RFP 12805B24R0030 Bathroom Renovations.pdf

PDF 360 KB Posted

Attached to
Bathroom Renovation - Manhattan KS Federal contract opportunity
Solicitation number
12805B24R0030
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Plains Area

About this file

This document is a Request for Proposals (RFP) for a Bathroom Renovation project at the USDA Center for Grain and Animal Health Research (CGAHR) in Manhattan, Kansas. The work is set aside for Total Small Business with the applicable NAICS code of 236220. The magnitude of the construction project is between $100,000 and $250,000.

The contractor shall furnish all labor, materials, equipment, supplies, transportation, utilities, and supervision to complete the bathroom renovation project within 45 days after award. Proposals are due by July 15, 2024, and the contract will be awarded as a Firm-Fixed-Price contract. Attendance at the mandatory site visit on June 21, 2024 is required to submit a proposal. The procurement requires the use of biobased products to the extent they are reasonably available, meet performance standards, and are reasonably priced.

View the file

Other files for this federal contract opportunity

Other files attached to Bathroom Renovation - Manhattan KS, newest first.
File Type Posted
Amendment 0001 SF30 RFP 12805B24R0030.pdf PDF
Attachment 006 QandA Document.pdf PDF
Attachment 001 Wage Determination.pdf PDF
Attachment 002 SOW Bathroom Renovation.pdf PDF
Attachment 004 Pre-Award Survey Form.docx DOCX document
Attachment 003 SF24 Bid Bond.pdf PDF
Attachment 005 12805B24R0030 Site Visit Information.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1128115

USDA ARS PA AAO ACQ/PER PROP

2150 CENTRE AVENUE

BLDG D, SUITE 300

FORT COLLINS CO 80526

ARS-12805B

Chris Turner christopher.c.turner@usda.gov

CHRISTOPHER TURNER

1x 06/11/2024

12805B24R0030

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

A. Project Title: Bathroom Renovation - Manhattan KS CGAHR

B. Competition is set aside for Total Small Business. Applicable NAICS code is

236220.

C. In accordance with Federal Acquisition Regulation (FAR) 36.204 the magnitude of this construction project is between $100,000 and $250,000.

D. Prospective offerors shall complete block 14, 15 and 19 and provide pricing to

CLIN 0001 on the continuation sheet page 3. See section L.8 for further instructions for the preparation of proposals.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

0 45 calendar days and complete it within ________________ ________________ calendar days after receiving

07/15/2024

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

CHRISTOPHER C. TURNER

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 32

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

12805B24R0030

Delivery: 45 Days After Award

Delivery Location Code: ARS-126240

PA CENTER FOR GRAIN AND ANIMAL HEAL

1515 COLLEGE AVENUE

MANHATTAN KS 66502 US

0001 2 Each Bathroom Renovation Project Asset

543000B0001

See Attachment 002 Statement of Work for more details.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

RFP 12805B24R0030 Bathroom Renovations - Manhattan KS

SECTION B- SUPPLIES AND SERVICES AND PRICE/COST

B.1 SCOPE OF CONTRACT

The Contractor shall furnish all labor, materials, equipment, supplies, transportation, utilities, and supervision for complete construction of the following in accordance with the clauses, specifications, drawings, attachments, and other terms and conditions set forth in the attached statement of work.

B.2 SCHEDULE OF ITEMS

Please reference Page 3 OF336 to SF1442 “Continuation Sheet.” There are no option CLINS.

B.3 Period of Performance The base project Period of Performance is to be completed 45 days after award.

SECTION C - DESCRIPTION/SPECIFICATION/WORK STATEMENT

C.1 STATEMENT OF WORK/SPECIFICATIONS (AGAR 452.211-72) (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

(End of Clause)

C.2 PERMITS AND LICENSES

Pursuant to FAR 52.236-7 Permits and Responsibilities, the Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state, and local laws and regulations.

C.3 DIRECTIVES, INSTRUCTIONS AND REFERENCES

Only the Contracting Officer shall issue directives/instructions defining the roles and responsibilities and appointment of a Contracting Officer Representative (COR); Location Monitor (LM); Project Manager (PM);

Occupational Health & Safety Manager and/or any other functional appointment as deemed necessary for the scope of work.

C.4 WORK MANAGEMENT

The Contractor shall manage the total work effort associated with the services required to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality control. The Contractor shall provide a staff with the necessary management expertise to assure performance objectives and standards are met.

C.5 MATERIALS AND EQUIPMENT

Materials and equipment may not be stored at the jobsite lay down area after work hours unless approved in advance by the Contracting Officer. There will not be office space available at any location. All job site lay down areas are dependent upon the size and location of the work. Job site availability will be identified in the Scope of Work.

C.6 SERVICE INTERRUPTIONS/UTILITY OUTAGES

If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the Contracting Officer Representative ten calendar days in advance to allow notification of affected tenants and customers. If the discontinued service is due to an emergency breakdown the Contractor shall notify the Contracting Officer Representative as soon as practicable.

At a minimum, include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

C.7 EMPLOYEE REQUIREMENTS

The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract.

Personnel shall be fully knowledgeable of all safety and environmental requirements associated with the work they perform. Competent personnel shall be provided as required by each contract.

C.8 OSHA

Contractor must maintain a workplace and ensure that workplace conditions conform to applicable OSHA standards.

C.9 KEY PERSONNEL

The Contractor shall confirm to the Contracting Officer the List of Key Personnel and their qualifications provided as part of the base contract submittals. The contractor will provide any additional information requested by the Contracting Officer to certify their qualifications. The Contractor shall submit to the Contracting Officer a finalized organization chart showing the lines of authority of key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. The Contractor shall identify the personnel able to bind the Contractor contractually.

C.10 EMPLOYEE REQUIREMENTS

The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety and environmental requirements associated with the work they perform. Competent personnel shall be provided as required by the contract. Contractor staff may be required to obtain a USDA Linc Pass badge. Documents need to obtain the Linc Pass shall be provided by the Government after award, if required.

C.11 EMPLOYEE CONDUCT/REMOVAL OF EMPLOYEES

Contractor employees and Subcontractor employees shall conduct themselves in a proper, efficient, courteous, and businesslike manner. The Contractor shall remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of Agricultural Research Service. The Contracting Officers decision is final and not negotiable.

C.12 STATEMENT OF WORK/SPECIFICATIONS (AGAR 452.211-72) (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

(End of Clause)

C.13 PERIOD OF PERFORMANCE (AGAR 452.211-74) (FEB 1988)

The base project period of performance of this contract is 45 days after award.

(End of Clause)

SECTION D - PACKAGING AND MARKING

D.1 (FOR THIS SOLICITATION, THERE ARE NO CLAUSES IN THIS SECTION).

SECTION E - INSPECTION AND ACCEPTANCE

E.1 CLAUSES INCORPORATED BY REFERENCE (52.252-2) (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: http://acquisition.gov

CLAUSE TITLE DATE

52.246-12 Inspection of Construction AUG 1996 52.246-13 Inspection – Dismantling, Demolition, or Removal of Improvements AUG 1996

E.2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection will be performed at: the location of the project.

Acceptance will be performed at: See (b) above.

(End of Clause)

SECTION F - DELIVERIES OR PERFORMANCE

F.1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2) (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: http://acquisition.gov

NUMBER TITLE DATE

52.242-14 Suspension of Work APR 1984 52.242-17 Government Delay of Work APR 1984

F.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) (APR 1984)

The Contractor shall be required to:

(a) commence work under this contract within 10 calendar days after the date the Contractor receives the contract notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 45 days after award for the base project. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

SECTION G - CONTRACT ADMINISTRATION DATA

G.1 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

A Contracting Officer's Representative (COR) will be designated after contract award. The contractor will be notified by letter of the name and duties of the COR.

