Pacific Avenue Corridor Improvement Project - Apparent Bid Results

This document is an apparent bid results summary issued by the City of Long Beach Public Works Department for the Pacific Avenue Corridor Improvement Project (R-7280) as of October 5, 2026. The project encompasses comprehensive street improvements including pavement construction and removal, curb and sidewalk installation, traffic signal installations at twelve intersections, communications and fiber optic system infrastructure, landscaping, and bus stop facilities. The scope of work includes 78 line items with varied quantities, including approximately 6,700 cubic yards of asphalt pavement removal, 7,300 tons of asphalt pavement construction, 12,600 square feet of curb ramps, 11,600 linear feet of communication conduit, and installation of thirteen bus stop shelters. Two responsive bids were received for the project.

Sully-Miller Contracting Company submitted the lowest responsive bid at $17,117,131.00, compared to All American Asphalt's bid of $17,524,425.71, resulting in a bid difference of $407,294.71. Sully-Miller's bid includes a 51% self-performance rate with 49% subcontracted work totaling $8,448,899.00, while All American Asphalt's bid reflects a 52% self-performance rate with 48% subcontracted work totaling $8,435,479.90. Both bidders were deemed responsive to the bid requirements. The detailed bid tab summary indicates line-item pricing across all project components, with significant variation between bidders on certain items such as unclassified excavation, asphalt removal, and traffic signal installations.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPARENT BID RESULTS

Pacific Avenue Corridor Improvement Project

R-7280 | 10/5/2026

BIDDER TOTAL BASE BID RESPONSIVENESS

VEN0000705 - Sully-Miller Contracting Company $17,117,131.00 Responsive VEN0002193 - All American Asphalt $17,524,425.71 Responsive

Public Works Department 411 W. Ocean Blvd, 5th Floor

Long Beach, CA 90802

Item Number

Description UOM Quantity Unit Cost Extended Cost Unit Cost Extended Cost

1 MOBILIZATION & DEMOBILIZATION (5% MAX. OF TOTAL BID) LS 1 821,624.00 821,624.00 281,103.21 281,103.21

2 CLASS "A" FIELD OFFICE LS 1 175,000.00 175,000.00 125,950.00 125,950.00

3 SCHEDULING (BASELINE & BI-WEEKLY UPDATES) LS 1 20,000.00 20,000.00 712,530.00 712,530.00 4 STORMWATER BEST MANAGEMENT PRACTICES (BMP'S) LS 1 100,000.00 100,000.00 144,310.00 144,310.00 5 TRAFFIC CONTROL (EST. 250 WORKING DAYS) LS 1 491,600.00 491,600.00 555,642.00 555,642.00

6 MONUMENT RESTORATION & PERPETUATION (SURVEY MARKER & CORNER RECORD FILE) LS 1 55,000.00 55,000.00 21,999.50 21,999.50

7 ADJUST SURVEY MONUMENT CASING & COVER (WELL) EA 27 1,200.00 32,400.00 1,210.00 32,670.00

8 CONSTRUCTION STAKING LS 1 87,500.00 87,500.00 118,885.00 118,885.00

9 LA METRO FLAGGING, COORDINATION, & TRAINING LS 1 11,000.00 11,000.00 272,793.00 272,793.00

10 CLEARING AND GRUBBING LS 1 100,000.00 100,000.00 138,976.00 138,976.00

11 VEGETATION REMOVAL (309 W 33RD ST) SF 600 1.70 1,020.00 1.84 1,104.00

12 UNCLASSIFIED EXCAVATION CY 800 176.00 140,800.00 411.25 329,000.00

13 REMOVE EXISTING TREE EA 11 1,050.00 11,550.00 1,100.00 12,100.00

14 REMOVE EXISTING FULL DEPTH ASPHALT CONCRETE (AC) PAVEMENT (R&R, DIGOUTS, AND

SLOT PAVING) CY 6700 83.00 556,100.00 126.19 845,473.00

15 REMOVE EXISTING CONCRETE (SIDEWALK, CURBS, CURB AND GUTTER, CURB RAMPS,

DRIVEWAY APPROACHES, ALLEY INTERSECTIONS) CY 500 410.00 205,000.00 411.50 205,750.00

16 REMOVE EXISTING BUS BENCH EA 16 700.00 11,200.00 1,100.00 17,600.00

17 REMOVE EXISTING BUS SHELTER EA 1 10,000.00 10,000.00 2,200.00 2,200.00

18 COLD MILL 2"AC PAVEMENT SF 490000 0.52 254,800.00 0.29 142,100.00

19 REMOVE & SALVAGE EXISTING STREET LIGHT EA 15 8,096.00 121,440.00 8,834.00 132,510.00 20 CONSTRUCT 6" CRUSHED MISCELLANEOUS BASE (CMB) CY 700 197.00 137,900.00 141.00 98,700.00

21 CONSTRUCT TYPE II SLURRY SEAL TON 5 1,300.00 6,500.00 6,923.00 34,615.00

22 CONSTRUCT 2" ARHM, CLASS GG-C TON 9300 252.81 2,351,133.00 156.50 1,455,450.00

23 CONSTRUCT FULL DEPTH AC SLOT PAVEMENT PER CLB STANDARD PLAN NO. 116 (W PER

PLAN) TON 100 475.00 47,500.00 558.50 55,850.00

24 CONSTRUCT AC PAVEMENT (C2-PG-64-10) TON 7300 145.00 1,058,500.00 142.55 1,040,615.00 25 CONSTRUCT CEMENT STABILIZED PULVERIZED BASE (CSPB) CY 7700 31.50 242,550.00 68.85 530,145.00 26 CONSTRUCT 6" PCC CURB PER SPPWC STANDARD PLAN NO. 120-3, TYPE A1-6 LF 1200 46.00 55,200.00 24.56 29,472.00

27 CONSTRUCT 6" PCC MOUNTABLE CURB PER SPPWC STANDARD PLAN NO. 121-3, TYPE B1-6,

MODIFIED PER DETAIL ON CD-001 LF 1700 38.00 64,600.00 37.26 63,342.00

28 CONSTRUCT 6" PCC CURB AND GUTTER PER SPPWC STANDARD PLAN NO. 120-3, TYPE A2-

6, W=24" LF 1100 91.00 100,100.00 42.30 46,530.00

29 CONSTRUCT 6" PCC CURB AND GUTTER PER SPPWC STANDARD PLAN NO. 120-3, TYPE A2-

6, W=12" LF 1700 76.00 129,200.00 31.60 53,720.00

30 CONSTRUCT 4" THICK PCC SIDEWALK PER SPPWC STANDARD PLAN NO. 112-2 SF 10000 14.50 145,000.00 9.65 96,500.00 31 CONSTRUCT PCC CURB RAMP PER CLB STANDARD PLAN NO. 122, CASE PER PLAN SF 12600 17.25 217,350.00 21.00 264,600.00

PW-26-787 R-7280 Pacific Avenue Corridor Improvement Project - Bid Tab Summary 10/5/26

VEN0000705 - Sully-Miller Contracting Company

VEN0002193 - All American Asphalt

Description UOM Quantity Unit Cost Extended Cost Unit Cost Extended Cost

PW-26-787 R-7280 Pacific Avenue Corridor Improvement Project - Bid Tab Summary 10/5/26

VEN0000705 - Sully-Miller Contracting Company

VEN0002193 - All American Asphalt

32 CONSTRUCT 6" THICK PCC DRIVEWAY OR ALLEY APPROACH PER CLB STANDARD PLAN NO.

105 OR 106 SF 2400 19.50 46,800.00 14.80 35,520.00

33 CONSTRUCT STAMPED CONCRETE PER DETAIL ON SHEET CD-001, 4" THICK SF 3000 22.00 66,000.00 13.80 41,400.00 34 CONSTRUCT PCC MEDIAN CURB SCUPPER PER DETAIL ON SHEET CD-001 EA 9 3,000.00 27,000.00 648.50 5,836.50 35 CONSTRUCT 10" PCC BUS STOP STREET PAD PER CLB STANDARD PLAN NO. 113 SF 1300 60.00 78,000.00 21.90 28,470.00 36 ADJUST WATER VALVE BOX AND COVER PER CLB STANDARD PLAN NO. 126 EA 47 1,850.00 86,950.00 1,100.00 51,700.00

37 ADJUST GAS VALVE BOX AND COVER EA 7 1,850.00 12,950.00 1,100.00 7,700.00

38 ADJUST MANHOLE FRAME AND COVER TO GRADE EA 8 2,000.00 16,000.00 1,375.00 11,000.00

39 ADJUST SEWER MANHOLE FRAME AND COVER EA 4 2,000.00 8,000.00 1,375.00 5,500.00

40 ADJUST TO GRADE EXISTING PULL BOX EA 15 1,250.00 18,750.00 1,030.50 15,457.50

41 ADJUST EXISTING DECORATIVE BIKE RACK TO GRADE EA 5 600.00 3,000.00 2,200.00 11,000.00

42 SIGNING & STRIPING LS 1 460,200.00 460,200.00 405,259.00 405,259.00

43 TRAFFIC SIGNAL - PACIFIC AVE & W 19TH STREET LS 1 500,000.00 500,000.00 440,658.00 440,658.00 44 TRAFFIC SIGNAL - PACIFIC AVE & W 20TH STREET LS 1 501,298.00 501,298.00 552,497.00 552,497.00 45 TRAFFIC SIGNAL - PACIFIC AVE & W 21ST STREET LS 1 568,823.00 568,823.00 626,178.00 626,178.00 46 TRAFFIC SIGNAL - PACIFIC AVE & W HILL STREET LS 1 481,167.00 481,167.00 530,530.00 530,530.00 47 TRAFFIC SIGNAL - PACIFIC AVE & W 23RD STREET LS 1 548,379.00 548,379.00 603,870.00 603,870.00 48 TRAFFIC SIGNAL - PACIFIC AVE & W BURNETT ST LS 1 522,061.00 522,061.00 575,153.00 575,153.00 49 TRAFFIC SIGNAL - PACIFIC AVE & W 25TH STREET LS 1 539,829.00 539,829.00 594,540.00 594,540.00 50 TRAFFIC SIGNAL - PACIFIC AVE & W WILLOW STREET LS 1 295,606.00 295,606.00 328,054.00 328,054.00 51 TRAFFIC SIGNAL - PACIFIC AVE & W 27TH STREET LS 1 158,409.00 158,409.00 178,350.00 178,350.00 52 TRAFFIC SIGNAL - PACIFIC AVE & W 28TH STREET LS 1 193,525.00 193,525.00 216,667.00 216,667.00 53 TRAFFIC SIGNAL - PACIFIC AVE & W 29TH STREET LS 1 518,384.00 518,384.00 571,140.00 571,140.00 54 TRAFFIC SIGNAL - PACIFIC AVE & W SPRING STREET LS 1 286,207.00 286,207.00 317,798.00 317,798.00 55 TRAFFIC SIGNAL - PACIFIC AVE & W 31ST STREET LS 1 503,263.00 503,263.00 554,641.00 554,641.00 56 TRAFFIC SIGNAL - PACIFIC AVE & W WARDLOW RD LS 1 205,369.00 205,369.00 229,590.00 229,590.00 57 FURNISH AND INSTALL NEW COMMUNICATION 4" SCHEDULE 80 PVC CONDUIT LF 11600 92.93 1,077,988.00 101.40 1,176,240.00

58 FURNISH AND INSTALL NEW COMMUNICATION #6E OR EXISTING PULLBOX

REPLACEMENT/RETROFIT EA 20 4,288.00 85,760.00 4,679.00 93,580.00

59 NEW CHRISTY N48E VAULTS EA 14 5,920.00 82,880.00 6,459.00 90,426.00

60 FURNISH AND INSTALL NEW 288-STRAND SMFO CABLE INTO NEW/EXISTING CONDUIT LF 11100 10.35 114,885.00 11.30 125,430.00 61 FURNISH AND INSTALL NEW 12-STRAND SMFO CABLE INTO NEW/EXISTING CONDUIT LF 500 4.16 2,080.00 4.54 2,270.00 62 FUSION SPLICE (MID-SPAN 288 SMFO - 12 SMFO) IN SPLICE ENCLOSURE EA 14 2,273.00 31,822.00 2,480.00 34,720.00

63 NEW NODE SWITCH (ETHERWAN EX 78924-COMPLETE ALL CONNECTIONS FOR INTENDED

OPERATION INCLUDING SFP'S, PATCH CABLES, AND SC-LC CONNECTORS) EA 14 4,697.00 65,758.00 5,125.00 71,750.00

64 FURNISH AND INSTALL 7-WAY MICRODUCTS LF 11500 7.78 89,470.00 8.50 97,750.00

65 COMMUNICATIONS AND FIBER OPTIC SYSTEM TESTING LS 1 14,243.00 14,243.00 15,541.00 15,541.00 66 FURNISH AND INSTALL NEW #10 GREEN TRACER WIRE LF 12000 0.81 9,720.00 0.88 10,560.00

Description UOM Quantity Unit Cost Extended Cost Unit Cost Extended Cost

PW-26-787 R-7280 Pacific Avenue Corridor Improvement Project - Bid Tab Summary 10/5/26

VEN0000705 - Sully-Miller Contracting Company

VEN0002193 - All American Asphalt

67 FURNISH AND INSTALL NEW 12-PORT FIBER PATCH PANEL (FPP) AND COMPLETED

CONNECTIONS TO DROP CABLE, PIGTAILS, AND FPP EA 14 2,273.00 31,822.00 2,480.00 34,720.00

68 REMOVE EXISTING PULL BOX EA 37 1,818.00 67,266.00 1,984.00 73,408.00

69 VERTICAL ROCK BED SF 110 28.00 3,080.00 29.75 3,272.50

70 FLAT ROCK BED SF 700 21.00 14,700.00 22.00 15,400.00

71 LANDSCAPE BOULDERS EA 12 520.00 6,240.00 550.00 6,600.00

72 LANDSCAPE PLANTING LS 1 26,000.00 26,000.00 27,500.00 27,500.00

73 MAINTENANCE AND PLANT ESTABLISHMENT LS 1 8,800.00 8,800.00 9,349.75 9,349.75

74 IRRIGATION SYSTEM LS 1 80,000.00 80,000.00 104,784.25 104,784.25

75 INSTALL BUS STOP SHELTER (13') EA 13 50,000.00 650,000.00 36,478.50 474,220.50

76 INSTALL BUS BENCH & SIGN EA 1 5,500.00 5,500.00 20,349.50 20,349.50

77 REMOVE EXISTING SIGN & INSTALL NEIGHBORHOOD MONUMENT SIGN EA 2 48,025.00 96,050.00 40,809.00 81,618.00

78 PORTLAND CEMENT FOR CSPB TON 630 231.00 145,530.00 244.75 154,192.50

Bid Total 17,117,131.00 17,524,425.71

Amount Subcontracted 8,448,899.00 8,435,479.90 Percent Subcontracted 49% 48% Self-Performance Rate 51% 52%