Procurement_of_Goods_and_Services-Intake_Form_-_Jud_Youell.msg
MSG file 176 KB Posted
- Attached to
- Spanaway Lake Fishing Pier Replacement Design
- Solicitation number
- 2026-RFQ-127
- Issued by
- Pierce County, Tacoma City, Washington
About this file
This is a Procurement of Goods and Services Intake Form submitted by Pierce County Parks & Recreation Department for the Spanaway Lake Fishing Pier Replacement Design project. Pierce County intends to hire a firm to complete pier design services for the Spanaway Lake Park Fishing Pier located at 14905 Bresemann Blvd S, Spanaway, WA. The scope of work includes completing construction documents (drawings, specifications, and cost estimates), assisting with permit and regulatory submittals, providing bid assistance, and offering construction administration services. The project encompasses design, permitting, bidding support, and construction administration for a new fishing pier that reached end-of-life and sustained watercraft damage in 2021. Preliminary design work is complete and permits are in process. The contract is project-specific with an anticipated start date of July 1, 2026, and pier construction is scheduled for July through September 2027. One contract will be awarded from this procurement.
The budget for this procurement is $200,000.00. The contract will be awarded through a standard evaluation process in OpenGov using a 100-point scoring model with criteria including submittal presentation (10 points), qualifications and experience (40 points), capacity and availability (15 points), approach to work (25 points), and references (10 points). Qualified vendors must have a minimum of five years' experience designing in-water piers, knowledge of in-water and shoreline permitting requirements for local, state, tribal, and federal agencies, and experience with Cultural Resource Assessments including archaeological field investigations. The procurement is not federally funded. The existing on-call contract expires in May 2026, creating an immediate need for continuation of the project. The Contract Specialist is Jeanette Peters, and additional procurement notices should be sent to Jud Youell.
Text of this file
Procurement of Goods and Services-Intake Form - Jud Youell
| From |
| pierce_county@piercecountywa.gov |
| To |
| PCPURCHASING |
| Recipients |
| PCPURCHASING@piercecountywa.gov |
Pierce County
Procurement of Goods and Services-Intake Form
Entry Details
GENERAL INFORMATION
Division Parks & Recreation
Department Contract Specialist Jeanette Peters
Email jeanette.peters@piercecountywa.gov
Procurement Title Spanaway Lake Fishing Pier Replacement
Purchase Type Services
Is this Federally Funded? No
Project Summary Pierce County is intending to hire a firm to complete pier design for the Spanaway Lake Park Fishing Pier.
Project Background The pier had reached its end-of-life and was damaged by watercraft in 2021. A subsequent structural analysis determined that the pier and support pilings should be replaced. Preliminary design work is complete and permits are in process.
CONTRACT TERM
Will this result in a project-specific or a blanket contract? Project-specific
If this will be a blanket contract, what is the initial term of contract ? Two Years
What is the budget for this procurement? $200,000.00
Anticipated number of resulting contracts: One
ANTICIPATED TIMELINE
Desired Contract Start Date 7/1/2026
Explain immediate need if there are time constraints The existing PPW On-call contract expires 05/2026. This contract is needed to continue moving the project forward.
SCOPE OF WORK
Scope of Project Complete construction documents for a new fishing Pier at Spanaway Lake Park.
Assist with permit and regulatory submittals and questions.
Bid assistance and construction administration services
Objective(s) Complete design, permitting, bidding and assist with construction administration for a new pier. Work include, but is not limited to construction drawing and specification preparation, cost estimating, Deliverables Deliverables include, but are not limited to:
Complete construction documents including drawings, specifications and estimates.
assist with permit applications and requests for information.
assist with construction administration. Note that this may include Cultural Resource construction site monitoring and other activities required by permitting agencies.
Other tasks as required to construct a new pier.
Minimum Requirements 5-years' minimum experience designing in-water piers; in-water and shoreline permitting requirements and processing including Shoreline and critical areas for local, state, tribal and federal agencies; Cultural Resource Assessments including archaeological field investigations and construction site monitoring.
Schedule(s) Pier construction - 07/2027 - 09/2027
VENDOR QUESTIONNAIRE
Questions Method List all questions in OpenGov
EVALUATION / SCORING
Evaluation Process Standard Process in OG
Scoring Model Points
1. Scoring Criteria Name Submittal Presentation
1. Total Points Possible for this Criteria 10
1. Brief description of the factors to be considered when evaluating this criteria The information was presented in a clear, logical manner, and is well-organized. All required information was provided.
2. Scoring Criteria Name Qualifications & Experience
2. Total Points Possible for this Criteria 40
2. Brief description of the factors to be considered when evaluating this criteria. How the qualifications of the firm and key individuals meet the needs of the County.
3. Scoring Criteria Name Capacity & Availability
3. Total Points Possible for this Criteria 15
3. Brief description of the factors to be considered when evaluating this criteria. The firm has the size, resources, and commitment to provide timely services based on the County needs
4. Scoring Criteria Name Approach to Work
4. Total Points Possible for this Criteria 25
4. Brief description of the factors to be considered when evaluating this criteria. The firm’s approach to work, including compliance with requirements, innovative offerings, services offered, and other related matters
5. Scoring Criteria Name Referrences
5. Total Points Possible for this Criteria 10
5. Brief description of the factors to be considered when evaluating this criteria. References either submitted with the qualifications or known to the County.
7. Will there be a Phase 2 Review Process No
Additional contacts who should receive a procurement notice? Yes
Name Jud Youell
Email judson.youell@piercecountywa.gov
Will someone else need to be added as an "Approver" in OpenGov? No
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .