REV SOW_1P45A19 NR 1 Prop Replace_CGC RAYMOND EVANS 2021.docx

DOCX document 17 KB Posted

Attached to
DIVE CRANE SUPPORT PROP REPLACEMENT SVS FOR CGC RAYMOND EVANS Federal contract opportunity
Solicitation number
70Z080-21-Q-P45A1900
Issued by
Department of Homeland Security US Coast Guard

View the file

Other files for this federal contract opportunity

Other files attached to DIVE CRANE SUPPORT PROP REPLACEMENT SVS FOR CGC RAYMOND EVANS, newest first.
File Type Posted
1P45A19 MPC CARD 154-WPC_B10018.D.pdf PDF
FBO PROP DIVE CRANE SVS KEYWEST CGC EVANS.docx DOCX document
KEY WEST FL MAR 2020 15-4583.txt TXT text file
REPS CERTS DEC 2020.docx DOCX document
PO 1P45A19 FAR CLAUSE 52-212-5 OCT 2020 (003).doc DOC document
REVISED 1P45A19 WK ITEM 1 Prop Port SB Renew In Water.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

USCGC RAYMOND EVANS

PR# 70Z080-21-Q-P45A1900

BACKGROUND: The United States Coast Guard Surface Forces Logistics Center (SFLC) is coordinating the service to have the CGC RAYMOND EVANS’ Propellers (Port & Starboard) for an in water removal and installed. This work item describes the requirements for the Contractor to remove, install, and perform quality assurance checks during the process and conduct an underway full power trial to ensure the meticulous guidelines and measurements are IAW OEM and Coast Guard standards.

1. SCOPE:

Dates: Mar 15 – Mar 20, 2021 Location: Coast Guard Cutter RAYMOND EVANS, located in Key West, FL.

Time: 0800-2000 daily

a. Labor:

i. Commercial Contractors that are dive certified w/ at least 3+ years of commercial dive experience.

ii. Commercial Contractors will remove and install the Port and Starboard propellers while cutter is in the water IAW attached Work Item One (1) (attached).

iii. 8 hour workday X Six(6) days.

iv. Commercial Contractor will replace the underwater body Hull Zincs IAW maintenance procedure card B10018 (attached).

v. Commercial Contractors will coordinate Crane services as appropriate.

b. Travel

i. Travel Expenses including airfare, tool shipment, rental car, meals, and hotel. (If applicable)

c. Deliverable

i. Coast Guard SFLC will require contractor to submit written reports and time sheets of all their efforts and findings.

ii. After work is completed and in the presence of the Coast Guard inspector, the contractor shall be present during dockside testing and underway sea trials to ensure that satisfactory work was performed and no discrepancies are noted.

iii. Interface with CG Technicians and inspectors.

2. REQUIREMENTS: Commercial Contractor will remove and install the Port and Starboard propeller on the Coast Guard Cutter RAYMOND EVENS while the cutter remains in the water. The Contractor will provide all tools (outside of Government Furnished Tools), crane services, lifting and safety straps, eyebolts and safety equipment needed to successfully complete the propeller remove and installs. Work performed will meet CG drawings and technical standards, and maintain Coast Guard configuration.

3. POINTS OF CONTACT: CWO Scott Woods, (410) 590-7215, email at David.s.woods@uscg.mil and MKC David Ellis (352) 229-4428, email at David.a.ellis@uscg.mil.

File details come from the government source that posted it. Updated .