G.2 CONTRACT CLOSEOUT

(a) Closeout Procedures:

(1) Comply with provisions in conditions of contract relating to submittals prior to substantial completion, or Owner's use of completed portions of work.

(2) Provide submittals required by governing authorities.

(b) Cleaning:

(1) Execute cleaning during progress of work and at completion of work.

(2) Reference other specification sections for additional specific work.

(3) Maintain premises and public properties free from accumulations of waste, debris, and rubbish caused by operations.

(4) At completion of work, remove waste materials, rubbish, tools, equipment, machinery, and surplus materials:

a. Clean all sight-exposed surfaces.

b. Leave project clean and ready for occupancy or use.

c. All floors are to be broom and wet-mop cleaned.

(5) Areas disturbed during construction operations shall be restored generally to match conditions existing prior to start of work.

(c) Project Record Drawings:

(1) Maintain documents in clean, dry, legible condition.

(2) Make documents available at all times for inspection by COR, CO, and other individuals as may be designated by the CO.

(3) Label each document "Project Record."

(4) Keep record documents current.

(5) Do not conceal work until required information has been recorded.

(6) At completion of work, and before final acceptance, submit as-built drawings in accordance with special contract requirements.

(d) Operating and Maintenance Manuals:

(1) System Demonstration

a. Prior to final inspection demonstrate operation of each system to the COR, CO, and other individuals as may be designated by the CO.

b. Instruct designated Government personnel in operation, adjustment, and maintenance of equipment and systems, using the operation and maintenance data as the basis of instruction.

(2) Warranties and Bonds:

a. Submit warranties and maintenance bonds prior to final application for payment.

1. Submit within ten days after date of substantial completion.

2. For items of work delayed materially beyond date of substantial completion, provide updated submittal within ten days after acceptance, listing date of acceptance as start of warranty period.

G.3 RELEASE FROM CLAIMS

The Contractor shall complete and submit a release of all claims against the Government arising under and by virtue of the purchase order, similar to the following with the final invoice/billing request:

For and in consideration for the receipt of final payment in the amount of $ under and pursuant to Purchase Order No. , the undersigned hereby releases the Government from any and all obligations whatsoever arising under said purchase order.

Name, Title, and Signature of Contractor DATE

G.4 SUPPLEMENT TO CHANGES CLAUSE

The provisions of the Changes and Changed Conditions Clause (FAR 52.243-5), as applicable, are supplemented as follows:

a) The contractor shall provide an itemized breakdown or take-off for all charges involving an increase or decrease in the contract price. The proposal shall be in sufficient detail that will enable the Government to determine the reasonableness of the contractor's and subcontractor's cost to do the change. As a minimum, the following shall be shown:

1. Material quantities and unit prices;

2. Labor costs (broken down by trades, hours worked, and hourly rate);

3. Labor burden (Fringe Benefits, Workmen's Compensation, and Public Liability Insurance);

4. Overhead;

5. Profit;

6. FICA, and FUTA employment taxes; and

7. Sales tax (if any).

b) On proposals offering a credit for work omitted, deductions for overhead and profit shall also be shown.

c) If the proposed change will result in an increase or decrease in the contract performance period, the contractor shall state the exact number of days involved. If the proposed change is approved and the Government agrees with the increase or decrease in completion time, the completion date will become a part of the contract modification.

d) Following (G.6) is a sample format for showing related costs as a result of a change order. A similar sheet shall accompany each written detailed cost breakdown. The sample format is self-explanatory and clearly shows the method for computing overhead, profit, and other items on proposed changes.

G.5 SUMMARY SHEET FORMAT

DATE

PROJECT

LOCATION

CONTRACT NUMBER

CONTRACTOR

CHANGE ORDER NO. DESCRIPTION

PRIME CONTRACTOR'S WORK

1. Direct Materials $

2. Sales Tax on Materials % of line 1 $

3. Direct Labor $

4. Insurance, Taxes, and Fringe Benefits % of line 3 $

5. Rental Equipment $

6. Sales Tax - Rental Equipment % of line 5 $

7. SUBTOTAL (lines 1-6) $

8. Overhead % of line 7 $

9. SUBTOTAL (add lines 7-8) $

SUBCONTRACTOR=S WORK

10. Direct Materials $

11. Sales Tax on Materials % of line 10 $

12. Direct Labor $

13. Insurance, Taxes, and Fringe Benefits % of line 12 $

14. Rental Equipment $

15. Sales Tax - Rental Equipment % of line 14 $

16. SUBTOTAL (lines 10-15)

17. Overhead % of line 16

18. SUBTOTAL (add lines 16-17) $

19. Profit % of line 18 $

20. SUBTOTAL (add lines 18-19) $

SUMMARY

21. Primes Work (from line 9) $

22. Subs Work (from line 20) $

23. SUBTOTAL (add lines 21-22) $

24. Primes Overhead on Sub % of line 16 $

25. Primes Profit % of line 16 $

26. SUBTOTAL (add lines 23-25) $

27. Primes Bond Premium % of line 26 $

28. TOTAL Cost $ Estimated time extension (if any and justification):

Signature and Title of Preparer Date

NOTE: THE CUMULATIVE TOTAL FOR OVERHEAD AND PROFIT OF ALL SUBCONTRACTORS AND THE PRIME CONTRACTOR SHALL NOT EXCEED 30 PERCENT. FOR PRIME CONTRACTORS WORK ONLY, THE CUMULATIVE

TOTAL FOR OVERHEAD AND PROFIT SHALL NOT EXCEED 20 %.

G.6 INVOICE PREPARATION AND SUBMISSION

Based upon acceptance of required contract deliverables, the contractor shall submit an original invoice and one copy to the Contracting Officer and the COR:

The contractor shall include the following information on each invoice in order to be considered a proper invoice:

1. Name and address of contractor.

2. Invoice number and Invoice date.

3. Contract number.

4. Description of work and period of performance.

5. Name, title, phone number, and complete mailing address of official to whom payment is to be sent.

6. Name, title, phone number, and complete mailing address of person to notify in the event of a defective invoice.

7. UEI Number.

8. Invoices must be submitted with ARS-371 and ARS-372, along with certified payroll records, Contractor certification, and updated CPM Schedule.

Once the paper invoice has been approved by the Contracting Officer, the Contractor shall submit the invoice electronically through the U.S. Department of Treasury Invoice Processing Platform (IPP) at www.ipp.gov. This is a mandatory requirement.

G.7 Contractor Performance Information and Contractor Performance Assessment Reporting System (CPARS)

(FAR 42.1502)

(a) General. Past performance evaluations shall be prepared at least annually and at the time the work under a contract or order is completed. Past performance evaluations are required for contracts and orders as specified in paragraphs (b) through (f) of this section, including contracts and orders performed outside the United States.

These evaluations are generally for the entity, division, or unit that performed the contract or order. Past performance information shall be entered into CPARS, the Government wide evaluation reporting tool for all past performance reports on contracts and orders. Instructions for submitting evaluations into CPARS are available at http://www.cpars.gov/

(b) Past performance evaluations shall be prepared for each construction contract of $700,000 or more, and for each construction contract terminated for default regardless of contract value. Past performance evaluations may also be prepared for construction contracts below $700,000.

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 INSURANCE COVERAGE-ALT 1 (AGAR 452.228-71) (NOV 1996)

Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability.

(1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(2) The Contractor shall have property damage liability insurance shall be required in the amount of $1.0 million per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the con contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(End of Clause)

H.2 USE OF PREMISES (AGAR 452.236-72) (NOV 1996)

Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer’s Representative. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor.

Unless accepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.

(End of Clause)

H.3 ARCHAEOLOGICAL OR HISTORIC SITES (AGAR 452.236-73) (FEB 1988)

If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

(End of Clause)

H.4 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION (AGAR 452.236-74) (NOV 1996)

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.)

(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, and impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.

(End of Clause)

H.5 MAXIMUM WORKWEEK - CONSTRUCTION SCHEDULE (AGAR 452.236-75) (NOV 1996)

Within 10 (ten) calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

A schedule as required by FAR clause 52.236-15, "Schedules for Construction Contracts" and

The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.

The maximum workweek that will be approved is 8:00 a.m. to 4:30 p.m., Mon. thru Fri., excluding Federal holidays.

MAXIMUM WORKWEEK - CONSTRUCTION SCHEDULE (SUPPLEMENT)

The following applies to all work performed on Government-owned property:

(a) Listed below are official Government holidays:

New Year’s Day January 1* Martin L. King Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Juneteenth As Indicated Independence Day July 4* Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11* Thanksgiving Day Fourth Thursday in November Christmas Day December 25* Inauguration Day January 20* (for Washington D.C. Metropolitan Area (WDCMA))

If a Sunday, the next succeeding day is selected.

*In accordance with Federal regulations, if these holidays fall on a Saturday, the holiday will be observed on Friday, if Sunday, holiday will be observed on Monday.

The contractor will be required to follow Government procedures for any unscheduled shut down of the Government installation due to weather conditions, security, Government identified emergency health and safety evacuation, etc.

(b) SEVERE WEATHER WARNING REQUIREMENTS: When a severe weather warning has been issued for the area in which construction is being performed, the contractor shall immediately take action to tie down, or otherwise secure structures, materials, and equipment on the job site that could become airborne as a result of strong winds, thunderstorms, rain or other weather related conditions, including protection from extreme or extended periods of cold or heat. These requirements are applicable 24 hours a day, 7 days a week.

(c) WORK OUTSIDE REGULAR HOURS: If the contractor desires to work outside regular hours, or on Saturday, Sunday, or Federal legal holidays, he shall submit a written request to the CO/COR 5 working days in advance to allow ample time for approval or disapproval and to enable satisfactory arrangements to be made for security, safety, and inspecting the work progress.

In cases where the contractor receives approval to work outside of normal working hours for his convenience, cost incurred by the contractor for overtime and additional cost incurred by the Government for services including inspection costs shall be borne by the contractor.

(End of Clause)

H.6 SAMPLES AND CERTIFICATES (AGAR 452.236-76) (FEB 1988)

When required by the specifications or the Contracting Officer, samples, certificates, and test data shall be submitted after award of the contract, prepaid, in time for proper action by the Contracting Officer or his/her designated representative. Certificates and test data shall be submitted in triplicate to show compliance of materials and construction specified in the contract performance requirements.

Samples shall be submitted in duplicate by the Contractor, except as otherwise specified, to show compliance with the contract requirements. Materials or equipment for which samples, certifications or test data are required shall not be used in the work until approved in writing by the Contracting Officer.

(End of Clause)

H.7 KEY PERSONNEL (AGAR 452.237-74) (FEB 1988)

The Contractor shall assign to this contract the following key personnel: Site Superintendent (End of Clause)

H.8 CONSTRUCTION PROGRESS AND PAYMENT SCHEDULE

Within 14 (fourteen) calendar days after the date of receipt of contract, the Contractor shall prepare and submit to the Contracting Officer for approval and signature, a copy of ARS Form 371, "Construction Progress and Payment Schedule." This form, in conjunction with ARS Form 372, "Contractor's Request for Payment Transmittal" (or an acceptable facsimile), will be the basis for partial payments to the Contractor. The values employed in making the schedule will be used only for determining partial payments and will not be considered as fixing a basis for additions to or deductions from the purchase order. Upon the Contracting Officer's approval and signature, a copy of the Form 371 (with original signatures) will be given to the Contractor. No work may be performed onsite unless and until the ARS Form 371 has been approved by the Contracting Officer. The ARS Form 371 is required even though progress or partial payments would not be requested by the Cooperator.

H.9 INVOICES

Invoices shall be submitted to the attention of the Contracting Officer Representative who will forward them to the Contracting Officer. Invoices shall contain, at a minimum, the name of the Company; Purchase Order Number; description of services, price for such services actually rendered; shipping and payment terms; and name (where practicable), title, phone number and complete mailing address of responsible official to whom payment is to be sent. In order for invoices to be processed, certified payroll records must have been received by the Contracting Officer for the period being invoiced. NO INVOICES WILL BE PROCESSED UNLESS CURRENT CERTIFIED PAYROLL RECORDS ARE ON FILE WITH THE CONTRACTING OFFICER IN ACCORDANCE WITH THE CONSTRUCTION WAGE RATES REQUIREMENT. All invoices will be returned to the Contractor without payment action until payroll records are received by the Contracting Officer. The final invoice shall include a Release of Claims Form as shown in Section G.4 of the contract.

H.10 LIST OF MATERIALS

(a) The Contractor shall submit for approval a complete list, in duplicate, of brands, type, and make of various equipment and materials proposed to be used. If the Contractor fails to submit such a list, or names of equipment which does not comply with the specifications, or if the manufacturers named are unsatisfactory, the Government reserves the right to reject same and to select satisfactory substitute materials. This selection shall be final and finding upon the Contractor, and the work shall be installed on this basis without change in contract price.

(b) To properly identify and to prove compliance with the requirements of the specifications, the Contractor shall give the following data for each product included in the list of materials.

Section heading of the specifications under which material is specified.

Manufacturer’s name and address.

Grade, type, trade or catalog number.

Size, capacity, and other pertinent data.

(c) All materials, fixtures, and equipment furnished and installed under this contract shall be new and of the best quality; shall be standard cataloged products or reputable manufacturers products or of special manufacture, satisfying completely the contract requirements.

(d) Similar items, unless otherwise specified herein or approved by the Contracting Officer, shall be the product of the same manufacturer, and those fulfilling the same requirements as to size and construction shall be identical.

(e) Substitutions and/or Approved Equal: Where particular make, brand or type of material or equipment is mentioned in these specifications, it is to denote quality standard of article desired, but does not restrict contractor to brand specified; however, any substitution must be met with approval of the Contracting Officer. Other products comparable in type, quality, utility, and price are acceptable if approved by the Contracting Officer. Burden of proof of equality shall rest with the Contractor. The Contracting Officer shall be sole judge of paralleled quality.

H.11 COOPERATION WITH OTHER CONTRACTORS

During the period of construction for the work covered by this contract, other contractors performing work for the Government may be operating concurrently at the site. To minimize interference and delay to the construction progress of all concerned, all contractors shall cooperate with each other and fully coordinate their construction operations. As far as practicable, all contractors performing work for the Government at the site shall have equal rights to the use of all referenced facilities. In a dispute regarding the use of such facilities, the matter shall be referred to the Contracting Officer.

H.12 PROPERTY DAMAGE LIABILITY INSURANCE

The Contractor shall ensure that the property damage liability insurance policy (or rider) required by FAR 52.228-5, Insurance–-Work on a Government Installation, is in full compliance with all the terms and conditions of this contract. The policy shall not contain any exclusions or exceptions that would limit or adversely affect the Government’s rights and remedies under any other clause in this contract or other Federal regulation or law. Should there be any exclusions or exceptions contained in the policy that limits or adversely affects the Government’s rights, the Contractor shall be responsible for the full amount of any damages that occur to the immediate facilities, adjacent facilities/property, and other Government property under the control of the Contractor due to fraud, negligence, vandalism, willful misconduct, or violation of Federal, state, or local safety regulations, building codes and laws. The Contractor shall have full responsibility and is liable for these facilities and properties until the Government has accepted the contract as being completed in full and a release from claims has been received from the Contractor.

For those areas where the Government has taken "beneficial occupancy" prior to completion and acceptance of the whole contract, the contractor shall not be responsible for those specific areas under Government control, except in such instances where damage occurs to those areas as a result of negligence, fraud, vandalism, willful misconduct, or violation of Federal, state, or local safety regulations, building codes, or laws in those areas under the control of the Contractor.

This liability and responsibility includes the activities of all the Contractor’s personnel, their subcontractors and suppliers.

H.13 SUBCONTRACTORS, OUTSIDE ASSOCIATES AND CONSULTANTS

Any subcontractors, outside associates or consultants required by the Contractor in connection with the services covered by the contract will be limited to individuals or firms that were specifically identified at time of award or agreed upon during negotiations. The Contractor shall obtain the Contracting Officer’s written consent before making any substitution for these individuals or firms.

H.14 ENERGY EFFICIENCY

As required in clause 52.223-15 Energy Efficiency in Energy-Consuming Products, the contractor shall only provide products that earn the ENERGY STAR label and meet ENERGY STAR specifications for energy efficiency.

The contractor is encouraged to visit http://www.energystar.gov for complete product specifications and updated lists of qualifying products.”

H.15 BIOBASED PRODUCTS REQUIREMENTS

(a) This procurement requires the use of biobased products to the extent that such products are reasonably available, meet agency or relevant industry performance standards, and are reasonably priced. Where available, these products should first be acquired from among qualified products that fall under the umbrella of items designated through the USDA BioPreferred SM Program.

(b) The Contractor must comply with the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C.

8102; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Federal Acquisition Regulation;

Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February, 2012 to provide biobased products.

(c) The Contractor shall utilize products and material made from biobased materials (e.g. biobased greases;

biobased hydraulic fluids, biobased absorbents) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).

(d) The following is an example list of products that may be used in this minor construction contract for which biobased products are available and the designated biobased content. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

Adhesive and Mastic Removers – 58 percent Asphalt and Tar Removers - 80 percent Asphalt Restorers – 68 percent Carpet – 7 percent Carpet and Upholstery Cleaners – 54 percent and Spot Removers – 7 percent Composite Panels – Acoustical – 37 percent; Interior Panels – 55 percent; Plastic Lumber – 23 percent;

Structural Interior Panels – 89 percent; Structural Wall Panels – 94 percent and Countertops and Solid Surface - _ 89 percent Concrete and Asphalt Cleaners – 70 percent Concrete and Asphalt Release Fluids – 87 percent Dust Suppressants – 85 percent Erosion Control Materials – 77 percent Floor Coverings (Non Carpet) – 91 percent General Purpose Cleaners - 54 percent Hand Soaps and Cleaners – 64 percent Industrial Cleaners – 41 percent Insulating Foam – 7 percent Leather, Vinyl, and Rubber Care Products – 55 percent Paint- Interior Paints and Coatings, Latex – 20 percent and Oil-based – 67 percent Paint Removers – 41 percent Roof Coatings – 20 percent Wastewater Systems Coatings –47 percent Water Tank Coatings – 59 percent Wood and Concrete Sealers – Membrane Concrete Sealers- 11 percent and Penetrating Liquids – 79 percent Wood and Concrete Stains – 39 percent

(e) The Contractor should also note that USDA-designated biobased products are available for purchase through the AbilityOne Program (formerly known as the Javits- Wagner-O’Day (JWOD) Program). Under this program, members of organizations including the National Industries for the Blind (NIB) and the National Institute for the Severely Disabled (SourceAmerica) offer products and services that are mandatory by Federal agencies. A search of the AbilityOne Program’s online catalog (www.ability.gov) indicated biobased products that include but are not limited to: cleaners (glass, hand, and multipurpose), graffiti removers, and sorbents.

(f) Reporting Requirements FAR Clause 52.223-2 requires:

• The contractor shall report their purchases of biobased products to the reporting portal within the System for Award Management (SAM).

• The report must be submitted no later than October 31 of each year during contract performance and at the end of contract performance.

End of this section

SECTION I – CONTRACT CLAUSES

I.1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2) (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: http://acquisition.gov

CLAUSE TITLE DATE

52.203-7 Anti-Kickback Procedures JUN 2020 52.203-12 Limitations on Payments to Influence Certain Federal Transactions JUN 2020 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform JUN 2020

Employees of Whistleblower Rights 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First Tier Subcontract Awards JUN 2020 52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and Certifications DEC 2014 52.204-23 Prohibition on Contracting for Hardware, Software, and Services NOV 2021 or Provided by Kaspersky Lab and Other Covered Entities 52.204-25 Prohibition on Contracting for Certain Telecommunications and NOV 2021

Surveillance Services or Equipment 52.204-27 Prohibition on a ByteDance Covered Application JUN 2023 52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition. DEC 2023 52.209-6 Protecting the Government’s Interest When Subcontracting with NOV 2021

Contractors Debarred, Suspended, or Proposed for Debarment 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations NOV 2015 52.213-4 Terms and Conditions Simplified Acquisitions (Other Than Commercial

Products and Commercial Services

MAY 2024

52.215-8 Order of Precedence-Uniform Contract Format OCT 1997 52.219-6 Notice of Total Small Business Set-Aside NOV 2020 52.219-28 Post-Award Small Business Program Representation MAR 2023 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards -Overtime Compensation. MAY 2018 52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JULY 2021 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance with Construction Wage Rate Requirements and MAY 2014

Related Regulations 52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2015 52.222-27 Affirmative Action Compliance Requirements for Construction APR 2015 52.222-35 Equal Opportunity for Veterans JUN 2020 52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020 52.222-50 Combating Trafficking in Persons NOV 2021 52.222-54 Employment Eligibility Verification MAY 2022 52.222-55 Minimum Wages Under Executive Order 13658 JAN 2022 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022 52.223-2 Reporting of Biobased Products Under Service and Construction

Contracts.

MAY 2024

52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-9 Estimate of Percentage of Recovered Material Content for EPA MAY 2008

Designated Items

CLAUSE TITLE DATE

52.223-20 Aerosols MAY 2024 52.223-21 Foams MAY 2024 52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.226-7 Drug-Free Workplace MAY 2024 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving. MAY 2024 52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-11 Pledges of Assets (Deviation) FEB 2021 52.228-12 Prospective Subcontractors Requests for Bonds DEC 2022 52.228-15 Performance and Payment Bonds-Construction (Deviation) JUN 2020 52.232-1 Payments APR 1984 52.232-5 Payments Under Fixed-Price Construction Contracts MAY 2014 52.232-16 Progress Payments NOV 2021 52.232-23 Assignment of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer-System for Award Management OCT 2018 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors MAR 2023 52.233-1 Disputes MAY 2014 52.233-3 Protest after Award AUG 1996

Note: In addition to the requirements of FAR 52.223-2; The contractor shall report to the environmental point of contact, with a copy to the Contracting Officer, on the product types and dollar value of any USDA-designated biobased products purchased by the contractor during the previous fiscal year.

• The report must be submitted no later than October 31 of each year during contract performance and at the end of contract performance.

• The environmental point of contact for all USDA Agencies is: Karen Zhang Karen.Zhang@dm.usda.gov Phone: 202-401-4747

• Biobased reporting shall be completed by following the instructions provided in the System for Award Management (SAM).

I.2 BUY AMERICAN - CONSTRUCTION MATERIALS (FAR 52.225-9) (OCT 2022)

a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-26 Preconstruction Conference FEB 1995 52.237-2 Protection of Government Buildings, Equipment, and Vegetation. APR 1984 52.243-5 Changes and Changed Conditions APR 1984 52.244-6 Subcontracts for Commercial Items (Deviation) FEB 2024 52.246-21 Warranty of Construction MAR 1994 52.253-1 Computer Generated Forms JUN 1991

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.

supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .