This solicitation is for an ANS Decontamination Facility to be constructed at Ridgway Reservoir, Colorado. The Bureau of Reclamation is seeking offers for construction services including site work, an equipment building, wash pad, safety equipment, decontamination equipment, utilities, electrical work, asphalt paving, and a propane system. Offerors must submit responses by August 22, 2022 at 2:00 PM Mountain Time to the contracting officer. The period of performance is from September 15, 2022 to May 22, 2023. This is a total small business set-aside solicitation. The estimated value is between $250,000 to $500,000. The document includes specifications, drawings, general contract clauses and provisions, and an invitation for site visits. Evaluation will be based on technical approach and price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ANS Decontamination Facility

(Ridgway Reservoir, CO)

SOLICITATION NO. 140R4022R0018

UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF RECLAMATION

UPPER COLORADO BASIN REGION

SALT LAKE CITY, UTAH

This Solicitation is a Total Small Business Set-Aside.

Solicitation Closing Date: August 22, 2022

Solicitation Closing Time: 14:00 (2:00 PM) Mountain Daylight Time

Emailed proposals must be delivered to:

BUREAU OF RECLAMATION

Contracting Officer, Dwane Esplin, desplin@usbr.gov

Proposals must be received in the Contracting Officer’s email inbox no later than 14:00 hours

(2:00 PM) MDT on or before August 22, 2022 to be considered for award.

Emailed proposals must be clearly labeled with the following naming scheme:

*Proposal – Company Name 140R4022R0018 – ANS Decontamination Facility (Ridgway

Reservoir, CO)*

Only electronic proposals will be accepted.

Inquiries regarding this Solicitation should be made to:

Dwane D. Esplin, Contracting Officer

E-mail: desplin@usbr.gov

All correspondence regarding this Solicitation should reference ANS Decontamination Facility, (Ridgway Reservoir, Colorado) Solicitation No. 140R4022R0018 in the subject line.

Site Visit: For Site Visit information, please see section L, FAR CLAUSE 52.236-27 A1.

Deadline for Questions: Offerors must submit all technical questions to Dwane D. Esplin at desplin@usbr.gov no later than August 12, 2022 - 14:00 PM (MDT)

ONLY WRITTEN QUESTIONS WILL RECEIVE A RESPONSE. Each question submitted must reference the solicitation number (140R4022R0018) and the specific section, clause, paragraph, or drawing. Reclamation will post an amendment to SAM.gov to all questions with answers which may affect proposals.

Please read Section M - Provision WBR 1452.215-82 Evaluation Factors for Award – Quality

Predominance - Bureau of Reclamation thoroughly for evaluation of proposal and award information.

NOTE: Vendors are required to submit electronic proposals in three clearly marked files as outlined in

WBR 1452.215-81 - Proposal Instructions – Bureau of Reclamation. Failure to submit a three-volume proposal in the appropriate electronic format is considered non-responsive and will not be evaluated.

mailto:desplin@usbr.gov

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado) i

Table of Contents

SECTION A – SF-1442

SECTION B – SUPPLIES OR SERVICES AND PRICES

B.1 SCHEDULE

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

SECTION D – PACKAGING AND MARKING

SECTION E - INSPECTION AND ACCEPTANCE

E.1

E.2

SECTION F - DELIVERIES OR PERFORMANCE

F.1

F.2

SECTION G - CONTRACT ADMINISTRATION DATA

G.1

G.2

G.3

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1

SECTION I - CONTRACT CLAUSES

I.1

I.2

I.3

I.4

I.5

I.6

I.7

I.8

I.9

I.10

I.11

I.12

I.13

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado) ii

I.14

I.15

I.16

I.17

I.18

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF

OFFERORS

K.1

K.2

K.3

K.4

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

L.1

L.2

L.3

L.4

L.5

L.6

L.7

L.8

L.9

L.10

L.11

L.12

L.13

SECTION M - EVALUATION FACTORS FOR AWARD

M.1

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040568838

Bureau of Reclamation

Upper Colorado Region

Regional Office 125 South State Street, Room 8100

R40

Salt Lake City UT 84138

Dwane Esplin 801-524-3743

1x 07/22/2022

140R4022R0018

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

ANS Decontamination Facility (Ridgway Reservoir, CO)

See Final Specifications and Drawings in their entirety.

The estimated magnitude of this project is between $250,000 and $500,000.

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 233 calendar days and complete it within ________________ ________________ calendar days after receiving

08/22/2022

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Dwane D. Esplin

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 68

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140R4022R0018

Legacy Doc #: BOR

Delivery Location Code: 0009910014

Bureau of Reclamation-UC-WCAO

445 West Gunnison Ave Suite 221

Grand Junction CO 81501 US

Period of Performance: 09/15/2022 to 05/22/2023

00010 ANS Decontamination Facility at Ridgway

Reservoir, Colorado

Price Schedule - CLIN 1 through 17.

Product/Service Code: Y1JZ

Product/Service Description: CONSTRUCTION OF

MISCELLANEOUS BUILDINGS

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND PRICES

B.1 SCHEDULE

(a) Offers will be considered for award on the following Price Schedule but no offer will be considered for award on only a part of the price schedule.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only. Except as provided in the contract clause at FAR 52.211-18, Variation in

Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated

Quantity does not apply to lump sum items.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and

Preparatory Work, for CLIN 1.

(e) Definitions:

(1) CLIN – Contract Line Item Number.

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

END OF SCHEDULE

Item 00010

CLIN Section Supplies or Services Estimated Quantity Unit Unit Price Amount

1 WBR 1452.232-81 Mobilization and Preparatory Work -$

2 02 41 07 Removal and Disposal of Existing Features -$

3 03 30 00 ANS Equipment Building Slab, Wash Pad, Curbs & Propane Tank Slab 26 cubic yards -$

4 05 50 00 Safety Ladder & Stand -$

5 05 50 00 Pipe Bollards -$

6 11 11 26 ANS Decontamination Equipment -$

7 11 11 26 Furnishing and Laying 4-inch and Smaller PVC Schedule 80 Pipe 80 linear feet -$

8 13 34 20 ANS Equipment Building -$

9 22 11 16 Furnishing and Laying 1-inch Polyethylene Tubing 80 linear feet -$

10 26 05 02 Complete Electrical System -$

11 31 23 11 Earthwork for ANS Equipment Building Slab, Retention Pond &

Miscellaneous Features -$

12 31 23 11 Class 3 Aggregate Sub-base 150 cubic yards -$

13 31 23 11 Class 6 Aggregate Base 120 cubic yards -$

14 32 12 22 4-Inch Asphalt Concrete Pavement 530 Square yards -$

15 33 05 22 Horizontal Directional Drilling 330 linear feet -$

16 33 05 31 48-inch Manhole Structure 2 Each -$

17 43 41 14 Propane Tank & Propane Gas Piping System -$

For the lump sum of

For the lump sum of

For the lump sum of

For the lump sum of

TOTAL FOR PRICE SCHEDULE:

For the lump sum of

PRICE SCHEDULE

For the lump sum of

For the lump sum of

For the lump sum of

For the lump sum of

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

SEE ATTACHMENT 1 AND 2 FOR THE SPECIFICATIONS AND DRAWINGS IN THEIR ENTIRETY.

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

SECTION D – PACKAGING AND MARKING

THERE ARE NO CLAUSES INCLUDED IN THIS SECTION

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

SECTION E - INSPECTION AND ACCEPTANCE

E.1 52.246-12 INSPECTION OF CONSTRUCTION AUG 1996

(a) Definition - "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The

Contractor shall maintain complete inspection records and make them available to the

Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not -

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the

Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary.

The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may -

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

(1) By contract or otherwise, replace or correct the work and charge the cost to the

Contractor; or

(2) Terminate for default the Contractor's right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the

Contractor shall defray the expenses of the examination and of satisfactory reconstruction.

However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the

Government's rights under any warranty or guarantee.

(End of clause)

E.2 52.246-21 WARRANTY OF CONSTRUCTION MAR 1994

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to

Government-owned or controlled real or personal property, when that damage is the result of:

(1) The Contractor's failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall-

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the

Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in

Government-furnished material or design.

(j) This warranty shall not limit the Government's rights under the Inspection and

Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

SECTION F - DELIVERIES OR PERFORMANCE

F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND

COMPLETION OF WORK

APR 1984

The Contractor shall be required to:

(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) Prosecute the work diligently, and (c) complete the ANS

Decontamination Facility construction no later than May 22, 2023. The time stated for completion shall include final cleanup of the premises. The completion date is based on the assumption that the successful offeror will receive the notice to proceed by September 30, 2022. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

F.2 52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984

If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the

Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

SECTION G - CONTRACT ADMINISTRATION DATA

G.1 1452.201-70 AUTHORITIES AND DELEGATIONS SEP 2011

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction

(written or oral) that the Contractor considers in excess of the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the

COR.

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting

Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.

G.2 WBR

1452.201-80

CONTRACTING OFFICER’S

REPRESENTATIVE’S AUTHORITIES AND

LIMITATIONS -- BUREAU OF

RECLAMATION

MAY 2018

(a) Performance of the work under this contract shall be subject to the technical direction of the

Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:

(1) Inspecting and accepting or rejecting work performed under the contract.

(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the

Contractor on all technical matters relating to the contract. The COR will supervise or oversee all

Government technical and administrative personnel assigned to assist the COR.

(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.

(b) The Contractor will receive a copy of the written COR designation from the Contracting

Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting

Officer.

(c) Technical direction must be within the scope of work stated in the contract. Only the

Contracting Officer is authorized to determine if a change is within the scope of the contract;

therefore, the COR does not have the authority to, and may not, issue any technical direction that

(1) Constitutes a direction of additional work outside the Contract requirements;

(2) Constitutes a change as defined in the contract clause entitled “Changes;”

(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;

(4) Changes any of the expressed terms, conditions or specifications of the contract; or

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.

(d) All technical direction shall be issued in writing by the COR.

(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the

COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the

Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting

Officer to modify the contract accordingly. Upon receiving the notification from the

Contractor, the Contracting Officer must -

(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or

(2) Advise the Contractor that the Government will issue a written change order.

(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”

G.3 DOI-AAAP

ELECTRONIC INVOICING AND PAYMENT

REQUIREMENTS - INVOICE PROCESSING

PLATFORM (IPP)

APR 2013

Payment requests must be submitted electronically through the U. S. Department of the

Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the

Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

The contractor submits an electronic copy of their business invoice to the Contracting

Officer Representative (COR) and the Contracting Officer at the time of IPP submission.

Please refer to FAR 32.905(b) for proper invoicing information.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment https://www.ipp.gov/

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado) can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

mailto:ippgroup@bos.frb.org mailto:ippgroup@bos.frb.org

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 DOI-AAAP

NOTICE TO CONTRACTORS -

CONTRACTOR PERFORMANCE

ASSESSMENT REPORTING SYSTEM

DEC 2015

(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance

Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

(b) The past performance evaluation process is a totally paperless process using CPARS.

CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance

Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

(c) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

(d) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available athttps://www.cpars.gov/.

(e) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible athttps://www.cpars.gov/.

(1) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

(2) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

(3) All information provided should be reviewed for accuracy prior to submission.

(4) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

(5) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, http://www.cpars.gov/ http://www.cpars.gov/ https://www.cpars.gov/

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado) the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

(6) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

(f) The following guidelines apply concerning your use of the past performance evaluation:

(1) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the

CO for instructions.

(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

SECTION I - CONTRACT CLAUSES

I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEB 1998

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

FAR Clauses - https://www.acquisition.gov/far/

CLAUSE TITLE DATE

52.202-1 Definitions JUN 2020

52.203-3 Gratuities APR 1984

52.203-5 Covenant Against Contingent Fees MAY 2014

52.203-6 Restrictions on Subcontractor Sales to the Government JUN 2020

52.203-7 Anti-Kickback Procedures JUN 2020

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

MAY 2014

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity MAY 2014

52.203-12 Limitation on Payments to Influence Certain

Federal Transactions

JUN 2020

52.203-17 Contractor Employee Whistleblower Rights and

Requirement To Inform Employees of Whistleblower Rights

JUN 2020

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

JAN 2017

52.204-4 Printed or Copied Double-Sided on Postconsumer

Fiber Content Paper

MAY 2011

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

JUN 2020

52.204-13 System for Award Management Maintenance OCT 2018

52.204-14 Service Contract Reporting Requirements OCT 2016

52.204-18 Commercial and Government Entity Code Maintenance AUG 2020

52.204-19 Incorporation by Reference of Representations and Certifications

DEC 2014

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by

Kaspersky Lab and Other Covered Entities

NOV 2021

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.209-6

Protecting the Government’s Interest When

Subcontracting with Contractors Debarred, Suspended, or

Proposed for Debarment

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters

OCT 2018

52.209-10 Prohibition on Contracting With Inverted

Domestic Corporations

NOV 2015

https://www.acquisition.gov/far/

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

52.215-2 Audit and Records – Negotiation JUN 2020

52.215-8 Order of Precedence—Uniform Contract Format OCT 1997

52.215-21 Requirements for Certified Cost or Pricing Data and Data

Other Than Certified Cost or Pricing Data –

Modifications

NOV 2021

52.219-8 Utilization of Small Business Concerns OCT 2018

52.222-3 Convict Labor JUN 2003

52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation

MAY 2018

52.222-6 Construction Wage Rate Requirements

AUG 2018

52.222-7 Withholding of Funds MAY 2014

52.222-8 Payrolls and Basic Records JUL 2021

52.222-9 Apprentices and Trainees JUL 2005

52.222-10 Compliance with Copeland Act Requirements FEB 1988

52.222-11 Subcontracts (Labor Standards) MAY 2014

52.222-12 Contract Termination-Debarment MAY 2014

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards

FEB 1988

52.222-15 Certification of Eligibility MAY 2014

52.222-21 Prohibition of Segregated Facilities APR 2015

52.222-26 Equal Opportunity SEP 2016

52.222-27 Affirmative Action Compliance Requirements for Construction

APR 2015

52.222-35 Equal Opportunity for Veterans

JUN 2020

52.222-36 Equal Opportunity for Workers with Disabilities

JUN 2020

52.222-37 Employment Reports on Veterans

JUN 2020

52.222-40 Notification of Employee Rights Under the National Labor Relations Act

DEC 2010

52.222-50 Combating Trafficking in Persons NOV 2021

52.222-54 Employment Eligibility Verification MAY 2022

52.222-55 Minimum Wages Under Executive Order 13658 JAN 2022

52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022

52.223-6 Drug-Free Workplace MAY 2001

52.223-15 Energy Efficiency in Energy-Consuming Products DEC 2007

52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

AUG 2018

52.223-18 Encouraging Contractor Policies to Ban text Messaging

While Driving

JUN 2020

52.225-13 Restrictions on Certain Foreign Purchases

FEB 2021

52.227-1 Authorization and Consent JUN 2020

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement

JUN 2020

52.227-4 Patent Indemnity-Construction Contracts DEC 2007

52.227-14 Rights in Data-General MAY 2014

52.227-23 Rights in Proposal Data (Technical) JUN 1987

52.228-2 Additional Bond Security OCT 1997

52.228-11 Pledges of Assets FEB 2021

52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014

52.228-14 Irrevocable Letter of Credit NOV 2014

52.228-15 Performance and Payment Bonds - Construction JUN 2020

52.229-3 Federal, State And Local Taxes FEB 2013

52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014

52.232-16 A1 Progress Payments – Alternate I (Mar 2000) NOV 2021

52.232-17 Interest MAY 2014

52.232-23 Assignment of Claims MAY 2014

52.232-27 Prompt Payment for Construction Contracts JAN 2017

52.232-33 Payment by Electronic Funds Transfer-- System for Award Management

OCT 2018

52.232-39 Unenforceability of Unauthorized Obligations

JUN 2013

52.232-40 Providing Accelerated Payments to Small Business Subcontractors

NOV 2021

52.233-1 A1 Disputes - Alternate I (December 1991)

MAY 2014

52.233-3 Protest After Award AUG 1996

52.233-4 Applicable Law for Breach of Contract Claim OCT 2004

52.236-3 Site Investigation and Conditions Affecting the Work APR 1984

52.236-5 Material and Workmanship APR 1984

52.236-6 Superintendence by the Contractor APR 1984

52.236-7 Permits and Responsibilities NOV 1991

52.236-8 Other Contracts APR 1984

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas

APR 1984

52.236-11 Use and Possession Prior to Completion APR 1984

52.236-12 Cleaning Up APR 1984

52.236-13 Accident Prevention NOV 1991

52.236-15 Schedules for Construction Contracts APR 1984

52.236-17 Layout of Work APR 1984

52.236-21 A1 Specifications and Drawings for Construction - Alternate I (April 1984)

FEB 1997

52.236-26 Preconstruction Conference FEB 1995

52.242-13 Bankruptcy JUL 1995

52.242-14 Suspension of Work APR 1984

52.243-4 Changes JUN 2007

52.243-6 Change Order Accounting APR 1984

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

52.244-2 Subcontracts JUN 2020

52.244-6 Subcontracts for Commercial Items JAN 2022

52.248-3 Value Engineering – Construction OCT 2020

52.249-2 A1 Termination for Convenience of the Government (Fixed-Price)

- Alternate I (September 1996)

APR 2012

52.249-10 Default (Fixed-Price Construction)

52.253-1 Computer Generated Forms JAN 1991

I.2 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)

(a) Definition. Small business concern, as used in this clause—

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.

(2) Affiliates, as used in paragraph (a)(1) of this clause, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships.

SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) Applicability. This clause applies only to-

(1) Contracts that have been totally set aside for small business concerns; and

(2) Orders set aside for small business concerns under multiple-award contracts as described in

8.405-5 and 16.505(b)(2)(i)(F).

(c) General. (1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.

(2) Any award resulting from this solicitation will be made to a small business concern.

I.3 52.219-14 LIMITATIONS ON SUBCONTRACTING (DEVIATION) (SEP 2021)

(a) This clause does not apply to the unrestricted portion of a partial set-aside.

(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—

(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and

(2) Is considered small for the size standard under the North American Industry Classification System

(NAICS) code the prime contractor assigned to the subcontract.

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado)

(c) Applicability. This clause applies only to—

(1) Contracts that have been set aside for any of the small business concerns identified in

19.000(a)(3);

(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;

(4) Orders expected to exceed the simplified acquisition threshold and that are—

(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or

(ii) Issued directly to small business concerns under multiple-award contracts as described in

19.504(c)(1)(ii);

(5) Orders, regardless of dollar value, that are—

(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or

(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and

(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.

(d) Independent contractors. An independent contractor shall be considered a subcontractor.

(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the

Contractor agrees to the following requirements in the performance of a contract assigned a North American

Industry Classification System (NAICS) code applicable to this contract:

(1) Services (except construction). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.

(i) The following services may be excluded from the 50 percent limitation:

(A) Other direct costs, to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service. Examples include airline travel, work performed by a transportation or disposal entity under a contract

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado) assigned the environmental remediation NAICS code (562910), cloud computing services, or mass media purchases.

(B) Work performed outside the United States on awards made pursuant to the

Foreign Assistance Act of 1961, or work performed outside the United States required to be performed by a local contractor.

(2) Supplies (other than procurement from a nonmanufacturer of such supplies). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.

(3) General construction. It will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 85 percent subcontract amount that cannot be exceeded.

(4) Construction by special trade contractors. It will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 75 percent subcontract amount that cannot be exceeded.

(f) The Contractor shall comply with the limitations on subcontracting as follows:

(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause –

[Contracting Officer check as appropriate.]

_X_ By the end of the base term of the contract and then by the end of each subsequent option period; or

__ By the end of the performance period for each order issued under the contract.

(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.

(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.

I.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM SEP 2021

REPRESENTATION

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance

Solicitation No. 140R4022R0018 ANS Decontamination Facility (Ridgway Reservoir, Colorado) has been extended for a cumulative period not to exceed six months under the clause at 52.217-

8, Option to Extend Services, or other appropriate authority.

Small business concern—

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (d) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships.

SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of…