

PHASE II:

PHASE III:

TOTAL TIMEFRAME: 133 DAYS

THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:

THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):

WORK IN PUBLIC CORRIDORS/WAITING AREAS

WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING

FINISHES

CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS

INFECTION CONTROL CLASS & SAFETY MEASURES:

THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE

BUILDING.

REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26

THROUGHOUT THE ENTIRETY OF THE PROJECT.

PHASE IV:

PHASE V:

PHASE VI:

PHASE VII:

5 DAYS

5 DAYS

5 DAYS

5 DAYS

4 DAYS

4 DAYS

PHASE VIII: 4 DAYS

PHASE IX:

PHASE X:

PHASE XI:

PHASE XII:

PHASE XIII:

PHASE XIV:

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.

CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA

COR.

WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS

PHASE XV: 4 DAYS

PHASE XVI: 4 DAYS

PHASE XVII: 4 DAYS

MISC. OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

ACUTE MEDICINE OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

SLEEP LAB

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

HEMO-ONCOLOGY

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PACU

HOURS: M-F 6:00AM - 5:30 PM

NO WEEKENDS

PULMONARY - HOME OXYGEN

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

CARDIOLOGY - EP/CATH LAB

HOURS: M-F 7:30 AM - 5:30 PM

NO WEEKENDS

ENDOSCOPY

HOURS: M-F 7:30 AM - 5:30 PM

SATURDAY 7 AM - 2 PM

SURGERY - PRE-OP

HOURS: M-F 7:30 AM - 5:00 PM

WEEKENDS: EMERGENCY ONLY

SURGERY - OPERATING SUITE

HOURS: M-F 7:00 AM - 7:00 PM

WEEKENDS: EMERGENCY ONLY

MICU

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

PCU - CURRENT COVID WARD

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

GU

HOURS M-F: 7:30 AM - 4:30 PM

NO WEEKENDS

2B306A 2B3072B306B2B303

2B338A

2B301L

2B301M2B301N

2B301A

2B1502B149

2B146A

2B147

2B146B

2B149

2B413

2B410

2B411

2B1452B1442B143A

2B142 2B141

2B150

2B139

2B137

2B136

2B134

2B132

2B131

2B130

2B129

2B128

2B127

2B125

2B126

2B100B

2B100A

2B301B

2C328 2C326H2C326G2C326F

2C323A

2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C1532C155

2B1242B1232B1222C1362C134 2C134A

2C133B

2C133A

2C133

2C100

2C400B

2C417

2C416

2C400C

2C420

2C415

2C414

2C413

2C411

2C129

2C400A

2C412

2C100B

2C100A

2C157

2C154

2C170

2C171 2D301H

2D301G

2D301F

2D301E

2D301D2D3022D301C 2D3032D304

2D307

2D301A

2D301Q

2D301P

2D301O

2D301N

2C1302C1312D100

2D100A2E314

2E300A

2E313

2E312

2E311

2E310

2E300A 2D100N

2D198

2D197

2D196A

2D196

2D195

2D194

2D193

2D192A

2D192

2D100L

2D163

2D161

2D160

2D159

2E370A

2C1392C1382C137

2D275

ALL DOORS FACING

CORRIDOR TO BE

PROTECTED DURING

CONSTRUCTION

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 1 CONSTRUCTION

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 1 CONSTRUCTION

E

E

DOOR TO REMAIN

AVAILABLE TO STAFF FOR

EMERGENCY USE DURING

CONSTRUCTION PHASE

E

E

TEMPORARY PARTITION

WALL

6'- 5"

CONSTRUCTION AREA

3'-10"

ENDOSCOPY PROJECT - PHASE 1 AREA

VA ACTIVATION STARTING MID-DECEMBER

AutoCAD SHX Text

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

-FD

CHAIR

XXXXXX

X X XX XX X XX X

XX

X X X

X

X X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X

XX

X X

X X

X X

X X

X X

X X

X

X X X X X

X X

X

X X

X X X

X X X

X X

X X X

X X

X

X

X X

X

X X X

A

2D258

A B C D E F

GHIJKL

OIT Telecom/ Data Closet

OIT Telecom/ Data Closet OIT Telecom/

Data Closet

BLOOD

DRAW CAB. &

CHAIR

OIT Telecom/ Data Closet

BATTERY

CABINET

NO.1

UPS

CABINET

NO.1

UPS

CABINET

NO.2

BATTERY

CABINET

NO.2

UTS

NO.1

UTS

NO.2

RSP

NO.1

RSP

NO.2

WOW

VO VSVO SV

V OSV

2B301BA

2S7

FE

F E

FE

F E

FE

F E

FE

F E

F E

DESIGN DEVELOPMENT SUBMISSION

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

F i l e

P a t h

P

M

FULLY SPRINKLERED

Louis Stokes Cleveland

VA Medical Center

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANTS

321 4 6 7 8 9 10

REPLACE SECOND FLOOR

FLOORING

10701 EAST BLVD. CLEVELAND, OHIO

541-21-201

NICK CARROZZA

CJK KMSRevisions: Date:

E T

G

DE

I

RET

S

HCRA

I

KACZMAR

STANLEY

NO. 4988

T

E R

S

ATE

I

T C

J.

O

O

FO

H

COST ESTIMATING:

MCGUINESS UNLIMITED, INC.

15724 STILLWOOD AVE.

CLEVELAND, OH 44111

P. 440.667.5120

MECH./ELEC. ENGINEERING:

FFE, INC.

110 BOGGS LANE, SUITE 170

SPRINGDALE, OH 45246

P. 513.522.2107

HAZ. MATERIALS ASSESSMENT:

STEPHEN J. SEBESTA & ASSOC., INC.

30628 DETROIT RD. #258

WESTLAKE, OH 44145

P. 216.781.0060

BID ISSUE SUBMISSION

65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20

FINAL CDs SUBMISSION 11.5.20

BID ISSUE SUBMISSION 5.10.21

8.31.20

SCALE: 1/16"=1'-0"

SECOND FLOOR - PHASE 2

LIFE SAFETY PLANNORTH

SECOND FLOOR INTERIM LIFE

SAFETY PLAN - PHASE 2

LS-2.25.10.21

LIFE SAFETY LEGEND:

TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA

SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF

CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR

EXISTING 2 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED SMOKE BARRIER

EXISTING O HOUR RATED SMOKE PARTITION

E EXIT

FE

FIRE EXTINGUISHER

EXIT SIGN LOCATION

LIFE SAFETY GENERAL NOTES:

1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING

HEALTH CARE OCCUPANCY" PER NFPA 101 2018.

2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS

3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)

4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.

5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND

COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY

DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY

STANDARDS.

HAZARDOUS ROOM

EXISTING 2 HOUR RATED SMOKE BARRIER

FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"

SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON

COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON

REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"

TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY

BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE

APPROVED BY THE COR.

PROJECT SCOPE BOUNDARY

SOLID WHITE AREA INDICATES

CONSTRUCTION AREA WITHIN SCOPE

OF WORK

GRAY HATCHED AREA INDICATES AREA

OUTSIDE OF SCOPE OF WORK

PHASING DURATION & CONSTRUCTION TIMEFRAMES:

THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING

HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:

PRE-CONSTRUCTION: 60 DAYS

PHASE I: 5 DAYS

PHASE II:

PHASE III:

TOTAL TIMEFRAME: 133 DAYS

THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:

THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):

WORK IN PUBLIC CORRIDORS/WAITING AREAS

WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING

FINISHES

CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS

INFECTION CONTROL CLASS & SAFETY MEASURES:

THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE

BUILDING.

REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26

THROUGHOUT THE ENTIRETY OF THE PROJECT.

PHASE IV:

PHASE V:

PHASE VI:

PHASE VII:

5 DAYS

5 DAYS

5 DAYS

5 DAYS

4 DAYS

4 DAYS

PHASE VIII: 4 DAYS

PHASE IX:

PHASE X:

PHASE XI:

PHASE XII:

PHASE XIII:

PHASE XIV:

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.

CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA

COR.

WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS

PHASE XV: 4 DAYS

PHASE XVI: 4 DAYS

PHASE XVII: 4 DAYS

MISC. OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

ACUTE MEDICINE OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

SLEEP LAB

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

HEMO-ONCOLOGY

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PACU

HOURS: M-F 6:00AM - 5:30 PM

NO WEEKENDS

PULMONARY - HOME OXYGEN

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

CARDIOLOGY - EP/CATH LAB

HOURS: M-F 7:30 AM - 5:30 PM

NO WEEKENDS

ENDOSCOPY

HOURS: M-F 7:30 AM - 5:30 PM

SATURDAY 7 AM - 2 PM

SURGERY - PRE-OP

HOURS: M-F 7:30 AM - 5:00 PM

WEEKENDS: EMERGENCY ONLY

SURGERY - OPERATING SUITE

HOURS: M-F 7:00 AM - 7:00 PM

WEEKENDS: EMERGENCY ONLY

MICU

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

PCU - CURRENT COVID WARD

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

GU

HOURS M-F: 7:30 AM - 4:30 PM

NO WEEKENDS

2B306A 2B3072B306B2B303

2B338A

2B301L

2B301M2B301N

2B301A

2B1502B149

2B146A

2B147

2B146B

2B149

2B413

2B410

2B411

2B1452B1442B143A

2B142 2B141

2B150

2B139

2B137

2B136

2B134

2B132

2B131

2B130

2B129

2B128

2B127

2B125

2B126

2B100B

2B100A

2B301B

2C328 2C326H2C326G2C326F

2C323A

2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C1532C155

2B1242B1232B1222C1362C134 2C134A

2C133B

2C133A

2C133

2C100

2C400B

2C417

2C416

2C400C

2C420

2C415

2C414

2C413

2C411

2C129

2C400A

2C412

2C100B

2C100A

2C157

2C154

2C170

2C171 2D301H

2D301G

2D301F

2D301E

2D301D2D3022D301C 2D3032D304

2D307

2D301A

2D301Q

2D301P

2D301O

2D301N

2C1302C1312D100

2D100A2E314

2E300A

2E313

2E312

2E311

2E310

2E300A 2D100N

2D198

2D197

2D196A

2D196

2D195

2D194

2D193

2D192A

2D192

2D100L

2D163

2D161

2D160

2D159

2E370A

2C1392C1382C137

2D275

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 2 CONSTRUCTION

E

E

E

TEMPORARY PARTITION

WALL

7'- 5"

CO

NS

TR

UC

TI

ON

A

RE

A

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 2 CONSTRUCTION

ALL DOORS FACING

CORRIDOR TO BE

PROTECTED DURING

CONSTRUCTION

DOOR TO REMAIN

AVAILABLE TO STAFF FOR

EMERGENCY USE DURING

CONSTRUCTION PHASE

E

ENDOSCOPY PROJECT - PHASE 1 AREA

VA ACTIVATION STARTING MID-DECEMBER

3'- 8 1

/2"

3'-9 1/2"

AutoCAD SHX Text

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

CHAIR

XXXXXX

X X XX XX X XX X

XX

X X X

X

X X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X

XX

X X

X X

X X

X X

X X

X X

X

X X X X X

X X

X

X X

X X X

X X X

X X

X X X

X X

X

X

X X

X

X X X

A

2D258

A B C D E F

GHIJKL

OIT Telecom/ Data Closet

OIT Telecom/ Data Closet OIT Telecom/

Data Closet

BLOOD

DRAW CAB. &

CHAIR

OIT Telecom/ Data Closet

BATTERY

CABINET

NO.1

UPS

CABINET

NO.1

UPS

CABINET

NO.2

BATTERY

CABINET

NO.2

UTS

NO.1

UTS

NO.2

RSP

NO.1

RSP

NO.2

WOW

VO VSVO SV

V OSV

2B301BA

2S7

FE

F E

FE

F E

FE

F E

FE

F E

F E

DESIGN DEVELOPMENT SUBMISSION

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

F i l e

P a t h

P

M

FULLY SPRINKLERED

Louis Stokes Cleveland

VA Medical Center

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANTS

321 4 6 7 8 9 10

REPLACE SECOND FLOOR

FLOORING

10701 EAST BLVD. CLEVELAND, OHIO

541-21-201

NICK CARROZZA

CJK KMSRevisions: Date:

E T

G

DE

I

RET

S

HCRA

I

KACZMAR

STANLEY

NO. 4988

T

E R

S

ATE

I

T C

J.

O

O

FO

H

COST ESTIMATING:

MCGUINESS UNLIMITED, INC.

15724 STILLWOOD AVE.

CLEVELAND, OH 44111

P. 440.667.5120

MECH./ELEC. ENGINEERING:

FFE, INC.

110 BOGGS LANE, SUITE 170

SPRINGDALE, OH 45246

P. 513.522.2107

HAZ. MATERIALS ASSESSMENT:

STEPHEN J. SEBESTA & ASSOC., INC.

30628 DETROIT RD. #258

WESTLAKE, OH 44145

P. 216.781.0060

BID ISSUE SUBMISSION

65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20

FINAL CDs SUBMISSION 11.5.20

BID ISSUE SUBMISSION 5.10.21

8.31.20

SCALE: 1/16"=1'-0"

SECOND FLOOR - PHASE 3

LIFE SAFETY PLANNORTH

SECOND FLOOR INTERIM LIFE

SAFETY PLAN - PHASE 3

LS-2.35.10.21

LIFE SAFETY LEGEND:

TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA

SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF

CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR

EXISTING 2 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED SMOKE BARRIER

EXISTING O HOUR RATED SMOKE PARTITION

E EXIT

FE

FIRE EXTINGUISHER

EXIT SIGN LOCATION

LIFE SAFETY GENERAL NOTES:

1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING

HEALTH CARE OCCUPANCY" PER NFPA 101 2018.

2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS

3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)

4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.

5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND

COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY

DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY

STANDARDS.

HAZARDOUS ROOM

EXISTING 2 HOUR RATED SMOKE BARRIER

FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"

SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON

COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON

REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"

TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY

BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE

APPROVED BY THE COR.

PROJECT SCOPE BOUNDARY

SOLID WHITE AREA INDICATES

CONSTRUCTION AREA WITHIN SCOPE

OF WORK

GRAY HATCHED AREA INDICATES AREA

OUTSIDE OF SCOPE OF WORK

PHASING DURATION & CONSTRUCTION TIMEFRAMES:

THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING

HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:

PRE-CONSTRUCTION: 60 DAYS

PHASE I: 5 DAYS

PHASE II:

PHASE III:

TOTAL TIMEFRAME: 133 DAYS

THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:

THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):

WORK IN PUBLIC CORRIDORS/WAITING AREAS

WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING

FINISHES

CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS

INFECTION CONTROL CLASS & SAFETY MEASURES:

THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE

BUILDING.

REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26

THROUGHOUT THE ENTIRETY OF THE PROJECT.

PHASE IV:

PHASE V:

PHASE VI:

PHASE VII:

5 DAYS

5 DAYS

5 DAYS

5 DAYS

4 DAYS

4 DAYS

PHASE VIII: 4 DAYS

PHASE IX:

PHASE X:

PHASE XI:

PHASE XII:

PHASE XIII:

PHASE XIV:

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.

CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA

COR.

WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS

PHASE XV: 4 DAYS

PHASE XVI: 4 DAYS

PHASE XVII: 4 DAYS

MISC. OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

ACUTE MEDICINE OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

SLEEP LAB

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

HEMO-ONCOLOGY

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PACU

HOURS: M-F 6:00AM - 5:30 PM

NO WEEKENDS

PULMONARY - HOME OXYGEN

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

CARDIOLOGY - EP/CATH LAB

HOURS: M-F 7:30 AM - 5:30 PM

NO WEEKENDS

ENDOSCOPY

HOURS: M-F 7:30 AM - 5:30 PM

SATURDAY 7 AM - 2 PM

SURGERY - PRE-OP

HOURS: M-F 7:30 AM - 5:00 PM

WEEKENDS: EMERGENCY ONLY

SURGERY - OPERATING SUITE

HOURS: M-F 7:00 AM - 7:00 PM

WEEKENDS: EMERGENCY ONLY

MICU

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

PCU - CURRENT COVID WARD

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

GU

HOURS M-F: 7:30 AM - 4:30 PM

NO WEEKENDS

2B306A 2B3072B306B2B303

2B338A

2B301L

2B301M2B301N

2B301A

2B1502B149

2B146A

2B147

2B146B

2B149

2B413

2B410

2B411

2B1452B1442B143A

2B142 2B141

2B150

2B139

2B137

2B136

2B134

2B132

2B131

2B130

2B129

2B128

2B127

2B125

2B126

2B100B

2B100A

2B301B

2C328 2C326H2C326G2C326F

2C323A

2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C1532C155

2B1242B1232B1222C1362C134 2C134A

2C133B

2C133A

2C133

2C100

2C400B

2C417

2C416

2C400C

2C420

2C415

2C414

2C413

2C411

2C129

2C400A

2C412

2C100B

2C100A

2C157

2C154

2C170

2C171 2D301H

2D301G

2D301F

2D301E

2D301D2D3022D301C 2D3032D304

2D307

2D301A

2D301Q

2D301P

2D301O

2D301N

2C1302C1312D100

2D100A2E314

2E300A

2E313

2E312

2E311

2E310

2E300A 2D100N

2D198

2D197

2D196A

2D196

2D195

2D194

2D193

2D192A

2D192

2D100L

2D163

2D161

2D160

2D159

2E370A

2C1392C1382C137

2D275

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 3 CONSTRUCTION

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 3 CONSTRUCTION

E

E

E

E

TEMPORARY PARTITION

WALL

ALL DOORS FACING

CORRIDOR TO BE

PROTECTED DURING

CONSTRUCTION

91'-8" COMMON PATH OF

TRAVEL DISTANCE

CONSTRUCTION AREA

ENDOSCOPY PROJECT - PHASE 1 AREA

VA ACTIVATION STARTING MID-DECEMBER

3'-9 1/2"

3'- 8 1

/2"

AutoCAD SHX Text

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

CHAIR

XXXXXX

X X XX XX X XX X

XX

X X X

X

X X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X

XX

X X

X X

X X

X X

X X

X X

X

X X X X X

X X

X

X X

X X X

X X X

X X

X X X

X X

X

X

X X

X

X X X

A

2D258

A B C D E F

GHIJKL

OIT Telecom/ Data Closet

OIT Telecom/ Data Closet OIT Telecom/

Data Closet

BLOOD

DRAW CAB. &

CHAIR

OIT Telecom/ Data Closet

BATTERY

CABINET

NO.1

UPS

CABINET

NO.1

UPS

CABINET

NO.2

BATTERY

CABINET

NO.2

UTS

NO.1

UTS

NO.2

RSP

NO.1

RSP

NO.2

WOW

VO VSVO SV

V OSV

2B301BA

2S7

FE

F E

FE

F E

FE

F E

FE

F E

F E

DESIGN DEVELOPMENT SUBMISSION

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

F i l e

P a t h

P

M

FULLY SPRINKLERED

Louis Stokes Cleveland

VA Medical Center

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANTS

321 4 6 7 8 9 10

REPLACE SECOND FLOOR

FLOORING

10701 EAST BLVD. CLEVELAND, OHIO

541-21-201

NICK CARROZZA

CJK KMSRevisions: Date:

E T

G

DE

I

RET

S

HCRA

I

KACZMAR

STANLEY

NO. 4988

T

E R

S

ATE

I

T C

J.

O

O

FO

H

COST ESTIMATING:

MCGUINESS UNLIMITED, INC.

15724 STILLWOOD AVE.

CLEVELAND, OH 44111

P. 440.667.5120

MECH./ELEC. ENGINEERING:

FFE, INC.

110 BOGGS LANE, SUITE 170

SPRINGDALE, OH 45246

P. 513.522.2107

HAZ. MATERIALS ASSESSMENT:

STEPHEN J. SEBESTA & ASSOC., INC.

30628 DETROIT RD. #258

WESTLAKE, OH 44145

P. 216.781.0060

BID ISSUE SUBMISSION

65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20

FINAL CDs SUBMISSION 11.5.20

BID ISSUE SUBMISSION 5.10.21

8.31.20

SCALE: 1/16"=1'-0"

SECOND FLOOR - PHASE 4

LIFE SAFETY PLANNORTH

SECOND FLOOR INTERIM LIFE

SAFETY PLAN - PHASE 4

LS-2.45.10.21

LIFE SAFETY LEGEND:

TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA

SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF

CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR

EXISTING 2 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED SMOKE BARRIER

EXISTING O HOUR RATED SMOKE PARTITION

E EXIT

FE

FIRE EXTINGUISHER

EXIT SIGN LOCATION

LIFE SAFETY GENERAL NOTES:

1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING

HEALTH CARE OCCUPANCY" PER NFPA 101 2018.

2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS

3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)

4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.

5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND

COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY

DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY

STANDARDS.

HAZARDOUS ROOM

EXISTING 2 HOUR RATED SMOKE BARRIER

FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"

SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON

COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON

REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"

TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY

BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE

APPROVED BY THE COR.

PROJECT SCOPE BOUNDARY

SOLID WHITE AREA INDICATES

CONSTRUCTION AREA WITHIN SCOPE

OF WORK

GRAY HATCHED AREA INDICATES AREA

OUTSIDE OF SCOPE OF WORK

PHASING DURATION & CONSTRUCTION TIMEFRAMES:

THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING

HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:

PRE-CONSTRUCTION: 60 DAYS

PHASE I: 5 DAYS

PHASE II:

PHASE III:

TOTAL TIMEFRAME: 133 DAYS

THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:

THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):

WORK IN PUBLIC CORRIDORS/WAITING AREAS

WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING

FINISHES

CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS

INFECTION CONTROL CLASS & SAFETY MEASURES:

THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE

BUILDING.

REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26

THROUGHOUT THE ENTIRETY OF THE PROJECT.

PHASE IV:

PHASE V:

PHASE VI:

PHASE VII:

5 DAYS

5 DAYS

5 DAYS

5 DAYS

4 DAYS

4 DAYS

PHASE VIII: 4 DAYS

PHASE IX:

PHASE X:

PHASE XI:

PHASE XII:

PHASE XIII:

PHASE XIV:

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.

CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA

COR.

WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS

PHASE XV: 4 DAYS

PHASE XVI: 4 DAYS

PHASE XVII: 4 DAYS

MISC. OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

ACUTE MEDICINE OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

SLEEP LAB

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

HEMO-ONCOLOGY

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PACU

HOURS: M-F 6:00AM - 5:30 PM

NO WEEKENDS

PULMONARY - HOME OXYGEN

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

CARDIOLOGY - EP/CATH LAB

HOURS: M-F 7:30 AM - 5:30 PM

NO WEEKENDS

ENDOSCOPY

HOURS: M-F 7:30 AM - 5:30 PM

SATURDAY 7 AM - 2 PM

SURGERY - PRE-OP

HOURS: M-F 7:30 AM - 5:00 PM

WEEKENDS: EMERGENCY ONLY

SURGERY - OPERATING SUITE

HOURS: M-F 7:00 AM - 7:00 PM

WEEKENDS: EMERGENCY ONLY

MICU

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

PCU - CURRENT COVID WARD

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

GU

HOURS M-F: 7:30 AM - 4:30 PM

NO WEEKENDS

2B306A 2B3072B306B2B303

2B338A

2B301L

2B301M2B301N

2B301A

2B1502B149

2B146A

2B147

2B146B

2B149

2B413

2B410

2B411

2B1452B1442B143A

2B142 2B141

2B150

2B139

2B137

2B136

2B134

2B132

2B131

2B130

2B129

2B128

2B127

2B125

2B126

2B100B

2B100A

2B301B

2C328 2C326H2C326G2C326F

2C323A

2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C153

2C155

2B1242B1232B1222C1362C134 2C134A

2C133B

2C133A

2C133

2C100

2C400B

2C417

2C416

2C400C

2C420

2C415

2C414

2C413

2C411

2C129

2C400A

2C412

2C100B

2C100A

2C157

2C154

2C170

2C171 2D301H

2D301G

2D301F

2D301E

2D301D2D3022D301C 2D3032D304

2D307

2D301A

2D301Q

2D301P

2D301O

2D301N

2C1302C1312D100

2D100A2E314

2E300A

2E313

2E312

2E311

2E310

2E300A 2D100N

2D198

2D197

2D196A

2D196

2D195

2D194

2D193

2D192A

2D192

2D100L

2D163

2D161

2D160

2D159

2E370A

2C1392C1382C137

2D275

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 4 CONSTRUCTION

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 4 CONSTRUCTION

E

E

E

E

CONSTRUCTION AREA

TEMPORARY PARTITION

WALL

ENDOSCOPY PROJECT - PHASE 1 AREA

VA ACTIVATION STARTING MID-DECEMBER

3'- 8 1

/2" 3'-10"

AutoCAD SHX Text

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

CHAIR

XXXXXX

X X XX XX X XX X

XX

X X X

X

X X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X

XX

X X

X X

X X

X X

X X

X X

X

X X X X X

X X

X

X X

X X X

X X X

X X

X X X

X X

X

X

X X

X

X X X

A

2D258

A B C D E F

GHIJKL

OIT Telecom/ Data Closet

OIT Telecom/ Data Closet OIT Telecom/

Data Closet

BLOOD

DRAW CAB. &

CHAIR

OIT Telecom/ Data Closet

BATTERY

CABINET

NO.1

UPS

CABINET

NO.1

UPS

CABINET

NO.2

BATTERY

CABINET

NO.2

UTS

NO.1

UTS

NO.2

RSP

NO.1

RSP

NO.2

WOW

VO VSVO SV

V OSV

2B301BA

2S7

FE

F E

FE

F E

FE

F E

FE

F E

F E

DESIGN DEVELOPMENT SUBMISSION

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

F i l e

P a t h

P

M

FULLY SPRINKLERED

Louis Stokes Cleveland

VA Medical Center

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANTS

321 4 6 7 8 9 10

REPLACE SECOND FLOOR

FLOORING

10701 EAST BLVD. CLEVELAND, OHIO

541-21-201

NICK CARROZZA

CJK KMSRevisions: Date:

E T

G

DE

I

RET

S

HCRA

I

KACZMAR

STANLEY

NO. 4988

T

E R

S

ATE

I

T C

J.

O

O

FO

H

COST ESTIMATING:

MCGUINESS UNLIMITED, INC.

15724 STILLWOOD AVE.

CLEVELAND, OH 44111

P. 440.667.5120

MECH./ELEC. ENGINEERING:

FFE, INC.

110 BOGGS LANE, SUITE 170

SPRINGDALE, OH 45246

P. 513.522.2107

HAZ. MATERIALS ASSESSMENT:

STEPHEN J. SEBESTA & ASSOC., INC.

30628 DETROIT RD. #258

WESTLAKE, OH 44145

P. 216.781.0060

BID ISSUE SUBMISSION

65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20

FINAL CDs SUBMISSION 11.5.20

BID ISSUE SUBMISSION 5.10.21

8.31.20

SCALE: 1/16"=1'-0"

SECOND FLOOR - PHASE 5

LIFE SAFETY PLANNORTH

SECOND FLOOR INTERIM LIFE

SAFETY PLAN - PHASE 5

LS-2.55.10.21

LIFE SAFETY LEGEND:

TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA

SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF

CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR

EXISTING 2 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED SMOKE BARRIER

EXISTING O HOUR RATED SMOKE PARTITION

E EXIT

FE

FIRE EXTINGUISHER

EXIT SIGN LOCATION

LIFE SAFETY GENERAL NOTES:

1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING

HEALTH CARE OCCUPANCY" PER NFPA 101 2018.

2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS

3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)

4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.

5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND

COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY

DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY

STANDARDS.

HAZARDOUS ROOM

EXISTING 2 HOUR RATED SMOKE BARRIER

FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"

SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON

COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON

REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"

TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY

BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE

APPROVED BY THE COR.

PROJECT SCOPE BOUNDARY

SOLID WHITE AREA INDICATES

CONSTRUCTION AREA WITHIN SCOPE

OF WORK

GRAY HATCHED AREA INDICATES AREA

OUTSIDE OF SCOPE OF WORK

PHASING DURATION & CONSTRUCTION TIMEFRAMES:

THE SCOPE OF WORK DESCRIBED IN THIS DRAWING PACKAGE REPRESENTS A MULTI-PHASED PROJECT THAT MUST BE UNDERTAKEN SIMULTANEOUSLY WITH THE FULL OCCUPANCY AND FUNCTION OF THE EXISTING

HOSPITAL. THE PROPOSED PHASING DURATING PLAN IS AS FOLLOWS:

PRE-CONSTRUCTION: 60 DAYS

PHASE I: 5 DAYS

PHASE II:

PHASE III:

TOTAL TIMEFRAME: 133 DAYS

THE FOLLOWING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:

THE FOLLOWING WORK SHALL TAKE PLACE AFTER HOURS (EVENINGS OR WEEKENDS):

WORK IN PUBLIC CORRIDORS/WAITING AREAS

WORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING

FINISHES

CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS

INFECTION CONTROL CLASS & SAFETY MEASURES:

THE WORK IDENTIFIED IN THIS PROJECT IS ASSIGNED A CLASS III INFECTION CONTROL CLASS AND SHALL APPLY TO THIS PROJECT THROUGHOUT THE ENTIRETY OF CONSTRUCTION. ALL CONTRACTORS AND CONSTRUCTION WORKERS ARE REQUIRED TO VACUUM THEIR CLOTHING FULLY IN THE TEMPORARY CONSTRUCTION AREAS IDENTIFIED ON THE DRAWINGS PRIOR TO ENTERING OCCUPIED PORTIONS OF THE

BUILDING.

REFER TO DEMOLITION PLANS FOR SCOPE OF TEMPORARY CONSTRUCTION BARRIERS REQUIRED FOR THE PROJECT. REFER TO AND FOLLOW ALL PROTOCOL IDENTIFIED IN "SAFETY REQUIREMENTS" 01 35 26

THROUGHOUT THE ENTIRETY OF THE PROJECT.

PHASE IV:

PHASE V:

PHASE VI:

PHASE VII:

5 DAYS

5 DAYS

5 DAYS

5 DAYS

4 DAYS

4 DAYS

PHASE VIII: 4 DAYS

PHASE IX:

PHASE X:

PHASE XI:

PHASE XII:

PHASE XIII:

PHASE XIV:

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

4 DAYS

TEMPORARY CONSTRUCTION BARRIERS MUST BE FULLY IN PLACE AND INTACT DURING CONSTRUCTION.

CONTRACTORS, HOWEVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AWAY DURING REGULAR SHIFT HOURS, AND MUST COORDINATE SUCH ACTIVITIES WITH STAFF AND VA

COR.

WORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT AND ON WEEKENDS. ALL PHASES WILL START FRIDAYS @ 5:30 PM AND END 4-5 DAYS LATER. WORK IS NOT PERMITTED DURING THE WEEK DURING DAY HOURS AND MUST BE DONE IN THE EVENINGS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEWED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS

PHASE XV: 4 DAYS

PHASE XVI: 4 DAYS

PHASE XVII: 4 DAYS

MISC. OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

ACUTE MEDICINE OFFICES

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

SLEEP LAB

HOURS: M-F 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

HEMO-ONCOLOGY

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

PULMONARY - STAFF

HOURS M-F: 7:00 AM - 3:30 PM

NO WEEKENDS

PACU

HOURS: M-F 6:00AM - 5:30 PM

NO WEEKENDS

PULMONARY - HOME OXYGEN

HOURS M-F: 7:00 AM - 5:30 PM

NO WEEKENDS

CARDIOLOGY - EP/CATH LAB

HOURS: M-F 7:30 AM - 5:30 PM

NO WEEKENDS

ENDOSCOPY

HOURS: M-F 7:30 AM - 5:30 PM

SATURDAY 7 AM - 2 PM

SURGERY - PRE-OP

HOURS: M-F 7:30 AM - 5:00 PM

WEEKENDS: EMERGENCY ONLY

SURGERY - OPERATING SUITE

HOURS: M-F 7:00 AM - 7:00 PM

WEEKENDS: EMERGENCY ONLY

MICU

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

PCU - CURRENT COVID WARD

HOURS: 24 HOURS A DAY

7 DAYS A WEEK

GU

HOURS M-F: 7:30 AM - 4:30 PM

NO WEEKENDS

2B306A 2B3072B306B2B303

2B338A

2B301L

2B301M2B301N

2B301A

2B1502B149

2B146A

2B147

2B146B

2B149

2B413

2B410

2B411

2B1452B1442B143A

2B142 2B141

2B150

2B139

2B137

2B136

2B134

2B132

2B131

2B130

2B129

2B128

2B127

2B125

2B126

2B100B

2B100A

2B301B

2C328 2C326H2C326G2C326F

2C323A

2B1192B1202B121 2C1432C1422C1412C1462C1482C1492C1502C1532C155

2B1242B1232B1222C1362C134 2C134A

2C133B

2C133A

2C133

2C100

2C400B

2C417

2C416

2C400C

2C420

2C415

2C414

2C413

2C411

2C129

2C400A

2C412

2C100B

2C100A

2C157

2C154

2C170

2C171 2D301H

2D301G

2D301F

2D301E

2D301D2D3022D301C 2D3032D304

2D307

2D301A

2D301Q

2D301P

2D301O

2D301N

2C1302C1312D100

2D100A2E314

2E300A

2E313

2E312

2E311

2E310

2E300A 2D100N

2D198

2D197

2D196A

2D196

2D195

2D194

2D193

2D192A

2D192

2D100L

2D163

2D161

2D160

2D159

2E370A

2C1392C1382C137

2D275

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 5 CONSTRUCTION

ALL EXISTING EGRESS

PATHS TO REMAIN

UNAFFECTED DURING

PHASE 5 CONSTRUCTION

E

E

E

STAIR DOOR NOT IN USE

DURING PHASE. VA TO

ISSUE ILSM AS REQUIRED

ALL DOORS FACING

CORRIDOR TO BE

PROTECTED DURING

CONSTRUCTION

TEMPORARY PARTITION

WALL

TEMPORARY PARTITION

WALL

ENDOSCOPY PROJECT - PHASE 1 AREA

VA ACTIVATION STARTING MID-DECEMBER

3'- 8"

3'-9 1/2"

AutoCAD SHX Text

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SR

AutoCAD SHX Text

SL

AutoCAD SHX Text

-FD

AutoCAD SHX Text

SL

CHAIR

XXXXXX

X X XX XX X XX X

XX

X X X

X

X X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X

XX

X X

X X

X X

X X

X X

X X

X

X X X X X

X X

X

X X

X X X

X X X

X X

X X X

X X

X

X

X X

X

X X X

A

2D258

A B C D E F

GHIJKL

OIT Telecom/ Data Closet

OIT Telecom/ Data Closet OIT Telecom/

Data Closet

BLOOD

DRAW CAB. &

CHAIR

OIT Telecom/ Data Closet

BATTERY

CABINET

NO.1

UPS

CABINET

NO.1

UPS

CABINET

NO.2

BATTERY

CABINET

NO.2

UTS

NO.1

UTS

NO.2

RSP

NO.1

RSP

NO.2

WOW

VO VSVO SV

V OSV

2B301BA

2S7

FE

F E

FE

F E

FE

F E

FE

F E

F E

DESIGN DEVELOPMENT SUBMISSION

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

F i l e

P a t h

P

M

FULLY SPRINKLERED

Louis Stokes Cleveland

VA Medical Center

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANTS

321 4 6 7 8 9 10

REPLACE SECOND FLOOR

FLOORING

10701 EAST BLVD. CLEVELAND, OHIO

541-21-201

NICK CARROZZA

CJK KMSRevisions: Date:

E T

G

DE

I

RET

S

HCRA

I

KACZMAR

STANLEY

NO. 4988

T

E R

S

ATE

I

T C

J.

O

O

FO

H

COST ESTIMATING:

MCGUINESS UNLIMITED, INC.

15724 STILLWOOD AVE.

CLEVELAND, OH 44111

P. 440.667.5120

MECH./ELEC. ENGINEERING:

FFE, INC.

110 BOGGS LANE, SUITE 170

SPRINGDALE, OH 45246

P. 513.522.2107

HAZ. MATERIALS ASSESSMENT:

STEPHEN J. SEBESTA & ASSOC., INC.

30628 DETROIT RD. #258

WESTLAKE, OH 44145

P. 216.781.0060

BID ISSUE SUBMISSION

65% CONSTRUCTION DOCUMENT SUBMISSION 10.9.20

FINAL CDs SUBMISSION 11.5.20

BID ISSUE SUBMISSION 5.10.21

8.31.20

SCALE: 1/16"=1'-0"

SECOND FLOOR - PHASE 6

LIFE SAFETY PLANNORTH

SECOND FLOOR INTERIM LIFE

SAFETY PLAN - PHASE 6

LS-2.65.10.21

LIFE SAFETY LEGEND:

TEMPORARY ZIP WALL PROTECTION TO BE PROVIDED AROUND CONSTRUCTION AREA PER VA

SAFETY STANDARDS. INSTALLATION OF ZIP WALL MAY NEED TO OCCUR AFTER RELOCATION OF

CASEWORK/FURNITURE. GC TO COORDINATE SEQUENCING OF INSTALL WITH COR

EXISTING 2 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED FIRE BARRIER

EXISTING 1 HOUR RATED SMOKE BARRIER

EXISTING O HOUR RATED SMOKE PARTITION

E EXIT

FE

FIRE EXTINGUISHER

EXIT SIGN LOCATION

LIFE SAFETY GENERAL NOTES:

1. SEE COVER SHEET FOR APPLICABLE CODE INFORMATION. BUILDING IS CLASSIFIED AS A "EXISTING

HEALTH CARE OCCUPANCY" PER NFPA 101 2018.

2. PROJECT SCOPE LINE IS INDICATED FOR GENERAL INTENT ONLY. CONTRACTOR WILL COMPLETE ALL WORK REGARDLESS IF IT IS LOCATED OUTSIDE OF PROJECT SCOPE AREA AS INDICATED ON ANY DRAWINGS

3. CONTRACTOR TO COVER OR ALTER EXIT SIGNS, OR TEMPORARILY RELOCATE EXISTING EXIT SIGNS WHICH, DUE TO CONSTRUCTION, TEMPORARILY DO NOT DEPICT EXIT PATHS AND/OR ARE IN THE WAY OF TEMPORARY CONSTRUCTION BARRIERS (TYP. OF ALL EXIT SIGNS IN OR BEYOND PROJECT AREA)

4. TRAVEL DISTANCES OVER 200' WILL REQUIRE INTERIM LIFE SAFETY MEASURES. COORDINATE WITH VA.

5. TEMPORARY FIRE ALARMS IN CONSTRUCTION AREAS: GC SHALL PROVIDE TEMPORARY FIRE ALARMS IN ALL CONSTRUCTION AREAS THROUGHOUT THE CONSTRUCTION DURATION UNTIL SUCH TIME THAT NEW FIRE ALARM SYSTEM DEVICES ARE INSTALLED, TESTED, AND IN FULL OPERATION. HEAT DETECTION DEVICES SHALL BE UTILIZED AND SHALL BE CONNECTED TO THE BUILDING FIRE ALARM SYSTEM AND

COORDINATED THROUGH THE VA ELECTRICAL SHOP. GC SHALL COORDINATE WITH VA SAFETY

DEPARTMENT FOR ALL TEMPORARY FIRE ALARM INSTALLATIONS TO ENSURE COMPLIANCE WITH SAFETY

STANDARDS.

HAZARDOUS ROOM

EXISTING 2 HOUR RATED SMOKE BARRIER

FIRE-RATED PLASTIC SHEETING/METAL STUD WALL TEMPORARY PARTITION WALL W/3'-0" X 7'-0"

SCWD DOOR FOR CONTRACTOR ACCESS ONLY. WALL AND DOOR TO BE REMOVED UPON

COMPLETION OF WORK U.N.O. PATCH/REPAIR EXISTING CONDITIONS AS REQUIRED UPON

REMOVAL OF ALL TEMPORARY CONSTRUCTION. REFER TO "TEMPORARY CONSTRUCTION BARRIER"

TYPICAL PARTITION DETAIL ON SHEET AS-601. SCHEDULE NOTE: CONSTRUCTION OF TEMPORARY

BARRIERS SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS UNLESS OTHERWISE

APPROVED BY THE COR.

PROJECT SCOPE BOUNDARY

SOLID WHITE AREA INDICATES

CONSTRUCTION AREA WITHIN SCOPE

OF WORK

GRAY HATCHED AREA INDICATES AREA

OU…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .