REVISED 1P45A19 WK ITEM 1 Prop Port SB Renew In Water.doc

DOC document 98 KB Posted

Attached to
DIVE CRANE SUPPORT PROP REPLACEMENT SVS FOR CGC RAYMOND EVANS Federal contract opportunity
Solicitation number
70Z080-21-Q-P45A1900
Issued by
Department of Homeland Security US Coast Guard

View the file

Other files for this federal contract opportunity

Other files attached to DIVE CRANE SUPPORT PROP REPLACEMENT SVS FOR CGC RAYMOND EVANS, newest first.
File Type Posted
1P45A19 MPC CARD 154-WPC_B10018.D.pdf PDF
REV SOW_1P45A19 NR 1 Prop Replace_CGC RAYMOND EVANS 2021.docx DOCX document
FBO PROP DIVE CRANE SVS KEYWEST CGC EVANS.docx DOCX document
KEY WEST FL MAR 2020 15-4583.txt TXT text file
REPS CERTS DEC 2020.docx DOCX document
PO 1P45A19 FAR CLAUSE 52-212-5 OCT 2020 (003).doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WTM_154WPB_MAR2021

WORK ITEM 1: Propeller, Port, Starboard, Renew, In Water

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to remove and install a new propeller on the port and starboard shaft, in water and to conduct a dock and sea trail after installation.

1.2 Government-furnished property.

MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/UNIT)

Y
**Propeller, RH
NSN: 2010-01-627-9761

PN: 531914

1ea.
$160,658.22
Y
**Propeller, LH
NSN: 2010-01-628-0276

PN: 531915

1ea.
$162,187.08
Y
**Kit, Installation Part-Replacement (see note 4.2)
NSN: 2010-01-629-4693

P/N: 950700

2kt.
$9,419.00
Y
*Kit, Propeller – Removal/Installation Tools and Equipment

(see note 4.3 for kit contents)

NSN: 2010-01-632-2198

P/N: 999120

1kt.
$22,970.00
N
Zinc Plate
NSN: 5340-01-627-8941

P/N: 950733

2ea
$327.24
N
Zinc Plate Mounting Bolts
P/N: 950756
8 ea
$5.20
N
Anodes, Zinc (stern tube)
NIIN: 01-644-5483

P/N: Z0020202H3n/a

16 ea
$50.00
N
Anodes, Zinc (B/T Gear case)
NIIN:12-356-1870

P/N: 1081226

1ea.
20.00
N
Anodes, Zinc (B/T Tunnel)
NIIN: 12-367-1265

P/N: 1010059

12ea.
200.00
N
Anodes, Zinc (Sea Chest Grate)
NIIN: 01-647-6179

P/N: GA-4

4ea.
50.00
N
Nut, Self-Locking
NIIN: 01-508-5774

P/N: 90715A145

2ea.
25.00
N
Screw, Prop Zinc Plate
NIIN: 01-634-0210

P/N: 950756

2ea
10.00
N
Screw, Sea Chest Grate Anode
NIIN: 01-619-7182

P/N: 93190A634

8ea.
25.00
N
Screw, Stern Tube Covers
NIIN: 01-616-1107

P/N: 90585A626

42ea.
150.00

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 154 WPC 204-301, Rev A, Equipment Removal Plan Coast Guard Drawing 154 WPC 243-201, Rev -, Main Propulsion Shafting A&D Coast Guard Drawing 154 WPC 243-202, Rev A, Shaft Locking Device Coast Guard Drawing 154 WPC 245-304, Rev -, Propeller Plans and Data Six Blade Propeller Coast Guard Drawing 154 WPC 245-303, Rev -, Propeller Plug Gauge and Shaft Ring Gauge Details for Propeller Shaft Coast Guard Publications

Coast Guard Technical Publication (TP) 8913, Sep 2014, Technical Repair Standard For Propellers Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements

Other References

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Stbd propeller removal. The Contractor shall accomplish the below specified tasks for the starboard propeller, using Coast Guard Drawings 154 WPC 204-301, 154 WPC 243-201, 154 WPC 243-202, 154 WPC 245-303 and 154 WPC 245-304 as guidance.

3.2.1 Port propeller removal. The Contractor shall accomplish the below specified tasks for the Port propeller, using Coast Guard Drawings 154 WPC 204-301, 154 WPC 243-201, 154 WPC 243-202, 154 WPC 245-303 and 154 WPC 245-304 as guidance.

3.2.2 The Contractor shall refer to Coast Guard Drawing 154 WPC 245-304, sheet 8 and TP-8913 chapters 2 and 3, for applicable propeller removal procedures using Government furnished equipment.

NOTE

While applying pressure with the hand pumps to release the propeller; the Contractor may have to go a little higher than expected pressure especially if the water is cold, basically apply pressure until the propeller pops down the shaft. Leave some threads on the nut so the prop doesn't come completely off.

3.2.3 The Contractor shall secure the propeller, maintaining positive control at all time, to prevent the propeller from falling to the bottom.

3.2.4 After removing the GFE propeller from its shipping crate, the Contractor shall inspect the GFE propeller’s shipping crate for re-use and submit a CFR. Safely package and secure the MTI propeller to the shipping crate to avoid any further damage during shipping, and turn over the removed propeller to the Coast Guard PA as an MTI item.

3.3 Stbd propeller installation. The Contractor shall install the starboard GFE propeller using Coast Guard Drawings 154 WPC 204-301, 154 WPC 243-201, 154 WPC 243-202, 154 WPC 245-303 and 154 WPC 245-304 as guidance.

3.3.1 Port propeller installation. The Contractor shall install the Port GFE propeller using Coast Guard Drawings 154 WPC 204-301, 154 WPC 243-201, 154 WPC 243-202, 154 WPC 245-303 and 154 WPC 245-304 as guidance.

3.3.2 The Contractor shall refer to Coast Guard Drawing 154 WPC 245-304, sheet 8 and TP-8913 chapter 7 , for applicable propeller installation procedures using Government furnished equipment.

3.4 Propeller zinc plate renewal. The Contractor shall renew both the port and starboard propeller zinc plates (Item 3) and the four associated mounting bolts (item 8) as shown in Coast Guard Drawing 154 WPC 245-304, using TP 8913 chapter 3, as reference.

3.5 Underwater Zinc Anode Replace. The Contractor shall renew the underwater body hull zincs IAW Maintence Procedure Card B10018.D.

3.6 Dock trials. The Contractor shall conduct dock trials to demonstrate the material readiness of the ship for sea trials. Additionally, all onboard tests conducted after installation and prior to sea trials to prove proper installation and satisfactory operation of equipment shall be conducted. Ensure that the dock trials are begun no later than 12 hours prior to the scheduled sea trials.

3.6.1 During dock trials, Contractor personnel shall observe tests under their cognizance and make such adjustments and repairs that are in scope, as required.

3.7 Sea trials. As soon as possible after completion of the dock trials, the Contractor shall coordinate performance of the seal trials to prove all repairs.

3.7.1 The Contractor shall have representatives on board the cutter to observe the trials for the purpose of observing whether or not the repairs are satisfactory.

3.7.2 The sea trials shall be carried out in free route, away from other shipping, as designated by the COR.

3.8 Post-trial examination. After the completion of the sea trial, the Contractor shall perform a careful and thorough examination of parts of the repaired machinery, as designated by the COR. If any part of the ship or its equipment fails to meet contractual requirements during trials, perform additional trials after corrective measures have been taken.

NOTES

1. Examples of dock trials include conducting cold (pre-lightoff) and hot checks, cycling machinery (rudders, BPU, turning gear, fin stabilizers), and conducting any post-docking shaft alignment verification checks. This time may also be used to on-load fuel, if needed for operations.

2. The conditions of the trials will be determined largely by the character of the work that has been performed in each case, and as designated by the COR. A full power trial should be run at this time unless the COR elects to defer this run until all new machinery parts are properly run-in or the training status of the crew permits full power operation without undue hazard.

3. This examination may be conducted by the Engineer Officer of the ship, in which case he shall report the results of the examination to the COR, fully describing any defects or improper conditions found.

4. Representatives of manufacturers who have furnished ship components may be invited to witness trials subject to approval of the CO or OINC of the ship.

4. NOTES

4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all tests.

4.2 Contents of Government Furnished “Kit, Installation Part-Replacement” See Coast Guard Drawing 154WPC 245-304.

QTY per prop
PC#
PN
Description
Matl
Price Ea
Price per set
1
3
950733
Anode Zinc Plate
Zinc
$413.26
$413.26
1
4
950724
Cover Plate
2205 SS
$83.54
$83.54
1
5
950726
Retaining Ring
304L SS
$180.50
$180.50
1
6
950746
"O" Ring Fwd End FW Cap
Buna-N
$27.84
$27.84
1
7
950744
"O" Ring Aft End FW Cap
Buna-N
$27.16
$27.16
4
8
950756
M16 X 2 X 50mm SS SHCS
SS
$5.70
$22.80
3
9
950755
M10 X 1.5 X 25mm SS SHCS
SS
$1.46
$4.37
2
10
950714
SS Hex "O" Ring Plug
SS
$41.54
$83.09
3
11
950738
Lifting Eye Bolt
Carbon Steel
$60.98
$182.93
6
12
950736
Plug - Lifting Hole
NiBrAl
$73.72
$442.32
1
13
950748
"O" Ring-Hub Fwd Propeller
Buna-N
$11.34
$11.34
3
14
950759
Anti Vibration Lock Washer
SS
$10.76
$32.28
8
15
950757
M6 X 1 X 20mm SS SHCS
SS
$1.28
$10.26

4.3 Contents of Government Furnished “Kit, Propeller – Removal/Installation Tools and Equipment”

QTY
PC#
PN
Description
Matl
Price Ea
Price per set
999130
SPANNER WRENCH
950742
SPACER]INSTALLATION
999122
HYD. INSTALLATION NUT
999124
SKF HYDRAULIC PUMP 15,000 PSI
999125
ENERPAC HYDRAULIC PUMP 10,000 PSI
999142
MCDANIEL GAGE
999144
HYD.SWIVEL FITTING
999146
HYD. STRAIGHT FITTING
999148
WASHER]HYD. FITTING
999135
SKF QUICK CONNECTING NIPPLE
999136
SKF QUICK CONNECTING COUPLING
999137
10-FOOT WEAT HYDRAULIC HOSE
999128
INSTRUCTION MANUAL

INST. ROD ] HYD. INST. NUT(5/8 DIA X 9