Questions and Answers - Robins North Safety Lines.pdf

PDF 57 KB Posted

Attached to
Robins North - Painting Safety Line
Solicitation number
RFQF3QCCL0141A004
Issued by

View the file

Other files

File Type Posted
Robins North Layout Hangar Doors.pdf PDF
Q and A - Robins North Safety Lines 3 March.docx DOCX document
RFQ F3QCCL1041A004 UPDATED.docx DOCX document
PWS.doc DOC document
RFQ F3QCCL1041A004 2 March.docx DOCX document
pic3.jpg JPG image
pic2.jpg JPG image
pic5.jpg JPG image
pic4.jpg JPG image
pic1.jpg JPG image
pic6.jpg JPG image
CDRL A002 - Accident Incident Report.pdf PDF
DRAWING -- Robins North Layout 01.pdf PDF
1006806868_RFQ F3QCCL0141A004 25 Feb.docx DOCX document
CDRL A001.pdf PDF
Appendix C-Robins North Painting Safety Lines.docx DOCX document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Robins North – Painting Safety Lines

Questions & Answers

10 February 2021

1. What is the width and length of the Hangar Doors?

Each hangar door is 30inches wide by 52feet long

2. What product is specified for the floor coating? Is it the same for both interior and exterior?

Best guess on floor coating needs to be weather resistant and anti‐slip/skid, maybe even reflective or high visibility markings

3. Have the interior or exterior of the hanger floor been previously coated? If so when?

These lines have never been painted inside or out. The interior is currently coated with a grey paint for easy clean up

4. What is the timeframe or estimated project start date?

Contract estimated award date is 21 April 2021 – Project start date can begin within 10 days of contract award