NCCDC Moisture Intrusion Project Summary
This specification document details a comprehensive construction project issued by the State of Delaware, Office of Management and Budget (OMB), Division of Facilities Management for moisture intrusion remediation at the New Castle County Detention Center located at 963 Centre Road, Wilmington, Delaware. The project scope encompasses exterior renovation at water infiltration locations into the basement, including new exterior concrete slabs sloping away from the building, new flashing within brick veneer, seals around foundation wall pipe penetrations, removal and replacement of all pipe insulation, and replacement of existing chiller and air handler units serving the basement and kitchen. Bids will be received until 1:00 PM on June 4, 2026, with public opening and reading at 2:00 PM the same day at the Haslet Armory in Dover, Delaware. A mandatory pre-bid meeting is scheduled for May 18, 2026, at 10:00 AM at the Ferris Maintenance shop (959 Centre Road, Wilmington). Contract documents are available from R G Architects, LLC for a non-refundable fee of $50.00 per set. The anticipated physical work schedule is approximately six weeks. The contract will utilize the AIA A101-2017 Standard Form of Agreement with a stipulated sum basis of payment, and successful bidders must submit bid security equivalent to ten percent of the bid amount, with performance and payment bonds equal to one hundred percent of the contract price required upon execution.
Bidders must demonstrate compliance with prevailing wage requirements under Delaware Code Title 29, Chapter 69, including submission of subcontractor lists identifying all trades, craft training compliance affidavits, and employee drug testing programs compliant with OMB Regulation 4104. The contract includes a $10,000 General Owner's Allowance for owner-elected changes, with any unused allowance returned via credit change order at project conclusion. No specific funding source or contract price is identified in the specification documents. All materials and equipment must be new and of superior quality without damage or imperfections; used equipment is prohibited except where drawings specifically authorize reuse. The project carries a two-year warranty period from the date of Substantial Completion, during which the contractor must provide maintenance services and emergency response within specified timeframes. Contractors must maintain a fully capable service facility within forty-five miles of the project site with emergency service response within eight hours for critical issues and three working days for normal service requests.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OMB-MC3705000126-Ad1.pdf | ||
| OMB-MC3705000126-wage.pdf | ||
| OMB-MC3705000126-RFP.pdf | ||
| OMB-MC3705000126-dwgs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF DELAWARE
OMB/DIVISION OF FACILTIES MANAGEMENT
CONTRACT No. MC3705000126
SPECIFICATIONS
FOR
MOISTURE INTRUSION
AT
NEW CASTLE COUNTY DETENTION CENTER
963 CENTRE ROAD
WILMINGTON, DELAWARE 19805
PREPARED
BY
R G ARCHITECTS, LLC.
200 WEST MAIN STREET
MIDDLETOWN, DELAWARE 19709
RGA PROJECT NO. #23058
ISSUED FOR BIDDING
APRIL 2026
NOT FOR BIDDING PURPOSES
NCCDC MOISTURE INTRUSION
MC3705000126
R G ARCHITECTS, LLC PROJECT TITLE PAGE
23058 00 01 01 - 1
STATE OF DELAWARE
OMB/DIVISION OF FACILTIES MANAGEMENT
CONTRACT No. MC3705000126
SPECIFICATIONS
FOR
MOISTURE INTRUSION
AT
NEW CASTLE COUNTY DETENTION CENTER
963 CENTRE ROAD
WILMINGTON, DELAWARE 19805
PREPARED
BY
R G ARCHITECTS, LLC.
200 WEST MAIN STREET
MIDDLETOWN, DELAWARE 19709
RGA PROJECT NO. #23058
ISSUED FOR BIDDING
APRIL 2026
MOISTURE INTRUSION NCCDC
PROJECT TITLE PAGE R G ARCHITECTS, LLC
00 01 01 - 2 23058
THIS PAGE INTENTIONALLY LEFT BLANK
R G ARCHITECTS, LLC SEALS PAGE
23058 00 01 07 - 1
SECTION 00 01 07
SEALS PAGE
1.1 DESIGNS PROFESSIONALS OF RECORD SEAL
A. ARCHITECT:
1. GERALD D. ROZANSKI, AIA
2. (LICENSE #5995)
3. R G ARCHITECTS, LLC.
4. 200 W. MAIN STREET
MIDDLETOWN, DE 19709
5. (302) 376-8100
6. Responsible for Division 00-32 Sections as applicable
Except where indicated as prepared by other design professionals of record.
B. HVAC/ELECTRICAL ENGINEER:
1. JOHN R. FARINA, P.E.
2. (LICENSE #13559)
3. DEDC, LLC.
4. 315 SOUTH CHAPEL STREET
NEWARK, DE 19711
5. (302) 738-7172
6. Responsible for Division 22-26 Sections as applicable
Except where indicated as prepared by other design professionals of record.
SEALS PAGE R G ARCHITECTS, LLC
00 01 07 - 2 23058
NCCDC MOISTURE INTRUSTION
R G ARCHITECTS, LLC TABLE OF CONTENTS
23058 00 01 10 - 1
SECTION 00 01 10
TABLE OF CONTENTS
A. Specifications for this project are arranged in accordance with the Construction Specification Institute numbering system and format. Section numbering is discontinuous and all numbers not appearing in the Table of Contents are not used for this Project.
B. DOCUMENTS BOUND HEREWITH
DIVISION 00 – PROCUREMENT AND CONTRACT REQUIREMENTS
INTRODUCTORY INFORMATION
00 01 01 – PROJECT TITLE PAGE
00 01 07 – SEALS PAGE
00 01 10 – TABLE OF CONTENTS
00 01 15 – LIST OF DRAWING SHEETS
PROCUREMENT REQUIREMENTS
00 11 16 – INVITATION TO BID
00 21 13 – INSTRUCTIONS TO BIDDERS
00 41 13 – BID FORM
00 43 13 – BID BOND
CONTRACTING REQUIREMENTS
00 52 13 – STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR
(SAMPLE AIA A101-2017)
(SAMPLE AIA A101-2017 – EXHIBIT A)
00 54 13 – SUPPLEMENT TO AGREEMENT BETWEEN OWNER & CONTRACTOR A101-2017
00 54 14 – SUPPLEMENT TO A101-2017 – EXHIBIT A – INSURANCE & BONDS
00 61 13.13 – PERFORMANCE BOND
00 61 13.16 – PAYMENT BOND
00 62 76 – APPLICATION AND CERTIFICATE FOR PAYMENT FORMS
(SAMPLE AIA G702 & G703)
00 72 13 – GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION A201-2017
(SAMPLE AIA A201-2017)
00 73 13 – SUPPLEMENTARY GENERAL CONDITIONS A201 – 2017
00 73 13.10 – SCHEDULING GUIDELINES
00 73 46 – WAGE DETERMINATION SCHEDULE
MOSITURE INTRUSION NCCDC
TABLE OF CONTENTS R G ARCHITECTS, LLC
00 01 10 - 2 23058
00 81 13 – GENERAL REQUIREMENTS
00 81 14 – DRUG TESTING FORMS
00 81 15 – AFFIDAVIT OF CRAFT TRAINING COMPLIANCE
DIVISION 01 – GENERAL REQUIREMENTS
01 10 00 – SUMMARY
01 21 00 – ALLOWANCES
01 21 16 – ALLOWANCE AUTHORIZATION FORM
01 23 00 - ALTERNATES
01 25 00 – SUBSTITUTION PROCEDURES
01 26 00 – CONTRACT MODIFICATION PROCEDURES
01 29 00 – PAYMENT PROCEDURES
01 31 00 – PROJECT MANAGEMENT AND COORDINATION
01 32 00 – CONSTRUCTION PROGRESS DOCUMENTATION
01 32 33 – PHOTOGRAPHIC DOCUMENTATION
01 33 00 – SUBMITTAL PROCEDURES
01 33 01 – SUBMITTAL COVER SHEET
01 40 00 – QUALITY REQUIREMENTS
01 50 00 – TEMPORARY FACILITIES AND CONTROLS
01 60 00 – PRODUCT REQUIREMENTS
01 73 00 – EXECUTION
01 73 29 – CUTTING AND PATCHING
01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 77 00 – CLOSEOUT PROCEDURES
01 78 39 – PROJECT RECORD DOCUMENTS
01 79 00 – DEMONSTRATION AND TRAINING
01 91 13 – GENERAL COMMISSIONING REQUIREMENTS
DIVISION 02 – EXISTING CONDITIONS
02 41 19 – SELECTIVE DEMOLITION
NCCDC MOISTURE INTRUSTION
R G ARCHITECTS, LLC TABLE OF CONTENTS
23058 00 01 10 - 3
DIVISION 03 – CONCRETE
03 30 00 – CAST-IN-PLACE CONCRETE
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 65 00 – FLEXIBLE FLASHING SELF-ADHERING TYPE 304 STAINLESS STEEL
07 65 10 – FLEXIBLE FLASHING DRAINING PLANE SYSTEM
07 92 00 – JOINT SEALANTS
DIVISION 22 – PLUMBING
22 10 05 – PLUMBING PIPING
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 17 – SLEEVES AND SLEEVE SEALS FOR HVAC PIPING
23 05 48 – VIBRATION AND SEISMIC CONTROLS FOR HVAC
23 05 53 – IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 05 93 – TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 19 – HVAC PIPING INSULATION
23 09 50 – BUILDING AUTOMATION SYSTEM (BAS) GENERAL
23 09 51 – BAS BASIC MATERIALS, INTERFACE DEVICES, AND SENSORS
23 09 52 – BAS OPERATOR INTERFACES
23 09 53 – BAS FIELD PANELS
23 09 54 – BAS COMMUNICATION DEVICES
23 09 55 – BAS SOFTWARE AND PROGRAMMING
23 09 58 – SEQUENCE OF OPERATION
23 09 59 – BAS SYSTEM COMMISSIONING
23 21 13 – HYDRONIC PIPING
23 21 14 – HYDRONIC SPECIALTIES
23 73 14 – INDOOR AIR HANDLING UNITS
23 81 27 – SPLIT-SYSTEM HEATING AND COOLING
DIVISION 26 – ELECTRICAL
26 05 05 – SELECTIVE DEMOLITION FOR ELECTRICAL
26 05 19 – LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
MOSITURE INTRUSION NCCDC
TABLE OF CONTENTS R G ARCHITECTS, LLC
00 01 10 - 4 23058
26 05 26 – GROUNDING AND BONDING
26 05 29 – HANGERS AND SUPPORTS
26 05 33.13 – CONDUIT FOR ELECTRICAL SYSTEMS
26 05 33.16 – BOXES FOR ELECTRICAL SYSTEMS
26 05 53 – IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 05 83 – WIRING CONNECTIONS
26 27 26 – WIRING DEVICES
26 28 13 – FUSES
26 28 16.13 – ENCLOSED CIRCUIT BREAKERS
26 28 16316 – ENCLOSED SWITCHES
DIVISION 31 – EARTHWORK
31 20 00 – EARTH MOVING
END OF SECTION
R G ARCHITECTS, LLC LIST OF DRAWING SHEETS
23058 00 01 15 - 1
LIST OF DRAWING SHEETS
T10-1 TITLE SHEET
T10-2 LEGENDS & ABBREVIATIONS & CODE SUMMARY
ARCHITECTURAL
A10-1 OVERALL FIRST FLOOR PLAN
D11-1 FLOOR PLANS – DEMOLITION
A11-1 FLOOR PLANS – NEW WORK
A20-1 EXTERIOR ELEVATIONS
A30-1 WALL SECTIONS
A31-1 SECTIONS & DETAILS
A31-2 FLASHING DETAILS
MECHANICAL
M00-0 MECHANICAL NOTES, LEGENDS & ABBREVIATIONS
M10-1 DEMOLITION FIRST FLOOR & GROUND LEVEL PLANS
M10-2 DEMOLITION BASEMENT PLANS
M11-1 FIRST FLOOR GROUND LEVEL PLANS
M11-2 BASEMENT PLANS
M11-3 FLOOR PLANS UNIT REPLACEMENT
M50-0 MECHANICAL SCHEDULES & DETAILS
ELECTRICAL
E00-0 ELECTRICAL TITLE SHEET
E10-1 ELECTRICAL BASEMENT DEMOLITION PLAN – PHASE 1
E10-2 ELECTRICAL FIRST FLOOR DEMOLITION PLAN – PHASE 1
E11-1 ELECTRICAL BASEMENT NEW WORK PLAN – PHASE 1
E11-2 ELECTRICAL GROUND FLOOR NEW WORK PLAN – PHASE 1
E11-3 ELECTRICAL DEMOLITION & NEW WORK PLAN – PHASE 2
LIST OF DRAWING SHEETS R G ARCHITECTS, LLC
00 01 15 - 2 23058
R G ARCHITECTS, LLC INVITATION TO BID
23058 00 11 16 - 1
SECTION 00 11 16
INVITATION TO BID
Sealed bids for OMB/DFM Contract No. MC3705000126 Project Name: NCCDC Moisture Intrusion will be received by the State of Delaware, Office of Management and Budget, Division of Facilities Management, by way of the Bonfire Portal at https://DFM.bonfirehub.com until 1:00pm local time on June 4, 2026. Bidder bears the risk of late submission.
Bids will be opened and read aloud at 2:00pm local time on June 4, 2026, at the Haslet Armory, 122 Martin Luther King Blvd. S., Dover, DE 19901.
The project involves the exterior renovation at water infiltration locations into the basement. Renovation consists of new exterior concrete slab sloping away from the building, new flashing inside of brick veneer, and new seals around foundation wall pipe penetrations. In addition, scope includes removing and replacing all pipe insulation.
Scope also includes the replacement of the existing chiller and air handler unit that serves the existing basement and existing kitchen.
A MANDATORY Pre-Bid Meeting will be held on May 18, 2026, at 10:00am local time at the Ferris Maintenance shop located at 959 Centre Road, Wilmington, DE 19805 for the purpose of establishing the listing of subcontractors and to answer questions. Representatives of each party to any Joint Venture must attend this meeting. ATTENDANCE OF THIS MEETING IS A PREREQUISITE FOR BIDDING
ON THIS CONTRACT.
Contract documents may be obtained at the office of R G Architects, upon receipt of $50.00 per set/non-refundable. Checks are to be made payable to “R G Architects, LLC.”
Bidders will not be subject to discrimination on the basis of race, creed, color, sex, sexual orientation, gender identity or national origin in consideration of this award, and Minority Business Enterprises, Disadvantaged Business Enterprises, Women-Owned Business Enterprises and Veteran-Owned Business Enterprises will be afforded full opportunity to submit bids on this contract. Each bid must be accompanied by a bid security equivalent to ten percent of the bid amount and all additive alternates. The successful bidder must post a performance bond and payment bond in a sum equal to 100 percent of the contract price upon execution of the contract. The Owner reserves the right to reject any or all bids and to waive any informalities therein. The Owner may extend the time and place for the opening of the bids from that described in the advertisement, with not less than two calendar days’ notice by certified delivery, facsimile machine or other electronic means to those bidders’ receiving plans.
INVITATION TO BID R G ARCHITECTS, LLC
00 11 16 - 2 23058
R G ARCHITECTS, LLC INSTRUCTIONS TO BIDDERS
23058 00 21 13 - 1
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS
TABLE OF ARTICLES
1. GENERAL
2. BIDDER’S REPRESENTATION
3. BIDDING DOCUMENTS
4. BIDDING PROCEDURES
5. CONSIDERATION OF BIDS
6. POST-BID INFORMATION
7. PERFORMANCE BOND AND PAYMENT BOND
8. FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR
INSTRUCTIONS TO BIDDERS R G ARCHITECTS, LLC
00 21 13 - 2 23058
ARTICLE 1: GENERAL
1.1 DEFINITIONS
1.1.1 Whenever the following terms are used, their intent and meaning shall be interpreted as follows:
1.2 STATE: The State of Delaware.
1.3 AGENCY: Contracting State Agency as noted on cover sheet.
1.4 DESIGNATED OFFICIAL: The agent authorized to act for the Agency.
1.5 BIDDING DOCUMENTS: Bidding Documents include the Bidding Requirements and the proposed Contract Documents. The Bidding Requirements consist of the Advertisement for Bid, Invitation to Bid, Instructions to Bidders, Supplementary Instructions to Bidders (if any), General Conditions, Supplementary General Conditions, General Requirements, Special Provisions (if any), the Bid Form (including the Non-collusion Statement), and other sample bidding and contract forms. The proposed Contract Documents consist of the form of Agreement between the Owner and Contractor, as well as the Drawings, Specifications (Project Manual) and all Addenda issued prior to execution of the Contract.
1.6 CONTRACT DOCUMENTS: The Contract Documents consist of the, Instructions to Bidders, Supplementary Instructions to Bidders (if any), General Conditions, Supplementary General Conditions, General Requirements, Special Provisions (if any), the form of agreement between the Owner and the Contractor, Drawings (if any), Specifications (Project Manual), and all addenda.
1.7 AGREEMENT: The form of the Agreement shall be AIA Document A101, Standard Form of Agreement between Owner and Contractor where the basis of payment is a STIPULATED SUM. In the case of conflict between the instructions contained therein and the General Requirements herein, these General Requirements shall prevail.
1.8 GENERAL REQUIREMENTS (or CONDITIONS): General Requirements (or conditions) are instructions pertaining to the Bidding Documents and to contracts in general. They contain, in summary, requirements of laws of the State; policies of the Agency and instructions to bidders.
1.9 SPECIAL PROVISIONS: Special Provisions are specific conditions or requirements peculiar to the bidding documents and to the contract under consideration and are supplemental to the General Requirements. Should the Special Provisions conflict with the General Requirements, the Special Provisions shall prevail.
1.10 ADDENDA: Written or graphic instruments issued by the Owner/Architect prior to the execution of the contract which modify or interpret the Bidding Documents by additions, deletions, clarifications or corrections.
1.11 BIDDER OR VENDOR: A person or entity who formally submits a Bid for the material or Work contemplated, acting directly or through a duly authorized representative who meets the requirements set forth in the Bidding Documents.
1.12 SUB-BIDDER: A person or entity who submits a Bid to a Bidder for materials or labor, or both for a portion of the Work.
R G ARCHITECTS, LLC INSTRUCTIONS TO BIDDERS
23058 00 21 13 - 3
1.13 BID: A complete and properly executed proposal to do the Work for the sums stipulated therein, submitted in accordance with the Bidding Documents.
1.14 BASE BID: The sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents as the base, to which Work may be added or from which Work may be deleted for sums stated in Alternate Bids (if any are required to be stated in the bid).
1.15 ALTERNATE BID (or ALTERNATE): An amount stated in the Bid, where applicable, to be added to or deducted from the amount of the Base Bid if the corresponding change in the Work, as described in the Bidding Documents is accepted.
1.16 UNIT PRICE: An amount stated in the Bid, where applicable, as a price per unit of measurement for materials, equipment or services or a portion of the Work as described in the Bidding Documents.
1.17 SURETY: The corporate body which is bound with and for the Contract, or which is liable, and which engages to be responsible for the Contractor's payments of all debts pertaining to and for his acceptable performance of the Work for which he has contracted.
1.18 BIDDER'S DEPOSIT: The security designated in the Bid to be furnished by the Bidder as a guaranty of good faith to enter into a contract with the Agency if the Work to be performed or the material or equipment to be furnished is awarded to him.
1.19 CONTRACT: The written agreement covering the furnishing and delivery of material or work to be performed.
1.20 CONTRACTOR: Any individual, firm or corporation with whom a contract is made by the Agency.
1.21 SUBCONTRACTOR: An individual, partnership or corporation which has a direct contract with a contractor to furnish labor and materials at the job site, or to perform construction labor and furnish material in connection with such labor at the job site.
1.22 CONTRACT BOND: The approved form of security furnished by the contractor and his surety as a guaranty of good faith on the part of the contractor to execute the work in accordance with the terms of the contract.
1.23 CUSTOM FABRICATION: As defined in 29 Del. C. § 6902, the term “custom fabrication” means the offsite fabrication, assembly, or other production of non-standard goods or materials, including components, fixtures or parts thereof, specifically for a public works project. Such goods and materials shall include those used in the following trades or systems: (1) Plumbing or pipe fitting systems, including heating, ventilating, air-conditioning, refrigeration systems, sheet metal or other duct systems; (2) Electrical systems; (3) Mechanical insulation work; (4) Ornamental iron work; and (5) Commercial signage that does not attempt or appear to direct the movement of traffic on highways or roadways or interfere with, imitate, or resemble any official traffic sign, signal or device.
ARTICLE 2: BIDDER'S REPRESENTATION
2.1 PRE-BID MEETING
2.1.1 A pre-bid meeting for this project will be held at the time and place designated. Attendance at this meeting is a pre-requisite for submitting a Bid, unless this requirement is specifically waived elsewhere in the Bid Documents.
INSTRUCTIONS TO BIDDERS R G ARCHITECTS, LLC
00 21 13 - 4 23058
2.2 By submitting a Bid, the Bidder represents that:
2.2.1 The Bidder has read and understands the Bidding Documents and that the Bid is made in accordance therewith.
2.2.2 The Bidder has visited the site, become familiar with existing conditions under which the Work is to be performed, and has correlated the Bidder’s personal observations with the requirements of the proposed Contract Documents.
2.2.3 The Bid is based upon the materials, equipment, and systems required by the Bidding Documents without exception.
2.3 JOINT VENTURE REQUIREMENTS
2.3.1 For Public Works Contracts, each Joint Venturer shall be qualified and capable to complete the Work with their own forces.
2.3.2 Included with the Bid submission, and as a requirement to bid, a copy of the executed Joint Venture Agreement shall be submitted and signed by all Joint Venturers involved.
2.3.3 All required Bid Bonds, Performance Bonds, Material and Labor Payment Bonds must be executed by both Joint Venturers and be placed in both of their names.
2.3.4 All required insurance certificates shall name both Joint Venturers.
2.3.5 Both Joint Venturers shall sign the Bid Form.
2.3.6 Both Joint Venturers shall include their Federal E.I. Number with the Bid.
2.3.7 In the event of a mandatory Pre-bid Meeting, each Joint Venturer shall have a representative in attendance.
2.3.8 Due to exceptional circumstances and for good cause shown, one or more of these provisions may be waived at the discretion of the State.
2.4 ASSIGNMENT OF ANTITRUST CLAIMS
2.4.1 As consideration for the award and execution by the Owner of this contract, the Contractor hereby grants, conveys, sells, assigns and transfers to the State of Delaware all of its right, title and interests in and to all known or unknown causes of action it presently has or may now or hereafter acquire under the antitrust laws of the United States and the State of Delaware, relating to the particular goods or services purchased or acquired by the Owner pursuant to this contract.
ARTICLE 3: BIDDING DOCUMENTS
3.1 COPIES OF BID DOCUMENTS
3.1.1 Bidders may obtain complete sets of the Bidding Documents from the Architectural/Engineering firm designated in the Advertisement or Invitation to Bid in the number and for the deposit sum, if any, stated therein.
3.1.2 Bidders shall use complete sets of Bidding Documents for preparation of Bids. The issuing Agency nor the Architect assumes no responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
R G ARCHITECTS, LLC INSTRUCTIONS TO BIDDERS
23058 00 21 13 - 5
3.1.3 Any errors, inconsistencies or omissions discovered shall be reported to the Architect immediately.
3.1.4 The Agency and Architect may make copies of the Bidding Documents available on the above terms for the purpose of obtaining Bids on the Work. No license or grant of use is conferred by issuance of copies of the Bidding Documents.
3.2 INTERPRETATION OR CORRECTION OF BIDDING DOCUMENTS
3.2.1 The Bidder shall carefully study and compare the Bidding Documents with each other, and with other work being bid concurrently or presently under construction to the extent that it relates to the Work for which the Bid is submitted, shall examine the site and local conditions, and shall report any errors, inconsistencies, or ambiguities discovered to the Architect.
3.2.2 Bidders or Sub-bidders requiring clarification or interpretation of the Bidding Documents shall make a written request to the Architect at least seven days prior to the date for receipt of Bids. Interpretations, corrections and changes to the Bidding Documents will be made by written Addendum. Interpretations, corrections, or changes to the Bidding Documents made in any other manner shall not be binding.
3.2.3 The apparent silence of the specifications as to any detail, or the apparent omission from it of detailed description concerning any point, shall be regarded as meaning that only the best commercial practice is to prevail and only material and workmanship of the first quality are to be used. Proof of specification compliance will be the responsibility of the Bidder.
3.2.4 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for all permits, labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work.
3.2.5 The Owner will bear the costs for all impact and user fees associated with the project.
3.3 SUBSTITUTIONS
3.3.1 The materials, products and equipment described in the Bidding Documents establish a standard of quality, required function, dimension, and appearance to be met by any proposed substitution. The specification of a particular manufacturer or model number is not intended to be proprietary in any way. Substitutions of products for those named will be considered, providing that the Vendor certifies that the function, quality, and performance characteristics of the material offered is equal or superior to that specified. It shall be the Bidder's responsibility to assure that the proposed substitution will not affect the intent of the design, and to make any installation modifications required to accommodate the substitution.
3.3.2 Requests for substitutions shall be made in writing to the Architect at least ten days prior to the date of the Bid Opening. Such requests shall include a complete description of the proposed substitution, drawings, performance and test data, explanation of required installation modifications due the substitution, and any other information necessary for an evaluation. The burden of proof of the merit of the proposed substitution is upon the proposer. The Architect’s decision of approval or disapproval shall be final. The Architect is to notify Owner prior to any approvals.
3.3.3 If the Architect approves a substitution prior to the receipt of Bids, such approval shall be set forth in an Addendum. Approvals made in any other manner shall not be binding.
INSTRUCTIONS TO BIDDERS R G ARCHITECTS, LLC
00 21 13 - 6 23058
3.3.4 The Architect shall have no obligation to consider any substitutions after the Contract award.
3.4 ADDENDA
3.4.1 Addenda will be mailed or delivered to all who are known by the Architect to have received a complete set of the Bidding Documents.
3.4.2 Copies of Addenda will be made available for inspection wherever Bidding Documents are on file for that purpose.
3.4.3 No Addenda will be issued later than 2 calendar days prior to the date for receipt of Bids except an Addendum withdrawing the request for Bids or one which extends the time or changes the location for the opening of bids.
3.4.4 Each bidder shall ascertain prior to submitting his Bid that they have received all Addenda issued, and shall acknowledge their receipt in their Bid in the appropriate space. Not acknowledging an issued Addenda could be grounds for determining a bid to be non-responsive.
ARTICLE 4: BIDDING PROCEDURES
4.1 PREPARATION OF BIDS
4.1.1 Submit the bids on the Bid Forms included with the Bidding Documents.
4.1.2 Submit the original Bid Form for each bid. Bid Forms may be removed from the project manual for this purpose.
4.1.3 Execute all blanks on the Bid Form in a non-erasable medium (typewriter or manually in ink).
4.1.4 Where so indicated by the makeup on the Bid Form, express sums in both words and figures, in case of discrepancy between the two, the written amount shall govern.
4.1.5 Interlineations, alterations or erasures must be initialed by the signer of the Bid.
4.1.6 BID ALL REQUESTED ALTERNATES AND UNIT PRICES, IF ANY. If there is no change in the Base Bid for an Alternate, enter “No Change”. The Contractor is responsible for verifying that they have received all addenda issued during the bidding period. Work required by Addenda shall automatically become part of the Contract.
4.1.7 Make no additional stipulations on the Bid Form and do not qualify the Bid in any other manner.
4.1.8 Each copy of the Bid shall include the legal name of the Bidder and a statement whether the
Bidder is a sole proprietor, a partnership, a corporation, or any legal entity, and each copy shall be signed by the person or persons legally authorized to bind the Bidder to a contract.
A Bid by a corporation shall further give the state of incorporation and have the corporate seal affixed. A Bid submitted by an agent shall have a current Power of Attorney attached, certifying agent's authority to bind the Bidder.
4.1.9 Bidder shall complete the Non-Collusion Statement form included with the Bid Forms and include it with their Bid.
4.1.10 In the construction of all Public Works projects for the State of Delaware or any agency thereof, preference in employment of laborers, workers or mechanics shall be given to bona
R G ARCHITECTS, LLC INSTRUCTIONS TO BIDDERS
23058 00 21 13 - 7 fide legal citizens of the State who have established citizenship by residence of at least 90 days in the State.
4.1.11 Each bidder shall include a signed Affidavit for the Bidder certifying compliance with OMB
Regulation 4104 - “Regulations for the Drug Testing of Contractor and Subcontractor Employees Working on “Large Public Works Projects.” “Large Public Works” is based upon the current threshold required for bidding Public Works as set by the Purchasing and Contracting Advisory Council.
4.2 BID SECURITY
4.2.1 All bids shall be accompanied by a deposit of either a good and sufficient bond to the agency for the benefit of the agency, with corporate surety authorized to do business in this State, the form of the bond and the surety to be approved by the agency, or a security of the bidder assigned to the agency, for a sum equal to at least 10% of the bid plus all add alternates, or in lieu of the bid bond a security deposit in the form of a certified check, bank treasurer’s check, cashier’s check, money order, or other prior approved secured deposit assigned to the State. The bid bond need not be for a specific sum, but may be stated to be for a sum equal to 10% of the bid plus all add alternates to which it relates and not to exceed a certain stated sum, if said sum is equal to at least 10% of the bid. The Bid Bond form used shall be the standard OMB form (attached). The bid bond may be an electronic bond and need not be transmitted as a paper document.
4.2.2 The Agency has the right to retain the bid security of Bidders to whom an award is being considered until either a formal contract has been executed and bonds have been furnished or the specified time has elapsed so the Bids may be withdrawn or all Bids have been rejected.
4.2.3 In the event of any successful Bidder refusing or neglecting to execute a formal contract and bond within 20 days of the awarding of the contract, the bid bond or security deposited by the successful bidder shall be forfeited.
4.3 SUBCONTRACTOR LIST
4.3.1 In accordance with Title 29, Chapter 69, Section 6962(d)(10)b of the Delaware Code, each Bidder shall submit with their Bid a completed List of Sub-Contractors included with the Bid Form. NAME ONLY ONE SUBCONTRACTOR FOR EACH TRADE. The bidder must list in each category the full name and address (City & State) of the sub-contractor that the Bidder will be using to perform the work and provide material for that subcontractor category. Should the Bidder’s listed subcontractor intend to provide any of their subcontractor category of work through a third-tier contractor, the Bidder shall list that third-tier contractor’s full name and address (City & State). If the Bidder intends to perform any category of work itself, it must list its full name and address. For clarification, if the Bidder intends to perform the work themselves, the Bidder may not insert “not applicable”, “N/A”, “self” or anything other than its own full name and address (City & State). To do so shall cause the bid to be rejected. In addition, the failure to produce a completed subcontractor list with the bid submittal shall cause the bid to be rejected. If you have more than three (3) third-tier contractors to report in any subcontractor category, print out additional page(s) containing the appropriate category, complete the rest of your list of third-tier contractors for that category, notate the addition in parentheses as (CONTINUATION) next to the subcontractor category and an asterisk (*) next to any additional third-tier contractors, and submit it with your bid.
4.3.2 It is the responsibility of the Contractor to ensure that their Subcontractors are in compliance with the provisions of this law. Also, if a Contractor elects to list themselves as a Subcontractor for any category, they must specifically name themselves on the Bid Form
00 21 13 - 8 23058 and be able to document their capability to act as Subcontractor in that category in accordance with this law.
4.4 AFFIDAVIT OF CONTRACTOR QUALIFICATIONS
4.4.1 In accordance with Title 29, Chapter 69, Section 6962(d)(10)b.3 of the Delaware Code, each Bidder shall submit with their Bid the Affidavit of Contractor Qualifications certifying that the Bidder will abide by the contractor’s qualifications outlined in the construction bid specifications for the duration of the contract term. After a contract has been awarded the successful bidder shall not substitute another subcontractor whose name was submitted on the Subcontractor Form except for the reasons in the statute and not without written consent from the awarding agency. Failure to utilize the subcontractors on the list will subject the successful bidder to penalties as outlined in the General Requirements Section 5.2 of the contract.
4.5 AFFIDAVIT OF CRAFT TRAINING COMPLIANCE
4.5.1 In accordance with Title 29, Chapter 69, Section 6962(c)(13) of the Delaware Code, contractors and subcontractors must provide craft training for journeyman and apprentice levels if all of the following apply:
A. A project meets the prevailing wage requirement under Title 29, Chapter 69, Section 6960 of the Delaware Code.
B. The contractor employs 10 or more total employees.
C. The project is not a federal highway project
Failure to provide required craft training on the project may subject the successful contractor and/or subcontractor(s) to penalties as outlined in Title 29, Chapter 69, Section 6962(c)(13) of the Delaware Code.
Bidders shall submit the Affidavit of Craft Training Compliance prior to contract execution.
4.6 EQUALITY OF EMPLOYMENT OPPORTUNITY ON PUBLIC WORKS
4.6.1 During the performance of this contract, the contractor agrees as follows:
A. The Contractor will not discriminate against any employee or applicant for employment because of race, creed, sex, color, sexual orientation, gender identity or national origin. The Contractor will take affirmative action to ensure the applicants are employed, and that employees are treated during employment, without regard to their race, creed, sex, color, sexual orientation, gender identity or national origin. Such action shall include, but not be limited to, the following:
Employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places available to employees and applicants for employment notices to be provided by the contracting agency setting forth this nondiscrimination clause.
B. The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, creed, sex, color, sexual orientation, gender identity or national origin."
4.7 PREVAILING WAGE REQUIREMENT
23058 00 21 13 - 9
4.7.1 Wage Provisions: For renovation and new construction projects whose costs exceed the thresholds contained in Delaware Code, Title 29, Section 6960, the minimum wage rates for various classes of laborers and mechanics shall be as determined by the Department of Labor, Division of Industrial Affairs of the State of Delaware.
4.7.2 The employer shall pay all mechanics and labors employed directly upon the site of work, or engaged in custom fabrication work, as that term is defined in Article 1.23 herein and as also as defined in 29 Del. C § 6902 and described in 29 Del. C. § 6960(b), regardless of where the work is performed, unconditionally and not less often than once a week and without subsequent deduction or rebate on any account, the full amounts accrued at time of payment, computed at wage rates not less than those stated in the specifications, regardless of any contractual relationship which may be alleged to exist between the employer and such laborers and mechanics.
4.7.3 As per 29 Del. C. § 6960(b), the scale of the wages to be paid must be posted by the employer in a prominent and easily accessible place at the site of the work. There may be withheld from the employer so much of accrued payments as may be considered necessary by the Department of Labor to pay laborers and mechanics employed by the employer the difference between the rates of wages required by the contract to be paid laborers and mechanics on the work and rates of wages received by such laborers and mechanics to be remitted to the Department of Labor for distribution upon resolution of any claims.
4.7.4 Every contract based upon these specifications shall contain a stipulation that sworn payroll information, as required by the Department of Labor, be furnished weekly. The Department of Labor shall keep and maintain the sworn payroll information for a period of 6 months from the last day of the work week covered by the payroll.
4.8 SUBMISSION OF BIDS
4.8.1 Enclose the Bid, the Bid Security, and any other documents required to be submitted with the Bid in a sealed opaque envelope. Address the envelope to the party receiving the Bids.
Identify with the project name, project number, and the Bidder's name and address. If the Bid is sent by mail, enclose the sealed envelope in a separate mailing envelope with the notation "BID ENCLOSED" on the face thereof. The State is not responsible for the opening of bids prior to bid opening date and time that are not properly marked.
4.8.2 Deposit Bids at the designated location prior to the time and date for receipt of bids indicated in the Advertisement for Bids. Bids received after the time and date for receipt of bids will be marked “LATE BID” and returned.
4.8.3 Bidder assumes full responsibility for timely delivery at location designated for receipt of bids.
4.8.4 Oral, telephonic or telegraphic bids are invalid and will not receive consideration.
4.8.5 Withdrawn Bids may be resubmitted up to the date and time designated for the receipt of
Bids, provided that they are then fully in compliance with these Instructions to Bidders.
4.9 MODIFICATION OR WITHDRAW OF BIDS
4.9.1 Prior to the closing date for receipt of Bids, a Bidder may withdraw a Bid by personal request and by showing proper identification to the Architect. A request for withdraw by letter or fax, if the Architect is notified in writing prior to receipt of fax, is acceptable. A fax directing a modification in the bid price will render the Bid informal, causing it to be ineligible for consideration of award. Telephone directives for modification of the bid price shall not be permitted and will have no bearing on the submitted proposal in any manner.
00 21 13 - 10 23058
4.9.2 Bidders submitting Bids that are late shall be notified as soon as practicable and the bid shall be returned.
4.9.3 A Bid may not be modified, withdrawn or canceled by the Bidder during a thirty (30) day period following the time and date designated for the receipt and opening of Bids, and Bidder so agrees in submitting their Bid. Bids shall be binding for 30 days after the date of the Bid opening.
ARTICLE 5: CONSIDERATION OF BIDS
5.1 OPENING/REJECTION OF BIDS
5.1.1 Unless otherwise stated, Bids received on time will be publicly opened and will be read aloud. An abstract of the Bids will be made available to Bidders.
5.1.2 The Agency shall have the right to reject any and all Bids. A Bid not accompanied by a required Bid Security or by other data required by the Bidding Documents, or a Bid which is in any way incomplete or irregular is subject to rejection.
5.1.3 If the Bids are rejected, it will be done within thirty (30) calendar day of the Bid opening.
5.2 COMPARISON OF BIDS
5.2.1 After the Bids have been opened and read, the bid prices will be compared and the result of such comparisons will be made available to the public. Comparisons of the Bids may be based on the Base Bid plus desired Alternates. The Agency shall have the right to accept Alternates in any order or combination.
5.2.2 The Agency reserves the right to waive technicalities, to reject any or all Bids, or any portion thereof, to advertise for new Bids, to proceed to do the Work otherwise, or to abandon the Work, if in the judgment of the Agency or its agent(s), it is in the best interest of the State.
5.2.3 An increase or decrease in the quantity for any item is not sufficient grounds for an increase or decrease in the Unit Price.
5.2.4 The prices quoted are to be those for which the material will be furnished F.O.B. Job Site and include all charges that may be imposed during the period of the Contract.
5.2.5 No qualifying letter or statements in or attached to the Bid, or separate discounts will be considered in determining the low Bid except as may be otherwise herein noted. Cash or separate discounts should be computed and incorporated into Unit Bid Price(s).
5.3 DISQUALIFICATION OF BIDDERS
5.3.1 An agency shall determine that each Bidder on any Public Works Contract is responsible before awarding the Contract. Factors to be considered in determining the responsibility of a Bidder include:
A. The Bidder’s financial, physical, personnel or other resources including
Subcontracts;
B. The Bidder’s record of performance on past public or private construction projects, including, but not limited to, defaults and/or final adjudication or
R G ARCHITECTS, LLC INSTRUCTIONS TO BIDDERS
23058 00 21 13 - 11 admission of violations of the Prevailing Wage Laws in Delaware or any other state;
C. The Bidder’s written safety plan;
D. Whether the Bidder is qualified legally to contract with the State;
E. Whether the Bidder supplied all necessary information concerning its responsibility; and, F. Any other specific criteria for a particular procurement, which an agency may establish; provided however, that, the criteria be set forth in the Invitation to Bid and is otherwise in conformity with State and/or Federal law.
5.3.2 If an agency determines that a Bidder is nonresponsive and/or nonresponsible, the determination shall be in writing and set forth the basis for the determination. A copy of the determination shall be sent to the affected Bidder within five (5) working days of said determination.
5.3.3 In addition, any one or more of the following causes may be considered as sufficient for the disqualification of a Bidder and the rejection of their Bid or Bids.
5.3.3.1 More than one Bid for the same Contract from an individual, firm or corporation under the same or different names.
5.3.3.2 Evidence of collusion among Bidders.
5.3.3.3 Unsatisfactory performance record as evidenced by past experience.
5.3.3.4 If the Unit Prices are obviously unbalanced either in excess or below reasonable cost analysis values.
5.3.3.5 If there are any unauthorized additions, interlineation, conditional or alternate bids or irregularities of any kind which may tend to make the Bid incomplete, indefinite or ambiguous as to its meaning.
5.3.3.6 If the Bid is not accompanied by the required Bid Security and other data required by the Bidding Documents.
5.3.3.7 If any exceptions or qualifications of the Bid are noted on the Bid Form.
5.4 ACCEPTANCE OF BID AND AWARD OF CONTRACT
5.4.1 A formal Contract shall be executed with the successful Bidder within twenty (20) calendar days after the award of the Contract.
5.4.2 Per Section 6962(d)(13)a., Title 29, Delaware Code, “The contracting agency shall award any public works contract within thirty (30) days of the bid opening to the lowest responsive and responsible Bidder, unless the Agency elects to award on the basis of best value, in which case the election to award on the basis of best value shall be stated in the Invitation To Bid. Any public school district and its board shall award public works contracts in accordance with this section’s requirements except it shall award the contract within 60 days of the bid opening.”
00 21 13 - 12 23058
5.4.3 Each Bid on any Public Works Contract must be deemed responsive by the Agency to be considered for award. A responsive Bid shall conform in all material respects to the requirements and criteria set forth in the Contract Documents and specifications.
5.4.4 The Agency shall have the right to accept Alternates in any order or combination, and to determine the low Bidder on the basis of the sum of the Base Bid, plus accepted Alternates.
5.4.5 The successful Bidder shall execute a formal contract, submit the required Insurance
Certificate, and furnish good and sufficient bonds, unless specifically waived in the General Requirements, in accordance with the General Requirement, within twenty (20) days of official notice of contract award. The successful Bidder shall provide, at least two business days prior to contract execution, copies of the Employee Drug Testing Program for the Bidder and all listed Subcontractors. Bonds shall be for the benefit of the Agency with surety in the amount of 100% of the total contract award. Said Bonds shall be conditioned upon the faithful performance of the contract. Bonds shall remain in affect for period of two (2) years after the date of the Certificate of Final Payment.
5.4.6 If the successful Bidder fails to execute the required Contract, Bond and all required information, as aforesaid, within twenty (20) calendar days after the date of official Notice of the Award of the Contract, their Bid guaranty shall immediately be taken and become the property of the State for the benefit of the Agency as liquidated damages, and not as a forfeiture or as a penalty. Award will then be made to the next lowest qualified Bidder of the Work or readvertised, as the Agency may decide.
5.4.7 Each bidder shall supply with its bid its taxpayer identification number (i.e., federal employer identification number or social security number) and should the vendor be awarded a contract, such vendor shall provide to the agency the taxpayer identification license numbers of such subcontractors. Such numbers shall be provided on the later of the date on which such subcontractor is required to be identified or the time the contract is executed.
The successful Bidder shall provide to the agency to which it is contracting, within 30 days of entering into such public works contract, copies of all Delaware Business licenses of subcontractors and/or independent contractors that will perform work for such public works contract. However, if a subcontractor or independent contractor is hired or contracted more than 20 days after the Bidder entered the public works contract the Delaware Business license of such subcontractor or independent contractor shall be provided to the agency within 10 days of being contracted or hired.
5.4.8 The Bid Security shall be returned to the successful Bidder upon the execution of the formal contract. The Bid Securities of unsuccessful bidders shall be returned within thirty (30) calendar days after the opening of the Bids.
ARTICLE 6: POST-BID INFORMATION
6.1 CONTRACTOR’S QUALIFICATION STATEMENT
6.1.1 Bidders to whom an award of a Contract is under consideration shall, if requested by the
Agency, submit a properly executed AIA Document A305, Contractor’s Qualification Statement, unless such a statement has been previously required and submitted.
6.2 Bidders to whom an award of a Contract has been made must produce their Delaware
Business License before the Contract can be executed.
ARTICLE 7: PERFORMANCE BOND AND PAYMENT BOND
7.1 BOND REQUIREMENTS
23058 00 21 13 - 13
7.1.1 The cost of furnishing the required Bonds, that are stipulated in the Bidding Documents, shall be included in the Bid.
7.1.2 If the Bidder is required by the Agency to secure a bond from other than the Bidder’s usual sources, changes in cost will be adjusted as provide in the Contract Documents.
7.1.3 The Performance and Payment Bond forms used shall be the standard OMB forms
(attached). The Performance Bond and/or the Payment Bond may be electronic bonds and need not be transmitted as paper documents.
7.2 TIME OF DELIVERY AND FORM OF BONDS
7.2.1 The bonds shall be dated on or after the date of the Contract.
7.2.2 The Bidder shall require the attorney-in-fact who executes the required bonds on behalf of the surety to affix a certified and current copy of the power of attorney.
ARTICLE 8: FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR
8.1 Unless otherwise required in the Bidding Documents, the Agreement for the Work will be written on AIA Document A101, Standard Form of Agreement Between Owner and Contractor Where the Basis of Payment is a Stipulated Sum.
00 21 13 - 14 23058
R G ARCHITECTS, LLC BID FORM
23058 00 41 13 - 1
NEW CASTLE COUNTY DETENTION CENTER
NCCDC MOISTURE INTRUSION
963 CENTRE ROAD, WILMINGTON, DE 19805
CONTRACT #: MC3705000126
BID FORM
For Bids Due: June 4, 2026 To: State of Delaware OMB/DFM
Haslet Armory Building
122 Martin Luther King Jr Blvd South
Dover, Delaware 19901
Name of Bidder:
Delaware Business License No.: Taxpayer ID No.:
(Other License Nos.):
Phone No.: ( ) - Fax No.: ( ) -
The undersigned, representing that he has read and understands the Bidding Documents and that this bid is made in accordance therewith, that he has visited the site and has familiarized himself with the local conditions under which the Work is to be performed, and that his bid is based upon the materials, systems and equipment described in the Bidding Documents without exception, hereby proposes and agrees to provide all labor, materials, plant, equipment, supplies, transport and other facilities required to execute the work described by the aforesaid documents for the lump sum itemized below:
ALLOWANCES
The base bid above includes all allowances specified in the contract documents.
Allowance No. 1: Include an allowance entitled “General Owner’s Allowance” in the amount of $10,000.00. This allowance will be utilized by the owner for owner-elected changes to the work. Any or all unused allowance monies shall be returned to the owner via a credit change order at the end of the project. This allowance shall be carried as an individual line-item on the
Application for Payment. Acknowledge/Initial: ______
BID FORM R G ARCHITECTS, LLC
00 41 13 - 2 23058
NEW CASTLE COUNTY DETENTION CENTER
NCCDC MOISTURE INTRUSION
963 CENTRE ROAD, WILMINGTON, DE 19805
CONTRACT #: MC3705000126
ALTERNATES
Alternate prices conform to applicable project specification section. Refer to specifications for a complete description of the following Alternates. An “ADD” or “DEDUCT” amount is indicated by the crossed out part that does not apply.
ALTERNATE No. 1: ADD All work to replace the existing basement AHU-1 and its outdoor CU-1 with a new AHU-1 and
CU-1.
Add/Deduct:
ALTERNATE No. 2: ADD All work to replace the existing walk-in refrigerator/freezer units EVAP-1, EVAP-2, EVCU-1, and EVCU-2 with new units.
Add/Deduct:
ALTERNATE No. 3: ADD All work to replace the existing dry storage equipment IDU-1 and HP-1 with new units.
Add/Deduct:
R G ARCHITECTS, LLC BID FORM
23058 00 41 13 - 3
NEW CASTLE COUNTY DETENTION CENTER
NCCDC MOISTURE INTRUSION
963 CENTRE ROAD, WILMINGTON, DE 19805
CONTRACT #: MC3705000126
BID FORM
I/We acknowledge Addendums numbered and the price(s) submitted include any cost/schedule impact they may have.
This bid shall remain valid and cannot be withdrawn for thirty (30) days from the date of opening of bids (60 days for School
Districts and Department of Education), and the undersigned shall abide by the Bid Security forfeiture provisions. Bid Security is attached to this Bid.
The Owner shall have the right to reject any or all bids, and to waive any informality or irregularity in any bid received.
This bid is based upon work being accomplished by the Sub-Contractors named on the list attached to this bid.
Should I/We be awarded this contract, I/We pledge to achieve substantial completion of all the work within calendar days of the Notice to Proceed.
The undersigned represents and warrants that he has complied and shall comply with all requirements of local, state, and national laws; that no legal requirement has been or shall be violated in making or accepting this bid, in awarding the contract to him or in the prosecution of the work required; that the bid is legal and firm; that he has not, directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken action in restraint of free competitive bidding.
Upon receipt of written notice of the acceptance of this Bid, the Bidder shall, within twenty (20) calendar days, execute the agreement in the required form and deliver the Contract Bonds, and Insurance Certificates, required by the Contract Documents.
I am / We are an Individual / a Partnership / a Corporation
By Trading as
(Individual’s / General Partner’s / Corporate Name)
(State of Corporation)
Business Address:
Witness: By:
( Authorized Signature )
(SEAL)
( Title )
Date:
ATTACHMENTS
Sub-Contractor List
Non-Collusion Statement
Affidavit of Employee Drug Testing Program
Affidavit of Contractor Qualifications
Bid Security
(Others as Required by Project Manuals)
BID FORM R G ARCHITECTS, LLC
00 41 13 - 4 23058
NEW CASTLE COUNTY DETENTION CENTER
NCCDC MOISTURE INTRUSION
963 CENTRE ROAD, WILMINGTON, DE 19805
CONTRACT #: MC3705000126
BID FORM
SUBCONTRACTOR LIST
In accordance with Title 29, Chapter 69, Section 6962(d)(10)b of the Delaware Code, the following subcontractor listing must accompany any bid submittal.