S02 Attachment 2 -550-23-108 BID Drawings.pdf
PDF 6 MB Posted
- Solicitation number
- 36C25226B0008
About this file
Summary
This is a complete set of 100% construction documents for the renovation of room 58-1 R102 at the VA Illiana Healthcare System in Danville, Illinois (Project Number 550-23-108). The project scope includes renovating approximately 4,342 square feet on the first floor to accommodate the Supply Chain Management Service, with full sprinkler coverage required throughout.
The construction documents comprise 44 pages of detailed architectural, mechanical, plumbing, fire suppression, and electrical drawings prepared by Guidon Design Inc. Key scope elements include: demolition of existing walls, doors, and equipment; construction of new steel stud partition walls with fire ratings up to 2 hours; installation of new HVAC systems including a 3,650 CFM air handling unit (58AHU-01), six variable air volume (VAV) boxes, and associated ductwork; plumbing rough-ins for three lavatories and two sinks with healthcare-specific fixtures; fire suppression system modifications with new sprinkler heads; and comprehensive electrical work including new lighting fixtures, receptacles, power distribution panels, and technology infrastructure. The project requires coordination with existing building systems, infection control protocols during construction, and compliance with 2021 ICC codes, NFPA standards, and VA design manuals. Construction phasing must maintain life safety and occupant access to adjacent operational areas. The contract includes detailed schedules for mechanical equipment, plumbing fixtures, electrical panelboards, and lighting fixtures, with specification references for materials, installation methods, and quality standards.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT
LOCATION
SHADE INDICATES
AREA OUT OF
PROJECT SCOPE
BLDG 58 KEYPLAN
N
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
A u to d e s k D o c s /1
.5
.2
R e n o v a te
-1 R f o r
S u p p ly C h a in M a n a g e m e n t S e rv ic e
/1
.5
.2
A v
.r v t
/1
/2
:0
:1
P
M
GI000
COVER SHEET
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
RENOVATE 58-1 R102 FOR
SUPPLY CHAIN MANAGEMENT
SERVICE
DANVILLE, IL
550-23-108
58-R102
04/30/2025 BS JL
550-23-108
RENOVATE 58-1 R102 FOR SUPPLY CHAIN
MANAGEMENT SERVICE
VA ILLIANA HEALTHCARE SYSTEM
DANVILLE, IL
100% CONSTRUCTION DOCUMENTS
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SHEET INDEX
SHEET NUMBER SHEET NAME
GENERAL
GI000 COVER SHEET
GI101 FIRST FLOOR LIFE SAFETY PLAN
GC101 INFECTION CONTROL PLAN
HA101 HAZARDOUS MATERIAL REMOVAL PLAN
ARCHITECTURAL
AE001 ARCHITECTURAL SYMBOLS AND ABBREVIATIONS
AE002 WALL TYPES
AD101 FIRST FLOOR DEMOLITION PLAN
AE101 FIRST FLOOR ARCHITECTURAL PLAN
AE111 FIRST FLOOR REFLECTED CEILING PLAN
AE601 DOOR SCHEDULE
AI101 FIRST FLOOR INTERIOR FINISH PLAN
AI201 ENLARGED INTERIOR PLANS & ELEVATIONS
AI501 CASEWORK & INTERIOR FINISH DETAILS
QH101 EQUIPMENT FLOOR PLAN
QH102 SIGNAGE PLAN & TYPES
FIRE SUPPRESSION
F000 FIRE SUPPRESSION SYMBOLS AND ABBREVIATIONS
FDX101 FIRST FLOOR FIRE SUPPRESSION DEMOLITION PLAN
FX101 FIRST FLOOR FIRE SUPPRESSION PLAN
PLUMBING
P000 PLUMBING SYMBOLS AND ABBREVIATIONS
PD101 FIRST FLOOR PLUMBING DEMOLITION PLAN
PP101 FIRST FLOOR PLUMBING PLAN
PP500 PLUMBING DETAILS
PP600 PLUMBING SCHEDULES
MECHANICAL
M000 MECHANICAL SYMBOLS AND ABBREVIATIONS
MD101 FIRST FLOOR MECHANICAL DEMOLITION PLAN
MH101 FIRST FLOOR MECHANICAL HVAC PLAN
MP101 FIRST FLOOR MECHANICAL PIPING PLAN
MM300 MECHANICAL SECTIONS AND ENLARGED PLAN
MM500 MECHANICAL DETAILS
MM501 MECHANICAL DETAILS
MM600 MECHANICAL SCHEDULES
MM700 MECHANICAL AIRFLOW SCHEMATIC
MM701 MECHANICAL PIPING SCHEMATIC
ELECTRICAL
E000 ELECTRICAL SYMBOL LEGENDS AND ABBREVIATIONS
E001 ELECTRICAL SYMBOL LEGENDS AND NOTES
EDL101 ELECTRICAL FIRST FLOOR LIGHTING DEMOLITION PLAN
EDP101 ELECTRICAL FIRST FLOOR POWER AND SYSTEMS DEMOLITION PLAN
EL101 ELECTRICAL FIRST FLOOR LIGHTING PLAN
EP101 ELECTRICAL FIRST FLOOR POWER PLAN
ET100 ELECTRICAL BASEMENT OVERALL TECHNOLOGY PLAN
ET101 ELECTRICAL FIRST FLOOR TECHNOLOGY PLAN
EP500 ELECTRICAL DETAILS
EP600 ELECTRICAL SCHEDULES
EP700 ELECTRICAL SINGLE LINE DIAGRAMS
AREA MAP
VICINITY MAP
CAMPUS MAP
PROJECT SITE LOCATION
PROJECT SITE LOCATION
PROJECT SITE LOCATION
Contact:Contact: Contact:
GUIDON DESIGN INC.
Al Halabi
Senior Electrical Engineer
ELECTRICAL
ENGINEER
VA ILLIANA HEALTHCARE SYSTEM
Ryan Smith
COR
1900 E. Main Street Danville, IL 61832 p: 217.260.7118 e: john.smith13@va.gov
OWNER
GUIDON DESIGN INC.
Branden Songer, RID, NCIDQ
Project Manager / Interior Designer
1221 North Pennsylvania Street Indianapolis, IN 46202 p: 317.800.6388 x 160 e: bsonger@guidon.com
PROJECT MANAGER
1221 North Pennsylvania Street Indianapolis, IN 46202 p: 317.800.6388 x 165 e: ahalabi@guidon.com
N
N
N
Contact:
GUIDON DESIGN INC.
Daniel Willeman
Project Engineer
PLUMBING
ENGINEER
1221 North Pennsylvania Street Indianapolis, IN 46202 p: 317.800.6388 e: dwilleman@guidon.com
Contact:
GUIDON DESIGN INC.
Jake Fague
Senior Mechanical Engineer
MECHANICAL
ENGINEER
1221 North Pennsylvania Street Indianapolis, IN 46202 p: 317.800.6388 e: jfague@guidon.com
Contact:
GUIDON DESIGN INC.
Dylan Christensen
Architect
1221 North Pennsylvania Street Indianapolis, IN 46202 p: 317.800.6388 x 155 e: dchristensen@guidon.com
ARCHITECT
Revisions: Date:
TOTAL OCCUPANCY
EXIT
OCCUPANCY LOAD FACTOR
EXITS REQUIRED
SQUARE FOOTAGE
OCCUPANCY TYPE
EGRESS EXIT
B
1500 SF
CODE ANALYSIS LEGEND
1 HR FIRE SEPARATION
FE
EXISTING FIRE EXTINGUISHER
DIAGONAL DISTANCE
EXIT SEPARATION DISTANCE
EGRESS PATH
PROJECT BOUNDARY
2 HR FIRE SEPARATION
PROJECT
LOCATION
SHADE INDICATES
AREA OUT OF
PROJECT SCOPE
BLDG 58 KEYPLAN
N
T R
A V
E L
D
IS
T A
N C
E
'-0
FE
EXIT
EXIT
P A
T H
O F
E G
R E
S S
'-4
D
IA
G O
N A
L D
IS
T A
N C
E = 125'-0"
EXIT
EXIT
E X
IT
S
E P
A R
A T
IO
N
D
IS
T A
N C
E
1'
-1 1"
4342 SF
15029
B
620 SF
MECHANICAL
102J
65 SF
UNUSABLE SPACE
102M
56 SF
COPY
102E
1356 SF
STORAGE/OPEN
OFFICE
102B
669 SF
OPEN OFFICE
102A
155 SF
MEN'S LOCKER
103A
126 SF
WOMEN'S LOCKER
103B
49 SF
STORAGE
103C
66 SF
TOILET
102D
186 SF
BREAK ROOM
102C
42 SF
STORAGE
102H
60 SF
ELEC.
102G
34 SF
MECH.
102F
250 SF
DOCK
C1-9
53 SF
FREIGHT ELEVATOR
ELEV
CONTRACTOR TO VERIFY IF EXISTING MASONRY
WALL CONSTRUCTION MEETS 1HR FIRE RATING.
IF NOT MET, CONTRACTOR TO UPGRADE AND
SEAL PENETRATIONS TO MEET RATING.
CONTRACTOR TO VERIFY IF EXISTING MASONRY WALL
CONSTRUCTION MEETS 1HR FIRE RATING. IF NOT MET,
CONTRACTOR TO UPGRADE AND SEAL PENETRATIONS
TO MEET RATING.
CONTRACTOR TO VERIFY IF EXISTING MASONRY
WALL CONSTRUCTION MEETS 1HR FIRE RATING.
IF NOT MET, CONTRACTOR TO UPGRADE AND
SEAL PENETRATIONS TO MEET RATING.
CONTRACTOR TO VERIFY IF UNDERSIDE OF STAIR
CONSTRUCTION MEETS 1HR FIRE RATING. IF NOT
MET, CONTRACTOR TO UPGRADE AND SEAL
STAIR SOFFIT TO MEET RATING.
13' - 11 1/2"
NOTE:
STORAGE UNDER STAIR IS NOT ALLOWED PER CODE.
FEC
158 SF
OFFICE
102N
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
A u to d e s k D o c s /1
.5
.2
R e n o v a te
-1 R f o r
S u p p ly C h a in M a n a g e m e n t S e rv ic e
/1
.5
.2
A v
.r v t
/1
/2
:0
:1
P
M
GI101
FIRST FLOOR LIFE SAFETY PLAN
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
RENOVATE 58-1 R102 FOR
SUPPLY CHAIN MANAGEMENT
SERVICE
DANVILLE, IL
550-23-108
58-R102
04/30/2025 BS JL
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
TELECOMMUNICATIONS Feb-16
SUSTAINABILITY Aug-17
STRUCTURAL Feb-14
STEAM, HEATING, HOT WATER, AND OUTSIDE DISTRIBUTION SYSTEMS
May-24 Sep-22
SITE PARKING, SITE DEVELOPMENT, SITE APPENDIX
Nov-16 Mar-24
SIGNAGE Apr-17
PLUMBING May-18
PHYSICAL SECURITY Jan-21
LIGHTING DESIGN Dec-15
INTERIOR DESIGN Nov-20
HVAC Nov-20
FIRE PROTECTION Dec-15
ESTIMATING Mar-11
ELECTRICAL Dec-19
COMMISSIONING AND RETRO COMMISSIONING Nov-13
AUTOMATED TRANSPORT SYSTEMS Nov-20
ASBESTOS ABATEMENT Jul-11
ARCHITECTURAL Aug-14
VA DESIGN MANUALS PG-18-10
CODES AND GUIDELINES REFERENCED WITHIN NFPA AND ICC CODES ARE TO ALSO BE FOLLOWED AND APPLIED TO ALL DESIGN AND CONSTRUCTION. REFER TO VA MANUAL PG-18-3, SPECIFICATIONS FOR ADDITIONAL CODES, STANDARDS, GUIDELINES AND REGULATIONS. CONTRACTOR IS RESPONSIBLE FOR CONSTRUCTING WORK COMPLIANT WITH OSHA, OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION STANDARDS.
OSHA, OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION STANDARDS.
SYSTEMS RELATING TO MAINTENANCE OF FACILITIES
BEHAVIORAL HEALTH DESIGN GUIDE 2019 ED.
GUIDELINES FOR DESIGN AND CONSTRUCTION OF OUTPATIENT FACILITIES 2018 ED.
GUIDELINES FOR DESIGN AND CONSTRUCTION OF HOSPITALS 2018 ED.
FGI, THE FACILITY GUIDELINES INSTITUTE
VA BARRIER FREE DESIGN GUIDE PG-18-13, ABAAS
ADAAG, ADA ACCESSIBILITY GUIDELINES
ACCESSIBILITY CODES
STANDARD 188-2018, LEGIONELLOSIS: RISK MANAGEMENT FOR BUILDING WATER SYSTEMS
STANDARD 170-2017, VENTILATION OF HEALTHCARE FACILITIES
ASHRAE STANDARDS, AS REFERENCED WITHIN OTHER CODES INCLUDING, BUT NOT LIMITED TO:
INTERNATIONAL ENERGY AND CONSERVATION CODE 2021 ED.
INTERNATIONAL FIRE CODE 2021 ED.
INTERNATIONAL FUEL GAS CODE 2021 ED.
INTERNATIONAL MECHANICAL CODE 2021 ED.
INTERNATIONAL PLUMBING CODE 2021 ED.
INTERNATIONAL BUILDING CODE 2021 ED.
ICC CODES, INTERNATIONAL CODE COUNCIL FULL LISTING OF CURRENT CODES, INCLUDING BUT NOT LIMITED TO:
NFPA 241 STANDARD FOR SAFEGUARDING CONSTRUCTION, ALTERATION, AND DEMOLITION OPERATIONS 2019 ED.
NFPA 220 STANDARD ON TYPES OF BUILDING CONSTRUCTION 2021 ED.
NPFA 101 LIFE SAFETY CODE 2021 ED.
NFPA 99 HEALTHCARE FACILITIES CODE 2021 ED.
NFPA 80 STANDARD FOR FIRE DOORS AND FIRE WINDOWS 2019 ED.
NFPA 70, NEC NATIONAL ELECTRICAL CODE 2020 ED.
NFPA 72 FIRE ALARM CODE 2019 ED.
NFPA 13 STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS 2019 ED.
NFPA 10 STANDARD FOR PORTABLE FIRE EXTINGUISHER 2018 ED.
NPFA, NATIONAL FIRE PROTECTION ASSOCIATION FULL LISTING OF CURRENT CODES, INCLUDING BUT NOT LIMITED TO:
GOVERNING BUIDLING CODES
BUILDING CODES
SCALE: 3/32" = 1'-0"GI101
1 FIRST FLOOR LIFE SAFETY PLAN
CONSTRUCTION ACTIVITY - INFECTION RISK: D
PATIENT RISK GROUP: MEDIUM
CLASS OF PRECAUTION MATRIX: III
A. REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATIONS.
B. REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
C. COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
D. COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA
PROTOCOLS AND PLAN IS APPROVED.
E. SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE
PHASING INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR
PROVIDED CMP SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW
THE FLOOR PLATE OF THE PROJECT BOUNDARY.
F. ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED
IN A SAFE MANOR UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED
AND BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
G. EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
H. WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
I. PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36"
STICKY WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY DOOR
LOCATION. MAT SHALL BE REPLACED OR CLEANED AS NECESSARY
J. PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
K. CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
L. ALL NEW MATERIAL SHALL BE MOVED THROUGH FACILITY ON COVERED
CARTS WITH 4 MIL. POLY SHEET.
M. ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
N. ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
O. PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
INFECTION CONTROL GENERAL NOTES
INFECTION CONTROL PROJECT INFORMATION
1. PROVIDE TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL
CONSTRUCTION PER NFPA 241. REFER TO DETAIL 1/GC101.
2. TEMPORARY CONSTRUCTION ACCESS DOOR.
INFECTION CONTROL PLAN NOTES
TEMPORARY WALLS. SEE PLAN AND PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS DOORS
REFERENCE AREA FOR ABOVE CEILING
WORK ON FLOOR BELOW.
RE: ENGINEERING DRAWINGS FOR FULL
SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
IC / PHASING LEGEND
CONTINUOUS FIRESAFE SEALANT
TOP AND BOTTOM, & BOTH SIDES
3 1/2" SOUND ATTENUATION BATT.
5/8" TYPE X GYPSUM BOARD, BOTH SIDES
3 5/8" METAL STUD @ 16" O.C. WITH
RUNNER CHANNELS ALONG TOP
AND BOTTOM
CONSTRUCTION
SIDE
PUBLIC
SIDE
6 MIL. FIRE RETARDANT VISQUEEN
MEMBRANE. CONTINUOUSLY ADHERE
TO THE STRUCTURAL DECK ABOVE AND
TO THE FLOOR BELOW WITH TAPE.
UNDERSIDE OF STRUCTURAL DECK
UL LISTING: U465
COORDINATE WITH EXISTING CEILING
R S T U V
102G
STORAGE
102H
STORAGE
102O
STORAGE
102J
STORAGE
102K
STORAGE
102I
HVAC
STAIR
C1-9
CORRIDOR
102F
LOUNGE
102D
LAB
102G-1
INPATIENT PHARMACY
102B
INPATIENT PHARMACY
102C
INPATIENT PHARMACY
102A
INPATIENT PHARMACY
102L
STORAGE
102M
STORAGE
102N
TLT
103A
CHIEF OFFICE
OFFICE
103B
VAULT
ELEVATOR
102G-2
INPATIENT PHARMACY
102M
STORAGE
M
IN
5'
MIN
5' - 0"
CONTRACTOR ACCESS
UP
PROJECT
LOCATION
SHADE INDICATES
AREA OUT OF
PROJECT SCOPE
BLDG 58 KEYPLAN
N
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
A u to d e s k D o c s /1
.5
.2
R e n o v a te
-1 R f o r
S u p p ly C h a in M a n a g e m e n t S e rv ic e
/1
.5
.2
A v
.r v t
/1
/2
:0
:1
P
M
GC101
INFECTION CONTROL PLAN
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
RENOVATE 58-1 R102 FOR
SUPPLY CHAIN MANAGEMENT
SERVICE
DANVILLE, IL
550-23-108
58-R102
04/30/2025 BS TD
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1 1/2" = 1'-0"GC101
TEMPORARY 1 HR FIRE RATED SMOKE BARRIER
WALL CONSTRUCTION NFPA 241
SCALE: 1/8" = 1'-0"GC101
2 INFECTION CONTROL PLAN
A. HAZMAT REMOVAL NOTES APPLY TO ENTIRE ROOMS. CONTRACTOR SHALL
IDENTIFY ALL MATERIALS DESCRIBED BY NOTE IN EACH ROOM AND
REMOVE ACCORDING TO SAFETY STANDARDS. REFERENCE SPECIFICATION
02 82 13.13.
B. ALL HAZARDOUS MATERIALS SHALL BE REMOVED IN COMPLIANCE WITH
APPLICABLE CODES AND LAWS.
C. THE CONTRACTOR IS RESPONSIBLE TO VERIFY THE HAZARD(S) AND LEVEL
OF PROTECTION REQUIRED FOR ALL EMPLOYEES OR SUBCONTRACTORS
TO COMPLETE THE CONSTRUCTION WORK.
D. PROVIDE COST FOR REMOVAL OF FLUORESCENT LIGHT TUBES AND CFL
BULBS, ASSUME 164 EACH.
E. REFER TO SPECIFICATION AND ATTACHMENTS FOR ADDITIONAL
INFORMATION.
F. BASED ON THE DATE OF THE EXISTING CONSTRUCTION IT IS ASSUMED
LEAD PAINT IS WITHIN THE PROJECT AREA. CONDUCT DEMOLITION OF THE
EXISTING SPACE WITH THE ASSUMPTION OF LEAD PAINT ON PAINTED DOOR
FRAMES. REFER TO SPECIFICATION SECTION 02 83 33.13 LEAD-BASED PAINT
REMOVAL, DISPOSAL AND FOR ADDITIONAL INFORMATION.
G. CONTRACTOR TO SUBMIT LEAD SURFACES STABILIZATION PLAN AND
PROCEDURES PRIOR TO COMMENCING WORK. SUBMITTAL SHALL BE IN
ACCORDANCE WITH SPECIFICATIONS.
1. REMOVE PIPE INSULATION THROUGHOUT PROJECT BOUNDARY - APPROX.
500 LF TOTAL.
2. REMOVE PAPER SEAM TAPE - APPROX. 1,100 SF TOTAL.
3. REMOVE CERAMIC WALL TILE GLAZING.
4. REMOVE LEAD CONTAMINATED DOOR FRAME.
HAZARDOUS MATERIAL REMOVAL GENERAL NOTES
HAZARDOUS MATERIAL REMOVAL PLAN NOTES
HAZMAT LEGEND
PAPER SEAM TAPE ACM REMOVAL
CERAMIC WALL TILE LEAD REMOVAL
R S T U V
102G
STORAGE
102H
STORAGE
102O
STORAGE
102J
STORAGE
102K
ELECTRICAL
102I
HVAC
STAIR
C1-9
CORRIDOR
102F
LOUNGE
102D
LAB
102G-1
INPATIENT PHARMACY
102B
INPATIENT PHARMACY 102C
INPATIENT PHARMACY
102A
INPATIENT PHARMACY
102L
STORAGE
102M
STORAGE
102N
TLT
103A
CHIEF OFFICE
OFFICE
103B
VAULT
ELEVATOR
102G-2
INPATIENT PHARMACY
102M
STORAGE
UP
PROJECT
LOCATION
SHADE INDICATES
AREA OUT OF
PROJECT SCOPE
BLDG 58 KEYPLAN
N
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
A u to d e s k D o c s /1
.5
.2
R e n o v a te
-1 R f o r
S u p p ly C h a in M a n a g e m e n t S e rv ic e
/1
.5
.2
A v
.r v t
/1
/2
:0
:1
P
M
HA101
HAZARDOUS MATERIAL REMOVAL
PLANGUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
RENOVATE 58-1 R102 FOR
SUPPLY CHAIN MANAGEMENT
SERVICE
DANVILLE, IL
550-23-108
58-R102
04/30/2025 BS DMC
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1/8" = 1'-0"HA101
1 FIRST FLOOR HAZMAT PLAN
SECTION REFERENCE
DRAWING NUMBER
SHEET LOCATION
DRAWING NUMBER
SHEET
LOCATION
DETAIL REFERENCE
OBJECT
REFERENCED
OBJECT
REFERENCED
X
XXXX
X
XXXX
SCALE: ??
VIEW TITLE
N
NORTH ARROW
LED RECESSED LIGHT FIXTURE
HVAC RETURN AIR GRILLE
HVAC EXHAUST DIFFUSER
ACCESS PANEL
OS
SPRINKLER
OCCUPANCY SENSOR
A 9'-0"
CEILING TAG CEILING TYPE
FINISHED CEILING HEIGHT
REFER TO CEILING LEGEND FOR MORE
INFORMATION
EXTENT OF REVISION
REVISION SET
MECH/ELEC ITEMS: REFER TO MEP SHEETS AS APPLICABLE
PROJECT BOUNDARY
BEYOND PROJECT BOUNDARY, NIC
DETAIL/DRAWING SCALE
TITLE OF DETAIL/DRAWING
DETAIL/DRAWING NUMBER
SHEET NUMBER
1. THE CONTRACT DOCUMENT DRAWINGS HAVE BEEN PREPARED USING REVIT®
SOFTWARE IN A MICROSOFT WINDOWS ENVIRONMENT. A BUILDING INFORMATION
MODEL (BIM) HAS BEEN DEVELOPED FOR DESIGN COMMUNICATION. THE MODEL
DOES NOT CONTAIN COMPLETE INFORMATION FOR USE IN COST ESTIMATING,
SYSTEMS PERFORMANCE, COORDINATION, SCHEDULING, OR FACILITIES
MANAGEMENT.
2. THE CONTRACT DOCUMENT DRAWINGS HAVE BEEN PREPARED USING THE
CONSTRUCTION SPECIFICATIONS INSTITUTE'S UNIFORM DRAWING SYSTEM AND THE
NATIONAL CAD STANDARD AS GUIDES.
3. DISCREPANCIES IN THE CONTRACT DOCUMENTS SHALL BE IMMEDIATELY BROUGHT
TO THE ATTENTION OF THE ARCHITECT AND OWNER’S REPRESENTATIVE/COR.
CONTRACTOR SHALL PROVIDE THE HIGHER GRADE OF QUALITY AND/OR GREATER
QUANTITY OF WORK WHEN BIDDING IF A CLARIFICATION CAN NOT BE OBTAINED BY
THE BID DUE DATE.
4. CONTRACTOR IS RESPONSIBLE FOR COORDINATING SCOPE OF WORK WITH
OWNER’S REPRESENTATIVE/COR AND VARIOUS FACILITY PERSONNEL INVOLVED
WITH UTILITY SHUT DOWN, INFECTION CONTROLS, OCCUPANT/EMPLOYEE SAFETY,
ACCESS CONTROL, ETC.
5. ANY INDICATION OF PROJECT LIMITS OR BOUNDARY OF DEMARCATION ARE SHOWN
FOR THE CONVENIENCE OF THE CONTRACTOR, THE FULL SCOPE OF THE PROJECT
LIMIT OF BOUNDARY REQUIRES COORDINATION WITH THE DESIGN SCOPE OF WORK
AND ACCESS TO EXISTING UTILITIES FOR TIE IN.
6. DRAWINGS ARE PREPARED FROM FIELD VERIFICATION, EXISTING FACILITY DRAWING
BASE FILES, AND USING DIMENSIONS, CONFIGURATIONS AND DETAILS OF SPECIFIC
MANUFACTURERS AS A BASIS OF DESIGN. CONTRACTOR IS RESPONSIBLE FOR
VERIFICATION OF ACTUAL DIMENSIONS, THE COORDINATION OF THE DETAILS WITH
THE PRODUCTS WHICH ARE PROVIDED PER THE SCOPE OF THE SPECIFICATIONS
AND THE SURROUNDING CONSTRUCTION. CONTRACTOR SHALL VERIFY DIMENSIONS,
ROUGH-IN DIMENSIONS, CONNECTIONS, AND OVERALL INSTALLATION
REQUIREMENTS.
7. CONTRACTOR IS RESPONSIBLE FOR THE COMPLETION OF THE ENTIRE SCOPE OF
WORK OUTLINED IN THE CONTRACT DOCUMENTS. CONTRACTOR IS RESPONSIBLE
FOR THE COORDINATION OF ALL SUB-CONTRACTORS AND THE SCOPE OF WORK
THEY PROVIDE. SUB-CONTRACTORS ARE RESPONSIBLE FOR THEIR FULL SCOPE OF
WORK WITHIN THE CONTRACT DOCUMENTS, TRADES ARE NOT SEGMENTED TO ONLY
CERTAIN SHEETS AND SPECIFICATIONS, CROSS COORDINATION IS REQUIRED.
8. CONTRACTOR AND SUB-CONTRACTORS ARE BOTH RESPONSIBLE FOR
UNDERSTANDING INFORMATION OUTLINED IN THE SPECIFICATIONS, KEY NOTES,
GENERAL NOTES, LEGEND, CODES, ETC., PROVIDED IN THE CONTRACT DOCUMENTS.
9. CONTRACTOR AND SUB-CONTRACTORS ARE BOTH RESPONSIBLE FOR PROVIDING
AND MAINTAINING SMOKE/FIRE RATINGS OF NEW CONSTRUCTION AND EXISTING
CONSTRUCTION AS INDICATED ON DRAWINGS. THIS INCLUDES PATCHING
PENETRATIONS IN SHAFTS, WALLS, SLABS AND ROOF. ONLY U.L. APPROVED
METHODS, MATERIALS AND INSTALLATION ARE ACCEPTABLE.
10. MECHANICAL, PLUMBING, FIRE PROTECTION AND ELECTRICAL DRAWINGS SHOW
INFORMATION IN A DIAGRAMMATIC FASHION WITHOUT DIMENSIONING. THE GENERAL
CONTRACTOR IS TO COORDINATE THE LOCATIONS OF ALL MECHANICAL, PLUMBING
AND ELECTRICAL EQUIPMENT WITH RESPECT TO THE ARCHITECTURAL AND
STRUCTURAL DETAILING OF SHAFTS, CHASES, CEILING CONSTRUCTION, ETC.
11. CONTRACTOR IS RESPONSIBLE FOR VERIFYING DIMENSIONS IDENTIFIED AND NOT
IDENTIFIED IN THE CONTRACT DOCUMENTS WITH THE EXISTING AND NEW
CONSTRUCTION ELEMENTS. CONTRACTOR IS RESPONSIBLE FOR VERIFICATION
BETWEEN THE CONTRACT DOCUMENTS, INSTALLED AND UNINSTALLED
CONSTRUCTION BEFORE THE ORDERING OF MATERIALS AND EQUIPMENT. NOTIFY
ARCHITECT AND OWNER’S REPRESENTATIVE/COR OF ANY DISCREPANCIES OR
MISSING DIMENSIONS.
12. DO NOT SCALE THE DRAWINGS. DRAWING SCALES AS INDICATED ARE FOR GENERAL
ORIENTATION AND CONTEXT ONLY.
13. THE TERM "ALIGN" MEANS TO INSTALL DIFFERENT/SIMILAR COMPONENTS OF
CONSTRUCTION TO PROVIDE A FLUSH FINISH SURFACE.
14. ALL DIMENSIONS INDICATED ARE TO FACE OF EXISTING MEMBERS, FACE OF NEW
STRUCTURAL MEMBERS, FACE OF NEW MASONRY, FACE OF NEW STUDS OR COLUMN
GRID LINES UNLESS NOTED OTHERWISE.
15. FLOOR ELEVATION 100’-0” IS EQUAL TO THE FINISH FLOOR SLAB OF THE EXISTING
SLAB FLOOR CONSTRUCTION UNLESS OTHERWISE NOTED.
16. ROUGH OPENINGS SHALL ALLOW FOR SHIM SPACE.
17. CONTRACTOR TO PROVIDE WORK WHERE DETAILS AND NOTES ARE IDENTIFIED AS
“TYPICAL” OR “SIMILAR” EACH INSTANCE THAT IS THE SAME IN NATURE TO THE
DETAIL, AREA, OR ITEM REFERENCED.
18. PROVIDED WORK SHALL BE FURNISHED AND INSTALLED BY THE CONTRACTOR.
CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF DELIVERY, MOUNTING,
INSTALLATION, NECESSARY BLOCKING AND ROUGH-IN.
19. INSTALLED WORK IS THE CONTRACTOR INSTALLING OWNER FURNISHED MATERIALS
AND EQUIPMENT. CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF MATERIAL
DELIVERY, MOUNTING, INSTALLATION AND ROUGH IN.
20. FURNISHED WORK IS THE CONTRACTOR FURNISHING THE MATERIALS AND
EQUIPMENT TO THE OWNER. CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF
DELIVERY AND ROUGH-IN.
21. ALL PROVIDED WORK SHALL BE WITH NEW MATERIALS UNLESS SPECIFICALLY
CALLED OUT AS SALVAGED OR RELOCATED WITHIN THE CONTRACT DOCUMENTS.
22. ALL PERSONS DIRECTLY OR INDIRECTLY ASSOCIATED WITH THE PROJECT SHALL BE
FAMILIAR WITH THE RULES AND REGULATIONS OF THE OCCUPATIONAL SAFETY AND
HEALTH ACT, AND IMPLEMENT THOSE RULES AS THEY APPLY TO THIS PROJECT.
23. THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING AND PROTECTING ALL
UTILITY LINES. LOCATIONS SHOWN ARE APPROXIMATE. REPAIR ALL DAMAGE TO
UTILITY LINES CAUSED BY CONSTRUCTION OPERATIONS AT NO COST TO THE
OWNER.
24. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL TEMPORARY BRACING AND SHORING
REQUIRED DURING CONSTRUCTION.
25. CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING ADJACENT
CONSTRUCTION, FINISHES, EQUIPMENT, AND TRAVEL ROUTE TO AND FROM THE
CONSTRUCTION SITE. ANY DAMAGE OR UNACCEPTABLE WEAR BY THE
CONSTRUCTION TEAM SHALL BE REPAIRED/REPLACED BY THE CONTRACTOR AT NO
COST TO THE OWNER.
26. IN THE CASE OF CONFLICTS OR DISCREPANCIES WITHIN OR AMONG THE CONTRACT
DRAWINGS, THE BETTER QUALITY, MORE STRINGENT REQUIREMENTS OR GREATER
QUALITY OF WORK, AS DETERMINED BY THE COR, SHALL BE PROVIDED.
27. CONTRACTOR IS RESPONSIBLE FOR PROVIDING AND COORDINATING HARDWARE,
ACCESS CONTROL AND AUTOMATIC OPERATORS ARE PROVIDED WITH COMPLETE
AND COMPATIBLE SYSTEMS REQUIRED FOR THEIR OPERATION. REFER TO DOOR
HARDWARE SCHEDULE, HARDWARE SPECIFICATIONS, AUTOMATIC OPERATOR
SPECIFICATIONS, ACCESS CONTROL SPECIFICATIONS AND ELECTRICAL DRAWINGS.
X
X
XXXX
SHEET LOCATION
VIEW NUMBER
X X
X
SHEET LOCATION
VIEW NUMBER
XXXX
BUILDING SECTION REFERENCE
DRAWING NUMBER
SHEET LOCATION
BUILDING X
XXXX
X
XXXX
ELEVATION REFERENCES
NEW WALL
WALL TO BE
REMOVED
S3A.G
INDICATES STRUCTURAL MATERIAL
INDICATES NOMINAL SIZE
INDICATES STRUCTURE AND FINISH HEIGHTS
INDICATES QUALIFIER
EXISTING WALL TO
REMAIN
TEMPORARY IC
BARRIER WALL
CONSTRUCTION
ROOM
ROOM TAG
NEW DOOR
EXISTING DOOR
DEMOLISHED DOOR
REVISION TO PLAN CALLOUT
WALLS
DOOR TAG
KEY NOTE TAGS
WALL TAG : REFER TO WALL LEGEND FOR MORE INFORMATION
DOORS
PT-1
A
T
101 EQUIPMENT/FURNITURE TAG
FINISH INDICATION
FRAME / WINDOW
GLAZING1
1 PLAN NOTE
1 DEMOLITION NOTE
ALTERNATE/BID DEDUCT ITEM
KEY NOTE SYMBOLS
CONSTRUCTION GENERAL NOTESARCHITECTURAL SYMBOLS
REFLECTED CEILING PLAN SYMBOLS
A/C AIR CONDITION
A/E ARCHITECT/ENGINEER
AC ASBESTOS CEMENT OR ASPHALTIC CONCRETE
ACT ACOUSTICAL CEILING TILE
ADA AMERICANS WITH DISABILITIES ACT
ADMIN ADMINISTRATION
AFC ABOVE FINISHED COUNTER
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AFS ABOVE FINISHED SLAB
AHJ AUTHORITY HAVING JURISDICTION
AHU AIR HANDLING UNIT
AIA AMERICAN INSTITUTE OF ARCHITECTS
AISC AMERICAN INSTITUTE OF STEEL CONSTRUCTION
ALUM ALUMINUM
AMP AMPERE
ANOD ANODIZE
ANSI AMERICAN NATIONAL STANDARDS INSTITUTE
APPROX APPROXIMATE
ARCH ARCHITECT
ASI ARCHITECT'S SUPPLEMENTAL INSTRUCTION
AUTO AUTOMATIC
AUX AUXILIARY
AV AUDIO VISUAL
AWI ARCHITECTURAL WOODWORKING INSTITUTE
AWS AMERICAN WELDING SOCIETY
BLDG BUILDING
C CELSIUS CHANNEL OR CHANNEL CELSIUS
CF CONTRACTOR FURNISHED
CF/CI CONTRACTOR FURNISHED/CONTRACTOR INSTALLED
CF/OI CONTRACTOR FURNISHED/OWNER INSTALLED
CFS CUBIC FEET PER SECOND
CG CORNER GUARD
CJ CONSTRUCTION JOINT OR CONTROL JOINT
CL CENTER LINE
CLR CLEAR
CMU CONCRETE MASONRY UNIT
CO CARBON MONOXIDE, CLEANOUT
CO₂ CARBON DIOXIDE
COMM COMMUNICATION
COORD COORDINATE
CORR CORRIDOR
CT CERAMIC TILE
CTR CENTER
CU FT CUBIC FEET
CU IN CUBIC INCH
CU YD CUBIC YARD
DEMO DEMOLITION
DEPT DEPARTMENT
DIA DIAMETER
DIM DIMENSION
DN DOWN
DWG DRAWING
E EAST
EA EACH
EJ EXPANSION JOINT
ELEC ELECTRIC
ELEV ELEVATOR
EPA ENVIRONMENTAL PROTECTION AGENCY
EPDM ETHYLENE PROPYLENE DIENE MONOMER
EQ EQUAL
EQUIP EQUIPMENT
ETC AND SO FORTH OR ET CETERA
EXT EXTERIOR, EXTERNAL, OR EXTINGUISHER
F FAHRENHEIT OR FEMALE
FD FLOOR DRAIN
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FF EL FINISH FLOOR ELEVATION
FF&E FURNITURE, FIXTURE, AND EQUIPMENT
FLEX FLEXIBLE
FO FINISHED OPENING
FOC FACE OF CONCRETE OR FACE OF CURB
FOF FACE OF FINISH
FOM FACE OF MASONRY
FOS FACE OF SLAB OR FACE OF STUD
FP FIRE PROTECTION OR FIREPROOF
FPM FEET PER MINUTE
FPS FEET PER SECOND
FT FEET OR FOOT
GA GAGE OR GYPSUM ASSOCIATION
GC GENERAL CONTRACTOR
GD GUARD
GYP GYPSUM
HAZ MAT HAZARDOUS MATERIALS
HEPA HIGH EFFICIENCY PARTICULATE AIR (FILTER)
HM HECTOMETER OR HOLLOW METAL
HMD HOLLOW METAL DOOR
HMDF HOLLOW METAL DOOR AND FRAME
HMF HOLLOW METAL FRAME
HVAC HEATING, VENTILATING, AND AIR CONDITIONING
IBC INTERNATIONAL BUILDING CODE
ID IDENTIFICATION, INSIDE DIAMETER
ID NO IDENTIFICATION NUMBER
JAN JANITOR
LBS POUND
LED LIGHT EMITTING DIODE
LF LINEAR FEET (FOOT)
MACH MACHINE
MAX MAXIMUM
MECH MECHANICAL
MIN MINIMUM MINUTE OR MINUTE MINIMUM
MISC MISCELLANEOUS
mm MILLIMETER
MO MASONRY OPENING OR MOTOR OPERATED
MR MOISTURE RESISTANT
N NORTH
NA NOT APPLICABLE
NNIC NOT IN CONTRACT
O OXYGEN
OA OUTSIDE AIR OR OVERALL
OC ON CENTER
OF/CI OWNER FURNISHED/CONTRACTOR INSTALLED
OFD OVERFLOW DRAIN
OFF OFFICE
OF/OI OWNER FURNISHED/OWNER INSTALLED
OZ OUNCE
PREFAB PREFABRICATE
PREFIN PREFINISH
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
QA QUALITY ASSURANCE
QC QUALITY CONTROL
QTY QUANTITY
RA RETURN AIR
REV REVISION
RFI REQUEST FOR INFORMATION
RO ROUGH OPENING
SA SUPPLY AIR
SF SQUARE FOOT (FEET)
SIM SIMILAR
S SOUTH
SQ SQUARE
STC SOUND TRANSMISSION CLASS
ARCHITECTURAL ABBREVIATIONS
TA TOILET ACCESSORY
TEMP TEMPERATURE OR TEMPORARY
THRU THROUGH
TO TOP OF ___
TOB TOP OF BEAM
TOM TOP OF MASONRY
TOW TOP OF WALL
TV TELEVISION
TYP TYPICAL
UL UNDERWRITERS LABORATORIES
UPS UNINTERRUPTIBLE POWER SUPPLY
UV ULTRAVIOLET
VAR VARIES
VIF VERIFY IN FIELD
VOC VOLATILE ORGANIC COMPOUND
W/ WITH
W/O WITHOUT
WD WOOD
EXIT SIGN
HVAC SUPPLY DIFFUSER
1' x 4' RECESSED LINEAR FIXTURE
HVAC EXHAUST DIFFUSER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
A u to d e s k D o c s /1
.5
.2
R e n o v a te
-1 R f o r
S u p p ly C h a in M a n a g e m e n t S e rv ic e
/1
.5
.2
A v
.r v t
/1
/2
:0
:0
P
M
AE001
ARCHITECTURAL SYMBOLS AND
ABBREVIATIONSGUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
RENOVATE 58-1 R102 FOR
SUPPLY CHAIN MANAGEMENT
SERVICE
DANVILLE, IL
550-23-108
58-R102
04/30/2025 BS DMC
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
A. ALL WALLS WILL BE WALL TYPE S3A.Gi UNLESS OTHERWISE NOTED.
B. ALL WALL TYPE INDICATORS REFER TO THIS SHEET UNLESS OTHERWISE
NOTED.
C. REFER TO DIMENSION PLANS FOR PARTITION TYPE LOCATIONS.
PARTITIONS ARE DISTINGUISHED ON PLANS BY SYMBOL DESIGNATION
GRAPHIC DESIGNATION, OR A COMBINATION OF BOTH. NOT ALL
PARTITIONS ON THIS SHEET MAY BE USED. REFER TO PARTITION TYPE
SCHEDULE ON THIS SHEET FOR PARTITIONS USED ON THIS PROJECT.
D. ALL DIMENSIONS ARE FROM FACE OF STUD TO FACE OF STUD, OR TO FACE
OF BLOCK. REFER TO PARTITION S3A.G FOR PARTITION WIDTH
DIMENSIONS.
E. ALL WALLS STUDS TO BE 16" O.C. UNLESS OTHERWISE NOTED.
F. REFER TO SPECIFICATIONS AND TO TABLE ON THIS SHEET FOR MINIMUM
STUD GAUGE, MAXIMUM SPACING AND ALLOWABLE LIMITING HEIGHT
DEFLECTION CRITERIA FOR GYPSUM BOARD ASSEMBLIES AND REQUIRED
FINISHES. FOR WALLS WHERE STUDS ARE ATTACHED TO STRUCTURE
ABOVE, PROVIDE CROSS BRACING AS NECESSARY MEETING THE CRITERIA
INDICATED TO ACCOMMODATE THE SPECIFIED DEFLECTION CRITERIA OF
THE WALL.
G. ALL INTERIOR NON-BEARING STUDS TO BE DESIGNED FOR A DEFLECTION
EQUAL TO BUT NOT GREATER THAN L/240, UNLESS FULL HEIGHT FINISH IS
DETERMINED TO BE FRAGILE OR BRITTLE, THEN DEFLECTION TO BE L/360.
EXAMPLES OF FRAGILE FINISHES WOULD INCLUDE BUT NOT LIMITED TO
ANY TYPE OF WALL TILE, PLASTER OR PLASTER SKIM COAT.
H. ALTHOUGH WALL STUD SIZES ARE LISTED ON PLANS AND WALL TYPE S3A.G
IN AREAS WHERE STUDS ARE TO STRUCTURE ABOVE OR HIGH AREAS,
CONTRACTOR TO VERIFY SIZED INDICATED IS ADEQUATE FOR HEIGHT
LISTED. PROVIDE ADEQUATE SIZE STEEL STUD FRAMING AND NOTIFY
ARCHITECT OF ANY DISCREPANCY PRIOR TO FABRICATION OR
INSTALLATION.
I. KING STUDS AT DOOR FRAMES TO BE 18 GA. UNLESS OTHERWISE NOTED.
J. PROVIDE 5/8" TYPE "X" GYPSUM WALLBOARD FOR ALL OTHER WALL
CONSTRUCTION, UNLESS OTHERWISE NOTED.
K. PROVIDE 5/8" TYPE "X" GYPSUM WALLBOARD IN BULKHEAD CONSTRUCTION.
L. REFER TO LIFE SAFETY PLANS FOR LOCATIONS AND RATINGS OF SMOKE
AND FIRE RATED PARTITIONS. REFERENCE TEST NUMBERS APPLY ONLY TO
PARTITIONS INDICATED TO BE RATED.
M. FIRE RATING TEST NUMBERS ARE FOR UNDERWRITER'S LABORATORIES
(UL) ASSEMBLIES UNLESS OTHERWISE NOTED.
N. FIRE RESISTANT RATED PARTITIONS SHALL EXTEND TO THE INSIDE FACE
OF EXTERIOR SHEATHING, INCLUDING EXTENSIONS THROUGH SOFFITS.
O. SEAL ALL OPENINGS, GAPS, PENETRATIONS, AND JOINTS IN PARTITIONS
TYPES AS FOLLOWS:
a. FIRE RATED PARTITIONS: SEAL IN ACCORDANCE WITH THE
REQUIREMENTS SPECIFIED FOR THROUGH PENETRATION
FIRESTOP SYSTEMS AND FIRE RESISTIVE JOINT SYSTEMS.
b. SMOKE TIGHT PARTITIONS: SEAL COMPLETELY WITH
ELASTOMERIC SEALANT. FOR THE LOCATION AND EXTENT OF
PARTITIONS, DESIGNATED AS "SMOKE TIGHT", REFER TO THE LIFE
SAFETY DRAWINGS.
c. ALL OTHER LOCATIONS: SEAL AS INDICATED AND REQUIRED
ELSEWHERE BY THE CONTRACT DOCUMENTS.
P. INSULATION HEAD CONDITIONS AT FLOOR / ROOF DECK:
a. FIRE RESISTANT RATED PARTITIONS SHALL USE MINERAL WOOL
INSULATION AND APPROPRIATE FIRE RATED SEALANT.
b. NON-RATED PARTITIONS REQUIRING SOUND ATTENUATION SHALL
USE SOUND ATTENUATION BATTS (SAB).
Q. PROVIDE STENCILED IDENTIFICATION FOR RATED PARTITIONS.
R. STC RATING APPLIES WHERE PARTITION TAG QUALIFIER INDICATES WITH
AN "i". PROVIDE SOUND ATTENUATION BATTS OF THICKNESS INDICATED ON
SCHEDULE WHERE INDICATED BY QUALIFIER.
S. FOR PARTITIONS WITH STC RATINGS INDICATED SOUND ATTENUATION
BATTS TO EXTEND FULL HEIGHT OF PARTITION UNLESS OTHERWISE
NOTED. FLOOR TRACK TO BE SET IN A CONTINUOUS BED OF SEALANT.
T. WHERE PARTITION TYPE INDICATES SOUND ACOUSTICAL BATT, WITH FINISH
BOARD GOING TO DECK ON ONE SIDE ONLY, PROVIDE VAPOR BARRIER TO
SECURE INSULATION IN PLACE.
U. REFER TO DIMENSIONED PLANS FOR REFERENCE SYMBOLS INDICATING
THE EXTENT OF RADIATION PROTECTION.
V. PROVIDE 5/8" MOISTURE/MOLD RESISTANT GYPSUM BOARD IN SOILED
ROOMS, BATHROOMS, TOILET ROOMS, ON WALLS BEHIND PLUMBING
FIXTURES, AND IN ALL WET LOCATIONS EXCEPT IN SHOWER AREA.
W. PROVIDE CORNER AND END WALL FRAMING AS DETAILED ON 3/AE002.
WALL TYPES LEGEND AND GENERAL NOTES
X#X.#
INDICATES STRUCTURAL MATERIAL
CH = SHAFT WALL
F = FURRING
S = STEEL
M = MASONRY
W = WOOD
INDICATES NOMINAL SIZE
INDICATES STRUCTURE AND
FINISH HEIGHTS
QUALIFIER'S (X-X-X)
G GYPSUM BOARD FINISH
1SB 1 HR RATED SMOKE BARRIER
2SB 2 HR RATED SMOKE BARRIER
1F 1 HR FIRE RATED
2F 2 HR FIRE RATED
i SOUND INSULATION t THERMAL INSULATION
B BULLET RESISTANT
L LEAD LINED
M MESH (STEEL SECURITY MESH)
MR MOIST/MOLD RESISTANT GYPSUM
SP SMOKE PARTITION
TB TILE BACKER CEMENT BOARD
A = STRUCTURE TO DECK, FINISH TO DECK
B = STRUCTURE TO DECK, FINISH ONE SIDE TO DECK
C = STRUCTURE TO DECK, FINISH TO ABOVE CEILING
D = STRUCTURE TO ABOVE CEILING, FINISH TO ABOVE CEILING
P = PARTIAL HEIGHT WALL
U = STRUCTURE TO UNDERSIDE OF CEILING, FINISH TO UNDERSIDE OF CEILING
*SEE WALL TYPES FOR PROJECT SPECIFIC CONSTRUCTION
CH
2 1/2" 4" 6"
F 7/8
1 1/2" 2 1/2" 3 5/8"
4" 6" 8" 12"
S
2 1/2" 3 5/8"
4" 6" 8" 12"
M
2 5/8" 3 5/8" 5 5/8" 7 5/8" 11 5/8"
W
3/4"
3 1/2"
5 1/2" 7 1/4" 11 1/4"
" 1 HR FIRE/SMOKE
10'-0" MAX 10'-0" MAX
A. LETTERED STENCILS SHALL BE APPLIED TO EACH SIDE OF RATED PARTITIONS
AT 10'-0" INTERVALS; BUT NO LESS THAN ONCE PER PARTITION LENGTH.
B. USE THE FOLLOWING LANGUAGE FOR STENCILS:
"1 HR FIRE/SMOKE" "1 HR FIRE"
"2 HR FIRE/SMOKE" "2 HR FIRE"
"LIMIT TRANSFER OF SMOKE"
PERMANENT RED PAINT
LETTERING, TYP.
CEILING LINE
STENCILING NOTES
WALL TAG LEGEND
WALL TAG
STRUCTURAL
SIZE
FINISH DIM FIRE RATING UL DESIGN
MIN STC
RATING
COMMENTS
LINE OF STRUCTURE ABOVE
LINE OF CEILING
LINE OF STRUCTURE BELOW
PLAN
STRUCTURAL DIMENSION
5/8"
FINISH DIMENSION
STEEL STUD BRACING @ 4'-0" O.C.
CEILING
6"
5/8" TYPE X GYP BD
BEAD OF CONT. SEALANT
STEEL STUDS @ 16" O.C.
INSULATION PRESENT WITH QUALIFIER (i OR t)
EXISTING WALL / COLUMN, VIF.
F0D.G 7/8" 1 1/2" NA NA NA HAT CHANNEL @ 24" O.C.
WALL TYPES
WALL TAG
STRUCTURAL
SIZE
FINISH DIM FIRE RATING UL DESIGN
MIN STC
RATING
COMMENTS
LINE OF STRUCTURE ABOVE
LINE OF CEILING
LINE OF STRUCTURE BELOW
PLAN
5/8"
STRUCTURAL SIZE
5/8"
FINISH DIMENSION
5/8" TYPE X GYP BD
BEAD OF CONT. SEALANT
STEEL STUDS @ 16" O.C.
STEEL STUD BRACING @ 4'-0" O.C.
CEILING
DEEP LEG SLIP TRACK AT DECK
HOLD GYPSUM BACK FROM DECK FOR
DEFLECTION
INSULATION PRESENT WITH QUALIFIER (i OR t)
F3D.G 3 5/8" 4 1/4" NANANANA
S3A.Gi 3 5/8" 4 7/8" NA46NANA
WALL TAG
STRUCTURAL
SIZE
FINISH DIM FIRE RATING UL DESIGN
MIN STC
RATING
COMMENTS
S3A.1F 3 5/8" 4 7/8" NA40U4651 HR.
LINE OF STRUCTURE ABOVE
LINE OF CEILING
LINE OF STRUCTURE BELOW
PLAN
5/8"
STRUCTURAL SIZE
5/8"
FINISH DIMENSION
5/8" TYPE X GYP BD
BEAD OF CONT. SEALANT
STEEL STUDS @ 16" O.C.
STEEL STUD BRACING @ 4'-0" O.C.
CEILING
DEEP LEG SLIP TRACK AT DECK
HOLD GYPSUM BACK FROM DECK FOR
DEFLECTION
FILL FLUTES OF DECK WITH FIRE SAFING
AT FIRE RATED WALLS
INSULATION PRESENT WITH QUALIFIER (i OR t)
NOTE:
• TYPICAL LIMITING HEIGHTS-INTERIOR PARTITIONS, L/240 (5 PSF), WITH 5/8"GYPSUM BOARD EACH SIDE.
• PROVIDE DIAGONAL STUD BRACING AT ALL NON FULL HEIGHT INTERIOR PARTITIONS STAGGERED AT 48" O.C. TO DECK ABOVE. PROVIDE
STUD ATTACHMENT TO DECK W/ MIN. SPAN OF 2 DECK FLUTES. BRACING TO BE THE SAME SIZE AND GAUGE AS VERTICAL STUDS.
25 GA. STUDS (NON-COMPOSITE)
STUD WIDTH STUD SPACING ALLOW. DEFLECTION HEIGHT
16" L/240 6'-11"1-5/8"
24" L/240 6'-0"162S125-18
16" L/240 9'-6"2-1/2"
24" L/240 8'-4"250S125-18
16" L/240 12'-5"3-5/8"
24" L/240 10'-10"362S125-18
16" L/240 13'-9"4"
24" L/240 12'-0"400S125-18
22 GA. STUDS (NON-COMPOSITE)
STUD WIDTH STUD SPACING ALLOW. DEFLECTION HEIGHT
16" L/240 8'-1"1-5/8"
24" L/240 7'-1"162S125-27
16" L/240 11'-2"2-1/2"
24" L/240 9'-9"250S125-27
16" L/240 14'-6"3-5/8"
24" L/240 12'-8"362S125-27
16" L/240 16'-1"4"
24" L/240 14'-0"400S125-27
20 GA. STUDS (NON-COMPOSITE)
STUD WIDTH STUD SPACING ALLOW. DEFLECTION HEIGHT
16" L/240 8'-4"1-5/8"
24" L/240 7'-3"162S125-30
16" L/240 11'-7"2-1/2"
24" L/240 10'-1"250S125-30
16" L/240 15'-0"3-5/8"
24" L/240 13'-1"362S125-30
16" L/240 16'-8"4"
24" L/240 14'-7"400S125-30
16" L/240 22'-4"6"
24" L/240 19'-6"600S125-27
16" L/240 23'-1"6"
24" L/240 20'-2"600S125-30
18 GA. STUDS (NON-COMPOSITE)
STUD WIDTH STUD SPACING ALLOW. DEFLECTION HEIGHT
16" L/240 13'-0"2-1/2"
24" L/240 11'-5"250S125-43
16" L/240 17'-5"3-5/8"
24" L/240 15'-3"362S125-43
16" L/240 18'-10"4"
24" L/240 16'-5"400S125-43
16" L/240 26'-1"6"
24" L/240 22'-10"600S125-43
SSMA NON-COMPOSITE STUDS
HIGH PRIORITY PARTITION
LOWER PRIORITY PARTITION
HIGH PRIORITY CEILING /
ROOF ASSEMBLY
LOWER PRIORITY PARTITION
RATING
3 HOUR ASSEMBLY
2 HOUR ASSEMBLY
1 HOUR ASSEMBLY
SMOKE-RATED ASSEMBLY
NON-RATED ASSEMBLY
PRIORITY
NOTE: LOWER NUMBER, HIGHER PRIORITY
TOP OF METAL DECK OR CONCRETE
FIRE CAULKING AS REQUIRED BY UL# HWS0001
(BY FRAMING CONTRACTOR)
PACK FLUTES OF DECK WITH FIRE SAFING AS
REQUIRED PER UL# HWS0001
Z-CLIPS 2" WIDTH
BOTTOM OF METAL DECK
LIGHT GAUGE FRAMING DEFLECTION TRAK,
CONFORMING TO UL# HW-D-0060
5/8" TYPE X GYP. BD. EACH SIDE OF STUD
SCRIBED TO DECK UL# U465
METAL STUD
PARALLEL NOTE:
NON-RATED CONSTRUCTION SIMILAR W/O
FIRE SAFING & SCRIBING BYP. BD. TO DECK
6"
TOP OF METAL DECK OR CONCRETE
FIRE CAULKING AS REQUIRED BY UL# HWS0001
(BY FRAMING CONTRACTOR)
PACK FLUTES OF DECK WITH FIRE SAFING AS
REQUIRED PER UL# HWS0001
Z-CLIPS 2" WIDTH
BOTTOM OF METAL DECK
LIGHT GAUGE FRAMING DEFLECTION TRAK,
CONFORMING TO UL# HW-D-0060
5/8" TYPE X GYP. BD. EACH SIDE OF STUD
SCRIBED TO DECK UL# U465
METAL STUD
PERPENDICULAR NOTE:
NON-RATED CONSTRUCTION SIMILAR W/O
FIRE SAFING & SCRIBING BYP. BD. TO DECK
INSULATION STUFFED INSIDE BOX
METAL STUD FRAMING
CORNER BEAD AT ALL
OUTSIDE CORNERS (TYPICAL)
20 GA. METAL STUDS WRAPPED WITH
20 GA. TRACK ON BOTH SIDES,
CONTINUOUS FROM FLOOR TO DECK
INSULATION STUFFED INSIDE BOX
METAL STUD FRAMING
CORNER BEAD AT ALL
OUTSIDE CORNERS (TYPICAL)
20 GA. METAL STUDS WRAPPED WITH
20 GA. TRACK ON BOTH SIDES,
CONTINUOUS FROM FLOOR TO DECK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
A u to d e s k D o c s /1
.5
.2
R e n o v a te
-1 R f o r
S u p p ly C h a in M a n a g e m e n t S e rv ic e
/1
.5
.2
A v
.r v t
/1
/2
:0
:0
P
M
AE002
WALL TYPES
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
RENOVATE 58-1 R102 FOR
SUPPLY CHAIN MANAGEMENT
SERVICE
DANVILLE, IL
550-23-108
58-R102
04/30/2025 BS DMC
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1 1/2" = 1'-0"AE002
1 RATED WALL PRIORITY
SCALE: 1 1/2" = 1'-0"AE002
2 DEFLECTION TRACK
WALL TYPE SCHEDULE
WALL TYPES USED IN THIS PROJECT
F0D.G
F3D.G
S3A.1F
S3A.Gi
SCALE: 3" = 1'-0"AE002
3 TYPICAL CORNER FRAMING DETAIL
A. COORDINATE DEMOLITION WITH NEW CONSTRUCTION. ALL DEMOLITION AND
REPAIR NECESSARY TO COMPLETE NEW AND REMODEL CONSTRUCTION
SHALL BE PROVIDED. CONTRACTOR SHALL REMOVE EXISTING
IMPROVEMENTS WHETHER OR NOT SPECIFICALLY INDICATED ON THE
DRAWINGS TO FACILITATE THE COMPLETION OF ALL REQUIRED WORK.
CONTRACTOR SHALL VISIT THE SITE AND VERIFY ALL QUANTITIES AND
ITEMS REQUIRED TO BE REMOVED.
B. REFER TO ARCHITECTURAL SYMBOLS ON SHEET AE001 FOR DEMOLITION
SYSTEMS AND DRAWING NOMENCLATURE.
C. EXISTING STRUCTURE WITHIN THE PROJECT BOUNDARY SHALL REMAIN
UNLESS OTHERWISE NOTED.
D. SURFACES TO BE CUT AND CONDITIONS UNDER WHICH CUTTING IS TO BE
PERFORMED SHALL BE REVIEWED BY CONTRACTOR PRIOR TO CUTTING TO
VERIFY NO UNSAFE OR UNSATISFACTORY CONDITIONS EXIST. SUCH
CONDITIONS SHALL BE RECTIFIED BEFORE WORK MAY PROCEED.
E. EXTENTS OF DEMOLITION SHALL BE COORDINATED WITH THE FIRST FLOOR
ARCHITECTURAL PLAN AE101 AND ENGINEERING DRAWINGS FOR
ADDITIONAL INFORMATION.
F. DIMENSIONS SHOWN FOR EXISTING CONSTRUCTION TO BE DEMOLISHED
ARE APPROXIMATE AND ARE INTENDED TO GIVE A GENERAL SCOPE OF
WORK TO BE REMOVED OR TEMPORARILY REMOVED TO ACCOMMODATE
NEW CONSTRUCTION. COORDINATE DEMOLITION WORK WITH DESIGN
INTENT OF NEW CONSTRUCTION TO PROVIDE ADEQUATE AREA FOR THIS
WORK.
G. CONTRACTORS SHALL REMOVE INDICATED DEMOLITION OF CONSTRUCTION
ASSEMBLIES IN THEIR ENTIRETY, UNLESS OTHERWISE NOTED, TO
ACCOMMODATE NEW CONSTRUCTION.
H. REMOVE ALL CASEWORK ATTACHED TO OR ADJACENT TO DEMOLITION
WALLS.
I. MAKE ALL DEMOLITION CLEAN AND COMPLETE IN A MANNER TO RECEIVE
NEW FINISHES. DEMOLITION SHOULD BE PERFORMED IN A MANNER SUCH
THAT THE CONTRACTOR CAN SEAMLESSLY PATCH NEW WORK TO BE
SMOOTH AND UNDETECTABLE.
J. ABOVE CEILING WORK WHERE CEILINGS ARE TO REMAIN, CEILING TILES
SHALL BE REMOVED AND STORED IN A SAFE MANNER UNTIL CEILING TILES
CAN BE REINSTALLED. DAMAGED AND BROKEN CEILING TILES SHALL BE
REPLACED BY CONTRACTOR. GYPSUM BOARD CEILINGS SHALL BE PATCHED
AND PAINTED TO SEAMLESSLY MATCH EXISTING CEILING COLOR
FOLLOWING ABOVE CEILING DEMOLITION ACTIVITY. THIS SHALL INCLUDE
REPAIR TO THE CEILING GRID, SUSPENSION SYSTEM AND ALL ASSOCIATED
ASSEMBLIES AS WELL AS THE REPLACEMENT OF DAMAGED CEILING
PANELS, WITHIN AND BEYOND PROJECT LIMITS.
K. COORDINATE FULL SCOPE OF DEMOLITION WORK WITH ENGINEERING AND
VENDOR DRAWINGS.
L. WHERE EXISTING FLOOR FINISH IS REMOVED, FLOORING AND ADHESIVE
SHALL BE REMOVED TO PROVIDE A CLEAN FLOOR SLAB. FLOOR SLAB SHALL
BE FILLED/ LEVELED TO PROVIDE A LEVEL FINISH PER NEW FLOORING
MANUFACTURERS RECOMMENDATIONS. REFER TO SPECIFICATION 09 05 16.
M. FLOORING AND WALL BASE SHALL BE REMOVED THROUGHOUT PROJECT
BOUNDARY UNLESS OTHERWISE INDICATED.
N. REMOVE ALL WALL MOUNTED ACCESSORIES AND MOUNTING HARDWARE
THROUGHOUT PROJECT BOUNDARY UNLESS OTHERWISE NOTED.
O. REMOVE ALL PLUMBING FIXTURES AND ASSOCIATED ACCESSORIES
THROUGHOUT PROJECT BOUNDARY UNLESS OTHERWISE NOTED. REFER TO
PLUMBING PLAN FOR ADDITIONAL INFORMATION.
P. REMOVE ALL REMAINING CERAMIC WALL TILE THROUGHOUT PROJECT
BOUNDARY UNLESS NOTED OTHERWISE. PREPARE AREA FOR NEW FINISH
PER MANUFACTURER'S RECOMMENDATIONS.
Q. PATCH/REPAIR AND PRE ALL EXISTING PALSTER FINISHED WALLS FOR NEW
PAINT THROUGHOUT PROJECT BOUNDARY UNLESS NOTED OTHERWISE.
R. REMOVE ALL FLOOR AND WALL MOUNTED CASEWORK AND BUILT-IN
SHELVING THROUGHOUT PROJECT BOUNDARY UNLESS NOTED OTHERWISE.
S. VA TO REMOVE ALL EXISTING EQUIPMENT AND FURNITURE FROM PROJECT
BOUNDARY PRIOR TO START OF CONSTRUCTION.
DEMOLITION GENERAL NOTES
1. REMOVE PORTION OF EXISTING MASONRY WALL INDICATED - FLOOR TO
DECK.
2. REMOVE EXISTING EXTERIOR DOOR, SIDELIGHT, TRANSOM, FRAME AND
HARDWARE IN ITS ENTIRETY.
3. REMOVE ACOUSTIC PANEL CEILING ASSEMBLY IN ITS ENTIRETY. REMOVE
EXISTING CEILING MOUNTED FIXTURES AND EQUIPMENT.
4. REMOVE PLUMBING FIXTURES, GRABRAILS, ACCESSORIES, ETC. -REFER TO
PLUMBING PLANS FOR FURTHER INFORMATION.
5. REMOVE EXISTING VCT FLOORING, BASE AND FLOOR OVERBUILDS.
PREPARE/INFILL AND LEVEL FLUSH TO EXISTING TO RECEIVE NEW FLOOR
FINISH.
6. REMOVE SLIDING DOOR ASSEMBLY IN ITS ENTIRETY.
7. REMOVE EXISTING PORCELAIN TILE FLOORING, WALL TILE, AND MORTAR
BED. PREPARE/INFILL AND LEVEL FLOOR FLUSH TO EXISTING SUBFLOOR TO
RECEIVE NEW FLOOR FINISH.
8. REMOVE EXISTING WOOD WINDOW SILLS IF APPLICABLE. PREP FOR NEW
SOLID SURFACE SILL - REFER TO SHEET AI101.
9. REMOVE EXISTING EXTINGUISHER AND MOUNT. SALVAGE FOR
REINSTALLATION.
10. EXTENT OF WORK IN THIS SPACE TO BE ONLY THE FOLLOWING: REMOVE
WALL BASE, PATCH/REPAIR PLASTER WALLS AND PREP FOR NEW PAINT.
ACT CEILING ASSEMBLES TO BE REMOVED ENTIRELY. EXISTING
PLASTER/GYP CEILINGS TO REMAIN - PATCH/REPAIR AND PREP FOR NEW
PAINT.
11. PLUMBING FIXTURE TO REMAIN EXISTING.
12. REMOVE DISPENSING WINDOW. REMOVE EXISTING SERVICE BELL -
SALVAGE FOR REINSTALLATION IN NEW LOCATION. COORDINATE w/
ARCHITECTURAL PLAN.
13. FIRE EXTINGUISHER TO REMAIN EXISTING.
14. NO WORK TO OCCUR IN STAIRWELL.
15. REMOVE EXISTING DOOR, FRAME, AND HARDWARE IN ITS ENTIRETY. WHERE
DOORS ARE TO BE REMOVED AND OPENINGS TO BE INFILLED, REMOVE
MASONRY WALL CONSTRUCTION DOOR TO DECK - COORDINATE w/
ARCHITECTURAL PLAN.
16. REMOVE EXISTING VAULT DOOR, FRAME, HARDWARE, AND ASSOCIATED
ACCESS CONTROLS IN ITS ENTIRETY. DOOR TO BE HANDED OVER TO
OWNER.
17. SAWCUT CONCRETE FLOOR SLAB TO INSTALL NEW PLUMBING -
APPROXIMATELY 2'-0" WIDE. COORDINATE WITH PLUMBING DRAWINGS.
18. REMOVE STOREFRONT WALL ASSEMBLY IN ITS ENTIRETY.
19. REMOVE DRINKING FOUNTAIN.
20. AHU UNIT TO BE BROUGHT IN THROUGH EXISTING WINDOW. WINDOW TO BE
REMOVED AND REINSTALLED AS NEEDED. COORDINATE WITH CONTRACTOR
AND/OR OWNER.
21. REMOVE PORTION OF EXISTING MASONRY WALL INDICATED FOR NEW
OPENING.
22. REMOVE MASONRY INFILLED PORTION OF EXISTING EXTERIOR WALL FOR
NEW MECHANICAL, LOUVERS. REFER TO MECHANICAL DRAWINGS FOR
MORE INFORMATION.
23. REMOVE EXISTING EXHAUST FAN. REFER TO MECHANICAL DRAWINGS FOR
FURTHER INFORMATION.
#DEMOLITION PLAN NOTES
PROJECT
LOCATION
SHADE INDICATES
AREA OUT OF
PROJECT SCOPE
BLDG 58 KEYPLAN
N
R S T U V
13' - 0"
13' - 0"
1'
102G
STORAGE
102H
STORAGE
102O
STORAGE
102J
STORAGE
102K
ELECTRICAL
102I
HVAC
STAIR
C1-9
CORRIDOR
102F
LOUNGE
102D
LAB
102G-1
INPATIENT PHARMACY
102B
INPATIENT PHARMACY 102C
INPATIENT PHARMACY
102A
INPATIENT PHARMACY
102L
STORAGE
102M
STORAGE
102N
TLT
103A
CHIEF OFFICE
OFFICE
103B
VAULT
ELEVATOR
3'
4' - 10"
3 5
102G-2
INPATIENT PHARMACY
102M
STORAGE
10 1010
3 5
3 5
3 5
3 5
15 1
1'
/4
11' - 0"
V.I.F.
15' - 6"
V .I.
F
7' - 5 3/4"
22 2220
UP 23
DEMOLITION PLAN SYMBOLS
WALL TO BE REMOVED
DOOR TO BE REMOVED
DEMOLITION SYMBOLS LEGEND
NO DEMOLITION/ARCHITECTURAL WORK TO TAKE
PLACE IN THIS AREA.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
A u to d e s k D o c s /1
.5
.2
R e n o v a te
-1 R f o r
S u p p ly C h a in M a n a g e m e n t S e rv ic e
/1
.5
.2
A v
.r v t
/1
/2
:0
:0
P
M
AD101
FIRST FLOOR DEMOLITION PLAN
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
RENOVATE 58-1 R102 FOR
SUPPLY CHAIN MANAGEMENT
SERVICE
DANVILLE, IL
550-23-108
58-R102
04/30/2025 BS JL
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1/8" = 1'-0"AD101
1 FIRST FLOOR DEMOLITION PLAN
UP
A. ALL DIMENSIONS SHOWN ARE TO FACE OF WALL FRAMING/ MASONRY
UNLESS NOTED OTHERWISE. DIMENSIONS DESIGNATES AS "CLR" OR
"CLEAR" INDICATE A CLEAR DIMENSION FROM FACE OF FINISH TO FACE OF
FINISH.
B. VERIFY EXISTING FIELD CONDITIONS PRIOR TO BEGINNING WORK, AND
REPORT DISCREPANCIES IMMEDIATELY TO ARCHITECT FOR CLARIFICATION.
C. CONTRACTOR TO MAINTAIN/REPAIR RATING OF EXISTING PARTITIONS AS
AFFECTED BY DEMOLITION/NEW CONSTRUCTION, TYPICAL THROUGHOUT.
D. PROVIDE CONTROL JOINT ON CONTINUOUS GYPSUM BOARD WALLS
GREATER THAN 30' LONG.
E. PROVIDE CONTROL JOINTS AT CORNERS OF DOORS OR WINDOWS.
F. WHERE NO DIMENSION IS INDICATED, FINISH DOORS 6" FROM EDGE OF
STUD FRAMING AT CORNERS UNLESS OTHERWISE NOTED.
G. ALL NEW PARTITIONS ARE WALL TYPE S3A.Gi UNLESS NOTED OTHERWISE.
REFER TO WALL TYPE GENERAL NOTES AE002 FOR WALL BOARD MATERIAL.
H. NON-RATED WALL CONSTRUCTION THAT FORMS CHASE AREAS DOES NOT
REQUIRE GYPSUM BOARD INSTALLATION ON INTERIOR OF CHASE WALL.
REFER TO WALL TYPE F3D.Gi .
I. COLUMN DIMENSIONS ARE FOR REFERENCE AND SHALL BE VERIFIED IN THE
FIELD.
J. REFER TO ENLARGED FLOOR PLANS FOR ADDITIONAL DIMENSIONS FOR
TOILET AND BATH ROOMS.
K. DIMENSIONS INDICATED AS 'VIF' MAY INCREASE OR DECREASE TO MATCH
FIELD CONDITIONS. ALL OTHER DIMENSIONS WITHIN THE DIMENSION STRING
MUST BE MAINTAINED.
L. PROVIDE BLOCKING AND STRAPPING FOR WALL MOUNTED CASEWORK,
FURNITURE, AND ACCESSORIES. COORDINATE WITH FLOOR PLANS,
SCHEDULES, ELEVATIONS, AND ENGINEERING DRAWINGS FOR FULL SCOPE
OF WORK.
M. REFERENCE MECHANICAL, PLUMBING, FIRE PROTECTION AND ELECTRICAL
FOR COORDINATION ITEMS. COORDINATE AS REQUIRED INCLUDING
NECESSARY FRAMING, BLOCKING, ETC.
N. VERIFY EXISTING FIELD CONDITIONS PRIOR TO BEGINNING WORK, AND
REPORT DISCREPANCIES IMMEDIATELY TO ARCHITECT FOR CLARIFICATION.
O. PATCH EXISTING WALLS WHERE NEW WALLS MEET.
P. PROVIDE MINIMUM CLEARANCES AT ALL DOORS PER ADA REQUIREMENTS.
Q. REFER TO SHEET QH101 FOR EQUIPMENT SCHEDULE AND INFORMATION.
R. REFER TO SHEET AI201 FOR ACCESSORIES TO BE PROVIDED IN THE
TOILET/BATH ROOMS AND AT THE HAND LAVATORIES.
S. LEVEL AND INFILL FLOOR SLAB TO RECEIVE NEW FLOORING. REFER TO
SPECIFICATIONS AND FLOORING MANUFACTURE TOLERANCES FOR
ADDITIONAL INFORMATION.
ARCHITECTURAL GENERAL NOTES
ARCHITECTURAL PLAN NOTES
1. EXISTING FIRE EXTINGUISHER TO REMAIN.
2. EXISTING DOCK TO REMAIN.
3. INFILL WALL - ALIGN SURFACES TO RESULT IN A FLUSH FINISHED
CONDITION. REFER TO DETAIL 1/AE101.
4. ALIGN WALL FINISH FLUSH TO EXISTING.
5. REINSTALL SALVAGED FIRE EXTINGUISHER.
6. INFILL WALL FLOOR TO DECK - ALIGN SURFACES TO RESULT IN A FLUSH
FINISH. INSTALL WALL PROTECTION, ARCHITECTURAL BASE, AND WOOD
CRASHRAIL TO MATCH EXISTING.
7. INFILL EXTERIOR WALL WITH LIKE CONSTRUCTION TO MATCH EXISTING
WHERE EXHAUST FAN IS REMOVED. REFER TO MECHANICAL DRAWINGS FOR
MORE INFORMATION.
8. 4" HIGH CONCRETE HOUSEKEEPING PAD - REFER TO MECHANICAL
DRAWINGS FOR EXACT SIZE AND LOCATION.
9. INSTALL NEW 42"x60" ALUMINUM FRAME STATIONARY VIEWING WINDOW
TEMPERED CLEAR GLAZING. INSTALL BOTTOM OF WINDOW AT 3'-6" A.F.F.
10. CONTRACTOR TO VERIFY IF EXISTING MASONRY WALL CONSTRUCTION
MEETS 1HR FIRE RATING. IF NOT MET, CONTRACTOR TO UPGRADE AND
SEAL ALL PENETRATIONS TO MEET RATING.
11. INSTALL NEW FIRE RATED DOOR. MATCH EXISTING SIZE - V.I.F.
12. INSTALL FIXED LOUVER IN OPENING - MATCH OPENING SIZE. COORDINATE
WITH MECHANICAL DRAWINGS.
Q R S T XU V WPO
126 SF
WOMEN'S LOCKER
103B
155 SF
MEN'S LOCKER
103A
49 SF
STORAGE
103C
102 SF
HALLWAY
669 SF
OPEN OFFICE
102A
66 SF
TOILET
102D
620 SF
MECHANICAL
102J
56 SF
COPY
102E
1356 SF
STORAGE/OPEN
OFFICE
102B
186 SF
BREAK ROOM
102C
C1-9250 SF
DOCK
C1-9
42 SF
STORAGE
102H
60 SF
ELEC.
102G34 SF
MECH.
102F
63 SF
STORAGE
102K
99 SF
STORAGE
102L
102C
102D
103B
FE
3C
AE101
F3D.G
E Q
E Q
3'
CR
F0D.G
F0D.G
ELEV
ELEVATOR
65 SF
UNUSABLE SPACE
102M
3' - 0"
VERIFY w/ MECH
21' - 6"
V E
R
IF
Y w
/ M E
C H
4'
EQ EQ
2A
2'
/4 " 3
S3A.1F
S3A.1F
2B
S3A.1F
3'
CR
CR
12 12
3' - 10" 5' - 0" 4' - 2 1/4"
158 SF
OFFICE
102N
102N
FEC
PROJECT
LOCATION
SHADE INDICATES
AREA OUT OF
PROJECT SCOPE
BLDG 58 KEYPLAN
N
7' - 4"
/4
9'
/4
1' - 6"
1' - 3"
S3A.Gi
S3A.Gi
F3D.G
102D
F3D.G
PROVIDE IN-WALL
BLOCKING FOR GRAB
BARS
ø 5' - 6"
INSTALL PRIVACY FILM TO
WINDOW - REFER TO
FINISH PLANS
ALIGN NEW WALL FINISH
TO EXISTING JAMB
SIZE STUDS ACCORDINGLY TO
CREATE A FLUSH WALL FINISH ON
BOTH SIDES
ALIGN INFILL WALL TO
EXISTING FINISH - TYP
V .I.
F
EXISTING BRICK WALL AND
PLASTER FINISH
3 5/8" METAL STUD FRAMING
ALIGN INFILL WALL TO
EXISTING FINISH
EXISTING BRICK WALL AND
PLASTER FINISH
REFER TO PLAN
WHERE WALL THICKNESS MATCHING IS ACHIEVABLE
WHERE WALL THICKNESS MATCHING IS
NOT ACHIEVABLE
CORRIDOR SIDE
PROJECT SIDE
CONTROL JOINT, BOTH SIDES
CORNER BEAD, BOTH SIDES
CONTROL JOINT, ALL SIDES
SOUND BATT INSULATION -
INSTALL FULL HEIGHT AND WIDTH
SOUND BATT INSULATION -
INSTALL FULL HEIGHT AND WIDTH
FINISH PLASTER CORNER WITH TEAR AWAY BEAD AND
BLENDING SKIM COAT INTO PLASTER. APPLY PAINTABLE CAULK
AT INSIDE CORNER BETWEEN NEW AND EXISTING FRAME.
OR LAYER DRYWALL TO CREATE A SMOOTH CONTINUOUS
FINISH.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
A u to d e s k D o c s /1
.5
.2
R e n o v a te
-1 R f o r
S u p p ly C h a in M a n a g e m e n t S e rv ic e
/1
.5
.2
A v
.r v t
/1
/2
:0
:0
P
M
AE101
FIRST FLOOR ARCHITECTURAL
PLANGUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
RENOVATE 58-1 R102 FOR
SUPPLY CHAIN MANAGEMENT
SERVICE
DANVILLE, IL
550-23-108
58-R102
04/30/2025 BS JL
100% CONSTRUCTION
DOCUMENTS
FULLY…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .